Вы находитесь на странице: 1из 63

RMT 558_Construction Management & Facilities Management 2009

CHAPTER 1.0 - INTRODUCTION

The industrialized building system (IBS) can be generally interpreted as in which


all building components such as floors, walls, columns, beams, and roofs are
mass produced either in a factory or at site factory according to specifications
with standardize shapes and dimensions and transported to the construction
projects site to be assembled into a structure with minimal site wet work and
erected on the site properly joined to form the final units.
The development of industrialized building system (IBS) is not new in the
construction industry. The history of IBS in the UK housing industry dates back
from the mid 1900’s, when this and other forms of prefabricated construction
were used to address the problem of widespread destruction of housing stock
during the Second World War.

In the United States, the use of precast building components in the construction
industry began in the construction of prefabricated steel house by General House
in 1930. However the early efforts of rationalizing and implementation faded
quickly due to price in competitiveness, high capital and inconsistent local codes.
The use of precast building components increased sharply after the Second
World War due to the need to resolve critical shortage of houses.

The idea of industrialised building system (IBS) has received much attention in
the devastated countries after the Second World War. Though, Malaysia did not
suffer the impact of the war, the need to supply its population with affordable and
quality houses has prompted the government to promote the use of IBS as an
alternative to conventional building system.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 1


RMT 558_Construction Management & Facilities Management 2009

The implementation of precast concept by using precast concrete building were


introduced in Malaysia in 1966 when the government launched two pilot projects
for precast housing which involves the construction of Tuanku Abdul Rahman
Flats in Kuala Lumpur and the Rifle Range Road Flats in Penang. Both projects
were the first time whereby precast elements were used to construct mass
houses. Later, Perbadanan Kemajuan Negeri Johor (PKNS) import the precast
concrete technology from Germany for the construction ranging from low cost
housing to luxurious housing such as bungalows and semi detached.

1.1 Definition of IBS

To date there has been no one commonly-accepted or agreed definition of IBS.


However, there are a few definitions by researchers and experts in this field
which can be found through literature. Rahman and Omar (2006) defined IBS as
a construction system that is built using pre-fabricated components. The
manufacturing of the components is systematically done using machine,
formworks and other forms of mechanical equipment.

IBS is defined as products, systems and techniques used in making construction


less labour-oriented, faster as well as quality controlled. It generally involves
prefabricated products, factory manufactured elements that transported to the
construction sites and erected. (Shaari, Bulletin Ingénieur, 2003)

According to Abraham Warszawski (1999), IBS is defined as a set of element or


component which is inter-related towards helping the implementation of
construction works activities. He also expounded that an industrialisation process
is an investment in equipment, facilities, and technology with the objective of
maximising production output, minimising labour resource, and improving quality
while a building system is defined as a set of interconnected element that joint
together to enable the designated performance of a building.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 2


RMT 558_Construction Management & Facilities Management 2009

Trikha (1999) defined IBS as a system in which concrete components


prefabricated at site or in factory are assembly to form the structure with
minimum in situ construction.

Esa and Nuruddin (1998) asserted that IBS is a continuum beginning from
utilising craftsmen for every aspect of construction to a system that make use of
manufacturing production in order to minimise resource wastage and enhance
value for end users.

Perhaps the most comprehensive definition of IBS was clarified by Junid (1986).
He mentioned that IBS in the construction industry includes the industrialised
process by which components of a building are conceived, planned, fabricated,
transported and erected on site. The system includes a balanced combination
between the software and hardware components.

The software elements include system design, which is a complex process of


studying the requirement of the end user, market analysis, development of
standardised components, establishment of manufacturing and assembly layout
and process, allocation of resources and materials and definition of a building
designer conceptual framework. The software elements provide a prerequisite to
create the conducive environment for industrialised to expand.

Meanwhile, the hardware elements are categorised into three major groups.
These include frame or post and beam system, panel system, and box system.
The framed structures are defined as those structures that carry the loads
through their beams and girders to columns and to the ground whilst in panel
system load are distributed through large floor and wall panels. The box systems
include those systems that employ three-dimensional modules (or boxes) for
fabrication of habitable units are capable of withstand load from various
directions due to their internal stability.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 3


RMT 558_Construction Management & Facilities Management 2009

All the above definitions emphasised on prefabrication, off-site production and


mass production of building components as the main characteristic of IBS. The
focal of discussion in the study synergises the key concept of IBS as defined as
follows: A construction technique in which components are manufactured in a
controlled environment (on or off site), transported, positioned and assembled
into a structure with minimal additional site works (CIDB, 2003a).

1.2 Classification of IBS

Warszawski (1999) asserted that the building system could be classified in


different ways, depending on the particular interest of their users or producers.
Such classification use construction technology as a basis for classifying different
building systems. In this manner four major groups can be distinguished namely,
system with (1) timber, (2) steel, (3) cast in situ concrete, and (4) precast
concrete as their main structural and space enclosing materials. These systems
can be further classified according to the geometrical configuration of their main
framing components as follows (1) linear or skeleton (beams and columns)
system, (2) planar or panel systems, and (3) three dimensional or box systems.

According to Badir- Razali, generally, there are four types of building systems
currently available in Malaysia’s building system classification (Badir et al. 1998),
namely conventional, cast in-situ, prefabricated and composite building systems.
Each building system is represented by its respective construction method which
is further characterised by its construction technology, functional and geometrical
configuration.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 4


RMT 558_Construction Management & Facilities Management 2009

Fig. 1.1 Type of building system in Malaysia

Nonetheless, according to CIDB (2003), the structural aspects of IBS of the


systems, divided into five major types as follows:

1. Precast Concrete Framing, Panel and Box Systems


Precast columns, beams, slabs, 3-D components (balconies,
staircases, toilets, lift chambers), permanent concrete formwork, etc;

Figure 1.2 Precast concrete wall

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 5


RMT 558_Construction Management & Facilities Management 2009

2. Steel Formwork Systems


Tunnel forms, beams and columns molding forms, permanent steel
formworks (metal decks, etc;

Figure 1.3 Steel formwork system

3. Steel Framing Systems


Steel beams and columns, portal frames, roof trusses, etc;

Figure 1.4 Steel roof trusses

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 6


RMT 558_Construction Management & Facilities Management 2009

4. Prefabricated Timber Framing Systems


Timber frames, roof trusses, etc;

Figure 1.5 Prefabricated timber framing system for a double storey


house.

5. Block Work Systems


Interlocking concrete masonry units (CMU), lightweight concrete
blocks, etc.

Figure 1.6 Lightweight concrete blocks are used for wall construction

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 7


RMT 558_Construction Management & Facilities Management 2009

The pre-cast concrete components are among the most common prefabricated
elements that are available both locally and abroad. The pre-cast concrete
elements are concrete products that are manufactured and cured in a plant
environment and then transported to a job site for installation. The elements are
columns, beams, slabs, walls, 3-D elements (balconies, staircase, toilets, and lift
chambers), permanent concrete formwork and etc.

The steel formwork is prefabricated in the factory and then installed on site.
However the steel reinforcement and services conduit are installed on site before
the steel formwork are installed. The installation of this formwork is easy by using
simple bracing system. Then concrete is poured into the formwork and after
seven days, the formwork can be removed and there is some system whereby
the formwork served as a part of the structure itself after concreting. The steel
formwork systems are used in tunnel forms, beams, column moulding forms and
permanent steel formworks.

The elements of steel framing system are rolled into the specific sizes and then
the elements are fabricated that involves cutting, drilling, shot blasting, welding
and painting. Fabricated elements are sent to the construction site to be then
erected whereby welding and the tightening of bolts at joints are conducted. The
elements include steel beams and columns, portal frames and roof trusses.

The prefabricated timber framing system is normally used in the conventional


roof truss and timber frames. The timber is prefabricated by joining the members
of the truss by using steel plate. It is important that all members are treated with
the anti pest chemical. Then, the installation is done on site by connecting the
prefabricated roof truss to the reinforcement of the roof beams.

The elements of block work system include interlocking concrete masonry units
(CMU) and lightweight concrete blocks.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 8


RMT 558_Construction Management & Facilities Management 2009

The elements are fabricated and cured in the factory. The elements are normally
used as bricks in structures and interlocking concrete block pavement.

1.3 Essential Characteristics of IBS

It is plausible to review the prerequisite characteristics underlining the successful


implementation of industrialised building system. Each of them is briefly
discussed below.

1.3.1 Closed System

A closed system can be classified into two categories, namely production


based on client’s design and production based on precaster’s design. The
first category is designed to meet a spatial requirement of the client’s that
is the spaces required for various functions in the building as well as the
specific architectural design.
In this instance, the client’s needs are paramount and the precaster is
always forced to produce a specific component for a building. On the other
hand, the production based on precaster’s design includes designing and
producing a uniform type of building or a group of building variants, which
can be produced with a common assortments of component. Such
building includes school, parking garage, gas station, low cost housing,
etc. Nevertheless these types of building arrangement can be justified
economically only when the following circumstances are observed
(Warszawski, 1999).

(a) The size of project is large enough to allow for distribution of


design and production costs over the extra cost per component
incur due to the specific design.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 9


RMT 558_Construction Management & Facilities Management 2009

b) The architectural design observes large repetitive element and


standardisation. In respect to this, a novel prefabrication system
can overcome the requirement of many standardised elements by
automating the design and production process.

c) There is a sufficient demand for a typical type of building such as


school so that a mass production can be obtained.

d) There is an intensive marketing strategy by precaster to


enlighten the clients and designer the potential benefit of the
system in term of economics and non-economic aspects.

1.3.2 Open System

In view of the limitations inherent in the closed system, an open system


which allows greater flexibility of design and maximum coordination
between the designer and precaster has been proposed. This system is
plausible because it allow the precaster to produce a limited number of
elements with a predetermined range of product and at the same time
maintaining architectural aesthetic value.

In spite of many advantages inherent in an open system, its adoption


experiences one major setback. For example, joint and connection
problem occur when two elements from different system are fixed
together. This is because similar connection technology must be observed
in order to achieve greater structural performance.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 10


RMT 558_Construction Management & Facilities Management 2009

1.3.3 Modular Coordination

Modular co-ordination is a co-ordinated unified system for dimensioning


spaces, components, fitting, etc. so that all elements fit together without
cutting or extending even when the components and fittings are
manufactured by different suppliers (Trikha, 1999).

The objectives of modular co-ordination are:

a) To create a basis upon which the variety of types and sizes of


building components can be minimized. Through a rationalized
method of construction, each component is designed to be
interchangeable with other similar ones and hence, provide a
maximum degree of freedom and choice offered to the designer.
This can also be accomplished by adopting a relatively large basic
measurement unit (basic module) and by limiting the dimensions of
building components to recommended preferred sizes
(Warszawski, 1999).

b) To allow for easy adoption of prefabricated components to any


layout and for their interchange ability within the building. This is
achieved by defining the location of each component in the building
with reference to a common modular grid rather than with a
reference to other components (Warszawski, 1999).

The modular co-ordination for building component apply the basic length
unit or module of M=100cm. This allows the designer to apply this size or
its multiple in the production of building components.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 11


RMT 558_Construction Management & Facilities Management 2009

Although this concept seems to be easy for adoption, its application


involves a great degree of coordination and adjustment in the
manufacturing process and the interfacing aspects of components.

1.3.4 Standardisation and Tolerances

For accomplishing the requirement of modular co-ordination, all


components need to be standardised for production. Such standardisation
of space and elements need prescribing tolerances at different
construction stages such as manufactured tolerances, setting out
tolerances, and erection tolerances, so that the combined tolerance
obtained on statistical considerations is within the permitted limits (Trikha,
1999).

Production resources can be used in the most efficient manner if the


output is standardised. Then the production process, machinery, and
workers’ training can be best absorbed to the particular characteristics of
the product.

1.3.5 Mass Production

The investment in equipment, human recourses, and facilities associated


with an industrialisation can be justified economically only when large
production volume is observed. Such volume provides a distribution of the
fixed investment charge over a large number of product units without
unduly inflating their ultimate cost (CIDB Singapore, 1992).

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 12


RMT 558_Construction Management & Facilities Management 2009

1.3.6 Specialisation

Large production output and standardisation of precast elements allow a


high degree of labour specialisation with the production process. The
process can be subdivided into a large number of small homogenous
tasks. In such working condition, workers are exposed to their work
repetitiously with higher productivity level (Warszawski, 1999).

1.3.7 Good Organisation

High production volume, specialisation of work, and centralisation of


production requires a efficient and experiences organisation capable of a
high level of planning, organising, coordination and control function with
respect to production and distribution of the products (Warszawski, 1999).

1.3.8 Integration

In order to obtain an optimal result, a high degree of coordination must


exist between various relevant parties such as designer, manufacturer,
owner, and contractor. This is achieved through an integrated system in
which all these functions are performed under a unified authority
(Warszawski, 1999)

1.3.9 Production Facility

The initial capital investment for setting up a permanent factor is relatively


experience. Plant, equipment, skilled worker, management resources
need to be acquired before production can be commenced. Such huge
investment can only be breakeven if there is sufficiently demand for the
products.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 13


RMT 558_Construction Management & Facilities Management 2009

On the other hand, a temporary casting yard or factory can be established


at the project site in order to minimise the transportation costs (Peng,
1986).

1.3.10 Transportation

It is found that casting of large-panel system can reduce labour cost up to


30 percent. However, these cost savings are partially offset by the
transportation costs. The transportation of large panels is also subject to
the country’s road department requirement. These limitations must be
taken into consideration when adopting a prefabrication system
(Peng, 1986).

1.3.11 Equipment at Site


For the purpose of erecting and assembling precast panels into their
position, heavy crane is required especially for multi-storey building. It is
therefore important to incorporate this additional cost when adopting a
prefabrication system (Warszawski, 1999).

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 14


RMT 558_Construction Management & Facilities Management 2009

CHAPTER 2.0 - DEVELOPMENT OF IBS IN MALAYSIA

IBS in Malaysia has begun in early 1960’s when Ministry of Housing and Local
Government of Malaysia visited several European countries and evaluate their
housing development program (Thanoon et. al., 2003). After their successful visit
in 1964, the government had started first project on IBS aims to speed up the
delivery time and built affordable and quality houses. About 22.7 acres of land
along Jalan Pekeliling, Kuala Lumpur was dedicated to the project comprising
seven blocks of 17 storey flat there are 3000 units of low-cost flat and 40 shops
lot. This project was awarded to Gammon/ Larsen Nielsen using Danish System
of large panel of pre-fabricated system (CIDB, 2003b).

In 1965, the second housing project initiated by the government of Malaysia, the
project comprising a 6 block of 17 storey flat and 3 blocks of 18 storey flat at
Jalan Rifle Range, Penang. The project was awarded to Hochtief/Chee Seng
using French Estoit System (Din, 1984). Among the earliest housing
development project using IBS was Taman Tun Sardon, Penang. IBS pre-cast
component and system in the project was designed by British Research
Establishment for low cost housing in tropical countries. Nonetheless, the
building design was very basic and not considering the aspect of serviceability
such as the need of wet toilet and bathroom (Rahman and Omar, 2006).
Between 1981 and 1993, Perbadanan Kemajuan Negeri Selangor (PKNS) a
state government development agency acquired pre-cast concrete technology
from Praton Haus International based on Germany to build low cost house and
high cost bungalow in Selangor (CIDB, 2003b). The usage of steel structure as
part of IBS, first gained attention with the construction of 36-storeys Dayabumi
complex that was completed in 1984 by Takenaka Corporation of Japan (CIDB,
2003b).

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 15


RMT 558_Construction Management & Facilities Management 2009

Today, the use of IBS as a method of construction in Malaysia is evolving. Many


private companies in Malaysia have teamed up with foreign expert from
Australia, Netherlands, United State and Japan to offer pre-cast solution to their
project (CIDB, 2003b). In addition, more and more local manufacturers have
established themselves in the market. Pre-cast, steel frame and other IBS were
used as hybrid construction to build national landmark such as Bukit Jalil Sport
Complex, Lightweight Railway Train (LRT) and Petronas Twin Tower. It was
reported that at least 21 of various manufactures and suppliers of IBS are
actively promoting their system in Malaysia (Thanoon et al., 2003). Nevertheless,
the government of Malaysia still feels that the usage of IBS is still low despite the
plausible potential.

From the survey conducted by CIDB of Malaysia in 2003, the usage level of IBS
in local construction industry stands at 15% (CIDB, 2003b). The total registered
IBS contractors in Malaysia stand for 1,993 in year 2007 (Table 3 and 4) and
registered IBS manufacture in Malaysia until 2007 is 138 producing 347 IBS
products available in the market shown in Table 5.

Evidently that most of locally developed products are based on traditional


materials such as reinforced concrete and the most innovative materials are
based on imported technology (CIDB, 2007b). There is no mandatory
requirement on any certification or accreditation of components, companies or
installers in place. Whilst, there is no empirical data, there is some anecdotal
evidence suggests that there has been sporadic dumping of sub-standard foreign
products in Malaysia (CIDB, 2007b). A mechanism to ensure IBS products
marked to an acceptable standard must be introduced in the manufacturing
process. Testing of components, verify and certify them will limit only safe and
acceptable IBS panels are erected and thus CIDB will lead this roles.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 16


RMT 558_Construction Management & Facilities Management 2009

2.1 Implementation of IBS in Malaysia

In Malaysia, the implementation of IBS concept by using pre-cast concrete


building were introduce in Malaysia 1966 when the government launched two
pilot projects for pre-cast housing which involves the construction of Tuanku
Abdul Rahman Flats in Kuala Lumpur and the Rifle Range Road Flats in Penang.
Both projects were the first time whereby pre-cast elements were used to
construct mass houses.

Since 1980’s there are intensive marketing strategies launched by the Malaysian
Government t o introduce modular coordination, its acceptance has received
poor responses for the building industry. As a result even partial introduction on
IBS such as lintels and staircase has not been possible (Trikha, 1999).

Previously in the 7th Malaysia Plan, the country intended to construct about
800,000 units of houses for its population using the IBS construction, Indeed
585,00 units planned for the low and low medium cost houses. However the
achievements are disappointing with only 20% completed houses reported due to
use of conventional construction method. Although the government introduce
numerous incentives and promotions to encourage housing developer’s t invest
in such housing category (Ismail, 2001).

Under the 7th Malaysian Plan, the enforcement of modular Coordination through
the construction Industry Standard 1 & 2 only applies to the low cost housing
projects initiated by the ministry of Housing and Local Government Malaysia
(CIDB 2001). The enforcement by the local authorities did not apply to all the
parties involve in the construction contribute to the failure or the implementation
in Malaysia. Furthermore the incentives that promised to be given to developers
by the government does not clearly stated in the law of Malaysia.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 17


RMT 558_Construction Management & Facilities Management 2009

This is non conformance leads to the use conventional method which is less risky
to the developers.

In the 1998, the ministry of housing and local government and CIDB has come
up with the modular design guide which contain the modular coordination
concepts, the design rules, drawings and preferred dimensions for architectural
finishes material such as bricks, glass, gypsum board and etc. the important
aspects of prefabricated concrete in terms of modular dimensions, strength,
stability and the fire protection specifications are not indicated. The uniform
building by law (UBBL) has introduced several clauses to encourage the use of
IBS include the sub clause of 42(1):

a) The second line mentioned that ’11 meter square gross area’ is
replace by the ’10.8 meter square net area’ this is suitable for the area
room that has the dimension of 3000x3600mm and using the modular
dimension.

b) The forth line, ‘9.3 square gross area’ is replace by the ‘9.0 meter
square net area.’

c) The fifth line, ‘6.5 meter square gross area’ is replace by’6.3 meter
square net area

In the conventional construction the local authority only given the authority to
inspect the work after the completion of the project which is not practical. The
government should look into allowing the local authority to inspect the work in the
manufacturing process up the construction stage and lastly to the project
completion to ensure the quality is not compromised.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 18


RMT 558_Construction Management & Facilities Management 2009

In the year 2001, the government set the Malaysia standard 1064 in order to
standardize the IBS components in terms of dimensions. However the MS 1064
still have a lot of loop holes that still can be improve.

The important specifications such as types of materials, design standard,


connection types, construction method and the system implementation are not
included. These items will ensure the quality of IBS components can be improve
and the contractor can be implement a standardize system easily and this will
encourage the use of IBS in Malaysia especially in the private sector. However
the standards must not be too rigid to allow for technological improvement in
constructions method, system and etc.

Many involvements in materials and components are made before their


application in the building process. In most cases, construction firm acts as
system integrators and catalyst for transforming new technologies into
marketable products. These play an important role modifying and developing
new technologies that impact as feedback loop to producers in the upstream.
The forces for technology for adoption are the strongest among materials,
component manufacturers and high quality equipment for production purposes.
Property developers and government policy makers also feed the stream for
innovation by funding in research and development activities.

2.2 Impediments to progress of IBS in Malaysia

The government is the major key player in the construction industry has spent
billions of ringgit over the pat several Malaysia Plans to develop the country.
However the plans are the characterized by short falls, delays and lack of
coordination between all parties including the agencies at federal and state levels
and other major players in the constructions industry. The government has not
taken necessary actions for the globalization and the industrialization of the

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 19


RMT 558_Construction Management & Facilities Management 2009

construction industry. The selection of the IBS has been hindered by lack of
assessment criteria set by the approving authorities.

An IBS system can only be practiced by the practitioner if its major advantages
are valuable compare to the conventional system. However up to date, there is
inadequate collaborative scientific research undertaken to substantiate the
benefit of IBS system. Therefore it can be clearly seen that the implementation of
IBS is hindered by lack of scientific information. The academic curriculum in the
university seldom in corporate courses that technology, organization and the
construction and the design of IBS. Lack of the research and development to use
the local materials causes the dependence of foreign technology can be
expensive and quality of products may be compromised

The fragmented construction industry straddles over several professions and


business. The professionals, builders and the supplier do not communication to
input on ideas on implementation of IBS. However the main concerns for these
parties are just profit and the resistance to change due to unclear incentives
given by the government by using new technology.

The research output from research institution is not readily commercially


exploitable and does not appeal to potential users. The major players of the
construction industry are reluctant to carry out the research and development in
IBS because this can be seen as risky ventures. The country has not been
embarked upon venture capitalism in a proactive meaningful manner and as
such effort in universities and research institutions remain largely unexploited
and unused.

All parties involve in the construction industry should collaborate and to work
together in order to achieve the full utilization of IBS.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 20


RMT 558_Construction Management & Facilities Management 2009

The government play very important role in imposed new regulation, standard
and training in terms of knowledge, experience and construction method.
Moreover the standardization of dimensions of material needs to provide a
feedback loop from the constructor to enable the implementation to be improving
from time to time.

Incentives given by government should be clearly documented and making sure


that all parties is well informed through promotions by the media. Last but not
least, the government should have the authority over parties involved including
manufacturer, constructor, designer, financial institution and the transporters to
ensure they play heir respective roles in the successful implementations of IBS

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 21


RMT 558_Construction Management & Facilities Management 2009

CHAPTER 3.0 - ISSUES AND CHALLENGES IN IBS IMPLEMENTATION IN


MALAYSIA

3.1 Introduction

CIDB has published IBS Roadmap 2003- 2010 which entailed the needs and
requirement of Malaysian construction industry. This roadmap was endorsed by
Cabinet on 29th October 2003. The roadmap is a comprehensive document that
divides the IBS programmed into five main focus areas that reflect the inputs
needed to drive the programmed. They are Manpower, Materials, Management,
Monetary, and Marketing (CIDB, 2003a).

The inputs are then divided into elements and the activities to be implemented for
each element are then identified and included into the time span of the roadmap
in order to achieve the mission within the stipulated time-frame. The content of
this roadmap is focused towards achieving the industrialization of the
construction sector and the longer term objective of Open Building concept. It
has been five years since the launching of the roadmap and more than half-way
through the mission of industrializing construction (Hussein, 2007).

It is now pertinent to examine the progress and how close to the completion of
the mission to date. More importantly, it is imperative to evaluate whether the
implementation of the roadmap has met the market response to the IBS
programmed so far. Most policy issues have been resolved and implemented,
while all relevant documents required to support the programmed have been
developed. Notwithstanding these achievements a number of implementation
snags were identified as being potential hurdles to the full implementation of the
roadmap.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 22


RMT 558_Construction Management & Facilities Management 2009

These include the following which have been identified by IBS Steering
Committee 2003- 2005 (Hussein, 2007):

• Development of standard plans and standard component drawings


for common use,
• Apprentice and on-the-job training in the area of IBS moulds and
casts, and assembly of components,
• IBS testing and evaluation programmed,
• Vendor development program,
• Readiness of designers and consultant practices, quality control,
production of standard components in the field of IBS.

`Realizing the implementation of IBS is still to make headway, CIDB through its
research arm, Construction Research Institute of Malaysia (CREAM) has taken
the initiative from the problem identified earlier and has conducted three
workshops session with the industry between 2006 and 2007.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 23


RMT 558_Construction Management & Facilities Management 2009

3.2 Challenges & Issues on IBS

After a lengthy deliberation with the stakeholders, it was concluded that the
factors contributing to the delays of IBS implementation are as follows:-

3.2.1 IBS as mass construction method.


The term ‘IBS’ is often misinterpreted with negative meaning as it is
always linked with industrialized buildings that were built in1960s. These
buildings are normally associated with pre-fabricated mass construction
method, low quality buildings, leakages, abandoned projects, unpleasant
architectural appearances and other drawbacks. Due to the poor
architectural design, the old pre-fabricated buildings have given the public,
bad impression about precast concrete.

There have been quite a number of cases where the use of IBS had lead
to such drawbacks. For example, in the case of Pekeliling Flats in Kuala
Lumpur and Taman Tun Sardon, Gelugor, Penang. These two early pre-
fabricated flats were constructed in mass to produce low cost
accommodation for lower income groups. In the case of Taman Tun
Sardon, the IBS precast system was designed by British Research
Establishment, UK for low cost housing in tropical countries.

