Академический Документы
Профессиональный Документы
Культура Документы
e minimum overall project duration. A slippage or delay in completion of any activity by one time period will extend final completion correspondingly. The critical path by definition has no float. LONGEST PATH (LP) is the longest continuous path of activities through a project, which controls project early completion. It is possible for otherwise defined critical path activities to not be on the longest path and longest path activities to not show calculated critical float. The longest path analysis is unaffected by activity calendars. The longest path is determined by the string of activities, relationships, and lags that push the project to its latest, early finish date. The longest path is calculated by first performing a CPM forward pass to determine driving relationships and the projects latest, early finish date. The activity (or activities) with the latest, early finish dates are then identified and all predecessor driving relationships traced back to the project start date. These activities constitute the projects longest path. The longest path depends upon relationships driving the timing of activity starts, thus use of constraints and resource leveling can interrupt and invalidate longest path analysis. Use of interruptible activities can also result in false longest path indications. For complete accuracy, longest path analysis should take place absent of constraints, resource leveling, and/or interruptible activities.
Windows Analysis
A method of Delay Analysis that analyses the project in discrete 'windows' of time. The Status of the project and forecast Programme Completion Date is examined at the beginning of the time window and at the end of the time window. Any Variance (generally a Delay) is due to the events on the Critical Path within the window period. Also referred to as Time Slice Analysis.
What-If Analysis
The process of evaluation alternative strategies by changing the Sequence, Durations and Constraints on activities.
Having Experience of Almost 7 Years in the field of Construction, Well expert in Delay Analysis & Techniques used to identify Delays using the tools of Primavera P6. Development of Program Of Works and its Timely Monitoring, All type of Report Generation using Primavera P6.
5- Have you ever faced any disagreements in your previous job? How did you solve it out?
your have to take into consideration several disagreements. They can be between employees, between the superior and the employees, or even the client and the employees. If you reply that you have never had any disagreements, the interviewer will wonder whether you were really a key player for your skills or simply because you are a people pleaser. Make sure that you come up with at least one incident where employees and superiors had differences in thought and you were instrumental in changing the scenario.
7-Are you PMP certified? If you are not certified do you have a desire to attain a PMP certification?
Most employers are looking for PMP certified for project management vacancies. Be prepared to talk about your intentions, whether you already have it or you are currently in the planning stages of getting it.
Free Float : amount of time , an activity can be delayed without delaying the successor activity
Total Float : amount of time , an activity can be delayed without delaying the project finish date. Q2:What is a constraint in primavera? Constrains in primavera is to fix the early or late start or finish date of an activity as per following options: 1) Project Must Finish by 2) Mandatory Start / Mandatory Finish 3) Start / Finish On or After 4) Start / Finish On or Before 5) Start / Finish On 6) Expected Finish Q3:How can you define the Critical Path in primavera? The sequence of activities which describe the longest path from the data date to the end of the project. In a schedule without any constraints, this will be all activities with zero total float. (if you have constrains which force negative float, simply filtering on total float equal to or less than zero can bring up activities which are not on the critical path) Q4:What is WBS? WBS means Work Breakdown Structure. it represents a hierarchical breakdown of a Project into elements and deliverables. Q5:What is an open end activity in primavera? The open end activity is the activity that does not have any successor. Normally open end activity is not accepted in schedule because the total float will be calculate from the end of the project and these entire activities late dates gather at the end of the project and can not be prepare a logical late start plan. Q6:What is the difference between Retained Logic & Override Logic in progress update? If a project is generally running according to plan and activities are not progressed out of sequence then there will be virtually no difference between the two methods. BIG differences come when activities are progressed out of sequence. I believe in retained logic. Invariably that will produce the longest critical path but if activities have been progressed out of sequence, there could be some resulting illogical dependencies remaining, in particular resulting from dependencies with durations. Progress override invariably produces a shorter critical path and again there could be some illogical lack of dependencies resulting from activities having been progressed out of sequence. Q7:How do u measure & compare the progress using primavera? Progress is measured primarily against the baseline. If the baseline has been loaded with cost and/or resources, earned value management can be used for this purpose. If not, progress is measured as variance to baseline dates. Budget at Completion (BAC) Planned Value (PV) = budget at Completion (BAC) x Planned % Complete Earned Value (EV) = budget at Completion (BAC) x Actual% Complete
