Вы находитесь на странице: 1из 1

COMPANY

Inspection & Test Plan for PWHT


Job Description : Project : PO No. : Client : Consultant : Contractor: Sl. No. A EQUIPMENT 1 Calibration of Recorder B PROCESS 1 2 3 4 5 Class/ Area/Line No./Joint No./ Size Rate of Heating Rate of Cooling Soaking temperature & Time Individual Joint Chart Legend: HP = Hold Point; W = Witness Point; Rw = Review of ZEPL's document; S = Surveillance; WC = 100% checking by Contractor WC WC WC WC WC Rw Rw Rw S Rw WC Rw Yes Format No. Rev. QAP No. Rev. Sheet Date Activity CONTRACTOR CONSULTANT Records to be submitted / Format No. Remarks :0 : 1 of 1 :0

Yes

Signature With Seal

Name: Date: CONTRACTOR PMC/CONSULTANT

Prepared By

Checked & Approved By

Checked By

Approved By

Вам также может понравиться