DAILY LOG OF CONSTRUCTION

M T W Th F
PMIS. No.:
PROJECT:

PARK CONTRACT NO. DATE
October 19, 2014
CONTRACTOR CONTRACTOR REPRESENTATIVE ON JOB

WEATHER (Rain, Snow, Cloudy, Windy, etc.) TEMP. GROUND CONDITIONS (Dry, Damp, Wet, Frozen)
High Low
NO. CONTRACTOR'S MEN BY JOB CATEGORIES NO. SUBCONTRACTOR'S MEN BY JOB CATEGORIES
EQUIPMENT ON JOB
Brief description of size
No.
Units
Working
Yes No
MATERIALS DELIVERED
OFFICIAL VISITORS TO JOB SITE
STATUS OF WORK
ITEM
No.
Brief description of work in progress, questionable performance, etc. Include tests made and samples taken.
(Use comments section on reverse for other information, if necessary)
SIGNATURE TITLE:
FORM No. QCA-1
Rev. 01/03/05
CM INSPECTOR
CRITICAL POINT/MILESTONE INSPECTIONS (Describe item inspected, observations, problems, action items)
STATUS of GOVERNMENT FURNISHED SERVICES AND/OR SUPPLIES
SAFETY COMMENTS
DIFFICULTIES WITH CONTRACTOR OR REPRESENTATIVE
UNFORESEEN DEVELOPMENTS (Describe conditions, action taken; person contacted, recommended actions)
OTHER COMMENTS OR PERTINENT FACTS REGARDING JOB