BATTERIES AND CHARGERS

WHAT IS A BATTERY?

BATTERY IS AN ELECTROCHEMICAL DEVICE WHICH STORES CHEMICAL ENERGY AND RELEASES THE ELECTRICAL ENERGY PARTS OF BATTERY GRIDS ELECTRICALLY CONDUCTING FRAME WORK POSITIVE PLATE LEAD PEROXIDE ACTIVE MATERIAL NEGATIVE PLATE POROUS MASS OF LEAD IN SPONGY FORM SEPERATORS NON CONDUCTING POROUS MATERIAL PLACED BETWEEN POSITIVE AND NEGATIVE PLATE TO AVOID THE TOUCHING EACH OTHER ELECTROLITE H2SO4( SULPHURIC ACID )

WHY BATTERIES ARE USED..

STATION LT SUPPLY SHOULD BE ALLWAYS AVAILABLE TO KEEP THE PROTECTION SYSTEM IN ENERGISED CONDITION BUT UNFORTUNATELY THE LT SYSTEM IS NOT RELIABLE.HENCE A BACK UP OF DG SET IS KEPT IN ALL STATION, BUT TO START THE DG SET IT REQUIRES SOME TIME, DURING THAT TIME BATTERIES PROVIDES THE LOAD TO THE PROTECTION SYSTEM .THAT IS THE REASON PROTECTION SYSTEM IS ALWAYS DESIGNED FOR DC. BATTERIES CAN PROVIDE THE SUPPLY TO THE STATION PROTECTION SYSTEM UPTO 10-15 HOURS DEPENDING ON THE LOAD.

WHY BATTERIES ARE USED..

APART FROM THE PROTECTION SYSTEM THE MONITORING AND RECORDING SYSTEM LIKE ANNUNCIATION , EVENT LOGGER , DISTURBENCE RECORDER ,GPS ,RTU, SPEECH AND PROTECTION COUPLER OF PLCC ARE ALSO CONNECTED TO THE BATTERY SYSTEM FOR RELIABILITY

RANGES OF BATTERY SYSTEM AND CONNECTIVITY

THERE ARE BASICALLY TWO RANGES OF BATTERY SYSTEM AVAILABLE IN SUB-STATION 1. 220 VOLTS 2. 5O VOLTS

220 VOLTS BATTERIES

220V BATTERY SYSTEM IS BASICALLY THE SERIES CONNECTION OF 110 NOS OF 2.1V LEAD ACID BATTERIES EACH CAPACITY OF 400 AH IN EVERY SUB-STATION TWO SETS OF BATTERIES ARE KEPT FOR MORE RELIABILITY EACH SET IS CONNECTED WITH SEPARATE BATTERY CHARGERS THESE SETS ARE USED FOR STATION PROTECTION SYSTEM , DISTURBANCE RECORDER AND ANNUNCIATION SYSTEM

50 V BATTERIES SYSTEM

50V BATTERY SYSTEM IS BASICALLY THE SERIES CONNECTION OF 24 NOS OF 2.1V LEAD ACID BATTERIES EACH CAPACITY OF 400 AH IN EVERY SUB-STATION TWO SETS OF BATTERIES ARE KEPT FOR MORE RELIABILITY EACH SET IS CONNECTED WITH SEPARATE BATTERY CHARGERS THESE SETS ARE NORMALLY USED FOR PLCC SPEECH AND PROTECTION COUPLER AND MONITORING SYSTEM SUCH AS EVENT LOGGER AND GPS

BATTERY CHARGERS

BATTERY CHARGERS CONSISTS OF FLOAT CHARGER BOOST CHARGER STAND-BY CHARGER DCDB

FLOAT CHARGER

FLOAT CHARGER IS BASICALLY DESIGNED FOR CONSTANT VOLTAGE OPERATION . VOLTAGE CAN BE SET BETWEEN 200-250V FOR 220V CHARGER AND 45-55V FOR 50V CHARGER IT IS CONNECTED IN PARALLEL TO THE BATTERY SYSTEM AND TO THE LOAD IT KEEPS THE BATTERIES UNDER CHARGED CONDITION

BOOST CHARGER

BOOST CHARGER IS GENERALLY SAME AS THE FLOAT CHARGER EXCEPT THAT OUTPUT IS SET BETWEEN 200-300V FOR 220V AND BETWEEN 45-60V FOR 50V IT IS SWITCHED ON DURING INITIAL CHARGING , WHEN BATTERIES ARE DRAINED OUT AND DURING TOPPING UP OF BATTERIES WITH DISTILLED WATER