However, the design was very basic and not considering the aspect of
serviceability such as the need for wet toilets and bathrooms. Lacking in
this design consideration leads to problems of leakage that becomes the
common issue with precast buildings. In addition, in many cases the low
cost housings are not maintained properly, thus contributing further to the
poor image of IBS buildings.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 24


RMT 558_Construction Management & Facilities Management 2009

3.2.2 Lack of involvement from small contractors


From the survey it is found that many small contractors are reluctant to
adopt IBS system and prefer to continue using the conventional method of
construction. This is due to the fact that small contractors are already
familiar with the conventional system and for them the technology suit well
with small scale projects and therefore not willing to switch to mechanized
based system. Furthermore small contractors lack financial backup and
are not able to set up their own manufacturing plants as it involves very
intensive capital investment. In this case, financial issues become the
main obstacle for small contractors to move forward with the IBS system.
On the other hand, however, many big players in IBS industry have shown
good track records in building successful IBS projects. This shows that
IBS is a feasible system provided the parties involved have the capabilities
to carry out the work related to IBS such as analysis, design and
manufacturing of IBS components.

3.2.3 Lack of knowledge and exposure to IBS technology


Lack of knowledge in structural analysis and design of pre-fabricated
components among civil engineers and those related to construction
discourages further the implementation of IBS system. Unlike steel
structures, the subject of precast concrete design is normally not delivered
to undergraduate students in many universities. As a result, many junior
engineers are not really familiar with the precast concrete technology as
compared to structural steelwork. Knowledge in construction technology is
equally important. There are cases, where building projects are awarded
and constructed using IBS system but were carried out with many
difficulties.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 25


RMT 558_Construction Management & Facilities Management 2009

The most common problems encountered are improper assembly of the


components that normally involved the beam-to-column and column-to-
base connections. These problems arise due to the fact that the parties
involved in the construction underestimate the important of accuracy in
setting out the alignment and levelling of the bases. Basically, accurate
levelling and alignment of the bases are the two most important aspects
for the successful rapid erection of precast concrete components. Other
related technical issues are lack of knowledge capability in designing the
details of ties and connections of the pre-fabricated components
particularly in precast concrete construction. Poor connection system may
cause problem to site work such that the connections cannot be joined
properly due to poor construction details. In the case of steelwork
structures, there are many cases where buildings were designed to imitate
the conventional reinforced concrete structural system. This concept
results in exposed steel beams and columns. Eventually this invites many
serviceability problems such as leakage. Rain water can easily seep into
the internal building through the joint between the wall and steel beam.
Dampness leads to corrosion to the lighting system and the steel beam.

3.2.4 Designing a Feasible IBS System


IBS system if properly designed can deliver a more efficient construction
process due to many advantages such as greater speed of construction,
simpler construction process, reduced environmental impact and reduce
reliance on traditional labours. Therefore the challenge is to provide a
feasible and innovative IBS system that is acceptable to those involved
with construction as well as the users.

In order to achieve a feasible IBS system, the aspect of standardization


should be incorporated in designing the system.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 26


RMT 558_Construction Management & Facilities Management 2009

The standardisation can include the use of standard connections,


standard beam and column sizes. Standardisation of components may be
incorporated to reduce the cost of manufacturing. By implementing
standardization, many errors in production or erection due to variability
can be reduced. Standardisation may lead to improvement in quality,
decrease variability and increase the ease of manufacturing. In this case,
the challenging aspect related to a feasible system is the manufacturing of
the components.

For example, the steel mould used to form beams and columns must have
high degree of precision to produce accurate and consistent dimensions of
width, breadth and length and other related dimensions. The mould should
be of high quality with enough durability and strength and not easily
becomes dented or buckled during compaction of the concrete. In the
case of mechanical connections, the built in connection accessories to be
cast in the concrete component, must be located precisely prior to
concreting. Similarly any sleeves or opening in the component must be
done accurately.

3.2.5 Investment on Heavy Equipment for Mechanized Construction


System
The successful IBS construction system has some degree of dependency
to heavy and special equipment such as cranes. The high initial cost in
setting up the manufacturing plant as well as the cost of transportation has
reduced the margin of profit. It has been noticed that despite all the
advantages of adopting IBS, a significant portion of the construction
industry players still has a biased perception on IBS system. It is admitted
presently that switching to IBS would not guarantee significant savings in
the cost especially with the small volume of buildings constructed.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 27


RMT 558_Construction Management & Facilities Management 2009

However, IBS has demonstrated that the savings in the construction time
is able to compensate the higher construction cost incurred.

3.2.6 Awareness
In order for IBS system to be understood and used widely, the challenge is
to create mechanism of awareness. Many contractors and even engineers
are not well aware of the IBS system and not involved with the use of any
IBS system in their construction methods. Therefore, in order to create
awareness among practicing engineers and contractors, campaign to
reassure that IBS systems are able to provide fast, economical and high
quality products should be carried out.

The awareness campaigns may include seminars and short courses. For
example, CIDB in collaboration with universities, manufacturers and
professional bodies have carried out extensive seminars and roadshow to
give exposure to contractors and engineers about the IBS system. Also,
hands-on trainings in specialised works such as operating cranes and
welding works are also conducted to provide specilised and trained
workers in the IBS industry.

3.2.7 Knowledge
Specialized and additional engineering knowledge will be required to
design, manufacture and construct a good IBS system. All parties involved
from designers to erectors must have enough knowledge about the pre-
fabricated component based construction. In terms of design, the
engineers must have competent knowledge in analysis and design. In the
construction field, the contractors and site engineers must have enough
knowledge on the safe and accurate methods of erecting and assembling
loose components into a global structure.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 28


RMT 558_Construction Management & Facilities Management 2009

At university level, the students should be taught structural design


principles, material technologies and construction practices related to IBS
system such as precast concrete structures. Some local universities are
currently improving their curriculum by adding new topics related to IBS in
the existing syllabus. For example subjects related to precast concrete
design and construction are also offered as elective for final
undergraduate and graduate students. Apart from that, testing and
research have to be conducted to prove feasibility of design. Knowledge
gained from advanced research may elevate the level of understanding on
the behaviour of IBS structure and consequently the level of confidence.

Engineers with good technical knowledge in analysis, design,


manufacturing and construction have the ability to produce systematic IBS
systems. If the components are skillfully designed, erection can be carried
out efficiently. Furthermore, complying with good practices in design and
construction leads to high quality precast concrete structures. In this
aspect, the challenge is to produce many good and reliable manufacturers
and erectors with such knowledge capabilities to be part of the IBS
construction team.

3.2.8 Adoption of IBS System


The government through CIDB has embarked the IBS Roadmap 2003-
2010 that outlines several well-thought strategies and aggressive steps to
promote the use of IBS in Malaysia To facilitate further, the government
has encouraged the use of IBS for the construction of new government
quarters. Contractors adopting the IBS system are given incentive such as
levy exemption based on the percentage of IBS usage in a project.. The
government is taking the leading role in persuading the construction
industry to adopt a more systematic approach and methodology in
construction.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 29


RMT 558_Construction Management & Facilities Management 2009

The effort, started in 1998, is a strategic change in the construction


industry. If IBS is adopted, efficient, clean, safe and innovative are some
of the new attributes that will be associated with the construction industry.
With these outstanding features, plus attributes such as professionally
managed and handled, workers with relevant skills, proper coordination
and management as well quality will inevitably make IBS an excellent
option for those involved in the industry to become global industry players
in the international arena that demands high quality, efficient and
professional services.

3.2.9 - Barriers to IBS Implementation

Despite the plausible advantages, the majority of contractors are sceptical


to use IBS method. In fact, the majority of contactors are not ready to bid
IBS construction tender. Warszawski (1999) highlighted implementation
risk of using IBS compared to conventional labour intensive method and
later observed that adaptation of standardization requires a tremendous
education and training effort. Pan et al. (2008) has highlighted the barriers
of using IBS construction in a survey conducted for UK housebuilders. The
most mention barriers according to UK housebuilders are higher in capital
cost, complex interfacing between systems and the nature of UK planning
system which is not favourable to IBS. Goodier & Gibb (2006) highlighted
barriers hindering the use of IBS that include an increase in overall cost,
client resistance, lack of guidance and information, increased in risk and
insufficient workers skill. In a report on off-site manufacturing in Australia,
Blismas (2007) observed that very low IT integration in the construction
industry, high fragmentation in the industry, cost related issues, a lack of
codes and standards, difficulties in financing, limited capacity of suppliers
as the barriers contribute to limited take up on IBS. It also observed that
transportation of panels and modules is much more difficult in IBS
construction (Rahman & Omar, 2006).

