CONCEPTO
UND
CANT
PRECIO
TOTAL
1.01
OBRAS PRELIMINARES
01.01.01
01.01.02
1.02
TRABAJOS PRELIMINARES
01.02.01
01.02.02
TRAZO Y REPLANTEO
1.03
MOVIMIENTO DE TIERRAS
01.03.01
EXCAVACIN DE ZANJAS
M2
50.00
103.31
5165.50
GBL
1.00
1971.81
1971.81
ML
13619.47
0.52
7082.12
ML
13619.47
1.31
17841.51
ML
692.06
6.19
4283.85
ML
3550.07
7.55
26803.03
ML
3979.39
8.03
31954.50
ML
2132.51
8.52
18168.99
ML
999.25
10.47
10462.15
ML
872.85
11.36
9915.58
ML
871.26
15.14
13190.88
ML
1850.03
17.03
31506.01
ML
113.60
20.98
2383.33
ML
174.34
27.25
4750.77
ML
48.84
45.42
2218.31
ML
13619.47
0.92
12529.91
ML
8221.52
7.03
57797.29
ML
3131.76
7.27
22767.90
ML
1744.11
9.10
15871.40
ML
1963.63
10.98
21560.66
ML
223.18
12.23
2729.49
ML
8221.52
14.39
118307.67
ML
3131.76
15.51
48573.60
ML
1744.11
19.05
33225.30
ML
1963.63
22.81
44790.40
ML
223.18
25.66
5726.80
ML
692.06
5.65
3910.14
ML
3550.07
7.90
28045.55
ML
3979.39
11.06
44012.05
ML
2132.51
12.87
27445.40
ML
999.25
14.81
14798.89
ML
872.85
19.19
16749.99
ML
871.26
25.53
22243.27
ML
1850.03
29.43
54446.38
ML
113.60
38.20
4339.52
ML
174.34
47.70
8316.02
ML
48.84
63.54
3103.29
M3
6966.26
25.12
174992.45
01.03.02
01.03.04
01.03.05
ENTIBADO DE ZANJAS
01.04.01
ML
999.25
11.86
11851.11
01.04.02
ML
872.85
16.69
14567.87
01.04.03
ML
871.26
22.57
19664.34
01.04.04
ML
1850.03
28.37
52485.35
01.04.05
ML
113.60
36.13
4104.37
01.04.06
ML
174.34
47.47
8275.92
01.04.07
ML
48.84
56.43
2756.04
1.05
01.05.01
ML
10651.07
39.50
420717.27
01.05.02
ML
1687.10
56.70
95658.57
01.05.03
ML
1281.30
86.15
110384.00
CONCEPTO
UND
CANT
PRECIO
TOTAL
1.06
BUZONES Y EMPALMES
01.06.01
UND
25.00
1586.30
39657.50
01.06.02
UND
75.00
1962.10
147157.50
01.06.03
UND
50.00
2345.66
117283.00
01.06.04
UND
35.00
2681.19
93841.65
01.06.05
UND
21.00
3181.73
66816.33
01.06.06
UND
11.00
3498.67
38485.37
01.06.07
UND
8.00
3896.67
31173.36
01.06.08
UND
7.00
4239.54
29676.78
01.06.09
UND
7.00
4748.08
33236.56
01.06.10
UND
3.00
5367.11
16101.33
01.06.11
UND
1.00
5953.18
5953.18
01.06.15
UND
478.00
108.23
51733.94
01.06.16
UND
27.00
325.50
8788.50
01.06.17
UND
1.00
417.27
417.27
1.07
PRUEBAS DE CALIDAD
01.07.01
ML
13619.47
3.36
45761.42
ML
6835.20
3.43
23444.74
ML
6835.20
24.08
164591.62
ML
6835.20
0.69
4716.29
ML
6835.20
6.21
42446.59
ML
6835.20
13.14
89814.53
ML
6835.20
19.05
130210.56
M3
1.00
25.12
25.12
ML
6835.20
22.31
152493.31
2.01
TRABAJOS PRELIMINARES
02.01.01
TRAZO Y REPLANTEO
2.02
MOVIMIENTO DE TIERRAS
02.02.01
EXCAVACIN DE ZANJAS
02.02.05
02.03.01
2.04
CAJAS Y EMPALMES
02.04.01
712.00
102.30
72837.60
02.04.02
UND
712.00
85.30
60733.60
2.05
PRUEBAS DE CALIDAD
02.05.01
ML
6835.20
3.21
21940.99
M2
8.22
1.31
10.77
M3
10.85
23.62
