Overall Schedule (18 months duration) Start: 3/2/14 ID: 1 Finish: 10/8/15 Dur: 396 days?

Res:

Preliminary Works Start: 3/2/14 ID: 2 Finish: 7/7/15 Dur: 372 days Comp: 0%

Apply for Authority Approvals Start: 3/2/14 ID: 3 Finish: 18/2/14 Dur: 12 days Res:

Pre-construction Survey Start: 19/2/14 ID: 4 Finish: 28/2/14 Dur: 8 days Res:

Post Construction Survey Start: 1/7/15 ID: 5 Finish: 7/7/15 Dur: 5 days Res:

Cable Detection Surveys Start: 19/2/14 ID: 6 Finish: 25/2/14 Dur: 5 days Res:

Commencement Date Milestone Date: 3/2/14 ID: 7

Procurement & Pre-fabrication Works Start: 3/2/14 ID: 8 Finish: 9/5/14 Dur: 70 days Res:

Site Clearance & Work Area Preparation Start: 20/2/14 ID: 9 Finish: 26/3/14 Dur: 25 days Res:

Site Preparation Works Start: 13/3/14 ID: 11 Finish: 9/4/14 Dur: 20 days Res:

Shoring System Start: 25/3/14 Finish: 19/6/15 Res:

ID: 12 Dur: 324 days

Excavation & Backfilling works Start: 25/3/14 ID: 13 Finish: 3/7/15 Dur: 334 days Res:

Pipe Laying Works (including Pipe laying, Weld joint, Air Test, holiday test, painting & wrapping) Start of Pipe Laying Works Start: 23/4/14 ID: 14 Milestone Date: 23/4/14 Finish: 29/5/15 Dur: 288 days ID: 15 Comp: 0%

Pipe Laying under Jungle, Team 1 (~370m) Start: 23/4/14 ID: 16 Finish: 20/8/14 Dur: 86 days Res:

Pipe Laying under Fernvale Road, Team 2 & 3 (~950m) Start: 23/4/14 ID: 17 Finish: 29/5/15 Dur: 288 days Res:

Chambers & Access Manholes Construction Start: 25/8/14 ID: 18 Finish: 25/6/15 Dur: 219 days Res:

Connect to Existing Pipe Start: 1/6/15 ID: 19 Finish: 19/6/15 Dur: 15 days Res:

Reinstatement and Maintenance Work Start: 23/5/14 ID: 20 Finish: 30/6/15 Dur: 288 days Res:

Testing & Commissioning Start: 30/6/15 ID: 21 Finish: 10/8/15 Dur: 30 days Res:

As-built Document Preparation Start: 20/5/15 ID: 22 Finish: 3/7/15 Dur: 33 days Res:

Completion date Milestone Date: 10/8/15 ID: 23

Trial Holes Start: 20/2/14 Finish: 12/3/14 Res:

ID: 10 Dur: 15 days

NETWORK DIAGRAM, Construction Schedule Project: Portable Water Pipeline along Fernvale Road from Jalan Kayu to Sengkang West Avenue WEC Engineers and Constructors Pte Ltd (T2478)