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 30


RMT 558_Construction Management & Facilities Management 2009

More serious is the problem of making joints, locking, gluing, welding,


hammering or snapping components together which need time and
experience for perfection and reduced wastage. Moreover, the method
itself involving mechanized system and skilled worker to coordinate and
assembly introduces demand of precision not needed in other method.
IBS also appear to be slightly an expensive choice over the traditional
method and not appealing option which need extensive training and
apprenticeship (Thanoon et al. 2003) (Rahman & Omar, 2006).

3.2.10 Negative perception on IBS

Rahman & Omar (2006) observed that the term IBS is often misinterpreted
with negative image due to its past failures and unattractive architecture.
These buildings are normally associated with pre-fabricated, mass
construction method, low quality buildings, leakages, abandoned projects,
unpleasant architectural appearances and other drawbacks. Due to the
poor architectural design, the old pre-fabricated buildings have given the
public, bad impression about pre-cast concrete. Clients are often in doubt
of using IBS because of fear of customer rejection. Even construction
professionals are in doubt in IBS technology and relate IBS with a
potential post-construction problem. In addition, it is always not popular
among the designers as they found pre-fabrication has limiting their
creativity in design process (Hamid et al. 2008).

It is observed that lack of IBS branding and promotion taking place in the
market as the end user are neither misinterpret nor unaware of this
construction method. As a result, IBS is not creating enough pull factors to
encourage developers to adopt IBS. In comparison, IBS development in
Scandinavian and Japan provide higher customer focus and adopt mass-
customization of to enrich customer option. In UK, IBS is well associate
with sustainability and green construction.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 31


RMT 558_Construction Management & Facilities Management 2009

Better customer perception will create better understanding and demand


and will definitely encourage developers to push for IBS adoption.

3.2.11 loose supply chain integration

Construction is a multi-organization process, which involves client/owner,


designer, contractor, supplier and consultant. It also is a multi-stage
process, which includes conceptual, design, construction, maintenance,
replacement, and decommission. By moving construction activities
upstream from the construction site to factories where pre-assembly is
carried out, high demands will be raised on the management of the supply
chain and logistic activities (Pan et al. 2008) (Blismas, 2007) (Gibb, 2001).

In such arrangement the risk involve with any construction quality and
tolerance are also clearly identify and the party responsible for taking
corrective action is agreed from the outset of a project. Extensive
integration requires good IT tools to ensure supply chain continuity and
synchronization. Integration also includes developing supplier partnership
and establishes clear information flow using IT (Oostra & Jonson, 2007).
However, the current state of construction industry is being considered as
fragmented where the whole supply chains get their own strategy and
agenda. To worsen the situation, IT adoption in Malaysia is still low and
contribute to loose supply chain coordination and integration between
design and manufacture which is vital to IBS implementation.

3.2.12 Poor knowledge and lack of awareness

Client- According to IBS Roadmap Review (2007) report, the adoption of


IBS in Malaysia is a client driven e.g. Jaya Jusco, Tesco etc. where client
has insist on fast track construction. In housing development, client with a
good knowledge and awareness of IBS benefit will therefore encourage
appointed designers to design building in IBS.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 32


RMT 558_Construction Management & Facilities Management 2009

However, lack of awareness program lead to misinterpretation and thefore


contributed to a lack of interest from the client and decision makers
(Rahman & Omar, 2006). From the client point of view, unless the were
necessary fast track project e.g Tesco, Jusco project, IBS is often
misinterpreted as high risk and expensive solution.

Designer- Lack of knowledge among the IBS designers contributes to the


project delays. Designer need extra time to produce details drawing etc.

Local Authorities - Poor knowledge among the approving authorities has


resulting misunderstanding and misinterpreting of IBS and its relation to
the current building regulation. Familiarity with IBS will expedite design
approval and it is vital to ensure successful IBS project (Construction
Industry Master Plan, 2007). The majority of the authorities nonetheless is
not aware of IBS design and often takes more time than usual to process
design approval.

Policy Makers- It is also observed by Chung & Kadir (2007) recently that
of local authorities in Malaysia are unlikely to change local building
regulation to suit IBS as the amendment will consume a lot of time and
cost.

According to IBS Mid Term Review (2007), the enforcement of Modular


Coordination (MC) trough the amendment of Uniform Building by Low
(UBBL) is yet to be implemented due to poor knowledge and awareness
on this concept among the policy makers.

Workers- Government hoped IBS would help reduce dependence on


foreign workers by 30 per cent by 2015. But most industry people don't
think IBS will greatly reduce the number of workers in the industry. IBS is
taking the problem from a job-site environment to a factory environment,"
said a senior industry insider. Pre-cast means instead of going to the job

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 33


RMT 558_Construction Management & Facilities Management 2009

site to cast, I'm going to the factory to do the casting and then putting them
together at the job site. So how can you do pre-cast without the wet-trade
workers. He stressed that there's still a lack of skilled local workers
because of the mismatch between the training the CIDB provides and
industry needs (NST 30/8/2008)

3.2.13 Improper planning and failed to consider IBS at the design


stage
IBS as alternative method - At presents, the pre-casters and contracting
firm in Malaysia are involved after tender stage of the construction value
chain. IBS design needs to be addressed and plan form the design stage
to be successful adopted trough the integration of pre-caster, designer
and contracting firm and not trough proposing alternate design (IBS
Roadmap Review, 2007). As a result, a lot of IBS project in Malaysia (IBS
as alternate design) is not cost effective because the process of changing
in design requires a lot of further adjustment will rise the initial time and
cost. If IBS is considered at design stage will also solve issues related to
manufacturing, transportation and logistic that can be pre-plan ahead of
time.

Lack of proper planning on IBS - Moreover, IBS requires more coherent


structure of process planning and control from start to end of the project in
order to reach the goals and reduce defect and errors (Gibb, 2001)
(Warszawski, 1999).

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 34


RMT 558_Construction Management & Facilities Management 2009

"Books from Prof.Alistair G.F. Gibb; Off-site: prefabrication, pre-


assembly and modularisation and Industrialised and Automated
Building Systems : A Managerial Approach by Abraham Warszawski.
Prof.Gibb currently attached at University of Loughborough is
Frenchmen. When my first time i met him at UKTI Offsite / IBS
Seminar at Kuala Lumpur in 2005. While Warszawaski from Israel, i
had never met him before" (Rfd21 @
http://buildingsystem.blogspot.com/)

The overall project should be planned in such way that as soon as the
components are manufactured, it is possible to transport it to the
construction site and assemble it. Any delays either on manufacturing floor
or construction site has severe impact on staging requirement and
production planning where components from several construction projects
are scheduled for production at the same time.

Result - There are cases, where building projects are awarded and
constructed using IBS system but were carried out with many difficulties.
The most common problems encountered are improper assembly of the
components that normally involved the beam-to-column and column-to-
base connections due to impropoer planning and coordination at design
stage (Rahman & Omar, 2006)

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 35


RMT 558_Construction Management & Facilities Management 2009

3.2.14 IBS appears to be more expensive compared to traditional


method

"The key technology to IBS is the preparation of precast building


structure off-site, which is then brought to the construction site and
assembled. This allows building to be constructed with minimal effort
and time at the construction site, which in turn provides tremendous
cost savings to the contractors" (IBS Modular
@http://ibsmodular.blogspot.com/)

IBS appears to be slightly expensive choice over the traditional method


and not an appealing option to decision makers in Malaysia. IBS
construction requires high initial investment capital for pre-casters to
purchase new machinery, mould, importing foreign technology and wages
of skilled workers for installation process (IBS Steering Committee, 2006)
(Thanoon et al. 2003). IBS is also unattractive choice due to wide swing of
housing demand, high interest rate and unsure economic condition
(Thanoon et al. 2003).

"The potential for IBS sector in Malaysia is enormous to say the least. The
conservative estimate of the industry is approximately to RM2 billion,
making the future of the industry secure" (IBS Modular @
http://ibsmodular.blogspot.com/)

For contractor, using pre-fabricated components in IBS project require


them to procure the components in advance with requiring of paying
upfront deposit. This will give affecting the cash flow of existing payment
over project progress system. As a result, small and medium class
contractors viewed IBS as threats to their business and not as
opportunities (IBS Roadmap Review, 2007).

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 36


RMT 558_Construction Management & Facilities Management 2009

It appears that existing procurement and contracting system is not


‘favorable’ to both pre-caster and contractor which using IBS method.

3.2.15 Technical problem related to IBS

One of the biggest drawbacks for IBS adoption is the tendency to post
construction failure. It is much related to improper installation by untrained
constriction workforce and relatively wet climate in Malaysia.

