PROCESS FLOW SHEET OF

-
-
0
SCOPE
APPR
DESIGN
CHKD BY DESCRIPTION DATE REV
PROJ.
Owner :
Tittle :
Project :
FENI HALMAHERA TIMUR PROJECT
SUPV. ENG.
DRAWN
CHECKED
FENI HALTIM NO :
DRAWING NO : FeNIH-OP-M-11-0-005
DESIGNED
REVIEWED
APPROVED
SCALE DATE
DIM
NUM
REV
Contractor :
PT. ADHIKARYA ( PERSERO ), TBK.
EPC PACKAGE 2 WBS 4100 OXYGEN PLANT
RAW ORE CRUSHING AND STORAGE
Unloading Hopper for
Raw Ore, Concrete, 80
Ton
Crusher for Raw
Ore, Double Roller
Crusher, 250 t/h
Tripper for Raw
Ore, Travelling,
250 t/h
Crushed Ore
Storage, steel
construction with
roofing, 20000 t
Unloading hopper for raw ore,
Concrete construction, 60 t
Belt conveyor, 30
deg trough, 250 t/h
Belt conveyor, 30
deg trough, 250 t/h