Football Stadium

Haley Tran, Swati Arora, Pedro Garcia, Jason Didier, Kelsey Blair

Executive summery
Plano High School along with Plano Independence School District has build a large stadium to accommodate its growing population. The Stadium has a budget of 25 million and can hold maximum 20,000 people along with a large parking area.

Key Deliverables and milestones


The building plan must be completed by July 15th 2014. The site prep must be completed by September 15th 2014. The build must be completed by April 30th 2015. The stadium will be ready to open on May 30th 2014.

Stadium Budget: 25 million


Contengency budget Plumbing Management Reserve Electrical Architecture Payroll Engineering Miscellaneous Construction Technology

8%

8% 4%

12%

4% 4%

20% 28%

8% 4%

Timeline
The Project has one year to complete.

Scope and Resources


Scope
Design of stadium Construction od stadium and all features Plumbing Electrical engineering Playing field
Human resources Equipment Funding Capital Materials

Resources

Assumptions
10% staff will be absent at one point Staff working hours will be from 6a-3p, second shift will be from 6pm to 2am and weekend All equipment will be working properly and delivered on time All Key deliverables and milestones will be met on schedule No government restrictions will change the scope All resources will be readily available

Project Schedule

Project Schedule

Design

Features
Use of concrete material Standard sized field Equipped with electricity and lights Commentator box Two VIP boxes, one on each side Concession areas Two men and women restrooms Bleachers Artificial turf

Issues and Challenges


Weather
Tarps were kept on hand incase of rain Built runoffs so it would not flood during construction

Construction safety issues


Fenced off construction areas More dangerous constructions were done mostly on weekends and nights Noises were kept down during certain school hours Equipment was kept out of students reach. Background checks for all construction workers and maintenance Construction site will be heavily lit at night to avoid accidents