Actual Cost (AC) = No formula What youve actually spent on the project Schedule Performance Index (SPl) =Earned Value (EV) / Planned Value (PV) Schedule Variance (SV) =Earned Value (EV) Planned Value (PV) Cost Performance Index (CPI) =Earned Value (EV) / Actual Cost (AC) To Complete Performance Index (TCPI) =(Budget at Completion (BAC) Earned Value (EV) ) / (Budget at Completion (BAC) Actual Cost (AC) ) Cost Variance (CV) = Earned Value (EV) -Actual Cost (AC) For more information see this article:EVM earned value management Q8:What is resource allocation and resource leveling? Resource allocation is assigning resources to activities,determine the amount of labor, equipment and money required for any activity. Resource leveling is Resource requirements of all scheduled activities are compared to the maximum quantity available at the time of leveling.An activity is delayed if too few resources are available at any time during the activitys duration.The maximum quantity for a resource is determined through the Max units/time for a particular resource in the Resources Tab. Q9:What is an S Curve and how to create S Curve in primavera? An S-curve is a graph showing cumulative cost or value (measured in terms of money or manhours) against time. On a typical project, these graphs follow an S shape, hence the name. Typical data to be plotted on an S-Curve includes: Actual Cost (ACWP) Planned Value (BCWS) Early dates Planned Value (BCWS) Late dates Earned Value (BCWP) Forecast Value Early dates Forecast value Late dates Forecast Cost Early dates Forecast cost Late dates Q10:What are the difference between flag and milestone activity in primavera? Mile stone & flags both are events rather then activities. Some client likes to use flags rather than mile stone due the following differences. 1- With the use of flags the logic of main event can be easily tracked as these can not be created without predecessor as stand alone allocating the constraint.Where as mile stone can. 2- Flags can not update manually as Primavera automatically update the status where as milestone can be update manually. 3- Flags can not be constraint only driven by predecessor where as milestone can.
I think there is a growing demand for the planning engineers specially in the middle east, some new graduated engineers thinking to start their careers as planning engineers but they do not know what to do, Therefore i opened this discussion to share our knowledge and thoughts. I will put my point of view and every one is welcome to comment and share us with his / her thoughts. To be a successful planning engineer you should do the following :
1- Please take my golden advise NEVER EVER look for the salary in your first 5 years in your career, Money will come later on if you are well experienced and well educated. Just look for the experience first (Big projects, international companies, professional managers.etc) even if it will cost you less salary or more efforts, after few years you may get double salary of your colleges because you planned for your future. If you fail to plan, you plan to fail. 2- Do not start your carrier as a planning engineer, i believe you should work as a site engineer first to know the sequence of work and to feel the site work environment and this will help you later to estimate activities durations and sequence activity. I recommend to work 1 to 2 years as a site engineer. 3- Enhance your computer software knowledge, while you are working as a site engineer you need to enhance your software experience to be able to go to the next level, at least you should know Auto Cad, Excel, Word, and of course our favorite software Primavera. do a time schedules for the works you are supervising and show it to the project planning engineer and get his / her advise. 4- Next Level, Join the technical office: after you spent 1 or 2 years as a site engineer try to join the technical office in the site, mainly try to work as a quantity surveyor Q.S. This will improve your skills to read the drawings and to feel the numbers. Remember that planning engineer job mainly dealing with numbers such as quantities, productivity, progress percentages, manpower.etc, it is important for a successful planning engineer to know how to make a fast and accurate quantity surveyor or even to be monitoring a quantity surveyor under planning engineering department. I recommend to work 1 year as a quantity surveyor. 5- Study project management: the real planning engineer not the one who knows primavera only, you should know the concept of the project management and this will make your life much easy. So i recommend to study the PMIs Project Management Professional (PMP) during your work as a quantity surveyor Q.S, try to be certified from PMI because this will help you to go to the next level. 6- Next level, work as a scheduler or a junior planning engineer: if you succeeded to be a Project Management Professional (PMP) certified, then it will be easy to find a scheduler or a junior planning engineer job. Remember at this stage you still looking for experience not the money. I recommend to work as scheduler or a junior planning engineer for 2 years and it is better to complete one or more project from the very beginning to the very end.
