Вы находитесь на странице: 1из 1

Test Pressure:

Line Number
Line
Size
Drawing or Isometric
Number
Rev
(At Time
of Test)
From To
Paint
Code
Insul.
Code
Remarks
Note: Before procede with Pressure Test , N.D.E. and PWHT completeness shall be
by verified by Q.C.I.
Name Signature: Date:: Engineer: Name Signature: Date:
Approved by Company Company
Inspector: Name Signature: Date:: Inspector: Name Signature Date:
Verified by : Contractor QCI
eni Iraq b.v. - Zubair Oil Field Development Project
Reference : Piping Pressure Test Procedure No. 00250600DBQR2008M
Pressure Test Duration :
Format No. QIR- 118 sheet 1 of
Verified by : Contractor QCI
All above indicated Piping Lines have been Pressure Tested
with satisfactory result.
Work Package of Existing DGS Modification
PIPING PRESSURE TEST REPORT
Piping Test Pack No:
2) Gage No.:
Test Media:
1) Gage No.: