Академический Документы
Профессиональный Документы
Культура Документы
MODALIDAD:
PROPIETARIO:
PROCESO
CONTRATISTA
PLAZO:
INICIO DE OBRA:
TERMINO DE OBRA:
RESIDENTE:
SUPERVISOR:
INFORME N:
PERIODO DE TRABAJO
LOCALIDAD:
DISTRITO:
PROVINCIA:
REGION:
PRESUPUESTO
COSTO DIRECTO TOTAL :
1
23/01/2013 AL 28/02/2013
CASCAS
CASCAS
GRAN CHIMU
LA LIBERTAD
S/. 1,557,958.21
S/. 1,148,090.06
EMPRESA CONSTRUCTORA
VALORIZACION
31/12/10
DESCRIPCION
A:
B:
DESCUENTOS : (D)
AMORTIZACION DE ADELANTOS
ADELANTO DIRECTO
ADELANTO POR MATERIALES
AL
#REF!
#REF!
1.00 S/
#REF!
20.00%
40.00%
#REF!
#REF!
C:
#REF!
D:
MONTO NETO
#REF!
IGV (19%)
#REF!
E:
MONTO A FACTURAR
#REF!
F:
S/
S/
G:
#REF!
EMPRESA CONSTRUCTORA
PROPIETARIO
: "CONSTRUCCION DE PAVIMENTO RIGIDO Y VEREDAS AVENIDA 28 DE OCTUBRE, JR. PROGRESO, JR. BOLIVAR Y JR. LIMA,
EN EL DISTRITO DE CASCAS, PROVINCIA DE GRAN CHIMU - LA LIBERTAD
: MUNICIPALIDAD PROVINCIAL DE GRAN CHIMU INICIO DE OBRA
1/23/2013
CONTRATISTA
: CONSORCIO LIBERTAD
TERMINO DE OBRA
5/22/2013
MODALIDAD
PLAZO DE EJEC.
RESIDENTE DE OBRA
PRESUPUESTO ADJUDICADO
SUPERVISOR DE OBRA
PRESUPUESTO
S/IGV LIMITADA.
: EMPRESA COINSEC SAUCEDA EMPRESA INDIVIDUAL
DE RESPONSABILIDAD
PERIODO DE TRABAJO AL
: 23/01/2013 AL 28/02/2013
OBRA
MONTO
DESCRIPCION
A: VALORIZACION CONTRACTUAL
FORMULA 01 : GENERAL
#REF!
#REF!
#REF!
TOTAL (A)
FACTOR DE RELACIN
AVANCE FISICO DE OBRA MOC
TOTAL
B: MONTO NETO A PAGAR
EN EFECTIVO (VN-D)
VALORIZACION
CONTRATO
S/. 1,557,958.21
#REF!
S/. 1,148,090.06
% DE AVANCE
ACUMULADO
SALDO POR
VALORIZAR
(s/IGV)
ANTERIOR
ACTUAL
ACUMULADO
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
1.00
#REF!
#REF!
OBRA
PROPIETARIO
: "CONSTRUCCION DE PAVIMENTO RIGIDO Y VEREDAS AVENIDA 28 DE OCTUBRE, JR. PROGRESO, JR. BOLIVAR Y JR. LIMA, EN EL DISTRITO DE CASCAS, PROVINCIA DE GRAN CHIMU : MUNICIPALIDAD PROVINCIAL DE GRAN CHIMU
MODALIDAD
RESIDENTE
INSPECTOR
PERIODO
CODIGO
DESCRIPCION
PRESUPUESTO BASE
1,148,090.06
FORMULA 01 : GENERAL
1/23/2013
5/22/2013
120 DIAS CALENDARIO
S/. 1,557,958.21
S/. 1,148,090.06
VALORIZACION ANTERIOR
PARCIAL
PARTIDA
1.00
:
:
:
:
:
UBICACIN:
29.68%
PARCIAL
340,773.14
LOCALIDAD
DISTRITO
PROVINCIA
REGION
VALORIZACION ACTUAL
%
2.55%
PARCIAL
29,299.34
VALORIZACION ACUM.