For example, Lumut Naval Base project which consists of 29 blocks of 11-
storey apartments which was constructed in 1976 by Hazama Gumi and
supervised by FH Kocks GmBH who is the consulting engineers at that
time. The 11-storey apartments are built using pre-cast concrete walling
system. The apartments are still facing problems until today with regards
to defects caused by water penetrations and leakages largely due to the
construction joints and panel integration between the wall system and the
floor system (Anon, 2008). There's also an issue of renovation works
carried out which is constraint by the pre-cast system design and also the
M & E system. It will make IBS system not popular choice for developer
and customer because the majority of house owner in Malaysia would like
to renovate their dwelling at some point of their tenancy.

3.1.16 Mismatch between the roadmap and readiness among


contractors and designers.

The paper has agreed and accepted that IBS is ideal conceptualization
and simplifying construction work. However, the reality in the projects is
far from practical idealism in Malaysia. The transformation is not green a
good respond due to the unlikely construction readiness (Hamid et al.
2008). Superior construction technology requires highly skilled workers to
replace foreign workers but contractors left with no other choice.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 37


RMT 558_Construction Management & Facilities Management 2009

Local workforce is reluctant to join the industry because of the issues of


low wages combined with low emphasis on occupational safety and
health. The current training program to produce new construction
workforce is still not be able to cater vast demand of the market.

As such, regardless of foreign worker policy, foreign labor to do manual


job is still badly needed by the industry and it is available abundant in
cheaper cost (Construction Industry Master Plan, 2007).

Moreover, specialized skills such as system integrator or assemblers need


intensive training and apprenticeship which require more time and
investment (Thanoon et al. 2003) (IBS Steering Committee, 2006)
(Rahman & Omar, 2006). Contractors in Malaysia are also lack of past
experience in IBS and their professional is lack of technical knowledge in
this area (Hamid et al. 2008). Hamid et al. (2008) also observed lack of
R&D, low IT adoption and limited technology availability have generally
discourage IBS take up. It also appears that most innovative system and
components or using innovative materials are based on imported
technologies which are obviously more expensive and difficult to
purchase by local contractor (IBS Roadmap Review, 2007).

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 38


RMT 558_Construction Management & Facilities Management 2009

CHAPTER 4.0 – RECOMMENDATIONS AND WAY FORWARD.

4.1Introduction

An early effort by the Government of Malaysia to promote usage of Industrialised


Building System (IBS) and develop an Open Building System (OBS) concept as
an alternative to conventional and labor intensive construction method has yet to
make a headway. Although members of the industry are open to the idea, a
major portion of the industry stakeholders are indifferent, perhaps due to
resistance towards change, insufficient information and lack of technology
transfer method to support feasibility of change to IBS. In this case, it has proven
that it is difficult to introduce new technologies and method in the construction
sector when compared to other sectors. According to Hervas et. al (2007)
construction sector is known as a traditional sector that can be characterised as
reluctant and even resistant to change.

4.2 Recommendation and The Way Forward

4.2.1 K-Management
As the era of the K-economy enters into it’s stride, it is obvious that Global
players competing to provide unique services, processes, materials and systems
tends to impart better quality, higher speed and competitive costs. However,
there is deep concern that the construction industry as a whole is
underachieving. It has for many years maintained the time-tested but labour
intensive traditional approach in construction and investing too little in research
and development (R&D) and training even in this knowledge era. (IBS
Digest,2006)

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 39


RMT 558_Construction Management & Facilities Management 2009

Technological advances shall play a major role in changing the competitive work
environment in the construction industry and in providing companies with
capabilities to successfully produce and field new products, processes and
systems. The construction industry must indulge itself in innovations and
supportive of new ways of doing things. (IBS Digest,2006)

Knowledge was the driving force behind the Industrial Age. It was somehow
subsided and nearly forgotten until the next wave arrived which is the Digital Age.
This new age has resurfaced knowledge again as one of the key dimension to
propel global growth. Hence, Knowledge Management (KM) is now an important
discipline and an essential source that our economy cannot afford to do without,
if we were to have competitive advantage and remained relevant. (IBS
Digest,2006)

In Wikipedia, KM refers to a range of practices used by organizations to identify,


create, represent, and distribute knowledge for reuse, awareness and learning
across the organization. From business standpoint, Harvard Business Review
refers KM as the way companies generate, communicate, and leverage their
intellectual assets.
(IBS Digest,2006)

We have also seen over the last ten years, highly significant event took placed
on the advancement and explosion of information and communication technology
(ICT) driven by the liberalization of global economies. This has lead to
tremendous transformation in the manner businesses are being executed. (IBS
Digest,2006)

The world is not only becoming borderless but also flatter instead of round as the
bestseller writer, Thomas L Friedman put it. Information are now highly
accessible and being exploited to an unimaginable scale.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 40


RMT 558_Construction Management & Facilities Management 2009

The rat race for market positioning is as fierce as ever through the capitalization
of information, knowledge and innovation.This scenario has also lead major
economies to have greater access than ever before into countries such as India
and China to exploit its competitive resources leading to a more competitive
product and services in the marketplace. With this challenging phenomenon, it is
now overdue and absolutely critical that we need to expedite our readiness, the
know-how and competitiveness of our Malaysian Construction Industry in order
to survive and sustain; an industry which is now minus 1.6 % growth based on
2005 government statistics. (IBS Digest,2006)

The fragmented nature of our industry need to be consolidated and reconstructed


in order to realize the government’s aspirations on the National IBS Roadmap
which targets the industry to be industrialized by the year 2010. (IBS
Digest,2006)

As part of efforts to steer various sectors towards our Vision 2020, the Malaysian
government has also launched the National Knowledge-Based Economy
Masterplan which was first announced by the government in the Budget 2000.
This masterplan marks yet another key government initiative to further accelerate
the development of the nation into a knowledge-based economy. It provides
strategic framework outlining the changes to the fundamentals of the economy.
(IBS Digest,2006)

These National IBS Roadmap and Knowledge-Based Economy Masterplan have


provided a good base information related the policy targets and objectives.
However, this information alone will not progress our industrialisation effort. It is
only a reference document on policy direction. As such, strategies still need to be
formulated downstream within each sector. In doing so, we need to capture our
industry knowledge, consolidate, reconfigure and strategise to our best
competitive advantage, in order to progress. (IBS Digest,2006).

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 41


RMT 558_Construction Management & Facilities Management 2009

Another misconception on KM is that it is ICT oriented. ICT is purely a tool to an


end. It should not be treated as the driving factor for KM. Business strategies and
direction instead, are the true drivers for KM. With a cohesive and collaborative
effort involving government and industry, we are in position to consolidate our
fragmented industry information and ignite our latent intellectual assets. We
believe such assets do exist based on our exposure in national mega
infrastructural projects over the past 15 years as well as the world is now being
flatten with information at the press of a button. (IBS Digest,2006)
TO R
However, efforts on the ‘HOW TO’ for the National IBS Roadmap seems way
behind and need to be urgently accelerated. (IBS Digest,2006)

One of the major factor for this delay is that the industry by nature, is very much
project based instead of program based. The soft aspect has not been fully
exploited especially on the management of industry knowledge.
(IBS Digest,2006)

A knowledge based construction industry would induce a conducive environment


to propel the acceleration of our IBS Roadmap. However, current mindset on
‘information protectionism’ need to be phased out. This is very much due to the
current ‘Red Ocean’ overcrowded marketplace whereby companies are engaged
in head-to-head competition struggling to survive, let alone to sustain. (IBS
Digest,2006)
“The development of human capital, the upgrading of the mentality and
intellectual capacity of a nation is one of the biggest challenges under the Ninth
Malaysia Plan. If we wish to become a knowledge-based economy, if we wish to
be a developed country and maintain that developed status, the development of
human capital must be a priority. In the context of globalisation, high quality
human capital has become a necessity, not merely a luxury.”
YAB Dato’ Seri Abdullah Ahmad Badawi, 9MP Speech, 31st. March 2006

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 42


RMT 558_Construction Management & Facilities Management 2009

The ultimate way forward is for us to inject into ourselves intellectual knowledge
which will lead us to the Know-How by becoming the specialist within the
marketplace. This can be achieved by being more open minded, unbiased,
neutral, patriotic, passionate and aggressive in our efforts to support and
participate in the realisation of our National IBS Agenda .IBS on the other hand,
is a new industry with endless opportunities. In order to commence with this
exploration, it has to start with knowledge sharing as the new working culture
within the industry. This approach encourages investment on ‘trust’ which in turn,
will lead companies who used to be in competition, to better understand each
other and collaborate for improved market positioning in this new ‘Blue Ocean’
industry.(IBS Digest,2006)