7- Primavera and Microsoft excel are the core tools for the planning engineer: during your work as a scheduler or a junior planning engineer you should reach an advanced level in primavera and excel latest versions, i recommend to take advanced courses (could be online courses). 8- sharing your knowledge and experience with others: some people may think that if they share the knowledge and experience with others it reduce their chance to be special and give others more power with negative impact on the one who is sharing his ideas, knowledge and experience with others, This is totally not true because the moment you think that you know every thing is the same moment you will start falling behind. sharing knowledge and experience is a perfect method to promote your self and find out many many mistakes you was doing and thinking that every thing is perfect. Just try it . 9- Next start looking for a stable position with good salary: after reaching the step no. 8 you should be qualified for a good position as a planning engineer but i recommend to look for a stable company with good salaries for your next 3 to 4 years. work stability will be a factor now in your c.v, Therefore i recommend to choose a stable company or even if your existing company is stable that is fine. 10- Continue learning and improve your skills & knowledge: you can do this by checking the planning engineers websites, groups , forums or even study a master degree in management.
at the end of this article i want to draw you attention to the self motivation factors which will keep you going on the right road of success, never be disappointed from your mistakes or from others judgement. Remember the more you work the more chance you will do mistakes and the different between the successful planning engineer and the loser planning engineer that the first one learns from his mistakes and the second one get disappointed easily.
When using Retained Logic, the activity that starts out of sequence cannot finish until its predecessor has finished. The remaining duration of the out of sequence activity will be scheduled to begin after the predecessor is scheduled to finish. Retained Logic respects the network logic. When scheduling using Progress Override, Primavera P6 ignores the relationship between the activities and schedules any remaining duration of the out of sequence activity from the data date.
The updated time schedule is a copy of the baseline schedule with actual dates and percentage which represent the progress of work at certain date (Data Date). Once actual values applied to a baseline schedule it became an updated schedule with forecast completion dates for each activity could be earlier than the baseline schedule which mean (Ahead of schedule) or after the baseline schedule dates which mean (Behind the Schedule). 6- Revised Time Schedule: The revised time schedule is a recovery schedule to recover schedule delays due to any reason, revised time schedule could recover 100 % of the delays in the project and shorten the durations to complete the project as planned or it could not recover any durations if it is not possible and just represent a new completion date of the project.
1- Duration % complete:
Duration % of Original (or Planned) threshold value is expressed as a percentage. An issue is generated if the ratio of the activitys actual duration to its original or planned duration (actual duration / original or planned duration * 100) falls beyond the threshold values.
How it is calculated in primavera p6 : Duration % Complete(P6) = ( [Original Duration] [Remaining Duration] ) / [Original Duration] Example of calculating Duration % Complete : Original Duration: 20d , Actual Duration: 15d and Remaining Duration: 18d [Duration % Complete] = (20-18)/20 = 10%
to use the Duration % complete for an activity you should select the Duration % complete type from the activity details general tap as shown in the photo below
2- Units % complete:
Each assigned resource and assigned expense creates units in Primavera P6. The number of units depend on duration of the activity and your current settings the Units % is calculated from the actual
and remaining units, Units % Complete = [Actual Units / At Completion Units] x 100. see the figure below for more understanding
3- Physical % complete:
Physical percentage complete is a calculated field, which displays the percent complete based on the relative weights of the completed steps versus the incomplete steps. The physical progress of an activity is a manually-entered value determined by the user. The Physical % Complete is not rolled-up to WBS level, because its based on an external parameters, unknown to the software. to use the Physical % complete for an activity you should select the Physical % complete type from the activity details general tap as shown in the photo below
4- Schedule % complete:
schedule percent complete for an activity based on a straight forward calculation in primavera p6, schedule percent complete = ( [Data Date] [Baseline Start] ) / ( [Baseline Finish] [Baseline Start] ) When the Data Date is earlier than the Baseline Start date, Schedule % Complete is zero, when its after the Baseline Finish data, Schedule % Complete is 100%. Otherwise, Schedule % Complete show what percentage of the Baseline duration is passed by the Data Date. see the figure below for better understanding.
Schedule percent complete primavera p6 Schedule % Complete for WBS Elements: The Schedule % Complete of the WBS Element will be the ratio of the Baseline Costs before the Data Date to the Total Baseline Cost. The costs before the Data Date are called the Planned Value, or PV for short (Also called BCWS Budgeted Cost of Work Scheduled). The total baseline cost is called Budget At Completion or BAC for short. We can now formulate the calculation of Schedule % Complete for WBS Elements as: Schedule % Completed (WBS) = PV / BAC
5-Performance % Complete:
The percentage presentation of EV is usually called Performance % Complete. Performance % Complete of the Activities under the same WBS Element is calculated by one of these six options: 1. By Activity % Complete and without resource curves 2. By Activity % Complete and with resource curves 3. By WBS Milestones 4. By 0/100 method 5. By 50/50 method 6. By x/(100-x) custom method (1) and (2) are continuous and the rest of them are milestone progresses. (1) and (2) are dependent on the Activity progress, (3) is completely independent from the Activity progress, and the rest of them are only influenced by Actual Start and Actual Finish of the Activities.
