CV. POLA
REKAYASA UTAMA

PT. ARSARI
PADI PRATAMA

MODERN RICE MILLING PROJECT

Discipline Code:
CAL
Contract Job No.:
028-IPRO

Doc. No.:
00014

Doc. Title:

Foundation Calculation Utility Building of


Office & Laboratory
Page 1 of 11

FOUNDATION CALCULATION UTILITY BUILDING


OF OFFICE & LABORATORY

KONSULTAN
Rev
0

DESCRIPTION
First Issued

STATUS

OWNER

DATE

BY

CHKD

APVD

05-July-13

MS

EV

ARF

DATE

APVD

DOC. NO. : 00014

FOUNDATION CALCULATION UTILITY BUILDING


OF OFFICE & LABORATORY

REV
0

REVISION HISTORICAL SHEET


Rev No

Date

Description

ISSUED FOR REVIEW

ISSUED FOR APPROVAL

DOC. NO. : 00014

FOUNDATION CALCULATION UTILITY BUILDING


OF OFFICE & LABORATORY

REV
0

FOUNDATION PC1

Foundation of Mess/Apartement Building

Foundation Scheme

Information:
Pilecap width
Pilecap thickness
Pilecap depth
Pedestal

(B)
(T)
(D)
(C)
F
H
pile

=
=
=
=
=
=
=

0.80
0.60
1.30
0.25
0.50
1.80
5.00

m
m
m
m
m
m
m

DOC. NO. : 00014

FOUNDATION CALCULATION UTILITY BUILDING


OF OFFICE & LABORATORY

REV
0

1. LOAD PLANNING :
Pressure Force
Lateral Force

11.38
1.76

<.OK
<.OK

Ton
Ton

2. STRENGTH CAPACITY BORED PILE:


Pcompr. =

12.0

ton

Lateral Strength Capacity Single Bored Pile:


Hall =

( k..a ) /

Inform :

Ha =
k =

Allowable Horizontal Strength Capacity (kg)


Reaction coeff. of soil layers below
the surface in the lateral direct. (Kg/cm3)
= Pile Diameter (cm)
a = Nominal of Normal Friction (cm)

= 4
( k.)/4EI
E = Modulus elasticity pile (Kg/cm2)
I = Moment Inersia (cm4)
I =

125600

cm4

fc'=
Ec =
k =
a =
=

249
234530
0.13

kg/cm2
kg/cm2
kg/cm3

Hall =
=
=

1.00
0.00256

cm

( k.. a ) /
1965.5 Kg
1.965
Ton

3. PILE CAP CALCULATION


C

REV

DOC. NO. : 00014

FOUNDATION CALCULATION UTILITY BUILDING


OF OFFICE & LABORATORY

Foundation width (B) =


Foundation thickness (T) =
Effective thickness (d) =
=
=
Pedestal (C) =

0.80 m
0.60 m
T - (concrete layer T= 5cm)
0.55 m
55 cm
25 cm

Pons Friction Analysis:


2-way concrete friction :

vc

fc'1/2
1.663

MPa

16.63

Kg/cm2

1/
3

Pons Friction Area =

4*(C+d)*d

17600

Concrete strength friction :


Vc =

vc

tot

=
=

cm2

*4*(C+d)*d
292746 Kg

Pressure Force + Weigth of Pedestal


11.56 Ton

Pu = 1.3* Ptot =
=
Requirements
:
Pu =

15.03
15028

Pu < Vc
Pu < 0.75Vc
15028 kg

Ton
kg

<

Vc

219560

Kg

(OK)

Pile cap reinforcement:


=

11.56

Pile cap area (A) =

0.60

tot

qmax =

Load factor = 1.3

Ptot/A =

Ton
m2
19.32

qu =
qu =

Ton/m2

1.3*qmax * B
20.09

Ton/m

DOC. NO. : 00014

FOUNDATION CALCULATION UTILITY BUILDING


OF OFFICE & LABORATORY

Mu =
Mu =

-1/2C)2
Ton.m =

REV
0

1/ *q *(1/ B
2
u
2

0.76

75964.65

Kg.cm

Mu = Asfy (d-1/2a)
, in case

Mu =0.8 Asfy (d-1/2a)

a=

Asfy/0.85fc'b

Mu =0.8 Asfy (d-(Asfy/1.7fc'b))