STAND BY CHARGER

IT IS ALSO SAME AS FLOAT CHARGER EXCEPT THE FOLLOWING CHANGES IF THE MAIN FLOATS ARE ON THE STAND-BY CANNOT BE SWITCHED ON WHEN ANY ONE FLOAT CHARGER FAILS / TAKEN OUT FOR MAINTENANCE STAND-BY CAN BE TAKEN INTO SERVICE

DC DISTRIBUTION BOARD

IT IS A DISTRIBUTION BOARD FROM WHERE LOADS ARE CONNECTED SEPARATE DCDB IS AVAILABLE FOR EACH SET OF BATTERIES. COUPLING FACILITIES IS AVAILABLE

MAINTENANCE OF BATTERIES AND CHARGERS

DAILY MONITORING OF SPECIFIC GRAVITY , TEMPERATURE AND VOLTAGE OF CELLS LIMITS FOR SPECIFIC GRAVITY -1.2100.005 VOLTAGES-2.17V TEMPERATURE-27C

MAINTENANCE OF BATTERIES AND CHARGERS

MONTHLY MAINTENANCE
CHECKING OF ELECTROLYTE LEVEL AND TOPPING UP WITH DISTELLED WATER IF REQUITED CHECKING OF EMERGENCY DC LIGHTING IN CONTROL ROOM NOTE THE TOTAL BATTERY VOLTAGE ( SWITCH OFF THE CHARGER) MEASURE THE CELL VOLTAGE AND SPECIFIC GRAVITYOF ALL CELLS. CHECK THE ANY EARTH FAULT IN DC SYSTEM

MAINTENANCE OF BATTERIES AND CHARGERS

HALF YEARLY MAINTENANCE- S/D ACTIVITY


CHECKING OF CHARGER PANEL/ DCDB FORELECTRICAL CONNECTION TIGHTNESS AND CLEANLINESS

MAINTENANCE OF BATTERIES AND CHARGERS

YEARLY MAINTENANCE- S/D ACTIVITY


CHECKING OF CONTROL CARDS OF CHARGER MEASUREMENT OF TEST POINT VOLTAGES TESTING OF D.C E/F & UNDER VOLTAGE RELAYS IR MEASUREMENT OF CHARGER TRANSFORMERS BATTERY IMPEDANCE TEST CHECKING & CLEANING OF BATTERY CELL TERMINAL AND APPLICATION OF PETROLEUM GELLY, IF REQUIRED

MAINTENANCE OF BATTERIES AND CHARGERS

BATTERY IMPEDANCE TEST


CONNECT THE BATTERY IMPEDANCE TEST KIT TO THE BATTERY BANK . SELECT THE RANGE OF VOLTAGE UNDER TEST. ENSURE THAT TESTING INSTRUMENT IS EARTHED PROPERLY. SWITCH ON THE AC SUPPLY TO THE BATTERY IMPEDANCE TEST KIT AND READY LAMP WILL GLOW.

MAINTENANCE OF BATTERIES AND CHARGERS


WHEN THE BATTERY IMPEDANCE KIT IS ENERGISED TAKE THE MEASUREMENT OF TOTAL AC CURRENT USING CLAMP ON CURRENT PROBE( I) AND MEASURE THE CORRESPONDING VOLTAGE DROP ACROSS THE BATTERY CELL(Vb) . MEASURE AND RECORD THE TEMPARATURE.AND SPECIFIC GRAVITY OF CORRESPONDING CELL. THE INTERNAL IMPEDANCE (Z) OF THE CELL IS DETERMINED BY THE FORMULA Z=VB/I

MAINTENANCE OF BATTERIES AND CHARGERS

3 YEARLY MAINTENANCE S/D ACTIVITY


DISCHARGE TEST OF BATTERY SETS( CAPACITY TEST) PROCEDURE
SHIFT THE CONNECTED LOAD FROM THE BATTERY BANK IN WHICH TEST TO BE CARRIED OUT TO THE STAND BY BATTERY BANK DISCONNECT THE CHARGER FROM THE BATTERY CONNECT THE LOAD ( A VARIBLE RESITER BANK) TO THE BATTERY THROUGH A SWITCH SWITCH ON AND NOTE THE TIME( Tb) AND RECORD THE TERMINAL VOLTAGE AND INDIVIDUAL CELL VOLTAGES.