256.28
M3
1.76
303.98
535.00
M2
4.61
24.25
111.79
M3
3.03
361.79
1096.22
M2
29.56
30.25
894.19
KG
137.93
6.76
932.41
M2
13.17
27.44
361.38
CAMARA DE REJAS
3
CAMARA DE REJAS
3.01
OBRAS PRELIMINARES
03.01.00
TRAZO Y REPLANTEO
3.02
MOVIMIENTO DE TIERRAS
03.02.01
EXCAVACION MANUAL
3.03
CONCRETO SIMPLE
03.03.01
03.03.02
CONCRETO f'c=140kg/cm2
ENCOFRADO Y DESENCOFRADO
3.04
CONCRETO ARMADO
03.04.01
03.04.03
CONCRETO f'c=210kg/cm2
ENCOFRADO Y DESENCOFRADO
ACERO fy=4200Kg/cm2
3.05
REVOQUES Y ENLUCIDOS
03.05.01
3.06
CARPINTERIA METALICA
03.06.01
03.06.03
3.07
EMPALMES
03.07.01
03.04.02
03.06.02
3.50
83.72
293.02
UND
13.00
16.81
218.53
KG
1.43
6.76
9.67
2.00
96.35
192.70
CONCEPTO
UND
CANT
PRECIO
TOTAL
LAGUNAS FACULTATIVAS
4
LAGUNAS FACULTATIVAS
4.01
OBRAS PRELIMINARES
04.01.01
04.01.02
LIMPIEZA Y DESFORESTACION
TRAZO Y REPLANTEO
HA
6.16
1955.16
12043.79
M2
61612.19
0.35
21564.27
4.02
MOVIMIENTO DE TIERRAS
04.02.01
464828.55
04.02.06
4.03
OBRAS DE ARTE
04.03.01
04.02.02
04.02.03
04.02.04
04.02.05
2710.40
174183.00
1636.08
125017.60
1345.43
M3
2.43
361.32
M2
17.80
24.25
431.65
Kg
243.58
6.76
1646.60
M3
0.46
361.32
166.21
M2
4.57
24.25
110.82
Kg
393.90
6.76
2662.76
1918.61
04.03.02
04.03.03
878.01
ESTRUCTURAS DE INGRESO
ESTRUCTURAS DE DESCARGA
M3
5.31
361.32
M2
33.36
24.25
808.98
Kg
342.72
6.76
2316.79
2529.24
04.03.04
M3
7.00
361.32
M2
28.56
24.25
692.58
Kg
210.16
6.76
1420.68
04.03.05
ESTRUCTURAS DE SALIDA
M3
1.10
361.32
397.45
M2
17.88
24.25
433.59
Kg
99.24
6.76
670.86
UND
5.00
666.68
3333.40
92.00
56.70
5216.40
15.00
56.70
850.50
57.85
56.70
3280.10
UND
12.00
61.79
741.48
ML
100.00
24.08
2408.00
ML
100.00
0.69
69.00
ML
100.00
6.21
621.00
ML
100.00
30.30
3030.00
ML
100.00
13.14
1314.00
ML
100.00
19.05
1905.00
ML
100.00
3.36
336.00
M3
17.25
7.40
127.65
M2
10586.80
12.63
133711.28
4.04
COMPUERTA DE FIERRO
04.04.01
Compuertas de 35 x 35
4.05
04.0501
04.05.03
4.06
SUMINSTRO DE ACCESORIOS
04.06.01
4.07
04.07.01
04.07.08
EXCAVACION DE ZANJAS
REFINE Y NIVELACION DE ZANJAS
CAMA DE APOYO P/TUBERIAS
SUMINISTRO E INSTALACION DE TUBERIAS (300mm)
Relleno y Apisonado Hasta 0.30m
Relleno y Compactado C/Material Propio
DOBLE PRUEBA HIDRAULICA Y RESANE
ELIMINACION DE MATERIAL EXCEDENTE
4.08
FORESTACION Y PROTECCION
04.08.01
05.00.00
VARIOS
05.01.00
04.05.02
04.07.02
04.07.03
04.07.04
04.07.05
04.07.06
04.07.07
05.02.00
05.03.00
05.04.00
05.05.00
ML
10.00
950.00
9500.00
GLB
1.00
28630.00
28630.00
GLB
1.00
35600.00
35600.00
GLB
1.00
35000.00
35000.00
GLB
1.00
19675.73
19675.73
4,314,460.64
GG.GG 15%
UU 10%
647169.10
431446.06
S. TOTAL
5393075.80
IGV 19%
1024684.40
ESTUDIO 3.50%
SUPERVISION 5%
TOTAL
151006.12
215723.03
6,784,489.35
CONCEPTO
