INSTALLATION OF UNDERGROUND BURRIED DUCTS

Project: Owner: Project Manager: Consultant: Main Contractor : IR No.: Building No.: Level: Date:

CHECKED BY NO. 1 2 3 4 DESCRIPTION


Approved Material used (MIR)

REMARKS

Checking existing ground levels. Check Ducts, fittings & accessories used have an approved material submittal. Check that shop drawings are approved for construction. Check that trench has been cleared for duct laying. Check that the ducts have been installed as per approved shop drawing. Check the installation prior to back filling.

6 7

Remarks/Comments (if any):