Planners/schedulers fully understand the scope of the project and are pro-active both in interpreting the Clients requirements and producing project schedules. The project team effectively buys-in and owns the project schedule. Planning and scheduling information and documentation is produced which can be effectively utilized by project team members. The schedule is pro-actively analysed & reviewed to identify any potential restraints to progress. Any restraints identified being reviewed with all appropriate project team members, including the Project Manager. Any Specific project requirements should be identified and included in the Project Quality Plan The objectives of the Global / Regional / Industry / Quality Systems are met The Planning Manager is responsible for allocating planning resources, planning departmental budgetary control and maintenance of the quality procedures.
DEFINITIONS: Planning: The breakdown of work into its component events, and the sequencing, resourcing and strategy of those events. Scheduling: Detailed assignment of logic, duration & start/finish dates to project activities, within the overall plan.
Schedule/ Programme: Pictorial or tabular representation of the time phased events or activities required to execute the project. May be based on a critical path network (CPN). Critical Path Network (CPN): A representation of activities and/or events with their interrelationships and dependencies. Milestone: An event selected for its importance in the project and/or activity/deliverable. Precedence Network: A network diagram in which the nodes symbolise the project activities. Productivity/Efficiency: Ratio of hours earned versus hours expended. Performance Measurement Baselines: The original project quality, HSE, budget & contract duration objectives set by Management at Commencement. PBS Project Breakdown Structures: defines an hierarchical structure by which the work is to be done can include structures for Work, Cost, Contract, Organisation, Risk, Resources etc. PROGRESS MEASUREMENT: The Planner/Scheduler is responsible for ensuring that the various progress measurements used throughout the project are a fair representation of the actual project progress. As a minimum, the following should be provided: Studies/Engineering/Design: Actual % complete vs scheduled % complete. Work-hours expended vs budget work-hours. Productivity.Forecast work-hours at completion. Procurement: Schedule of planned, actual and forecast order and delivery dates, summary of inquiry PO packages issued. Contracts: Schedule of tender compilation and issue, tendering period, tender return, tender evaluation, award and completion dates for each construction contract package. Construction: Actual % complete vs scheduled % complete. RESOURCE PLANNING The Planner/Scheduler is also responsible for providing information to assist with the management of resources required to execute the work. These tasks include, but are not limited to: At the earliest possible stage, using the best available data, by assessing the Scope of Services and material quantities to provide management with an overall resource overview of the project.
From the project approved budgets assess the quantities of major resources required, issue discipline resource manpower requirement to Project Manager and Lead Discipline Engineers and determine if the supply may be a limiting factor. Where limitations occur pro-actively identify resolution by: - co-ordinating and re-sequencing activities - providing sufficient warning so that resources can be obtained - Recommend other actions such as work sharing, sub-contracting, etc. Provide and update forecasts of discipline manpower requirement and other facilities INTERACTIVE PLANNING: At various stages in each project, interactive planning sessions may be held with the Client and the Project team (including, where relevant, sub-contractors, vendors and construction contractors) with the intention of obtaining buy-in to the agreed schedule by all parties. This is designed to facilitate the production of an integrated project schedule which highlights the key constraints and major issues which impact successful execution. Alignment with key execution strategies is essential. The main tool is a time phased wall mounted bar chart which should be readily accessible to all parties involved in the project and can form the basis of the detailed schedules as well as recording key risks, assumptions and opportunities. TYPES OF SCHEDULE The Planner/Scheduler must produce documents that help co-ordinate, inform and optimize the schedule of a project. This can only be achieved if such documents are well thought out, agreed with the Project Manager and Discipline Leads and issued in a timely fashion. Each project should be examined and, along with the Project Manager, a determination made as to which types of schedules will be appropriate. The schedules to be utilized shall be stated in the Project Procedures. Upon receipt of instructions to proceed with the project, and prior to the first issue of the agreed Project Schedule, the project will be controlled with advanced 30 day or 60 day project initiation action list / Start Up Schedule to ensure that early activities are identified and acted upon to protect the overall schedule.