MAINTENANCE OF BATTERIES AND CHARGERS


MAINTAIN THE CONSTANT DISCHARGE CURRENT( Id) BY ADJUSTING THE LOAD SUCH THAT BATTRY BANK IS DISCHARGED AT 10% OF BATTERY CAPACITY RECORD THE INDIVIDUAL CELL VOLTAGE, BATTERY TERMINAL VOLTAGE AND SPECIFIC GRAVITY OF CELL IN ONE INTERVALS

MAINTENANCE OF BATTERIES AND CHARGERS

DISCHARGE CAN BE STOPPED WHEN THE VOLTAGE ACROSS THE BATTERY BANK FALLS TO 1.85 X NUMBER OF CELLS OR VOLTAGE ACROSS ANY ONE CELL FALLS TO 1.70 V NOTE DOWN THE STIP TIME (Ts) DISCHARGE TIME (Td) = (Ts)-(Tb) FORMULA OF % CAPACITY OF BATTERY BANK =(Id) X (Td) ------------ X 100 AH

MAINTENANCE OF BATTERIES AND CHARGERS

RECHARGING
RECONNECT THE BATTERY TO CHARGER RECHARGE THE BATTERY BANK AT CONSTANT NORMAL RE-CHARGE CURRENT OF 10% OF CAPACITY RECORD THE INDIVIDUAL CELL VOLTAGE, BATTERY TERMINAL VOLTAGE AND SPECIFIC GRAVITY OF CELL IN ONE INTERVALS CONTINUE CHARGING TILL THE VOLTAGE OF EACH CELL REACHES 2.55 V TO 2.65 V AND SPECIFIC GRAVITY REACHES TO 1.2100.005. STOP THE RECHARGING OPERATION

MAINTENANCE OF BATTERIES AND CHARGERS

GENERAL SAFETY INSTRUCTIONS


EQUIPMENTS REQUIRED IN BATTERY ROOM 1.HYDROMETER 2. VOLT METER GOLLLES & FACE SHIELDS ACID RESISTANCE GLOVES PROTECTIVE APRON GUM BOOTS PORTABLE OR STATIONERY WATER FACILITY

MAINTENANCE OF BATTERIES AND CHARGERS

GENERAL SAFETY INSTRUCTIONS


ELECTROLYTE SHOULD BE STORED SEPARATELY AS TO AVOID DAMAGE OF OTHER STORE ITEMS IN CASE OF SPILLAGE WHILE WORKING ON ACID, USE PROTECTIVE GOGGLES, RUBBER GLOVES,APRONS & GUM BOOTS BATTERY TERMINALS CONNECTIONS SHOULD BE KEPT CLEAN AND TIGHT TO AVOID SPARKS USE TOOLS WITH INSULATED HANDLE

DIESEL GENERATOR SET

DIESEL GENERATOR SET

GENERATOR IS A MACHINE WHICH CONVERT THE MECHANICAL ENERGY IN TO ELECTRICAL ENERGY GENERATOR IS BASED ON PRINCIPAL THAT WHENEVER FLUX CUT BY CONDUCTOR , AN EMF IS INDUCED WHICH WILL CAUSE A CURRENT TO FLOW IF THE CONDUCTOR CIRCUIT IS CLOSED.

DIESEL GENERATOR SET

WHEN THE LT SUPPLY IS NOT AVAILABLE D.G SET WILL BE TAKEN IN TO SERVICE TO FEED THE A.C SUPPLY TO THE SYSTEM. IF LT SUPPLY FAILED AND D.G SET FAILED TO START, SUPPLY WILL NOT BE AVAILABLE FOR BREAKER COMPRESSORS TO BUILD UP THE REQUIRED AIR PRESSURE FOR CIRCUIT BREAKERS, A.C PLANT TO KEEP THE PROTECTION RELAYS, PLCC PROTECTION SYSTEM UNDER DESIRED TEMPARATURE F/F SYSTEM TO PUMP THE WATER AT PRESSURE WHEN IS FIRE IS TAKEN PLACE BATTERY CHARGERS WILL NOT FEED THE LOAD TO SYSTEM AND AS WELL AS TO BATTERIES. HENCE BATTERIES GET DISCHARGED. FAN AND PUMPS OF ICTS WILL NOT RUN HENCE THE WINDING AND OIL TEMPARATURE RAISES. TO OVER COME THE ABOVE PROBLEMS D.G SETSHOULD BE KEPT UNDER HEALTHY CONDTION.

DIESEL GENERATOR SET

CHECKS BEFORE STARTING


CHECK THE ENGINE OIL LEVEL CHECKTHE FUEL SUPPLY CHECK THE HEALTHYNESS OF CONTROL PANEL CHECK AIR CLEANER CHECK THE COOLENT LEVEL CHECK THE LEAKS CHECK STARTING BATTERIES VOLTAGE AND SPECIFIC GRAVITY

DIESEL GENERATOR SET

STARTING PROCEDURE
START THE GENERATOR AT MINIMUM SPEED. WAIT FOR FEW MINUTES AND SLOWLY INCREASE THE SPEED UP TO 1500 RPM. CHECK THE VOLTAGE AND FREQUENCY AND ADJUST GOVERNER IF REQUIRED. CLOSE THE D.G. BREAKER AND CONNECT THE LOADS STEP BY STEP CHECK THE VOLTAGE, CURRENT, AND FREQUENCY. RECORD THE OIL/WATER TEMPARATURE, RUNNING HOURS,FUEL LEVEL ETC.ONCE IN EVERY TWO HOURS.

STOPPING PROCEDURE
REDUCE THE LOADS STEP BY STEP WAIT FOR FEW MINUTES AND BRING THE D.G.SET TO THE MINIMUM SPEED STOP THE D.G SET. RECORD THE FUEL LEVEL AND RUNNING HOURS.

D. G. SET

MAINTENANCE OF D.G.SETS
PREVENTIVE MAINTENANCE IS THE EASIEST AND LEAST EXPENSIVE TYPE OF MAINTENANCE.

MAINTENANCE SCHEDULE
A CHECKS B CHECK C CHECK D CHECK E CHECK

MAINTENANCE OF D.G.SETS

A CHECKS ( DAILY)
CHECK THE ENGINE OIL LEVEL DRAIN THE SEDIMENT FROM FUEL TANK CHECKTHE FUEL SUPPLY CHECK AIR CLEANER CHECK THE COOLENT LEVEL CHECK THE LEAKS CHECK STARTING BATTERIES

MAINTENANCE OF D.G.SETS

B CHECKS ( 3 MONTHS OR 200HRS)


1. REPEAT CHECK A AND 2. CHANGE ENGINE OIL & CHANGE ENGINE OIL FILTERS a) BRING ENGINE TO OPERATING TEMPARATURE AND SHUTDOWN ENGINE, REMOVE DRAIN PLUG FROM BOTTOM OF OIL PAN AND DRAIN OIL. b) INSTALL DRAIN PLUG IN OIL PAN FILL THE OIL IN CRANK CASE UP TO H ( HIGH LEVEL) MARK ON DIP STICK C) START ENGINE VISUALLY CHECK FOR OIL LEAKS d) SHUTDOWN THE ENGINE AND ALLOW 15 MINUTES FOR OIL TO DRAIN TO BACK IN TO OIL PAN. RECHECK OIL WITH DIPSTICK. ADD OIL AS REQUIRED.

MAINTENANCE OF D.G.SETS

B CHECKS ( 3 MONTHS OR 200HRS)


RECORD OIL PRESSURE CLEAN FUEL TANK CLEAN CRANKCASE BREATHER CHANGE WATER FILTER CHECK /ADJUST BELTS RECORD WATER TEMPARATURE

MAINTENANCE OF D.G.SETS

C CHECKS ( 1 YEAR OR 800HRS)


REPEAT A AND B CHECKS CHANGE FUEL FILTERS CHECK THE VENT PIPING & CLEAN OIL BATH AIR CLEANER ADJUST INJECTORS AND VALVES FOR ENGINE TO OPERATE PROPERLY. INJECTOR CONTROLS THE ENGINE BREATHING AND VALVES CONTROLS THE FUEL DELIVERY TO THE CYLINDERS. CHECK THE WATER PUMP CHECK THE VIBRATIONS

MAINTENANCE OF D.G.SETS

D CHECKS ( 2 YEAR OR 1600HRS)


REPEAT A,B,C CHECKS AND CLEAN AND CALIBRATE INJECTORS TO PREVENT RESTRICTION OF DELIVERY OF FUEL TO COMBUSTION CHAMBER CLEAN AND CALIBRATE FUEL PUMP INSPECT THE WATER PUMP CHECK YHE TURBOCHARGER BEARING CLEARANCE

MAINTENANCE OF D.G.SETS

SEASONAL CHECKS
CLEAN THE COOLING SYSTEM REPLACE HOSE AS REQUIRED CLEAN ELECTRIC CONNECTIONS CHECK THERMAL CONTROL CHECK THE OVER SPEED SWITCH CLEAN THE ENGINE WATER HEATER

FIREFIGHTING SYSTEM

FIRE FIGHTING SYSTEM CONISTIS OF


I.WATER BASED SYSTEM a) Hydrant system b) Automatic HVWS ( High velocity water spray) ( Emulsifier ) System

II DETECTION SYSTEM a) Smoke detectors b) Heat detectors


III. PORTABLE FIRE EXTENGISHERS a) CO2 Type b) DCP (Dry chemical Powder) c) Water-Co2 Type d) Foam Type e) Halon Type

WATER BASED SYSTEM

WATER BASED SYSTEM CONSISTING OF

FOLLOWING EQUIPMENTS.

AIR COMPRESSOR JOCKY PUMP HYDRANT PUMP MAIN ELECTRIC PUMP DIESEL ENGINE H.P TANK CONTROL, RELAY AND ANNOUNCIATION PANELS

WATER BASED SYSTEM

AIR COMPRESSOR
IT SUPPLIES THE AIR TO HP TANK TO MAINTAIN THE PRESSURE IN THE WATER LINE.

IT OPERATES ON HP TANK FLOAT SWITCH


IT SHOULD BE KEPT IN AUTO MODE.

WATER BASED SYSTEM

JOCKY PUMP
IT PUMPS THE WATER TO HP TANK TO MAINTAIN THE PRESSURE IN THE WATER LINE. IF THERE IS A MINOR WATER PRESSURE DROP IN THE SYSTEM DUE TO LEAKS IN THE GLAND PACKING OF VALUES, FLANGE JOINTS, OR DUE TO CHANGE IN THE ATMOSPHERIC TEMPARATURE THE JOCKY PUMP WILL START AND COMPENSATE THE MINOR LEAKAGES. IT SHOULD BE KEPT IN AUTO MODE. IT OPERATES ON HP TANK FLOAT SWITCH.

WATER BASED SYSTEM


HYDRANT SYSYEM I. System Description.


The hydrant System has been provided for the following areas of the Sub-Station. 1. Fire Water Pump House 2. L.T Sub-Station 3. D.G. Set Building 4. Control Room Building 5. Maintenance Building 6. Store area.

HYDRANT SYSTEM

WATER STORAGE
Water for the fire protection services has been made available in the fire water storage tank adjacent to the pump house. As per the TAC rules water to be stored for hydrant system should be 135 cum and 20 minutes water requirement of the largest equipment under the protection for HVWS system.

HYDRANT SYSTEM

II. The Water Supply, Pumping Capacity and other features of Hydrant System depend not only on the size of risk but also Fire growth and spread potentialities. Accordingly various categorized by TAC . DESCRIPTION Hydrant System is a wet line and the system is always kept pressurized at 8.0 Kgs/Cm. Hydrants Have been provided around the periphery of the various buildings at distance of not more than 60 mts from each other. Location of hydrants have been fixed keeping in mind to attendant the fire hazards at different sections of particular building being protected. Two Nos of Hoses ( 22 Mts/15 Mts ) Nozzles have been provided in each box.

HYDRANT SYSTEM

In the case of fire in a particular area, Hydrant located near by fire area to be opened by trained staff, manually. The Fire is fought by means of hoses and nozzles provided in the hose boxes

HYDRANT SYSTEM

SYSTEM OPERATION
When any hydrant is opened, the pressure in the line drops. When the pressure fallows below 6. 8 kgs/cm the pressure switch will send the impulse to the motor control panel. Due to this power will be supplied to the motor and hydrant pump will start automatically and continuous supply of water is made available for the hydrant outlets. After the fire has been quenched, the pump has to be stopped manually.

HYDRANT SYSTEM

IF HYDRANT PUMP FAILS TO START, THE PRESSURE IN NET WORK WILLFURTHER DROP DOWN TO 6.2 KGS/CM MAINELETRIC PUMP WILL START IF FURTHER DROPS TO 5.8 KGS/CM, DIESEL ENGINE PRESSURE SWITCH WILL ACTUATE AND DIESEL ENGINE WILL START AUTOMATICALLY AND PRESSURIZED WATER WILL BE SUPPLIED TO THE PIPE LINE. AFTER OPERATION DIESEL PUMP SHOULD BE SWITCHED OFF MANUALLY.

HYDRANT SYSTEM

ANNOUNCIATION SCHEME HYDRANT PUMP RUNNING FIRE IN THE HYDRANT SYSTEM FAILS TO START ( IF MOTOR FAILED TO START)

HYDRANT SYSTEM

STEP BY STEP STARTING SEQUENCE FOR HYDRANT SYSTEM


FIRE
FIRE IS NOTICED BY PEOPLE

WHAT IS TO BE DONE
REQUIRED NO OF HOSES AND BRANCH PIPES ARE TO BE TAKEN FROM HOSE BOXES AND BROUGHT NEAR THE HYDRANTS TO BE OPNED. BRANCH PIPES TO BE FIXED TO HOSES AND HOSES TO HYDRANTS. THE REQUIRED NO OF HYDRANTS TO BE OPENED. WATER STREAM FROM HOSES ARE TO BE DIRECTED TO ROOT FIRE BY TRAINED STAFF. NOTE: BEFORE OPERATING HYDRANT SYSTEM POWER SUPPLY TO ELETRICAL EQUIPMEN SHALL BE CUT OFF.

HYDRANT SYSTEM

WATE HAPPENS NEXT


PRESSURE IN THE HYDRANT HEADER DROPS HDRANT PUMP START AUTOMATICALLY AND FEED CONTINUOUS SUPPLY OF WATER TO THE HYDRANT POINTS. THE ANNUNCIATION HYDRANT PUMP RUNNING IS RECEIVED ON THE ANNUNCIATION

QUENCHING OF FIRE
FIRE IS QUENCHEDBY OPERATING THE HYDRANTS FOR THE NECESSARY TIME THE PUMP IS STOPPED MANUALLY, AFTER ENSURING THAT FIRE HAS BEEN QUENCHED.

HYDRANT SYSTEM

HYDRANT SYSTEM RESETTING


FIRST ENSURE THAT THE FIRE HAS BEEN COMPLETELY QUENCHED THE HYDRANT VALVES THAT WERE OPENED TO BE CLOSED HOSES AND BRANCH PIPES TO BE DISMANTLED WATER IS TO BE DRAINED FROM HOSES AND BRANCH PIPES HOSES AND BRANCH PIPES ARE TO BE DRIED. DRAINED HOSES AND BRANCH PIPES TO BE REPLACED IN THEIR ORIGINAL POSITION.

HVWS (EMULSFIRE) SYSTEM

EQUIPMENTS PROTECTED BY HVWS SYSTEM


AUTO TRANSFORMERS LINE REACTORS BUS REACTORS

HVWS SYSTEM

SAILENT FEATURES OF THE HVWS SYSTEM


THE HVWS SYSTEM APPLIES WATER IN THE FORM OF A SPRAY CONISTING OF AN AUTOMIZED SPARY OF WATER TRAVELLING AT HIGH VELOCITY. THREE PRINCIPLES OF THE EXTINGUISHMENT ARE EMPLOYED IN THE SYSTEM, VIZ. EMULSIFICATION, COOLING AND SMOTHERING. THE RESULT OF APPLYING THESE PRINCIPLES IS TO EXTINGUISH THE FIRE WITHIN A FEW SECONDS.

HVWS SYSTEM

VARIOUS COMPONENTS OF THE SYSTEM


PROJECTORS

DETECTORS
DELUGE VALVE

WATERMAINS AND PUMP SETS


ANNUNCIATION PANEL

STEP BY STEP STARTING SEQUENCE FOR HVWS SYSTEM


FIRE
FIRE IS DECTED BY QUARTZOID BULBS. ONE OR MORE QUARTZOID BULB DECTORS BURNT PRESSURE IN THE DECTION LINE DROPS THE ANNUNCIATION FIRE IS RECEIVED IN THE ANNUNCIATION PANEL

HVWS SYSTEM

WHAT HAPPENS NEXT


THE DELUGE VALVE OPENS AUTOMATICALLY WATER SPARYED ON TO THE EQUIPMENT THROUGH THE VARIOUS NOZZLES. THE PRESSURE IN THE HEADER UPSTREAM OF THE DELUGE VALVE DROPS

HVWS SYSTEM

THE ELECTRIC MOTOR WATER SPARY PUMP STARTS ELECTRIC MOTOR PUMP RUNNING ANNUNCIATION RECEIVED IN THE PANEL THE HVWS SYSTEM OPERATES CONTINUOUSLY TILL THE FIRE IS PUT OFF AFTER FIRE IS QUENCHED THE PUMP TO BE STOPED MANUALLY.

