Вы находитесь на странице: 1из 13

D

e
v
i
c
e
L
o
c
a
t
i
o
n
N
r

o
f

P
o
i
n
t
s
A
n
a
l
o
u
g
e

o
r

D
i
g
i
t
a
l
C
o
n
t
r
o
l

C
a
b
l
e

C
o
r
e
s
C
o
m
p
a
r
t
m
e
n
t

#
S
t
a
r
t
i
n
g

G
e
a
r

T
y
p
e
S
t
a
r
t
i
n
g

G
e
a
r

R
a
t
i
n
g

A
C
a
b
l
e

T
y
p
e
C
a
b
l
e

C
o
r
e
s
C
a
b
l
e

S
i
z
e
L
o
a
d

I
t
e
m

P
o
w
e
r

k
W
L
o
a
d

I
t
e
m
7
DOL Extract Fan 4.0kW
2 Room temp. detector Room 1 A
Supply fan isolator [Field] 1 D
3
HV Cooling [C-G-EF-02]
[C-G-EF-02]
Supply fan starter [MCC] 3 D 5
2
Extract Fan
Supply fan isolator [Field] 1 D 2
2 3 4.0kW
HV Cooling [C-G-EF-01] [C-G-EF-01]
Supply fan starter [MCC] 3 D 5
6
DOL
LPG Gas Meter
Castle Hotel Field 1
Sprinkler zone alarm L3 - east
P 2
Sprinkler zone alarm L2 - centre Field
Sprinkler zone alarm L4 - east Field 1 D 2
[FM200 Systems]
[LPG Gas Detection System]
2 1.5 3
2 3 16
5
4
DOL 16
DOL
[Fire Alarm]
[FAN COIL UNITS]
FCU bus Interface unit (Ground)
1.5
FCU bus Interface unit (First & Second)
3 2
Pump isolator
Pump Starter
CCWS Motorised Valve
ChW Motorised Valve
Pump Starter
Pump isolator
1 D
Field 1
Sprinkler zone alarm L1 - east
Sprinkler zone alarm LG - east
[Sprinkler]
Fire Alarm Interface Unit, zone 3
Pump isolator
Pump Starter
Immersion temp. detector
[C-G-HWG-02]
2
Motorised Valve
Immersion temp. detector
[C-G-HWG-01]
[C-G-P-01]
Pump isolator
Immersion temp. detector
[C-G-HWG-03]
Pump Starter
D
2
2
2
Field 1 D 2
Field 1 D 2
MCC 1 D 2
Room C
4
2
2
D
3 D 5
1 D 2
4
2 D
Fire Alarm Interface Unit, zone 2 MCC 1
Common alarm Field 1
Sprinkler zone alarm L5 - east
C-G-P-03
C-G-P-05
C
-
G
-
M
C
C
-
0
1
2
D
D
0.75kW Shunt pump
C-G-P-02
1.5
1.1kW HWS pump
C-G-P-01
Shunt pump DOL 16 2 3 1.5
1.5 2 3
0.37kW
0.37kW Shunt pump
C-G-P-04
0.37kW 16 Shunt pump
Pump isolator Field 1
3 Pump Starter MCC 5 D
3 A
3 A
Pipe 1
[C-G-CWG-01]
Immersion temp. detector Pipe 1 2 A
Pipe 1
Field 1 2 D
MCC
Field
Pipe 1 2 A
MCC 3 5 D
2
Motorised Valve Pipe 1
MCC 3 5 D
3 A
Pipe 1 2 A
Field 1 2 D
MCC 3
2 A Pipe 1
5 D
Motorised Valve Pipe A 1
DOL
Pipe 1 A 3
BEMS POINT SCHEDULE & MCC LOAD DIAGRAM
Castle Hotel, Ground Floor, Plant Room #1
1
3
16 DOL
D Field 1
3
C
2 Field 1 D
Room
Fire Alarm Interface Unit, zone 1 MCC 1
RE6309/D001369 Rev 0/2003 15910/1 BEMS Point Schedule + MCC Load Diagram
D
e
v
i
c
e
L
o
c
a
t
i
o
n
N
r

