Certificate of

Making Good
Issued by: address: Employer: address: Job reference: Certificate no: Issue date:

Contractor: address: Works: situated at: Contract dated: Under the terms of the above-mentioned Contract, I/we hereby certify that any defects, shrinkages or other faults specified in a schedule of defects delivered to the Contractor as an instruction and any other defect, shrinkage or fault which has appeared within the Rectification Period and has been required by an instruction to be made good
*Delete if not applicable

* the Works referred to in the Practical Completion Certificate


no. ______________ dated ___________________________

* Section no. ___________ of the Works referred to in the


Sectional Completion Certificate no. ______________ dated ___________________________

* the part of the Works identified in the


Statement of Partial Possession by the Employer no. ______________ dated ___________________________ Have in my/our opinion been made good on

On ______________________________________ 20______________

To be signed by or for the issuer named above

Signed_____________________________________

Meena Projects/Standard Documents/182526671.doc

Distribution

Employer Contractor Quantity Surveyor

Structural Engineer M&E Consultant File