%
32.23%
PARCIAL
370,072.48
: CASCAS
: CASCAS
: GRAN CHIMU
: LA LIBERTAD
PARCIAL
778,017.59
2.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
3.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
4.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
COSTO DIRECTO
#REF!
#REF!
1.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
RESUMEN EJECUTADO
Pgina 5
VALORIZACIN DE OBRA N 01
CONSORCIO LIBERTAD
FORMULA 01 : GENERAL
OBRA
PROPIETARIO
PROCESO
MODALIDAD
RESIDENTE
SUPERVISOR
PERIODO
: "CONSTRUCCION DE PAVIMENTO RIGIDO Y VEREDAS AVENIDA 28 DE OCTUBRE, JR. PROGRESO, JR. BOLIVAR Y JR. LIMA, EN EL DISTRITO DE CASCAS, PROVINCIA DE GRAN CHIMU - LA LIBERTAD
: MUNICIPALIDAD PROVINCIAL DE GRAN CHIMU
: ADP N 005-2012-MPGCH-PRIMERA CONVOCATORIA
INICIO DE OBRA
1/23/2013
: POR CONTRATA A SUMA ALZADA
:
TERMINO DE OBRA
5/22/2013
: ING. WILSON PORTALES ARIAS
:
PLAZO DE EJEC.
: EMPRESA COINSEC SAUCEDA EMPRESA INDIVIDUAL DE RESPONSABILIDAD LIMITADA.
:
120 DIAS CALENDARIO
TOTAL PRESUP.
S/. 1,557,958.21
: 23/01/2013 AL 28/02/2013
:
COSTO DIRECTO TOTAL
S/. 1,148,090.06
:
PRESUPUESTO BASE
METRADO
PARCIAL
CODIGO
DESCRIPCION
PARTIDA
UNID.
CANT.
P.U.
COSTO
UBICACIN:
LOCALIDAD
DISTRITO
PROVINCIA
REGION
VAL. ANTERIOR
METRADO
PARCIAL
: CASCAS
: CASCAS
: GRAN CHIMU
: LA LIBERTAD
VALORIZACION ACTUAL
%
METRADO
PARCIAL
VALORIZACION ACUM.
%
METRADO
PARCIAL
METRADO
PARCIAL
FORMULA 01 : GENERAL
01
01.01
970,528.06
OBRAS PROVICIONALES
13,833.77
01.01.01
gb
1.00
8,336.00
8,336.00
0.50
4,168.00
50.00%
0.25
2,084.00
25.00%
0.75
6,252.00
75.00%
0.25
2,084.00
25.00%
01.01.02
gb
1.00
1,860.43
1,860.43
0.25
465.11
25.00%
0.50
930.22
50.00%
0.75
1,395.32
75.00%
0.25
465.11
25.00%
01.01.03
1.00
2,458.90
2,458.90
1.00
2,458.90
100.00%
0.00
0.00%
1.00
2,458.90
100.00%
01.01.04
mes
4.00
294.61
1,178.44
1.00
294.61
25.00%
1.00
294.61
25.00%
2.00
589.22
50.00%
2.00
589.22
50.00%
m2
5,000.00
0.74
1,433.86
1,061.06
28.68%
3,000.00
2,220.00
60.00%
4,433.86
3,281.06
88.68%
566.14
418.94
11.32%
01.02
01.02.01
01.03
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
3,700.00
MOVIMIENTO DE TIERRAS
3,700.00
57,494.67
01.03.01
m3
2,243.82
8.76
19,655.86
713.05
6,246.32
31.78%
0.00%
713.05
6,246.32
31.78%
1,530.77
13,409.54
68.22%
01.03.02
294.25
10.58
3,113.17
44.38
469.54
15.08%
0.00%
44.38
469.54
15.08%
249.87
2,643.63
84.92%
01.03.03
m3
m3
132.08
77.06
10,178.08
132.08
10,178.08
100.00%
0.00%
132.08
10,178.08
100.00%
01.03.04
m3
66.46
78.56
5,221.10
01.03.05
m3
2,629.45
7.35
7,438.49
38.49%
0.00%
1,012.04
01.04
PAVIMENTO RIGIDO
19,326.46
1,012.04
66.46
5,221.10
100.00%
7,438.49
38.49%
1,617.41
11,887.97
61.51%
664,013.84
01.04.01
m2
5,000.00
3.38
16,900.00
1,433.86
4,846.45
28.68%
0.00%
1,433.86
4,846.45
28.68%
