INTRODUCTION
The objective of designing this water treatment plant for ALDEL campus is to provide clean water for the entire campus. The Water treatment plant is being designed for water that has been drawn from the ground.
POPULATION ESTIMATE
No. of students 1469
108
95
Canteen staff
20
1. Domestic 2. Industrial, Commercial and Community requirement based on 45000 litres per hect. per day
Water required for Gardening purpose @ 3 liters per 5076 person per day for 1692 Total Required Design requirement 93596 1,00,000
TESTS PERFORMED
Removing Hardness
SOFTENING
The two basic methods of softening public water supplies are
chemical precipitation (Lime and Soda ash) and ion exchange.
Other methods can also be used to soften water, such as electrodialysis, distillation, freezing, and reverse osmosis. These processes are complex and expensive .
Reactions
LIME ADDITION:-
Lime Required
229.13 mg/L
Lime Required
330 mg/L
70.25 mg/L
130 mg/L
Experiments performed
Total hardness test Jar test pH meter test Titration for chlorine content test
Aeration Tank
Design Criteria For Cascade Aerators
Design Calculation
Qmax = 0.1543 m3/sec. = 17 m2 =5m = 0.4 m = 50 cm Provide area at tray Diameter of bottom most tray Rise of each tray Tread of each tray