As =Mu /{0.8fy (d-(Asfy/1.7fc'b))}
As =
As

min

0.43

min*B*d
min = 0.002
2
8.80
cm

=
=

As

cm2

perlu

cm2
8.80
(5 D16 - 150 )

Reinforcement used :

16

3. BORED PILE CALCULATION


Pressure (P

1 bored pile)

=
=

(Pressure Force + concrete weight) / 3


4.18 ton

Pu = 1.3* P =

5.43

Ton

Main Reinforcement:

D =
Ag =
=
=

0.40

1/
4
D2

0.1256

m2

1256

cm2

Asmin =

1%* Ag

Asmin =

12.56

cm2

DOC. NO. : 00014

FOUNDATION CALCULATION UTILITY BUILDING


OF OFFICE & LABORATORY

REV
0

- Pressure effect:
Pu =
5.43
Ton
Pu = 0.8*(0.85fc'*(Ag-As) + As*fy)
{Pu/(0.65*0.8)}-0.85fc'Ag
fy - 0.85fc'

As =
As1 =

As

As

need

=
(

12.56
7 D16

-67.41

need

cm2

= Max ( As

cm2
)

min,

As1, As2)

Reinforcement used :

16

Coss bar Reinforcement:

Lateral (H

1 bored pile)

Vu = 1.3* pressure =
Vc =
=
Vs =
=

smin <
<

0.76

0.59

Ton

Ton

1/
6

fc'1/2 bd
11.64
Ton

Vu/ - Vc
-10.63

, = 0.75

Ton

8 mm

Try :

smin <
<

Av*fys

(Minimum coss bar)


Av = 2.1/4. 2

1.00

cm2

/3b

20.10

D
20.00

cm

1/
2

cm

Coss bar used :

-200

DOC. NO. : 00014

FOUNDATION CALCULATION UTILITY BUILDING


OF OFFICE & LABORATORY

REV
0

LAMPIRAN

REV

DOC. NO. : 00014

FOUNDATION CALCULATION UTILITY BUILDING


OF OFFICE & LABORATORY

JOINT REACTION
Node

L/C

1
2
3
4
5
6
19
20
21
22
23
24
114
115
116
117
125
126
127
128
129
130
137
138
139
140
141
142
143
151
152
153
154
155
156
157
188
189

COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20
COMB 20

Horizontal
Fx kN
0.907
-0.174
-2.391
0.507
-0.555
-1.773
1.966
17.6
-15.348
0.352
-0.677
-1.924
0.646
1.183
-0.587
0.075
-1.64
-0.289
1.883
-1.558
0.368
1.166
0.626
0.768
-1.462
2.154
-0.734
-0.52
-2.944
1.015
-0.16
0.647
1.58
-2.373
0.348
1.298
-2.172
2.19

Vertical
Fy kN
29.984
55.142
54.586
55.934
44.417
41.782
32.333
113.801
112.108
60.215
40.742
41.288
38.893
35.622
42.611
36.048
52.423
25.951
45.87
43.697
53.763
51.207
40.986
41.307
44.102
52.335
61.041
47.954
46.025
42.799
40.691
39.186
44.719
39.604
51.846
51.151
61.427
61.444

Horizontal
Fz kN
1.079
0.729
2.306
1.496
3.169
2.032
-1.314
-0.925
-1.332
-1.675
-1.376
-1.643
-0.334
0.849
1.21
1.42
-0.93
0.358
-0.995
-1.315
0.101
-1.518
1.628
0.815
1.468
-2.38
-2.841
-0.884
0.343
-0.863
0.078
1.126
0.976
1.267
1.626
1.637
-2.697
-2.69

Mx kNm
0.456
0.685
1.588
2.351
1.439
1.033
-0.297
0.299
0.514
-0.599
-0.032
-0.156
-0.041
0.367
0.839
0.98
-1.468
0.723
-1.497
0.366
0.663
-2.459
1.112
1.59
0.558
0.297
-0.192
0.102
0.367
-1.377
0.19
2.01
1.919
1.164
3.237
2.987
-4.759
-4.737