TYPES OF SCHEDULE The following types of schedules have been categorized for convenience: LEVEL 1 MAJOR MILESTONE SCHEDULES
MAJOR MILESTONE SCHEDULES Purpose Generally used to summarise the overall project performance for project management and client information purposes. LEVEL IV SCHEDULING STUDIES/LOOK-AHEADS ETC
Purpose To finitely manage aspects of the master schedule. To keep the discipline leads and field personnel informed of upcoming tasks. Typical Application On any project that has special scheduling needs defined by the Project Controls Manager in the Project Procedures. Every construction project that involves direct control of the labor. Contents Scheduling of individual deliverable, drawings, data sheets, specifications, line lists, requisitions, purchase orders, materials, process systems, RoS / Forecast On Site Delivery Dates etc. within the Level III activities etc. that may be necessary to properly manage the project. This activity should be done by the individual disciplines. Layout/Format As per the project needs. Two week look-aheads for field activities. Display summary information on project notice boards Timing/Frequency As required. Two week look-aheads are rolling every week and issued at least two working days before the first week and should be reviewed at the progress meeting as to their viability. AUDITS / RECORDS It is expected that, as part of the Quality System to maintain ISO accreditation, project will be audited against this procedure on an annual basis. Non conformances raised will be closed out by the project planner & planning manager. The planning manager may require specific audits more frequently. The project detailed schedule is a quality record. Baseline data, schedule updates, key changes to scope and methodology should all be recorded and kept within the filing and document record system for subsequent contract requirements, post project close out & reporting. The Project Close Out procedure requires an analysis of the key project parameters for subsequent use on further projects and cost & schedule database upkeep of metrics & benchmark data.
Typical Applications Proposals, at the planning stages of a major project, small studies, engineering projects with a low level of complexity, few activities and short duration, as a monthly summary of Level II and III schedules. Contents Schedule shall identify contract milestones, significant engineering, procurement, construction and operations milestones, other significant milestones and/or constraints. Normally restricted to one bar per discipline. LEVEL II INTERMEDIATE MILESTONE SCHEDULES
INTERMEDIATE MILESTONE SCHEDULES Purpose To inform groups of major constraints, due dates, manning levels, progress achievement, etc. and the critical path. Typical Applications Major proposals and studies, engineering projects with a medium level of complexity, small construction projects, contract payment milestones. Contents Schedule will be a further breakdown of Level 1 reflecting major activities for each phase i.e. engineering, procurement, construction and commissioning. Manpower histogram will indicate each phase manning requirement. Progress S Curve for each phase will indicate schedule % complete and actual % complete. LEVEL III DETAILED WORK SCHEDULES Purpose To inform all disciplines as to the status and progress of individual work packages, and of critical path issues. Typical Applications On all complex engineering-only projects and all EPC projects. Also on smaller projects where elements of the schedule are extremely critical and, hence, need to be managed at this level. Contents Schedule detailed into controllable and identifiable work activities which can be rolled-up to Level II. The schedule should identify key issue activities for deliverable types. The schedule will normally be generated from precedence logic network with critical path identified Typical Applications On all complex engineering-only projects and all EPC projects. Also on smaller projects where elements of the schedule are extremely critical and, hence, need to be managed at this level.
Contents Schedule detailed into controllable and identifiable work activities which can be rolled-up to Level II. The schedule should identify key issue activities for deliverable types. The schedule will normally be generated from precedence logic network with critical path identified, refer to Attachment 6.6 as typical which also includes a schedule risk analysis example. Layout/Format S Curves will be generated (per discipline) to monitor scheduled vs actual progress. Manpower histograms will be produced to identify individual
Manpower histogram discipline manning requirements. Summary WBS Report Document will be produced to provide an overview of the project status. It will contain original work-hour budget, unapproved change notices, approved change notices, current budget, work-hours expended, % achieved, productivity achieved, productivity to go, forecast work-hours to complete and forecast work-hours at completion, refer to Attachment 6.7 as typical of DD&E and Site Reports. Display summary information on project notice board Typical Analysis Typically at this level the schedule should be analysed for the top 5 critical paths and the current critical activities highlighted to the team. The logic and durations within these critical paths should be continually addressed to ensure schedule robustness. Forecast man hours / productivity to go and resourcing levels should be analysed for consistency Trend analysis on key parameters e.g. Material deliveries to site, pipe work productivity, schedule float usage etc Timing/Frequency Update continually. To be issued monthly by the 5th working day after the close-out date.