IF MAIN PUMP FAILS TO START


WATER PRESSURE IN SPRAYER HEADER REDECED EVEN FURTHER EITHER HYDRANT OR DIESEL PUMP STARTS THE SYSTEM OPERATES TILL THE FIRE IS QUENCHED PUMPS IS TO BE STOPPED MANUALLY

HVWS SYSTEM

SYSTEM RESETTING
THE WATER SPRAY PUMP IS STOPPED MANUALLY THE SLUICE VALVE BEFORE DELUGE VALVE IS TO BE CLOSED THE DELUGE VALVE AND PROJECTOR NETWORK PIPING IS TO BE DRAINED THE BULBS WHICH HAVE BEEN DAMAGED ARE TO BE REPLACED BY SIMILAR TYPE OF DECTORS. THE DELUGE VALUE TO BE RESETT. PRESSURISE THE DECTION LINE AROUND THE EQUIPMENT PRESSURISE THE WATER HEADER CHECK THE PRESSURE GAUGE READING NEAR THE DELUGE VALVE

FIRE FIGHTING SYSTEM

PREVENTIVE MAINTENANCE
MONTHLY MAINTENANCE
RUN MOTORS FOR FIVE MINUTES & CHECK FOR SMOOTH OPRATION CLEAN ALL MOTORS, PUMPS AND OTHER EQUIPMENTS IN THE PUMP HOUSE CLEAN THE FLOOR AND CEILING CHECK ALL VALVES CHECK THE OIL LEVEL IN DIESEL ENGINE

FIRE FIGHTING SYSTEM

QUARTERLY MAINTENANCE
CHECK COMPRESSOR OIL & REPLACE IF NECESSARY CHECKING OF BELT TIGHTNESS CLEANING OF OIL STAINERS

HALF YEARLY MAINTENANCE


MOTOR TERMINAL CONNECTION CHECKING ADJUSTMENT OF GLANDS FOR LEAKAGES AND TIGHTENING OF NUTS AND BOLTS

FIRE FIGHTING SYSTEM

YEARLY MAINTENANCE
OPERATE DELUGE SYSTEM FOR OIL FILLED EQUIPMENTS. CHECK THE FIRE HOUSE CABNETS ARE COMPLETE WITH HOSE REELS AND NOZZLES. SEAL THE CABNET WITH LEAD SEAL AFTER INSPECTION

SMOKE DETECTION SYSTEM

SMOKE DETECTION SYSTEM IS PROVIDED WITH IONISATION AND PHOTOELECTRIC TYPE SMOKE DETECTORS.

THE DETECTORS ARE PROVIDED IN THE FOLLOWING AREAS.


A.C PLANT ROOM,MAINTENANCE ROOM LT PANEL ROOM CABLE VAULT ROOM AHU ROOM & RECORD ROOM CONTROL ROOM AND CONFERENCE HALL PLCC & MRT ROOM

SMOKE DETECTION SYSTEM

SYSTEM OPERATION
GENERALLY FIRE BREAKS OUT MAINLY DUE TO THE SHORT CIRCUITING OF CABLE. IN WHICH CABLE INSULATION MELTS AND GIVES SMOKE INITIALLY, THE DENSITY OF THE SMOKE IS LESS THAN THE ATMOSPHRIC AIR AND HAS THE TENDENCY TO TRAVELL UP. WHEN THE SMOKE REACHES THE DETECTOR FIRE IS DETECTED AND THE ANNUNCIATION OF FIRE IN RESPECTIVE AREA IS RECEIVED IN THE FIRE ALARAM PANEL LOCATED IN THE CONTROL ROOM. THE HOOTER PROVIDED GIVES THE AUDIABLE SIGNAL. QUENCH THE FIRE BY USING FIRE EXTINGUISHERS.

SMOKE DETECTION SYSTEM

YEARLY MAINTENANCE
CHECK FOR OPERATION OF FIRE ALARM SYSTEM INSTALLED AT VARIOUS LOCATIONS BY AGARBATTI, OR SOME SMOKE DEVICE CHECK FOR ALARAM IN THE CONTROL PANEL CHECK THE CONDITION OF BATTERY CHECK FOR CLEANLINESS.