UND
CANT
PRECIO
TOTAL
1.01
OBRAS PRELIMINARES
01.01.01
01.01.02
1.02
TRABAJOS PRELIMINARES
01.02.01
01.02.02
TRAZO Y REPLANTEO
1.03
MOVIMIENTO DE TIERRAS
01.03.01
EXCAVACIN DE ZANJAS
M2
50.00
103.31
5165.50
GBL
1.00
1971.81
1971.81
ML
12487.52
0.52
6493.51
ML
12487.52
1.31
16358.65
ML
692.06
6.19
4283.85
ML
3443.13
7.55
25995.63
ML
3425.90
8.03
27509.98
ML
1660.99
8.52
14151.63
ML
999.25
10.47
10462.15
ML
872.85
11.36
9915.58
ML
871.26
15.14
13190.88
ML
185.30
17.03
3155.66
ML
113.60
20.98
2383.33
ML
174.34
27.25
4750.77
ML
48.84
45.42
2218.31
ML
12487.52
0.92
11488.52
ML
7561.09
7.03
53154.46
ML
2660.24
7.27
19339.94
ML
1744.11
9.10
15871.40
ML
298.90
10.98
3281.92
ML
223.18
12.23
2729.49
ML
7561.09
14.39
108804.09
ML
2660.24
15.51
41260.32
ML
1744.11
19.05
33225.30
ML
298.90
22.81
6817.91
ML
223.18
25.66
5726.80
ML
692.06
5.65
3910.14
ML
3443.13
7.90
27200.73
ML
3425.90
11.06
37890.45
ML
1660.99
12.87
21376.94
ML
999.25
14.81
14798.89
ML
872.85
19.19
16749.99
ML
871.26
25.53
22243.27
ML
185.30
29.43
5453.38
ML
113.60
38.20
4339.52
ML
174.34
47.70
8316.02
ML
48.84
63.54
3103.29
01.03.02
01.03.04
01.03.05
M3
5382.72
25.12
135213.93
1.04
ENTIBADO DE ZANJAS
01.04.01
ML
999.25
11.86
11851.11
01.04.02
ML
872.85
16.69
14567.87
01.04.03
ML
871.26
22.57
19664.34
01.04.04
ML
185.30
28.37
5256.96
01.04.05
ML
113.60
36.13
4104.37
01.04.06
ML
174.34
47.47
8275.92
01.04.07
ML
48.84
56.43
2756.04
1.05
01.05.01
ML
9519.12
39.50
376005.24
01.05.02
ML
1687.10
56.70
95658.57
01.05.03
ML
1281.30
86.15
110384.00
CONCEPTO
UND
CANT
PRECIO
TOTAL
1.06
BUZONES Y EMPALMES
01.06.01
UND
25.00
1586.30
39657.50
01.06.02
UND
72.00
1962.10
141271.20
01.06.03
UND
41.00
2345.66
96172.06
01.06.04
UND
27.00
2681.19
72392.13
01.06.05
UND
21.00
3181.73
66816.33
01.06.06
UND
11.00
3498.67
38485.37
01.06.07
UND
8.00
3896.67
31173.36
01.06.08
UND
7.00
4239.54
29676.78
01.06.09
UND
7.00
4748.08
33236.56
01.06.10
UND
3.00
5367.11
16101.33
01.06.11
UND
1.00
5953.18
5953.18
01.06.15
UND
412.00
108.23
44590.76
01.06.16
UND
27.00
325.50
8788.50
01.06.17
UND
1.00
417.27
417.27
1.07
PRUEBAS DE CALIDAD
01.07.01
ML
12487.52
3.36
41958.07
ML
6835.20
3.43
23444.74
ML
6835.20
24.08
164591.62
ML
6835.20
0.69
4716.29
ML
6835.20
6.21
42446.59
ML
6835.20
13.14
89814.53
ML
6835.20
19.05
130210.56
M3
1.00
25.12
25.12
ML
6835.20
22.31
152493.31
2.01
TRABAJOS PRELIMINARES
02.01.01
TRAZO Y REPLANTEO
2.02
MOVIMIENTO DE TIERRAS
02.02.01
EXCAVACIN DE ZANJAS
02.02.05
02.03.01
2.04
CAJAS Y EMPALMES
02.04.01
712.00
102.30
72837.60
02.04.02
UND
712.00
85.30
60733.60
2.05
PRUEBAS DE CALIDAD
02.05.01
ML
6835.20
3.21
21940.99
CAMARA DE REJAS
3.01
OBRAS PRELIMINARES
M2
8.22
1.31