3,566.14
12,053.55
71.32%
01.04.02
m2
5,000.00
22.55
112,750.00
1,433.86
32,333.54
28.68%
0.00%
1,433.86
32,333.54
28.68%
3,566.14
80,416.46
71.32%
01.04.03
ENCOFRADO Y DESENCOFRADO
604.70
69.74
42,171.78
69.43
4,842.05
11.48%
0.00%
69.43
4,842.05
11.48%
535.27
37,329.73
88.52%
01.04.04
m2
m2
5,000.00
81.28
406,400.00
552.18
44,881.19
11.04%
0.00%
552.18
44,881.19
11.04%
4,447.82
361,518.81
88.96%
01.04.05
kg
807.84
9.64
7,787.58
121.13
1,167.69
14.99%
0.00%
121.13
1,167.69
14.99%
686.71
6,619.89
85.01%
01.04.06
5,000.00
8.02
40,100.00
552.18
4,428.48
11.04%
0.00%
552.18
4,428.48
11.04%
4,447.82
35,671.52
88.96%
01.04.07
m2
m
1,630.30
23.25
37,904.48
1,630.30
37,904.48
100.00%
01.05
CONSTRUCCION DE CANALETAS
01.05.01
ENCOFRADO Y DESENCOFRADO
m2
332.28
69.74
23,173.21
332.28
23,173.21
100.00%
01.05.02
m3
56.23
422.30
23,745.93
56.23
23,745.93
100.00%
01.06
46,919.14
184,566.64
01.06.01
m2
73.60
72.62
5,344.83
73.60
5,344.83
100.00%
0.00
01.06.02
m2
522.80
85.64
44,772.59
392.80
33,639.39
75.13%
130.00
01.06.03
422.30
55,777.38
132.08
55,777.38
100.00%
0.00
m3
m3
132.08
01.06.04
88.03
422.30
37,175.07
58.78
24,822.79
66.77%
29.25
01.06.05
kg
7,415.09
5.45
40,412.24
7,415.09
40,412.24
100.00%
0.00
01.06.06
57.00
17.94
1,022.58
42.00
753.48
73.68%
15.00
01.06.07
5.25
11.80
61.95
3.90
46.02
74.29%
1.35
501.01
370.75
02
02.01
02.01.01
02.02
CONSTRUCCION DE VEREDAS
0.00%
73.60
5,344.83
100.00%
24.87%
522.80
44,772.59
100.00%
0.00%
0.00%
132.08
55,777.38
100.00%
33.23%
88.03
37,175.07
100.00%
0.00%
0.00%
7,415.09
40,412.24
100.00%
269.10
26.32%
57.00
1,022.58
100.00%
0.00%
15.93
25.71%
5.25
61.95
100.00%
0.00%
30.92%
0.00%
501.01
370.75
30.92%
1,119.34
828.31
69.08%
12,352.28
177,562.00
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO
11,133.20
1,199.06
m2
1,620.35
0.74
MOVIMIENTO DE TIERRAS
1,199.06
10,276.85
02.02.01
2.73
4,423.56
501.01
1,367.76
30.92%
0.00%
501.01
1,367.76
30.92%
1,119.34
3,055.80
69.08%
m2
m2
1,620.35
02.02.02
1,620.35
2.69
4,358.74
501.01
1,347.72
30.92%
0.00%
501.01
1,347.72
30.92%
1,119.34
3,011.02
69.08%
02.02.03
m3
203.34
7.35
1,494.55
62.63
460.33
30.80%
0.00%
62.63
460.33
30.80%
140.71
1,034.22
69.20%
149719031.xlsx.ms_office
Pgina 6
VALORIZACIN DE OBRA N 01
CONSORCIO LIBERTAD
FORMULA 01 : GENERAL
OBRA
PROPIETARIO
PROCESO
MODALIDAD
RESIDENTE
SUPERVISOR
PERIODO
: "CONSTRUCCION DE PAVIMENTO RIGIDO Y VEREDAS AVENIDA 28 DE OCTUBRE, JR. PROGRESO, JR. BOLIVAR Y JR. LIMA, EN EL DISTRITO DE CASCAS, PROVINCIA DE GRAN CHIMU - LA LIBERTAD
: MUNICIPALIDAD PROVINCIAL DE GRAN CHIMU
: ADP N 005-2012-MPGCH-PRIMERA CONVOCATORIA
INICIO DE OBRA
1/23/2013
: POR CONTRATA A SUMA ALZADA
:
TERMINO DE OBRA
5/22/2013
: ING. WILSON PORTALES ARIAS
:
PLAZO DE EJEC.