A.C PLANT

A.C. PLANT

DESCRIPTION
A.C PLANT CONSISTING OF THE FOLLOWING EQUIPMENTS.
MOTORS COMPRESSORS (770) CONDENSER PUMPS AHUS CONDENSERS LT SUPPLY PANELS & CONTROL PANELS

A.C. PLANT

DESCRIPTION
WHEN COMPRESSOR STARTS, IT COMPRESS THE FREON GAS . THE COMPRESSED FREON GAS WITH RAISED TEMPARATURE IS DELIVERED TO THE CONDENSER UNIT. IN CONDENSER UNIT THE GAS IS COOLED AND PARTIALLY IT BECOMS LIQUID. THE LIQUID GAS MIXTURE ENTERS THE AHU ROOM THROUG THE PIPES AND GETS EXPANDEDIN THE AHU . THE FREON BECOMES GAS AND THER BY ABSORB THE HEAT FROM THE AIR. THE FREON IN GAS STATE COMES OUT OF THE AHU THROUGH PIPES AND IS SUCKED BY THE COMPRESSOR AND CYCLE REPEATS.

A.C PLANT

SEQUENCE OF OPERATION
CHECKS BEFORE STARTING
CHECH THE WATER LEVEL IN WATER TANK. CHECK THE OIL LEVEL IN THE COMPRESSOR CHECK THE ALL SOLENOID VALVES ARE IN OFF POSITION CHECK THE HP,LP,OIL PRESSURE GAUGES. CHECK THE REQUIRED VALVES ARE IN OPEN CONDITION CHECK THE AVAILABILITY OF A.C SUPPLY CLOSE THE DOORS AND WINDOW,S OF THE ROOMS TO BE COOLED. CHECK FOR GAS LEAKAGE

A.C PLANT

AFTER CHECKS STARTING PROCEDURE


START THE AHU I& AHU II START THE WATER CONDENSER PUMP SWITCH ON THE CONTROL CIRCUIT UNIT START THE COMPRESSOR SWITCH ON THE RSV (RECIRCULATION SOLENOID VALVE) 2 CYLINDERS WILL COME IN TO SERVICE WAIT FOR FEW MINUTES SWITCH ON THE USV I ( ANOTHER 3 CYLINDERS WIIL COME IN TO SEVICE ) WAIT FOR FEW MINUTES SWITCH ON USVII( ANOTHER 2 CYLINDERS WIIL COME IN TO SEVICE) CHECK THE HP, LP, OIL PRESSURES, WATER PRESSURE ETC.

A.C PLANT

STOPPING PROCEDURE
REDUCE THE LOAD BY SWITCHING OFF USVII,USVI AND RSV WAIT FOR FEW MINUTES SWITCH OFF THE COMPRESSURE SWITCH OFF THE WATER CONDENSER PUMP. SWITCH OFF THE COTROL CIRCUIT UNIT SWITCH OFF THE AHU I & AHU II

A.C PLANT

CONTROL INTERLOCKS
CONDENSER PUMP STARTS ONLY IF AHU IS ON CONDENSER PUMP STOPS IF AHU TRIPS COMPRESSOR STOPS IF CONDENSER PUMP OR AHU TRIPS.

A.C PLANT

MAINTENANCE
MONTHLY MAINTENANCE COMPRESSORS
CHECK OIL LEVEL IN SIGHT CLASS CHECK THE ALIGHMENT, SAFETY GUARD LEAKAGE CHECKS FOR REFRIGERANTS AND OIL

CONTROL PANELS
CHECK FOR LOOSE CONTACTS OF TERMINALS CLEAN IN SIDE CONDENSER UNIT CHECKING OF WATER PRESSURE INLET/OUT LET CHECKING OF WATER LEAKS OPERATION OF INLET /OUTLET VALVE

A.C PLANT

HALF YEARLY MAINTENANCE


CHECKING OF OPERATION OF WATER LEVEL SWITCHES CHECKING OF WATER QUALITY LUBRICATION FOR ELECTRICAL MOVING PARTS MOTOR TERMINAL CONNECTION CHECKING

A.C PLANT

YEARLY MAINTENANCE
CLEANING OF STRAINER CLEANING OF CONDENSING COILS CHECKING FOR RUSTING, DAMAGE OF PAINT- REPAINTING IF NECESSARY CLEAN THE AHU FILTERS CHECK THE OIL PRESSURE SWITCH,HP,LP CUT OUT SWITCHES, SOLENOID VALVESETC. CLEANING OF WATER TANK AND REGENARATION OF CHEMICALS CHECKS FOR LOOSE CONTACTS ANY IN ALL CONTROL PANELS