10.77
M3
10.85
23.62
256.28
M3
1.76
303.98
535.00
M2
4.61
24.25
111.79
M3
3.03
361.79
1096.22
M2
29.56
30.25
894.19
KG
137.93
6.76
932.41
M2
13.17
27.44
361.38
3.50
83.72
293.02
UND
13.00
16.81
218.53
KG
1.43
6.76
9.67
2.00
96.35
192.70
CAMARA DE REJAS
03.01.00
TRAZO Y REPLANTEO
3.02
MOVIMIENTO DE TIERRAS
03.02.01
EXCAVACION MANUAL
3.03
CONCRETO SIMPLE
03.03.02
CONCRETO f'c=140kg/cm2
ENCOFRADO Y DESENCOFRADO
3.04
CONCRETO ARMADO
03.04.01
03.04.03
CONCRETO f'c=210kg/cm2
ENCOFRADO Y DESENCOFRADO
ACERO fy=4200Kg/cm2
3.05
REVOQUES Y ENLUCIDOS
03.03.01
03.04.02
03.05.01
3.06
CARPINTERIA METALICA
03.06.01
03.06.03
3.07
EMPALMES
03.07.01
03.06.02
CONCEPTO
UND
CANT
PRECIO
TOTAL
LAGUNAS FACULTATIVAS
4
LAGUNAS FACULTATIVAS
4.01
OBRAS PRELIMINARES
04.01.02
LIMPIEZA Y DESFORESTACION
TRAZO Y REPLANTEO
4.02
MOVIMIENTO DE TIERRAS
04.02.01
04.01.01
HA
6.16
1955.16
M2
61612.19
0.35
21564.27
464828.55
04.02.06
4.03
OBRAS DE ARTE
04.03.01
04.02.02
04.02.03
04.02.04
04.02.05
12043.79
2710.40
174183.00
1636.08
125017.60
1345.43
M3
2.43
361.32
M2
17.80
24.25
431.65
Kg
243.58
6.76
1646.60
04.03.02
878.01
ESTRUCTURAS DE INGRESO
M3
0.46
361.32
M2
4.57
24.25
110.82
Kg
393.90
6.76
2662.76
1918.61
04.03.03
166.21
ESTRUCTURAS DE DESCARGA
M3
5.31
361.32
M2
33.36
24.25
808.98
Kg
342.72
6.76
2316.79
2529.24
04.03.04
M3
7.00
361.32
M2
28.56
24.25
692.58
Kg
210.16
6.76
1420.68
04.03.05
ESTRUCTURAS DE SALIDA
M3
1.10
361.32
397.45
M2
17.88
24.25
433.59
Kg
99.24
6.76
670.86
UND
5.00
666.68
3333.40
92.00
56.70
5216.40
15.00
56.70
850.50
57.85
56.70
3280.10
UND
12.00
61.79
741.48
ML
100.00
24.08
2408.00
ML
100.00
0.69
69.00
ML
100.00
6.21
621.00
ML
100.00
30.30
3030.00
ML
100.00
13.14
1314.00
ML
100.00
19.05
1905.00
ML
100.00
3.36
336.00
M3
17.25
7.40
127.65
M2
10586.80
12.63
133711.28
4.04
COMPUERTA DE FIERRO
04.04.01
Compuertas de 35 x 35
4.05
04.0501
04.05.03
4.06
SUMINSTRO DE ACCESORIOS
04.05.02
04.06.01
4.07
04.07.01
04.07.08
EXCAVACION DE ZANJAS
REFINE Y NIVELACION DE ZANJAS
CAMA DE APOYO P/TUBERIAS
SUMINISTRO E INSTALACION DE TUBERIAS (300mm)
Relleno y Apisonado Hasta 0.30m
Relleno y Compactado C/Material Propio
DOBLE PRUEBA HIDRAULICA Y RESANE
ELIMINACION DE MATERIAL EXCEDENTE
4.08
FORESTACION Y PROTECCION
04.07.02
04.07.03
04.07.04
04.07.05
04.07.06
04.07.07
04.08.01
05.00.00
VARIOS
05.01.00
05.02.00
05.03.00
05.04.00
05.05.00
ML
10.00
950.00
9500.00
GLB
1.00
28630.00
28630.00
GLB
1.00
35600.00
35600.00
GLB
1.00
32156.00
32156.00
GLB
1.00
35000.00
35000.00
GLB
1.00
19675.73
19675.73
3,971,605.16
GG.GG 15%
UU 10%
595740.77
397160.52
S. TOTAL
4964506.45
IGV 19%
943256.23
ESTUDIO 3.50%
139006.18
SUPERVISION 5%
TOTAL
198580.26
6,245,349.12