SISTEM GARDU TRAKSI (SUBSTATION)

Arrester Incoming Metering Outgoing Outgoing Outgoing Outgoing Outgoing Outgoing Outgoing

Panel 20 kV

Panel 6 kV

20 kV dari PLN

Trafo 20kV/ 1200V

Trafo 20kV/ 380V

Trafo 20kV/ 6 kV

Trafo 6kV/ 380V

6 kV ke lintas PDL

Battery

Silicon Rectifier 1500 VDC (Negatif) 1500 VDC (Positif)


Negative Main Feeder Feeder Feeder Feeder Bypass

Panel AC / DC
COS

Battery Charger

DC Switchgear

Beban AC/DC

Panel Interkoneksi

Panel VCP

Panel LBD

LAA hulu LAA hilir Ke rel kereta

Prinsip Kerja Panel Interkoneksi & VCP


Trafo 20kV/ 1200V Silicon Rectifier DC Switchgear Trafo 20kV/6kV Trafo 20kV/380V Trafo 6kV/380V

Panel 20 kV

Panel 6 kV

Panel Interkoneksi
Gardu Traksi Operation Control Centers (OCC)
input touchscreen dari operator fibre optic fibre optic

Panel VCP

SCADA

Prinsip Kerja Panel LBD


Gardu Traksi B Gardu Traksi A Gardu Traksi C

DC Switchgear
intertripping

DC Switchgear
intertripping

DC Switchgear
intertripping

hardwire

hardwire

hardwire

Panel LBD

fibre optic

fibre optic

Panel LBD

fibre optic

fibre optic

Panel LBD