Earthquake Analysis Results per IBC-2000


User Entered Table Value 1615.1.2(1)
Fa
User Entered Table Value 1615.1.2(1)
Fv
Max. Mapped Acceleration Value for Short Periods Ss
Max. Mapped Acceleration Value for 1 sec. Period S1
Moment Reduction Factor
Tau
Force Modification Factor
R
Importance Factor
I
Site Class
Sms
Sm1
Sds
Sd1

=
=
=
=

Fa * Ss =
Fv * S1 =
2/3 * Sms
2/3 * Sm1

1.000
1.400
= 2/3
= 2/3

*
*
*
*

1.000
0.400
1.000
0.560

=
=
=
=

1.000
1.400
1.00
0.400
1.000
3.000
1.000
C

1.000
0.560
0.667
0.373

Check the Period (1/Frequency) from 16-39


3/4
= Ct * hn where Ct = 0.020 and hn = total Vessel Height [Ta]:
3/4
= 0.020 * 7699.9995 = 0.225 seconds
The Coefficient Cu from Table 1617.4.2 is 1.300
Check the Min. Value of T which is the Smaller of Cu*Ta and T, [T]:
= Min. Value of (1.300 * 0.225 , 1/33.000 ) = 0.0303 per 1617.4.2
As Time period is < 0.06 second, using section 1622.2.6.
Compute the Base Shear per 16-77, [V]:
= 0.3 * Sds * W * I
= 0.3 * 0.667 * 12377198 * 1.00 = 2475439 N
Note: Loads multiplied by the Scalar multiplier value of 0.7143
Final Base Shear,

V = 1768206.62 N