It is only with this ‘Open Collaboration’ environment that we are able to induce
participation, develop and steer, impactful downstream strategies to support the
roadmap implementation.This effort on KM however, need to be driven from both
top and bottom ends of industry heirarchy. Apart from being policy driven, each
industry organization plays an equally crucial role in developing industry’s
intellectual capability. This effort will result in the organization to be more
specialize and therefore provides an improved strategic positioning for the
industry as a whole. (IBS Digest,2006)

Based on the above, we need to create our own speciality and niche in order to
sustain. It is only through KM that this can be achieved and therefore,
necessitates companies to review their internal organizational strategies and
methodologies(IBS Digest,2006)

The essence of KM in an organization is best put forward by Alex Bennet, former


Chief Knowledge Officer of US Department of Navy. She describes the essence
of knowledge management is built on intellectual capital, which includes human

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 43


RMT 558_Construction Management & Facilities Management 2009

capital, social capital and corporate capital. All three are essential components of
enterprise knowledge (see diagram) (IBS Digest,2006)

Human capital is our greatest resource. It is made up of an individual’s past,


present and future. Social capital related to communications, human and virtual
networks, relationship, collaborations, etc. As for Corporate Capital, it covers
intellectual property, corporate assets and organizational processes. Knowledge
Management can be viewed as a process for optimizing the effective application
of intellectual capital to achieve organizational objectives.(IBS Digest,2006)

The current industry however, perceived as having assets, financial capital and
staff would be sufficient to realize company objectives. It is more focus on the
tangible aspect of the organization. The crucial intangible elements were
completely overlooked and this has impacted our competitiveness (IBS
Digest,2006)

In conclusion and as way forward, we clearly need to diagnose ourselves as


individual, company, associations, industry as well as the policy makers on the
state of our readiness to persevere the demanding and exhaustive rat race for
market positioning, and most critically our existence and sustainability in this ever
challenging Global climate. (IBS Digest,2006)

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 44


RMT 558_Construction Management & Facilities Management 2009

CIDB believes that R&D is the way forward for developing IBS. The R&D themes
and topics for IBS are aligned to the requirements of the IBS Roadmap 2003-
2010. Although the initiatives in IBS are lead by CIDB, participation from
contractors, consultants, academia, companies and research institutes are
critical. It is a daunting task as 2010 is just around the corner. The processes and
mechanisms to accomplish the target depend on the integration and acceptance
of IBS by players.

The coming three years will be very challenging. A strategic approach will be the
way forward. As the R&D arm for CIDB, CREAM’s R&D output will geared
towards industry’s application and requirements.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 45


RMT 558_Construction Management & Facilities Management 2009

4.2.2 CIMP and CREAM as strategic directions

A combination of integrated approaches and long term strategic partnering with


stakeholders tackling specific agenda on IBS’ 5M strategies are the way
forward. Well co-ordinated and planned R&D themes and titles discussed in
earlier section have to be implemented simultaneously with all players.

The content of Strategic Thrust 5 simplified in Figure 1 realized the importance of


IBS as the way forward for the construction in reducing labour dependency which
is expected to grow to 5 million people in 2010 (Utusan, 19th. June, 2005).

Despite policy and promotion of IBS, the implementation is still slow except in
Klang Valley. The common critical success factors identified to address the slow
uptake of IBS by the construction stakeholders include:
o Lack of driver/s from the construction industry stakeholders,
o Government initiatives (i.e. directives, incentives, secure projects) are
required,
o Price competitiveness
o Whole life cycle costing
o IBS Supply Chain
o Information Sharing
o One channel of implementation from Government Agency(i.e. JKR, KPKT)
o Centre of Research Excellence for the implementation of IBS
o Aesthetics
o Quality Control, speed
o Lack of knowledge on IBS

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 46


RMT 558_Construction Management & Facilities Management 2009

Strategic Thrust 5
In order to realize the implementation and expected target of IBS in Malaysia,
CIDB together with the stakeholders and experts have successfully published a
document titled IBS Roadmap 2003-2010 (summarized in Figure 2) as the action
plan for the industry to refer to and implement.
CIMP 2006-2015 and IBS Roadmap 2003 - 2010 are the strategic directions for
the industry to move forward. The understanding of each of the document needs
to be discussed with the stakeholders to strategize and to implement IBS.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 47


RMT 558_Construction Management & Facilities Management 2009

CREAM shall take the following actions as a prerequisite to expedite the


success of the roadmap implementation with respect to IBS:
 A long term and strategic approach of conducting research on IBS shall be
established,
 The involvement of universities, companies, organisations and research
institutes right from the onset of any IBS R&D project,
 Participation and inclusion of IBS in JKR building design, i.e. JKR IBS
Design must be incorporated in its Rekabentuk Bangunan Piawai for
Government quarters, schools and Government administrative offices.
(CREAM should discuss this matter further with JKR on any issues related
to R&D).
 Malaysian standard joints for IBS (wet or dry) must be designed and made
available for use by industry,
 CREAM initiatives to lead Centre of Research Excellence on IBS and act
as One Stop Centre for R&D are critical as this moves will consolidate the
effort to centralize and identify issues and problems first hand from
industry,
 The formation of R&D laboratory and CORE for IBS is urgent and CREAM
should initiate and take the lead,
 CREAM is to apply for double deduction status to expedite participation
from private entities as they will also benefit in getting tax rebates when
contributing research funds,
 Open Building System must be competitive in terms of cost, performance
and quality as compared to proprietary system and conventional methods
in order to be sustainable in the construction market,
 Not reinventing the wheel on R&D but to focus on IBS applied research,
 Soft issues related to IBS such as marketing, social impact, involvement of
Bumiputra contractors in vendor development programme as highlighted
in the roadmap should be taken on board at the early stage,

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 48


RMT 558_Construction Management & Facilities Management 2009

 A complete comprehensive study on IBS solutions encompassing the


entire value chain will ensure its success. These shall include verification,
validation and certification of process on IBS components, fabricator,
factory, erector and related skills of specialization,
 A technology transfer model via knowledge management adapted from
EU, Japan and Singapore best practices in implementing IBS will add
value and expedite the implementation process.

4.2.3 Endorsement of IBS Roadmap 2003-2010

The endorsement of IBS Roadmap 2003-2010 in Malaysia by the Malaysian


Parliament on 29th October 2003 expressed seriousness of the government and
the urgency of IBS implementation. It is a blueprint of total industrialisation of
construction industry towards achieving Open Building industry by the year 2010.

The roadmap is a comprehensive document that divided the IBS programme into
the five main focus areas that reflect the inputs needed to drive the programme
(Manpower, Materials, Management, Monetary, and Marketing) (IBS Roadmap,
2003).

The content of this roadmap is focused towards achieving the industrialisation of


the construction sector and the longer term objective of implementing Open
Building Systems concept. The key elements and activities of the roadmap are to
have a labour policy that gradually reduces percentage of foreign workers,
improve Uniform Building By- Law (UBBL), develop IBS professional courses and
IBS university syllabus, develop IBS standard plan for common use, establish
verification and certification scheme, establish vendor developing program and to
study relevant incentive to encourage IBS adoption.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 49


RMT 558_Construction Management & Facilities Management 2009

Industrialized Building Systems (IBS) or off-site construction has been introduced


to cope with a growing demand of affordable housing, solving issues associated
with foreign workers and improving image, quality and productivity of construction
related services in Malaysia.

Prior that, IBS Roadmap 2003-2010 has been published by the Government of
Malaysia to guide the practitioners, government agencies and professional
bodies with the strategies and implementation plan. Construction Industry Master
Plan (CIMP 2006-2015) has also higlighted the important of IBS under Strategic
Thrust 5. Nevertheless, despite the plausible advantages and strong support
from the government, IBS adoption in Malaysia has yet to obtain a good
response. This research is one of the innitiative by Construction Research
Institute of Malaysia (CREAM) and Construction Industry Development Board
(CIDB) Malaysia to benchmark best practice in those Critical Success Factors of
IBS companies in UK and Europe.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 50


RMT 558_Construction Management & Facilities Management 2009

The 5-M Strategies

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 51


RMT 558_Construction Management & Facilities Management 2009

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 52


RMT 558_Construction Management & Facilities Management 2009

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 53


RMT 558_Construction Management & Facilities Management 2009

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 54


RMT 558_Construction Management & Facilities Management 2009

4.2.4 Enforcement of the legislation, regulations, guidelines and Standards

Having identified the major impediments to the introduction of IBS in the country,
it is important to suggest measures to facilitate adoption of IBS. As we can
clearly see that lack of enforcement of the legislation, regulations, guidelines and
standards are major hindrances. Therefore the process of enforcement of
regulations needs to be done step by step to enable the IBS to be standardized
through modular coordination.

