MILESTONE LIST

KEADUE WWTP UPGRADE WORKS

KMCF ENGINEERING DUBLIN ROAD ATHLONE

2014

Milestone List Project: Upgrade Works to WWTP at Keadue, Co. Roscommon Milestone No.
1 2 3 4 5 6

Start Date: 01/03/2014 Completion Date


22/04/2014 09/05/2014 06/05/2014 07/06/2014 26/05/2014 17/06/2014

Milestone

Mandatory/Optional

Verification

Tendering Procurement Preliminaries Construction Testing Completion

Mandatory Mandatory Mandatory Mandatory Mandatory Mandatory

Project Manager Project Manager Project Manager Project Manager Site Engineer Site Engineer