Вы находитесь на странице: 1из 2

Sr.No. A Material cost dia.

(m) SHELL BOTTOM TOP Total plate(m3) Total plate(MT) ROUND UP (MT) INCLUSIVE OF 10% FABRICATION LOSS (MT) 6.1 6.2 6.2 ht. (m) 6.7 Thickness (M) VOLUME (M3) 0.008 1.03 0.01 0.30 0.008 0.24 1.57 12.24 12.50 13.75 14.00

Sub Total Rs.

Remark

ROUND UP (MT) COST OF THE PLATE PER MT Total cost of the body flanges, Fastners & other material Total (A) fabrication & erection cost manpower (Rs) 600 per man hour with consumable Nos 7 per day hours 8 per day Nos of days 40 cost (Rs) 1344000 Overhead in fabrication 10% Total (B) Total cost (A + B) Rubber Lining Cost Total (A + B + C) Profit margin 10% Total Transportation (2%)

50000 700,000.00 150,000.00 850,000.00

1,344,000.00 134,400.00 1,478,400.00 2,328,400.00 1,300,000.00 3,628,400.00 362,840.00 3,991,240.00 79,824.80 May be only for material cost

4,071,064.80

Add Crane & other facility

Erection of equipment: Rs. 18000/ MT WT (MT) QTY 4.5 Total cost of erection

COST 2 18000

TOTAL COST 162000.00

162000.00 162,000.00

#REF!

Person Days 2 Total cost of Mechanical commissioning Grand total (Mechanical Supply & Erection) Commissioning

Rate/day 6000.00 96,000.00 #REF! #REF!

Вам также может понравиться