: EMPRESA COINSEC SAUCEDA EMPRESA INDIVIDUAL DE RESPONSABILIDAD LIMITADA.
:
120 DIAS CALENDARIO
TOTAL PRESUP.
S/. 1,557,958.21
: 23/01/2013 AL 28/02/2013
:
COSTO DIRECTO TOTAL
S/. 1,148,090.06
:
PRESUPUESTO BASE
METRADO
PARCIAL
CODIGO
DESCRIPCION
PARTIDA
02.03
UNID.
CANT.
P.U.
CONCRETO SIMPLE
COSTO
UBICACIN:
LOCALIDAD
DISTRITO
PROVINCIA
REGION
VAL. ANTERIOR
METRADO
PARCIAL
: CASCAS
: CASCAS
: GRAN CHIMU
: LA LIBERTAD
VALORIZACION ACTUAL
%
METRADO
PARCIAL
VALORIZACION ACUM.
%
METRADO
PARCIAL
METRADO
PARCIAL
148,833.61
02.03.01
m2
1,620.35
9.68
15,684.99
501.01
4,849.78
30.92%
0.00%
501.01
4,849.78
30.92%
1,119.34
10,835.21
69.08%
02.03.02
m2
180.58
31.81
5,744.25
62.80
1,997.67
34.78%
0.00%
62.80
1,997.67
34.78%
117.78
3,746.58
65.22%
02.03.03
m2
1,620.35
68.11
110,362.04
501.01
34,123.79
30.92%
0.00%
501.01
34,123.79
30.92%
1,119.34
76,238.25
69.08%
02.03.04
m2
1,620.35
8.02
12,995.21
501.01
4,018.10
30.92%
0.00%
501.01
4,018.10
30.92%
1,119.34
8,977.11
69.08%
02.03.05
408.80
9.90
4,047.12
408.80
4,047.12
100.00%
02.04
VARIOS
0.00%
17,252.48
02.04.01
112.00
72.00
8,064.00
40.00
2,880.00
35.71%
0.00%
40.00
2,880.00
35.71%
72.00
5,184.00
64.29%
02.04.02
112.00
82.04
9,188.48
40.00
3,281.60
35.71%
0.00%
40.00
3,281.60
35.71%
72.00
5,906.88
64.29%
1,148,090.06
29.68%
COSTO DIRECTO
GASTOS GENERALES 10%
UTILIDADES 5%
TOTAL VALORIZADO
2.55%
29,299.34
32.23%
370,072.47
67.77%
778,017.59
10.00%
114,809.01
34,077.31
2,929.93
37,007.25
5.00%
57,404.50
17,038.66
1,464.97
18,503.62
38,900.87
1,320,303.57
391,889.11
33,694.24
425,583.34
894,720.23
340,773.14
18%
237,654.64
1,557,958.21
149719031.xlsx.ms_office
77,801.77
6,064.96
76,605.00
161,049.64
39,759.20
502,188.34
1,055,769.87
Pgina 7
CODIGO
DESCRIPCION
PARTIDA
01
01.01
01.01.01
01.01.02
01.01.03
01.01.04
01.02
01.02.01
01.03
01.03.01
01.03.02
01.03.03
01.03.04
01.03.05
01.04
01.04.01
01.04.02
01.04.03
01.04.04
01.04.05
01.04.06
01.04.07
01.05
01.05.01
01.05.02
01.06
01.06.01
01.06.02
01.06.03
01.06.04
01.06.05
01.06.06
01.06.07
02
02.01
02.01.01
02.02
02.02.01
02.02.02
02.02.03
02.03
02.03.01
02.03.02
02.03.03
02.03.04
02.03.05
02.04
02.04.01
02.04.02
METRADO TOTAL
UNID.
