24.11.12
STAGE-IV U#11
BLOWER PIPING : 380 JOINTS BAL IN PIPING WORKS 2 FITTER GANGS,2 HP WELDERS AVAILABLE / 2 FITTER & 1 WELDER REQ.
ESP 300 MT BAL; CHARGING OF B PASS, ATT OF A PASS AND ROOF COMPLETION REP. OF HEAT TRACE & EIP FOR COMMSG OF HOPPER HEATERS & ASH LEVEL INDICATOR.
PMPL) RE-ADJUSTMENT 143 NOS PIPING HANGERS AND HYDRAULIC TEST & INSULATION OF 22 LINES IS BALANCE ADDITIONAL MOBILISATION REQ. 02 GANGS FOR RE-ADJUSTMENT CRITICAL PIPING HANGERS 02 GANGS FOR BAL HYDRO TEST COMPLETION 04 GANGS FOR BAL INSULATION WORKS COMPLETION
BAL PAINTING COMPL : SUPPLY OF PAINTS AND BAL PAINTING WORKS TO BE COMPLETED
STAGE-IV U#12
PUMP ERECTION: CRITICAL FOR BLU ERECTION YET TO START; MOBILISATION TO BE DONE
INSULATION : 875 MT BALANCE IN BOILER (50 % WORK BALANCE) & RHS DUCT INSULATION AVAILABLE-65 / 100 MORE REQ. (20 FOR REFACTORY, 80 FOR LAGGING WORK) STRUCTURAL WORKS: MAJOR WORK BALANCE IN DRUM PLATFORM, FIRING FLOORS & APH PLATFORMS 08 FITTER GANGS & 08 WELDERS. AVAILABLE / 07 FITTERS & 07 WELDERS REQ.
PIPING WORKS: CRITICAL FOR STEAM BLOWING 27 P-91 JOINTS; 32 CRH JOINTS BAL, 179 SUPPORTS BAL; RT/UT208 & SR 165 BAL 08 FITTER GANGS, 03 P-91 WELDERS AVAILABLE / 04 FITTER GANGS, 02 P-91 WELDERS, 04 HP WELDERS REQ.
EDTA PREPARATION : PROCUREMENT OF CHEMICALS SUPPLY & ERECTION OF 03 MAIN PUMPS AND 01 TRANSFER PUMP TANK SHIFTING & TEMPORARY PIPING AND VALVE ERECTION BHEL/PMPL/ TO SUBMIT MOBILIZATION PROGRAMME FOR COMPLETION OF WORK FOR EDTA
READINESS : REQUIRED - 02 FITTER GANGS WITH 02 RIGGER AND 02 WELDER( PREFERABLY IBR) FOR ROUND THE CLOCK WORKING, TARGET- 20/12/12 TG INTEGRAL PIPING : PRESENT- 06 WELDERS ; ADDITIONAL - 02 WELDERS(SS/CS) REQUIRED
ERECTION- TDBFP/CEP/OTHERS : PRESENT- 03 FITTER GANGS; ADDITIONAL - 05 NOS PERSONS REQD TO EXPEDITE WORK PROGRESS RE JOINTS/ CROSS AROUND PIPING : 2 FITTERS GANGS WITH 06 WELDERS FOR ROUND THE CLOCK WORKING FROM 15 TH DEC12 CONDENSER TUBE FLARING : GANG REQUIRED BY 10TH DEC12; WITH 06 CUTTING M/C AND 04 FLARING M/C
DESCIPTION
CONTROL FLUID/SEAL STEAM/SPRAY/TURBINE DRAINSITEMS MISSING IN STORE YARD( LIST ATTACHED) CF TANK LOOSE ITEMS(CONSISTS OF SS BOLTS/THERMOWELL/GASKET) LP BYPASS STEAM BLOWING/HYDROTEST DEVICE- SENT TO UKAI SITE ON REQUEST MOTORS(TRANSFER PUMP OF COPU ROOM) CANVAL-46 FOR HP BYPASS SYSTEM
REMARKS
CF PIPING UNDER PROGRESS SHALL BE STOPPED AFTER 10 DAYS. ACTION YET TO BE TAKEN
2 3
4 5
02 NOS, MISSING AT SITE, COMMISSIONING IS HELD UP REQD- 04 BARRELS BORROWED FROM O&M FOR UNIT #11, PROCUREMENT IS TO BE TIED UP. REQD FOR EQUIPMENTS SUCH AS GENERATOR/BFPS/OTHERS IN ADVANCE, IN LAST UNIT WORK STOPPED DUE TO NON-AVL OF SHIMS ON MANY OCCASIONS
DESCIPTION
O RINGS AND GASKETS
REMARKS
REQD FOR EQUIPMENTS SUCH AS OIL FLUSHING/BFPS/OTHERS IN ADVANCE, IN LAST UNIT WORK STOPPED DUE TO NON-AVL OF GASKETS ON MANY OCCASIONS MISSING AT SITE, REQUIRED URGENTLY
8 9 10 11
480 NOS BOLTS FOR COUNTER FLANGE OF ECW/ACW PUMPS ACW MOTOR AFTER REPAIR( 02/03 PUMPS AVL IN UNIT#11) GAMA PLUGS- 250 NOS APPROX
12
REPAIRED AT MARATHON DEALER WORKS, NOT YET DESPATCHED MISSING AT SITE, SR OF BFD LINE IS HELD UP. ACTION TO BE INITIATED MISC ITEMS SUCH AS LOP MOTOR REPAIR/REPLACEMENT REQUIRED. ACTION TO BE TDBFP-B (HAVING ABNORMAL TAKEN IMMEDIATELY SOUND)- CIRCULATING PUMP MOTOR OF VACUUM PUMP ( DAMAGED), PRIMARY WATER PUMP ( HAVING SEAL LEAKAGE) ETC STEEL MATERIAL FOR OPERATING STEEL SECTIONS ARE NOT AVL, REQUIRES PLATFORM FOR CF ROOM, MOT IMMEDIATE AVAILABILITY AT SITE ROOM,MAL VALVE AREA
STAGE-V
MAJOR ISSUES
AWARD OF ENABLING WORKS CONTRACT