Вы находитесь на странице: 1из 13

Disclaimer: Slides provided as a courtesy. Preparation of final bid documents is ongoing.

Update on Status of Project


West 11th Road, West 12th Road, West 13th Road From Cross Bay Boulevard to Jamaica Bay
Broad Channel Area Borough of Queens, New York Project ID: HWQ1182A May 22, 2013

SCHEDULE
2012 JUL AUG SEP OCT NOV DEC 2013 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC 2014 JAN FEB MAR APR MAY NOTICE TO PROCEED 11/13/2013

ADVERTISE 6/30/2013 HURRICANE SANDY 10-28-12 DEP DRAINAGE PLAN 3/4/2013 PS&E 5/31/2013

Construction Duration: Estimated 3 Years

DEP WORK
New Storm Sewer Main New Water Main* New Sanitary Sewer Main* Sanitary and Storm Sewer on Mini-Piles*

LEGEND NEW WORK* ORIGINAL WORK

MINI-PILES

Disclaimer: Slides provided as a courtesy. Preparation of final bid documents is ongoing.

CONSENT LETTERS
TO DATE WE HAVE RECEIVED:
West 11th Road 42 signed letters; West 12th Road 43 signed letters; West 13th Road 26 signed letters.
LEGEND RECEIVED OUTSTANDING

STAGING
STAGE I STAGE II STAGE III STAGE IV CONSTRUCTION OF BULKHEAD/OUTFALL INSTALLATION OF MINI-PILES CONSTRUCTION OF STORM AND SANITARY SEWERS CONSTRUCTION OF CONCRETE HEADER, RETAINING WALLS, AND PROPERTY MITIGATION / IMPROVEMENTS (ZONE A) STAGE V CONSTRUCTION OF WATERMAIN/RETAINING WALL (ZONE B) STAGE VI CONSTRUCTION OF CONCRETE HEADER AND PRIVATE PROPERTY MITIGATION / IMPROVEMENTS (ZONE C) STAGE VII CONSTRUCTION OF CATCH BASINS AND CONNECTIONS STAGE VIII CONSTRUCTION OF ROADWAY ENTRANCE STAGE IX CONSTRUCTION OF BITUMINOUS WEARING COURSE STAGE X CONSTRUCTION OF PEDESTRIAN RAMP AND CROSSWALK - MALL

STAGING

STAGE II INSTALLATION OF MINI-PILES STAGE III CONSTRUCTION OF STORM AND SANITARY SEWERS

STAGE IV CONSTRUCTION OF CONCRETE HEADER, RETAINING WALLS, AND PROPERTY MITIGATION / IMPROVEMENTS (ZONE A)

Disclaimer: Slides provided as a courtesy. Preparation of final bid documents is ongoing.

STAGING

STAGE V CONSTRUCTION OF WATERMAIN/RETAINING WALL (ZONE B)

STAGE VI CONSTRUCTION OF CONCRETE HEADER AND PRIVATE PROPERTY MITIGATION / IMPROVEMENTS (ZONE C)

Disclaimer: Slides provided as a courtesy. Preparation of final bid documents is ongoing.

PARKING
TEMPORARY PARKING ALONG CROSSBAY BLVD SEVENTY FIVE (75) ADDITIONAL SPACES

LEGEND EXISTING PARKING TEMPORARY PROPOSED PARKING

WEST 10th ROAD TO WEST 14th ROAD

BUDGET
OVERALL BUDGET RESOURCES:
DOT
$26.33M $7.5 M for this project (HWQ1182A)

DEP
10.87M for this project (HWQ1182A)

DESIGN
Pull Over Zones at Fire Hydrants Shared Cross Section at a single elevation with Variations in pavement materials and patterns to highlight dominant uses

Bulkhead at End of Roadway

Distinctive Raised Entrance and Signage

DESIGN

QUESTIONS?