The first step is to study the current status of the construction industry in terms of
controlling the dimension of the prefabricated concrete product. The study
involves legislations, planning, design, manufacturing industry, construction
technology, surveying work and etc. The result of the study is used as a
foundation to plan for the implementation of modular coordination in IBS in
Malaysia. It is also used to formulate the National Modular Coordination Standard
MS 1064 as a basis to standardize the dimension for the design of building and
the fabricated components using metric system.

Next, the strategic planning for the implementation of modular coordination need
to be done. This strategic implementation plan needs to consider the construction
organization structure, the collaborative measures and the further improvement
that can be made to the current system practiced. This is to ensure that the
implementation of IBS using the modular coordination can be done successfully.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 55


RMT 558_Construction Management & Facilities Management 2009

Then, The effort will focus on the preparation of Malaysia Standard (MS) 1064 :
Guide to Modular Coordination in Building. Currently, there are 15 parts has been
approved for implementation by the Government of Malaysia.

Lastly, the execution of modular coordination through legislation is very important


to succeed in the industrialized building programmed. The implementation of
modular coordination into the uniform Building by Law, planning standard and
the building specification need to be executed. The government department such
as public Works Department and the local authorities are responsible to
introduce modular coordination through building regulations and specifications as
soon as possible.

4.3 Successful Implementation of IBS Projects

With the advanced knowledge in computer aided design, IBS buildings can be
designed and visualised analytically prior to the actual construction. The 3-
dimensional drawings can be developed to provide accurate component
dimensions and hence ensure buildability. Erection and construction procedures
can also be simulated and properly planned with the use of computer softwares.
Feasibility studies on the different building systems can be performed without
incurring much cost. Problems during construction can also be observed and
predicted. Any rectifications to the component design can be done before the
manufacturing process. These computer tools contribute to a well-planned and
systematic IBS system.

In relation to the advancement in computer-aided design, IBS buildings built in


Malaysia in the 1990s have shown significant improvement in terms structural
performance and architectural aspects. Some of these structures have become
the showcases and even the icon of the country.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 56


RMT 558_Construction Management & Facilities Management 2009

One good example is the Brickfields Secondary School 1. The school is located
in a busy and limited access site. With such construction constraints and to
expedite construction period, a building system utilising about 75% of pre-
fabricated components of precast concrete beams, columns, hollow core slabs
and solid planks were adopted. The precast concrete skeletal framed IBS system
is also widely used in many other projects. Figures 6 and 7 show the precast
concrete buildings that were built using precast concrete components of beams,
columns and slabs.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 57


RMT 558_Construction Management & Facilities Management 2009

Another successful examples of IBS systems using precast concrete load


bearing wall system are Senawang Police Quarter (see (a)), teachers’ quarters in
Kuala Kangsar (see (b)) and government quarters in Putra Jaya (see F(c)). A
total of 10,000 units of teachers’ quarters were built throughout the country using
the standard structural and architectural design.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 58


RMT 558_Construction Management & Facilities Management 2009

In the case of steel structures, there are also many successful IBS projects.
Figure 9 shows the KLCC convention centre, an icon building in the prestigious
Kuala Lumpur city centre. The building was built using a combination of
prefabricated steel roof truss with composite steel deck flooring system.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 59


RMT 558_Construction Management & Facilities Management 2009

5.0 Conclusion

Industrialized Building Systems (IBS) or off-site construction has been introduced


to cope with a growing demand of affordable housing, solving issues associated
with foreign workers and improving image, quality and productivity of construction
related services in Malaysia. Prior that, IBS Roadmap 2003-2010 has been
published by the Government of Malaysia to guide the practitioners, government
agencies and professional bodies with the strategies and implementation plan.
Construction Industry Master Plan (CIMP 2006-2015) has also higlighted the
important of IBS under Strategic Thrust 5. Nevertheless, despite the plausible
advantages and strong support from the government, IBS adoption in Malaysia
has yet to obtain a good response.

Survey on IBS system has been conducted through out Malaysia in 1996. The
purpose of this survey is to gather information on IBS buildings in Malaysia.
Besides that, a visual inspection study was also conducted to observe of any
problems related to IBS system. IBS features potential construction system for
the future with emphasis on quality, higher productivity and less labor intensive.
Besides the aim of gradually reducing the dependency on foreign labor and
saving the country’s loss in foreign exchange, IBS provides the opportunity for
the players in the construction industry to project a new image of the industry to
be at par with other manufacturing-based industry such as the car and electronic
industries.

The adoption of IBS promises to elevate every level of the construction industry
to new heights and image of professionalism. Finally, IBS should be seen as the
modern methods of construction where modern and systematic methods of
design, production planning and mechanized methods of manufacturing and
erection are applied.

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 60


RMT 558_Construction Management & Facilities Management 2009

The government through CIDB has embarked the IBS Roadmap 2003-2010 that
outlines several well-thought strategies and aggressive steps to promote the use
of IBS in Malaysia To facilitate further, the government has encouraged the use
of IBS for the construction of new government quarters. Contractors adopting the
IBS system are given incentive such as levy exemption based on the percentage
of IBS usage in a project.. The government is taking the leading role in
persuading the construction industry to adopt a more systematic approach and
methodology in construction.

The effort, started in 1998, is a strategic change in the construction industry. If


IBS is adopted, efficient, clean, safe and innovative are some of the new
attributes that will be associated with the construction industry. With these
outstanding features, plus attributes such as professionally managed and
handled, workers with relevant skills, proper coordination and management as
well quality will inevitably make IBS an excellent option for those involved in the
industry to become global industry players in the international arena that
demands high quality, efficient and professional services.

INDUSTRIALISED Building System (IBS) or pre-fabricated construction has not


yet met its targeted objectives, a Construction Industry Development Board
(CIDB) official said. CIDB chairman Tan Sri Jamilus Hussein said although the
administrative structure to transform from labour-intensive construction to a more
capital-intensive sector is in place, the market has not fully embraced the
concept. "With only two years to the end of the IBS Roadmap, we are far from
achieving the objectives," he said in his keynote address at the Malaysian
International IBS Exhibition (MIIE 2009) in Kuala Lumpur on 28 January 2009.

IBS is a technique that uses pre-fabricated components or off-site installation,


where project clients and developers can benefit from reduced building material
wastages. This is because the components are made to size already. The
system will enable buildings to be developed faster and stronger, hence save

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 61


RMT 558_Construction Management & Facilities Management 2009

costs and time. It will also help reduce dependence on foreign workers from
320,000 now to 250,000 by 2015. Works Minister Datuk Mohd Zin Mohamed had
said that more than two-thirds of the RM9.6 billion infrastructure projects under
the Public Works Department and related agencies must use IBS.

The IBS is a strategic step to move the local construction industry further up the
value chain, transforming it into a service industry that deals with components
manufactured in factories. "To achieve the objective, industrialisation of IBS
is essential to utilise market forces to bring down prices. We must also
review the IBS scoring system and separate the data on infrastructure
fabricated components from building IBS,"

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 62


RMT 558_Construction Management & Facilities Management 2009

References :

1. IBS Digest, Industrialised Building Systems Issue 2 2006 : ISBN 983-


2724-29-5
2. IBS Digest, Industrialised Building Systems Issue 1 2007
3. Rahman,A and Omar, W, Issues and Challenges in the
Implementation of Industrialised Building Systems in Malaysia.
4. Alashwal,A.M, Optimising Production line of IBS by using simulation
5. Chung,L.M, Implementation Strategy for IBS
6. http://www.cream.com.my/files/Summary.pdf
7. http://www.efka.utm.my/thesis/IMAGES/4MASTER/2008/JSB-
P/noriwanima071084d08ttt.pdf
8. http://ibsmodular.blogspot.com/2007/01/industrialised-building-
systems.html
9. Industrialised Building Systems (IBS) Roadmap 2003 – 2010. 2003.
Construction Industry Development Board.
10. http://www.mbam.org.my/mbam/images/@IBS%20-
%20Current%20Shortcomings%20And%20The%20Vital%20Role%20(62-
65).pdf
11. http://www.cidb.gov.my/cidbweb/information/publ/IBS%20Digest%202006
%20-%201.pdf
12. http://www.utusan.com.my/utusan/info.asp?pg=special/speech_2005budg
et.htm
13. http://findarticles.com/p/articles/mi_qn6207/is_/ai_n24955950
14. http://salfordbenchmarking.blogspot.com/2008_07_01_archive.html
15. http://www.asiaconst.com/past_conference/conference/14th/08Malaysia.p
df
16. http://www.asiaconst.com/past_conference/conference/14th/08Malaysia.p
df
17. http://eng.upm.edu.my/hrc/newsletter/nlv2i2.pdf

Industrialised Building System(IBS) by Jaspal Azam,Hidayah,Sharon,Syafiq,Ooi 63

Вам также может понравиться