Академический Документы
Профессиональный Документы
Культура Документы
BELLAZONA PHASE IV
Molino III , Bacoor Cavite
Prepared by :
Noted by :
Approved by :
JCW
13151062.xlsSUMMARY 01/19/2009
NOTE : Lined canal at Ridge Parks ( Excluded Area ) not yet included.
13151062.xlsSUMMARY 01/19/2009
MASAITO DEVELOPMENT CORPORATION
VP4 LAND DEVELOPMENT
PASONG BUWAYA IMUS, CAVITE
1 EARTHWORKS
1A. Clearing & Grubbing
A1 Clearing and grubbing sq.m. 200.00 50.0 10,000.00
sub - total - 10,000.00
13151062.xlsProject estimate
-
2B. Base preparation -
B1 roads 120.00 -
Base coarse cu.m. 12.00 750.00 9,000.00 -
Spreading sq.m. 120.00 5.0 600.00
Compaction sq.m. 120.00 7.0 840.00
Watering sq.m. 120.00 2.0 240.00
B2 curbs & gutter sq.m. 18.00 -
Base coarse sq.m. 1.80 750.00 1,350.00 -
Spreading cu.m. 18.00 5.0 90.00
Compaction sq.m. 18.00 7.0 126.00
Watering sq.m. 18.00 2.0 36.00
B3 sidewalk sq.m. 40.00 -
Base coarse sq.m. 2.00 750.00 1,500.00 -
Spreading cu.m. 40.00 5.0 200.00
Compaction sq.m. 40.00 7.0 280.00
Watering sq.m. 40.00 2.0 80.00
sub - total 11,850.00 2,492.00
-
2C Road concreting sq.m. 120.00 80.0 9,600.00
RMC G1,3000 psi,28 days sq.m. 18.00 3,340.00 60,120.00
DSB 12mm x 6m cu.m 20.00 148.00 2,960.00 -
CWN - 2" kgs. 5.00 50.00 250.00
Epocure drum, 1.00 6,500.00 6,500.00
Asphalt bags 2.00 1,000.00 2,000.00
sub - total 71,830.00 9,600.00
13151062.xlsProject estimate
2F Formworks l.m. 140.00 10.0 1,400.00
C-Purlins 150mm x 50mm x 2mm x 6m pcs 6.00 1,100.00 6,600.00
C-Purlins 75mm x 50mm x 2mm x 6m pcs 6.00 880.00 5,280.00
C-Purlins 250mm x 50mm x 2mm x 6m pcs 6.00 1,990.00 11,940.00
Plywood 4' x 8' x 1/4 thk. Ordinary pcs 350.00 -
DSB 12mm x 6m ( dowels=.40mlength ) pcs 5.00 148.00 740.00
G.I. Tie Wire, #18 kgs 1.00 50.00 50.00
sub - total 24,610.00 1,400.00
13151062.xlsProject estimate
B4 BEAM cu.m 1.11 - 750.0 832.50
Cement bags 9.99 205.00 2,047.95
Sand cu.m 0.56 700.00 388.50
Gravel 3/4" cu.m 1.11 800.00 888.00
RSB 10 MM x 20 PCS 30.00 108.00 3,240.00 50.0 1,500.00
RSB 12.MM PCS 30.00 148.00 4,440.00 60.0 1,800.00
TIE WIRE KGS 10.00 50.00 500.00 50.0 500.00
B5 Formworks sq.m. 93.53 200.0 18,706.00
Plywood 1/2" x 4' x 8' pcs 30.00 750.00 22,500.00
Coco lumber 2" x 4" x 8' bd.ft. 1,000.00 12.00 12,000.00
Cwn 3" kgs 20.00 50.00 1,000.00
sub - total 186,750.60 60,009.75
TOTAL MATERIAL AND LABOR Sub-total 284,910.60 114,909.75
B6 RIPRAP
sets 100.00 300.0 30,000.00
Escombro cu.m 100.00 750.00 75,000.00
Cement bags 350.00 205.00 71,750.00
Sand cu.m 39.00 700.00 27,300.00
Sub-total 174,050.00 30,000.00
SUB TOTAL
TOTAL MATERIAL AND LABOR 174,050.00 30,000.00
###
TOTAL MATERIALS COST 603,642.60