CANT.
METRADO ACTUAL
METRADO
METRADO ACUMULADO
METRADO
0.50
0.25
1.00
1.00
1,433.86
713.05
44.38
132.08
1,012.04
1,433.86
1,433.86
69.43
552.18
121.13
552.18
73.60
392.80
132.08
58.78
7,415.09
42.00
3.90
501.01
501.01
501.01
62.63
501.01
62.80
501.01
501.01
40.00
40.00
29.68%
10.00%
5.00%
18%
METRADO ACUMULADO
METRADO
PARCIAL
64.29% TRUE
64.29% TRUE
8,336.00
1,860.43
2,458.90
1,178.44
3,700.00
19,655.86
3,113.17
10,178.08
5,221.10
19,326.46
16,900.00
112,750.00
42,171.78
406,400.00
7,787.58
40,100.00
37,904.48
23,173.21
23,745.93
5,344.83
44,772.59
55,777.38
37,175.07
40,412.24
1,022.58
61.95
1,199.06
4,423.56
4,358.74
1,494.55
15,684.99
5,744.25
110,362.04
12,995.21
4,047.12
8,064.00
9,188.48
TRUE
#########
50.00%
25.00%
100.00%
25.00%
0.50
0.75
3.00
4,168.00
1,395.32
883.83
50.00%
75.00%
75.00%
28.68%
3,566.14
2,638.94
71.32% TRUE
31.78%
15.08%
100.00%
38.49%
1,530.77
249.87
66.46
1,617.41
13,409.54
2,643.63
5,221.10
11,887.97
68.22%
84.92%
100.00%
61.51%
TRUE
28.68%
28.68%
11.48%
11.04%
14.99%
11.04%
-
3,566.14
3,566.14
535.27
4,447.82
686.71
4,447.82
1,630.30
12,053.55
80,416.46
37,329.73
361,518.81
6,619.89
35,671.52
37,904.48
71.32%
71.32%
88.52%
88.96%
85.01%
88.96%
100.00%
TRUE
332.28
56.23
23,173.21
23,745.93
100.00%
75.13%
100.00%
66.77%
100.00%
73.68%
74.29%
130.00
29.25
15.00
1.35
11,133.20
12,352.28
269.10
15.93
30.92%
1,119.34
828.31
69.08% TRUE
30.92%
30.92%
30.80%
1,119.34
1,119.34
140.71
3,055.80
3,011.02
1,034.22
69.08% TRUE
69.08% TRUE
69.20% TRUE
30.92%
34.78%
30.92%
30.92%
-
1,119.34
117.78
1,119.34
1,119.34
408.80
10,835.21
3,746.58
76,238.25
8,977.11
4,047.12
35.71%
35.71%
72.00
72.00
70.32%
5,184.00
5,906.88
807,316.92
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
100.00% TRUE
100.00% TRUE
24.87%
33.23%
26.32%
25.71%
69.08%
65.22%
69.08%
69.08%
100.00%
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
TRUE
0.00%
100.00%
100.00%
100.00%
100.00%
100.00%
0.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
0.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
0.00%
0.00%
100.00%
100.00%
100.00%
0.00%
100.00%
100.00%
100.00%
100.00%
100.00%
0.00%
100.00%
0.00%
80,731.70
40,365.84
928,414.46
0.00
928,414.46
TRUE
TRUE
TRUE
TRUE
TRUE
114,809.01
57,404.50
#########
#########