SABOBA DISTRICT ASSEMBLY

In case of reply the

Office of the Number and date of this letter should be quoted Our Ref. AB/117/03/V.8/49 Your Ref:

District Chief Executive P. O. Box SB 1 SABOBA N/R 20th July, 2011

SPOT IMPROVEMENT OF NATAGU-GURIKPAGA PH I FEEDER ROAD (6.OKM) DEFECT LIABILITYCERTIFICATE This is to certify that the the works completed on 18 th January 2011 on the above mention project has been maintained over the maintainable period of six months by the contractor, M/s Dal- Sam Ventures . The project has therefore been taken over by Saboba District Assembly with effect from 19 th July, 2011

ABDALLAH B. YUSSIF DISTRICT ENGINEER (ROADS) THE MANAGING DIRECTOR M/S Dal-Sam Ventures P. O. BOX 742 BOLGATANGA

Cc: The Asst. Tech. Advisor LSDGP N. R. C. C. P. O. BOX TL 100 Tamale.