TOTAL LABOR /EQUIPMENT COST 118,784.00
DIRECT COST 722,426.60
MARK UP & CONTINGENCIES 12% 86,691.19
PROJECT COST 809,117.79
13151062.xlsProject estimate
MASAITO DEVELOPMENT CORPORATION
COMPUTATION SHEETS
224.32 2,018.88
TOTAL MATERIALS REQUIREMENTS 317.97 157.36 10.60 262.45
MATERIALS UNIT COST 1,820.00 80.00 24.00 420.00
TOTAL MATERIALS COST 578,711.95 12,588.49 254.44 110,230.85
TOTAL LABOR COST 2,018.88
DIRECT COST
954,491.41
MATERIAL REQUIREMENTS
ROAD PAVEMENT LENGTH TOTAL AREA OF BASE AREA RMC,2500psi basecourse Lastillas Epocure Asphalt
WIDTH 0.45+.15=0.6 of X SEC 3/4 G 0.125 0.20 200.00 100.00
NAME m lm lm 0.6 cu.m. cu.m. cu.m. drum bag
RL1 9.00 224.32 475.64 285.38 0.07 34.96 41.02 68.49 1.07 4.76
11,415.36
129,840.21
MATERIAL REQUIREMENTS
ROAD ROW PAVEMENT TOTAL WIDTH AREA RMC, cwn 2" basecourse Lastillas Epocure Asphalt Labor Cost
NAME WIDTH LENGTH LENGTH 0.075 4pcs/lm 0.05+30% .10m+20% 200m2/ 100 lm/bag 26.00
drum
m m lm m m sq.m. cu.m. kgs cu.m. cu.m. drum bag sq.m.
RL1 15.00 9.00 224.32 475.64 1.20 570.77 44.95 4.71 37.10 68.49 2.85 1.28 14,839.97
475.64 570.77
TOTAL MATERIALS REQUIREMENTS 44.95 4.71 37.10 68.49 2.85 1.28
MATERIALS UNIT COST 1,780.00 24.00 420.00 380.00 1,780.00 650.00
TOTAL MATERIALS COST 80,007.40 113.02 15,581.97 26,027.02 5,079.84 832.24
TOTAL LABOR COST 14,839.97
11,285,147.33
Prepared by :
Marlon Q. Melorin
ELEVATIONS
ROAD STATION DESIGN NGL FILL CUT LENGTH, meter AREA ROW VOLUME
NAME ROAD + - L x L-x FILL CUT FILL CUT
m m m m (total) (cut) (fill) sq.m. sq.m. m cu.m. cu.m.
RL 1 0+ 11.00 21.400 20.920 0.23 -
9.00 - 9.00 4.86 - 15.00 72.90 -
0+ 20.00 21.340 20.240 0.85 -
20.00 - 20.00 28.70 - 15.00 430.50 -
0+ 40.00 21.100 18.830 2.02 -
20.00 - 20.00 27.30 - 15.00 409.50 -
0+ 60.00 21.060 20.100 0.71 -
20.00 4.22 15.78 5.60 0.40 15.00 84.02 6.02
0+ 80.00 21.000 20.940 - (0.19)
20.00 20.00 - - 3.40 15.00 - 51.00
0+ 100.00 21.040 20.940 - (0.15)
20.00 20.00 - - 4.50 15.00 - 67.50
0+ 120.00 21.500 21.550 - (0.30)
20.00 20.00 - - 5.80 15.00 - 87.00
0+ 140.00 21.970 22.000 - (0.28)
20.00 11.91 8.09 0.77 1.67 15.00 11.52 25.02
0+ 160.00 22.440 22.000 0.19 -
20.00 - 20.00 2.60 - 15.00 39.00 -
0+ 180.00 22.910 22.590 0.07 -
20.00 18.51 1.49 0.05 8.05 15.00 0.78 120.78
0+ 200.00 23.380 24.000 - (0.87)
20.00 20.00 - - 9.60 15.00 - 144.00
0+ 220.00 23.500 23.340 - (0.09)
15.00 15.00 - - 4.50 15.00 - 67.50
0+ 235.00 23.550 23.810 - (0.51)
ELEVATIONS
STATION DESIGN DESIGN NGL FILL CUT LENGTH, meter AREA LOT DEPTH VOLUME
BLOCK LOT ROAD BLOCK + - L x L-x FILL CUT L AVE. FILL CUT
m m m m m (total) (cut) (fill) sq.m. sq.m. m m cu.m. cu.m.
