This section describes the method of measurement for masonry works including brick work, block work, and stone work. Brick/block work is measured along the centerline of the wall with no deductions for openings under 0.1 sqm or strings/sills/lintels if their height is less than or equal to one brick/block. Stonework is measured by mean dimensions with no deductions for voids under 0.1 sqm or strings/sills/lintels. Works are deemed vertical, and brick/block/stone walls, projections, isolated piers, steps, and stone walls, isolated/attached columns, lintels, and steps are measured by thickness, length, or number.
This section describes the method of measurement for masonry works including brick work, block work, and stone work. Brick/block work is measured along the centerline of the wall with no deductions for openings under 0.1 sqm or strings/sills/lintels if their height is less than or equal to one brick/block. Stonework is measured by mean dimensions with no deductions for voids under 0.1 sqm or strings/sills/lintels. Works are deemed vertical, and brick/block/stone walls, projections, isolated piers, steps, and stone walls, isolated/attached columns, lintels, and steps are measured by thickness, length, or number.
This section describes the method of measurement for masonry works including brick work, block work, and stone work. Brick/block work is measured along the centerline of the wall with no deductions for openings under 0.1 sqm or strings/sills/lintels if their height is less than or equal to one brick/block. Stonework is measured by mean dimensions with no deductions for voids under 0.1 sqm or strings/sills/lintels. Works are deemed vertical, and brick/block/stone walls, projections, isolated piers, steps, and stone walls, isolated/attached columns, lintels, and steps are measured by thickness, length, or number.
1. Measurement of Masonry Works (Section G): - This section covers the method of measurement of o Brick work o Block work o Stone work o Accessories for brick / block /stonewalling. 2. Brick work / Block work (Section G1): - Brick work / block work measured along the centerline of the wall. - Deductions are not made for following; Openings / Voids =/< 0.1 m 2 . Strings / sills/ lintels/ corbels, if height is equal /less than one brick / block work. - Thickness stated is nominal thickness. - Works deemed vertical. 2.1. Walls - thickness stated - m 2
2.2 Projections are attached piers whose length on plan is =/< 4 x their thickness. - m 2
2.3 Isolated Piers thickness stated - m 2
2.4 Steps (nr) - m 2
3. Stone work (Section G2): - Stonework measured according to mean dimensions. - No deduction is made for: o Voids = / < 0.10 m 2
o Strings / sills/ lintels/ corbels. - Thickness stated is nominal thickness. - Works deemed vertical. 3.1 Walls - thickness stated - m 2
3.2 Isolated columns - m 3.3 Attached columns - m (Columns are walls whose length on plan is =/< 4 x their thickness). 3.4 Lintels - m 3.5 Steps (nr) - m