Moment
My kNm
-0.01
-0.068
0.02
0.029
-0.008
0
0.001
-0.301
0.43
-0.07
0.129
-0.017
0.066
-0.016
-0.032
-0.001
0.033
-0.037
0.043
-0.036
0.007
0.064
-0.034
0.004
-0.099
-0.029
-0.003
0.008
-0.004
-0.022
-0.008
-0.006
-0.067
-0.058
-0.049
-0.077
-0.003
-0.003

Mz kNm
0.002
0.396
0.01
0.416
-0.009
0.308
-1.054
-3.706
2.676
0.497
0.37
0.607
-0.551
-2.126
-0.517
-0.203
-0.629
0.064
-0.794
0.57
0.256
-0.291
-0.2
-0.251
0.12
-0.746
-0.199
-0.315
5.091
-0.96
0.05
-0.217
-0.458
0.52
-0.181
-0.424
0.4
-0.426

REV

DOC. NO. : 00014

FOUNDATION CALCULATION UTILITY BUILDING


OF OFFICE & LABORATORY

PERHITUNGAN DAYA DUKUNG TIANG BOR


S-4

S-7

DEPTH

qc

fs

Qs

DEPTH

qc

fs

Qs

kg/cm2

kg/cm2

kN

kg/cm2

kg/cm2

kN

0.2

2.00

0.10

12.31

0.2

2.00

0.10

12.31

0.4

3.00

0.15

18.46

0.4

3.00

0.15

18.46

0.6

2.00

0.10

12.31

0.6

8.00

0.40

49.24

0.8

5.00

0.25

30.77

0.8

8.00

0.40

49.24

5.00

0.25

30.77

6.00

0.30

36.93

1.2

4.00

0.20

24.62

1.2

3.00

0.15

18.46

1.4

5.00

0.25

30.77

1.4

2.00

0.10

12.31

1.6

5.00

0.25

30.77

1.6

2.00

0.10

12.31

1.8

4.00

0.20

24.62

1.8

2.00

0.10

12.31

4.00

0.20

24.62

4.00

0.20

24.62

2.2

2.00

0.10

12.31

2.2

4.00

0.20

24.62

2.4

4.00

0.20

24.62

2.4

2.00

0.10

12.31

2.6

10.00

0.50

61.54

2.6

4.00

0.20

24.62

2.8

5.00

0.25

30.77

2.8

2.00

0.10

12.31

4.00

0.20

24.62

3.00

0.15

18.46

3.2

2.00

0.10

12.31

3.2

4.00

0.20

24.62

3.4

2.00

0.10

12.31

3.4

5.00

0.25

30.77

3.6

5.00

0.25

30.77

3.6

7.00

0.35

43.08

3.8

4.00

0.20

24.62

3.8

6.00

0.30

36.93

4.00

0.20

24.62

4.00

0.20

24.62

4.2

3.00

0.15

18.46

4.2

8.00

0.40

49.24

4.4

3.00

0.15

18.46

4.4

8.00

0.40

49.24

4.6

2.00

0.10

12.31

4.6

7.00

0.35

43.08

4.8

4.00

0.20

24.62

4.8

9.00

0.45

55.39

2.00

0.10

12.31

9.00

0.45

55.39

5.2

5.00

0.25

30.77

5.2

8.00

0.40

49.24

5.4

4.00

0.20

24.62

5.4

6.00

0.30

36.93

5.6

3.00

0.15

18.46

5.6

7.00

0.35

43.08

5.8

4.00

0.20

24.62

5.8

8.00

0.40

49.24

2.00

0.10

12.31

4.00

0.20

24.62

Qs =

535.43

Qs =

596.98

DOC. NO. : 00014

FOUNDATION CALCULATION UTILITY BUILDING


OF OFFICE & LABORATORY

REV
0

Analisa Daya Dukung Tiang Bor


Bore Pile diameter 40 cm
D=
0.4 m
Ab =
0.1256 m2
O=
1.256 m
L=
5 m
As =

6.3

m2

Qu = Qb + Qs
= Ab. qc + As. fs

qc =
Qb =
Fs1 =
Fs2 =

294.00
36.9
3
5

kN/m2
kN

Qba =
Qsa =
Qa =

12.31
107.1
119.4

kN
kN
kN

Qa rata2=
Qa =

qc =
Qb =
Fs1 =
Fs2 =

784.00
98.5
3
5

kN/m2
kN

Qba =
Qsa =
Qa =

32.82
119.4
152.2

kN
kN
kN

135.8 kN
120 kN

10