2 1 0+ 60.69 43.460 43.560 42.627 0.93 - 23.37
14.34 - 14.34 15.35 - 22.19 340.56 -
1-2 0+ 75.03 42.740 42.840 41.632 1.21 - 21.00
19.96 - 19.96 20.74 - 19.51 404.61 -
2-3 0+ 94.99 42.380 42.480 41.610 0.87 - 18.02
13.00 - 13.00 16.61 - 18.30 303.92 -
3-4 0+ 107.99 42.280 42.380 40.695 1.69 - 18.58
21.16 - 21.16 29.85 - 18.00 537.08 -
4-5 0+ 129.15 42.130 42.230 41.094 1.14 - 17.41
13.00 6.53 6.47 3.68 3.74 17.44 64.09 65.22
5-6 0+ 142.15 42.040 42.140 43.286 - (1.15) 17.46
15.03 6.96 8.07 5.37 3.99 15.46 82.98 61.61
6 0+ 157.18 41.930 42.030 40.700 1.33 - 13.45
1.0 EARTHWORKS
1.1 Clearing and grubbing
1.1a Clearing and grubbing sq.m. 54,891.00 7.00 384,237.00
Sub-total 384,237.00
1.2 Site grading ( CUT & FILL )
1.2a Excavation/cut of roadways and alleys cu.m 1,817.81 30.00 54,534.20
1.2b Fill of roadways and alleys cu.m 8,473.18 30.00 254,195.46
1.2c Excavation/cut of Blocks/open space & e.ment cu.m 3,073.12 30.00 92,193.61
1.2d Fill of Blocks/open space and easement cu.m 42,182.60 30.00 1,265,477.93
1.2e Lastillas cu.m 45,764.85 166.67 7,627,627.99
9,678,266.20
Prepared by :
Dennis C. Dizon
13151062.xlsearthworks summary Page 21 of 41 01/19/2009
RICHFIELD PROPERTIES INC.
COMPUTATION SHEETS
MATERIALS LABOR
ITEM UNIT QTY/ TOTAL UNIT TOTAL UNIT TOTAL
DESCRIPTIONS VALVE QTY COST COST COST COST
A. BLOW OFF VALVES sets 1.00 420.00 420.00
1 FITTINGS
C.I. Gate valves 100mm F/F pcs 1.00 1.00 2,570.00 2,570.00
C.I. Tee MJ/F 4 x 4 pcs 1.00 1.00 1,773.00 1,773.00
C.I. Elbow 100mm x 90deg. F/MJ pcs 1.00 1.00 1,700.00 1,700.00
C.I. End Cap 100mm dia. pcs 1.00 1.00 350.00 350.00
2 TRUST BLOCK 1:2 1/2: 5 -
Cement bags 0.68 0.68 95.00 64.60
Sand cu.m. 0.05 0.05 320.00 16.00
Gravel 3/4" cu.m. 0.09 0.09 520.00 46.80
3 VALVE BOX -
uPVC 100mm dia. x 1m pcs 1.00 1.00 202.58 202.58
Cement bags 0.59 0.59 95.00 56.05
Sand cu.m. 0.04 0.04 320.00 12.80 -
Gravel 3/4" cu.m. 0.08 0.08 520.00 41.60
DSB 16mm x 6m pcs 0.75 0.75 145.00 108.75 -
4 GRAVEL ENCASEMENT -
Gravel G1 cu.m. 0.05 0.05 420.00 21.00
- -
B. GATE VALVES sets 13.00 - 420.00 5,460.00
1 FITTINGS -
Gate valves 100mm F/F pcs 4.00 4.00 2,570.00 10,280.00
Gate valves 50mm F/F pcs 9.00 9.00 2,100.00 18,900.00 -
