Академический Документы
Профессиональный Документы
Культура Документы
GARISPANDUAN MSMA
1. What is MSMA? 2. Video Presentation 3. MSMA Key Elements & Other DIDs guideline
1. 2. 3. 4. MSMA design criteria Minimum Stream Crossing Standards River and shore reserves- Sabah Water Resources Enactment 1998 Back Shore ACK SHORE DEVELOPMENT PROJECTS-Setback Limits
1 K 2
4
5
1
Flash Flood
2
Mud Flood
3
Polluted Rivers
For mixed developments, the highest of the applicable storm ARIs from the Table shall be adopted. In the case where designing to the higher ARI would be impractical, the selection of appropriate ARI should be adjusted to optimise the cost to benefit ratio or social factors. If justified, a lower ARI might be adopted for the major system, with consultation and approval from the Department of Irrigation and Drainage (DID).
Existing Condition
Rare Flood Major Flood Design 500 Yr 50 @ 100 Yr 2- 5 Yr
On-site Detention
Above-ground Storages
Below-ground Storages Combined Storages
Landscaped Areas Impervious Areas Flat Roofs Surface Tanks Underground Tanks Pipe Packages
Dry Basins Wet Basins Infiltration Trench Infiltration Well Soakaway Pits Porous Pavement Infiltration Basins
33
4. Openness: Openness ratio (cross sectional area/crossing length) should be at least 0.3 meter with minimum clearance height of 1 meter; 5. Substrate: Natural bottom substrate should be installed to match the existing upstream and downstream substrates. The design should counter the displacement effect occurred during floods while maintaining it during normal flow;
6. Depth and Velocity: At low flows, water depths and velocities should be the same as they are in natural areas upstream and downstream of the crossings;
7. Hydrology and Hydraulic: Governed by DID Hydrological Procedures (HP) or Manual Saliran Mesra Alam (MSMA), Chapter 13, 14 and 27;
8. Clearance Soffit level: Minimum clearance soffit level should be 100 years design flood plus 1 meter; 9. Temporary culverts: Governed by criteria 2 above with minimum 0.6 meter diameter and number of culverts should cover the entire width of bankfull discharge.
ii) 400 metres for muddy coast measured from the seaward edge of mangrove vegetation/forest. However, no development should be allowed in areas where mangrove vegetation/ forest have been gazetted as permanent forest reserve under the National Forestry Act 1984.
TERIMA KASIH