C.I. Adaptor 100mm F/F pcs 8.00 8.00 1,050.00 8,400.00 -
C.I. Adaptor 50mm F/F pcs 18.00 18.00 650.00 11,700.00
2 TRUST BLOCK 1:2 1/2: 5 -
Cement bags 1.00 13.00 95.00 1,235.00
Sand cu.m. 0.10 1.30 320.00 416.00
Gravel 3/4" cu.m. 0.20 2.60 520.00 1,352.00 -
PREPARED BY :
MATRL'S REQMT'S 1.00 5.00 2.00 5.00 - 4.00 3.00 9.00 3.00 7.00 3.00 2.00 28.00
MTRL'S UNIT COST 1,700.00 1,700.00 1,700.00 1,565.00 1,565.00 350.00 210.00 1,700.00 1,700.00 1,150.00 1,150.00 95.00
TOTAL COST 1,700.00 8,500.00 3,400.00 7,825.00 - - 1,050.00 1,890.00 5,100.00 11,900.00 3,450.00 2,300.00 - 2,660.00
LABOR COST 170.00 170.00 170.00 170.00 170.00 170.00 170.00 170.00 85.00 85.00 85.00 85.00
TOTAL COST 170.00 850.00 340.00 850.00 - 680.00 510.00 1,530.00 255.00 595.00 255.00 170.00
DIRECT COST
PREPARED BY :
0.045 0.090
m3 m3
1.98 3.96
-
2.00 4.00
320.00 520.00
640.00 2,080.00 52,495.00
6,205.00
58,700.00
RL 5 3 2 0.00
RL6 12 13 0.00
13 14 0.00
14 15 0.00
RL7 8 10 0.00
9 10 0.00
10 11 0.00
11 OF 1 0.00
RL8 17 19 0.00
18 19 0.00
19 56 71.00 14.20
56 OF2 0.00
RL9 48 50 0.00
49 50 0.00
50 51 8.00 4.00
51 OF3 0.00
RL10 54 55 0.00
55 OF4 0.00
RL11 23 25 0.00
24 25 0.00
25 28 0.00
26 28 0.00
28 31 0.00
30 31 0.00
31 36 0.00
32 36 0.00
36 37 0.00
37 40 0.00
38 37 0.00
39 40 0.00
40 45 0.00
41 44 0.00
44 45 0.00
45 46 0.00
47 46 0.00
RL12 42 44 0.00
RL13 43 42 0.00
RL14 20 22 0.00
RL15 27 29 0.00
29 28 0.00
57 29 0.00
TOTAL MATERIAL REQUIREMENTS 0.00 240.00 71.00 253.00 8.00 0.00 154.75
MATERIAL UNIT COST 305.00 375.00 95.00
TOTAL MATERIALS COST 73,200.00 26,625.00 14,701.25
LABOR UNIT COST EXCAVATION 50.00 50.00
LABOR COST EXCAVATION 12,000.00 3,550.00
LABOR UNIT COST BACKFILLING 22.00 25.00
LABOR COST BACKFILLING 5,280.00 1,775.00
LABOR UNIT COST LAYING/COLLAR 18.00 20.00
LABOR COST LAYING/COLLAR 4,320.00 1,420.00
DIRECT COST
0.00 0.00
0.00 0.00 ###
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00 ###
0.78 21.94
0.00 0.00
0.00 0.00
0.00 0.00
0.22 5.13
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
5.80 130.29
320.00 320.00
1,857.28 41,693.12 158,076.65
15,550.00
7,055.00
5,740.00
186,421.65
MATERIALS LABOR
ITEM
ITEM / WORK DESCRIPTION Unit Qty. Unit Materials Unit
NO.
Cost Cost Cost
C.2 Manhole (450mm dia. & smaller) sets 8.00 - 700.00
C.2.1 Slab , 1: 2 1/2:5 mix cu.m 1.73 -
Cement bags 15.55 115.00 1,788.48
Sand cu.m 0.86 380.00 328.32
Gravel 3/4" cu.m 1.73 580.00 1,002.24
Gravel G1, Bedding cu.m 0.43 480.00 207.36
C.2.2 Chb wall, 1:4 mix sq.m. 31.68 -
CHB 6" , ord. pcs 396.00 7.50 2,970.00
Cement bags 24.05 115.00 2,765.19
Sand cu.m 2.67 380.00 1,015.80
Dsb 10mm x 6m pcs 28.67 78.00 2,236.29
No. 18 G.I. Tie wire kgs 1.59 32.00 50.86
C.2.3 Plastering 1:3 mix sq.m. 31.68 -
Cement bags 6.27 115.00 721.35
Sand cu.m 0.70 380.00 264.84
C.2.4 Capping 1: 2 1/2:5 mix cu.m 0.86 -
Cement bags 7.78 115.00 894.24
Sand cu.m 0.43 380.00 164.16
Gravel 3/4" cu.m 0.86 580.00 501.12
C.2.5 Grating / Ladder Rung -
Grating Dsb 10mm x 6m pcs 4.00 78.00 312.00
Ladder Rung 16mm x 6m pcs 2.67 189.00 504.00
C.2.6 Cover cu.m 0.42 -
Cement bags 3.78 115.00 434.70
Sand cu.m 0.21 380.00 79.80
Gravel 3/4" cu.m 0.42 580.00 243.60
Dsb 12mm x 6m pcs 6.00 106.00 636.00
Dsb 10mm x 6m pcs 5.33 78.00 416.00
No. 18 G.I. Tie wire kgs 0.78 32.00 24.81
C.2.7 Formworks sq.m. 20.00 -
Plywood 3/16 x 4' x 8' pcs 6.94 225.00 1,562.50
Coco lumber 2" x 4" x 8' bd.ft. 85.33 8.50 725.33
Cwn 3" kgs 1.54 24.00 36.86
sub - total 19,885.87
19,885.87
5,600.00
25,485.87
RICHFIELD PROPERTIES INC.
COMPUTATION SHEETS
MATERIALS LABOR
ITEM
ITEM / WORK DESCRIPTION Unit Qty. Unit Materials Unit
NO.
Cost Cost Cost
C.4 Manhole (600mm dia. & larger) sets 8.00 - 700.00
C.4.1 Base slab cu.m 4.95 -
Cement bags 44.55 115.00 5,123.25
Sand cu.m 2.48 380.00 940.50
Gravel 3/4" cu.m 4.95 580.00 2,871.00
Gravel G1, Bedding cu.m 0.99 480.00 475.20
C.4.2 Wall cu.m 16.39 -
Cement bags 147.55 115.00 16,967.79
Sand cu.m 8.20 380.00 3,114.86
Gravel 3/4" cu.m 16.39 580.00 9,508.52
Dsb 12mm x 6m pcs 224.11 106.00 23,755.78
No. 18 G.I. Tie wire kgs 17.91 32.00 573.15
C.4.3 Suspended Slab cu.m 2.36 -
Cement bags 21.24 115.00 2,442.60
Sand cu.m 1.18 380.00 448.40
Gravel 3/4" cu.m 2.36 580.00 1,368.80
Dsb 12mm x 6m pcs 61.78 106.00 6,548.44
No. 18 G.I. Tie wire kgs 4.94 32.00 157.99
C.4.4 Grating / Ladder Rung -
Grating Dsb 10mm x 6m pcs 4.00 78.00 312.00
Ladder Rung 16mm x 6m pcs 9.33 189.00 1,764.00
C.4.5 Cover cu.m 0.42 -
Cement bags 3.78 115.00 434.70
Sand cu.m 0.21 380.00 79.80
Gravel 3/4" cu.m 0.42 580.00 243.60
Dsb 12mm x 6m pcs 6.00 106.00 636.00
Dsb 10mm x 6m pcs 5.33 78.00 416.00
No. 18 G.I. Tie wire kgs 0.78 32.00 24.81
C.4.6 Formworks sq.m. 153.48 -
Plywood 3/16 x 4' x 8' pcs 53.29 225.00 11,990.63
Coco lumber 2" x 4" x 8' bd.ft. 2,805.31 8.50 23,845.11
Cwn 3" kgs 50.50 24.00 1,211.89
sub - total 115,254.82
TOTAL 115,254.82
5,600.00 120,854.82
115,254.82
5,600.00
120,854.82
RICHFIELD PROPERTIES INC.
COMPUTATION SHEETS
MATERIALS LABOR
ITEM
ITEM / WORK DESCRIPTION Unit Qty. Unit Materials Unit
NO.
Cost Cost Cost
C.3 Outfall Protection
C.3.2 Outfall 1&2 sets 2.00 - 800.00
Escombro cu.m 8.12 400.00 3,246.30
Cement bags 14.61 115.00 1,679.96
Sand cu.m 1.62 380.00 616.80
sub - total 5,543.06
TOTAL 5,543.06
1,600.00 1,600.00
- 3,246.30
- 1,679.96
- 616.80
1,600.00 7,143.06
1,600.00 7,143.06
5,543.06
1,600.00
7,143.06
RICHFIELD PROPERTIES INC.
COMPUTATION SHEETS
PREPARED BY :
ROAD NAME Length uPVC PIPE ( 6M ) C-150, atlanta SAND BEDDING TOTAL
100mm 75mm 50mm DEPTH WIDTH Sand
m pcs pcs pcs m m cu.m.
559.00 100.00 0.28 0.40 62.61
605.00 108.00 0.21 0.35 44.47
TOTAL
PREPARED BY :
ROAD R.O.W. DOUBLE SINGLE TOTAL SIZE OF P.E. Tubing / stub out Total P.E. Tubing
NAME SHORT LONG SHORT LONG Stub out PIPE SHORT LONG SHORT LONG
pcs pcs pcs pcs pcs m m m m
RL1 12.00 5.00 4.00 - 1.00 10.00 100.00 2.60 10.60 13.00 53.00
RL5 6.50 - - - - - 50.00 1.10 6.60 - -
RL6 6.50 2.00 - - - 2.00 50.00 1.10 6.60 2.20 -
RL7 6.50 1.00 1.00 - - 2.00 50.00 1.10 6.60 1.10 6.60
RL8 6.50 1.00 1.00 - 1.00 3.00 50.00 1.10 6.60 1.10 13.20
RL9 6.50 1.00 - 1.00 1.00 3.00 50.00 1.10 6.60 2.20 6.60
RL10 5.00 1.00 - - - 1.00 50.00 3.10 3.10 3.10 -
RL11 10.00 6.00 5.00 1.00 2.00 14.00 100.00 2.60 8.60 18.20 60.20
RL12 6.50 1.00 1.00 - - 2.00 50.00 1.10 6.60 1.10 6.60
RL13 6.50 - - - - - - 1.10 6.60 - -
RL14 8.00 2.00 3.00 - 1.00 6.00 50.00 1.60 7.60 3.20 30.40
RL15 8.00 1.00 1.00 - - 2.00 50.00 1.60 7.60 1.60 7.60
TOTAL 21.00 16.00 2.00 6.00 45.00 46.80 184.20
MATERIALS LABOR
ITEM UNIT QTY/ TOTAL UNIT TOTAL UNIT TOTAL
DESCRIPTIONS SET QTY COST COST COST COST
1 PIPING
P.E. Tubing 3/4" dia. l.m. 265.65 18.75 4,980.94 6.50 1,726.73
2 Saddle Clamp
50mm dia. x 20mm pcs 21.00 68.00 1,428.00 180.00 3,780.00
100 mm dia. x 20mm pcs 24.00 96.00 2,304.00 180.00 4,320.00
3 Stub out
A. Double Stub out sets 37.00
Brass straight coupling 3/4" dia.GV pcs 2.00 74.00 90.00 6,660.00
G.I. Tee 3/4" dia. pcs 1.00 37.00 16.50 610.50
G.I. Nipple 3/4" dia. x 12" pcs 2.00 74.00 21.50 1,591.00
G.I. Elbow reducer 3/4" dia.x1/2" dia. pcs 2.00 74.00 13.50 999.00
G.I. Nipple 3/4" dia. x 20" pcs 2.00 74.00 35.00 2,590.00
G.I. End cap 1/2" dia. pcs 2.00 74.00 7.20 532.80
Teplon tape pcs 2.00 74.00 10.00 740.00
B. Single Stub out sets 8.00
Brass straight coupling 3/4" dia.GV pcs 2.00 16.00 90.00 1,440.00
G.I. Reducer 3/4" dia.x 1/2" dia. pcs 1.00 8.00 13.50 108.00
G.I. Nipple 3/4" dia. x 20" pcs 1.00 8.00 35.00 280.00
G.I. End cap 1/2" dia. pcs 1.00 8.00 7.20 57.60
Teplon tape pcs 1.00 8.00 10.00 80.00
C. Thrust Block 1 : 2 1/2 :5 sets 45.00
Cement bags 0.05 2.25 95.00 213.75
Sand cu.m. 0.004 0.18 320.00 57.60
Gravel 3/4" cu.m. 0.007 0.32 520.00 163.80
Prepared by :