o
f

P
o
i
n
t
s
A
n
a
l
o
u
g
e

o
r

D
i
g
i
t
a
l
C
o
n
t
r
o
l

C
a
b
l
e

C
o
r
e
s
C
o
m
p
a
r
t
m
e
n
t

#
S
t
a
r
t
i
n
g

G
e
a
r

T
y
p
e
S
t
a
r
t
i
n
g

G
e
a
r

R
a
t
i
n
g

A
C
a
b
l
e

T
y
p
e
C
a
b
l
e

C
o
r
e
s
C
a
b
l
e

S
i
z
e
L
o
a
d

I
t
e
m

P
o
w
e
r

k
W
L
o
a
d

I
t
e
m
BEMS POINT SCHEDULE & MCC LOAD DIAGRAM
Castle Hotel, Ground Floor, Plant Room #1
8
1. A = Analogue; D = Digital; C = Communication
2. Starters: DOL = Direct On Line; SD = Star/Delta; AT = Auto Transformer; Inv = Inverter
3 Cable Type :1 = Xlpe/Swa/LSF, 2 = PVC/PVC, 3 = PVC single conductors in conduit
2
Pump run monitoring Field 3 D 4
High level alarm Field 1 D
D 2
4
Common alarm Field 1
D Pump run monitoring Field 3
D 2
High level alarm Field 1 D 2
Common alarm Field 1
Field 1 D 2
Activate water feature 2 Field 1 D
D 2
Common alarm water feature 1 Field 1 D 2
Field 1
[Water Feature Courtyard]
Activate water feature 1 Field 1
Common Alarm
Security room alarm
Common alarm water feature 2
Sump Pump Station (C-S-P-05 A/B)
Sump Pump Station (C-S-P-06 A/B)
Lift Monitoring System
D 2
2
1 D 2
4. Numbers of Points and control cable cores are given for guidance. Tenderer to review against written specified requirements and make due allowance for what is required
Field
Sewage Pumping Station 1 (SPS-01)
Common alarm Field 1
4
D 2
2 High level alarm Field 1 D
1 D 2
Pump run monitoring
Sewage Pumping Station 2 (SPS-02)
Common alarm Field
Field 3 D
4 Pump run monitoring Field 3 D
1 D 2
High level alarm Field
D 2
Sump Pump Station (C-S-P-01 A/B)
Common alarm Field 1
2
Pump run monitoring Field 3 D
D 2
High level alarm Field 1
High level alarm Field 1 D
4
Sump Pump Station (C-S-P-02 A/B)
Common alarm Field 1 D
Sump Pump Station (C-S-P-03 A/B)
Common alarm Field 1
2
Pump run monitoring Field 3 D 4
D
D 2
High level alarm Field 1 D 2
4
Sump Pump Station (C-S-P-04 A/B)
Common alarm Field 1 D 2
Pump run monitoring Field 3
2
Pump run monitoring Field 3 D 4
High level alarm Field 1 D
RE6309/D001369 Rev 0/2003 15910/2 BEMS Point Schedule + MCC Load Diagram
D
e
v
i
c
e
L
o
c
a
t
i
o
n
N
r

o
f

P
o
i
n
t
s
A
n
a
l
o
u
g
e

o
r

D
i
g
i
t
a
l
C
o
n
t
r
o
l

C
a
b
l
e

C
o
r
e
s
C
o
m
p
a
r
t
m
e
n
t

#
S
t
a
r
t
i
n
g

G
e
a
r

T
y
p
e
S
t
a
r
t
i
n
g

G
e
a
r

R
a
t
i
n
g
C
a
b
l
e

T
y
p
e
C
a
b
l
e

C
o
r
e
s
C
a
b
l
e

S
i
z
e
L
o
a
d

I
t
e
m

P
o
w
e
r
L
o
a
d

I
t
e
m
1. A = Analogue; D = Digital; C = Communication
2. Starters: DOL = Direct On Line; SD = Star/Delta; AT = Auto Transformer; Inv = Inverter
3 Cable Type :1 = Xlpe/Swa/LSF, 2 = PVC/PVC, 3 = PVC single conductors in conduit
MCC 1 D
2
[C-G-SCS-01]
2
DOL 16 2 3 2.5
2
[C-G-AH2-01]
1
Supply fan isolator [AHU] 1 D
Monitoring system common alarm Field 1 D
1 A
Mixing damper 2 [AHU] 1 A
Mixing damper 3 [AHU] 1 A
Room hum detector Room 1 A 2
[AHU] 1 A
Duct LL temp detector [AHU] 1 A 2
2
Duct RA Hum detector [AHU] 1 A 2
2
D
1 A
1 A
1 A
1
1.1kW Supply fan
Supply fan SD 4 5.5 kW
[Coldroom Equipment]
2
1 P 2
Field
Field
1
A
Speciality Kitchen
Main Kitchen
Pre Filter DP switch [AHU] 1 D
Supply fan starter [MCC]
[AHU]
[C-G-SCS-01]
Duct SA temp. detector
Motorised Valve [AHU] 1
Motorised Valve 1
1
3
Room temp. detector Room
Mixing damper 1
Main Filter DP switch
[AHU]
Extract fan isolator
Filter DP switch [AHU]
Motorised Valve
3
3
2
[C-G-AH2-01]
[AHU]
Duct RA temp. detector [AHU]
Duct RA Air Quality Detector [AHU]
BEMS POINT SCHEDULE & MCC LOAD DIAGRAM
30 2 12
Castle Hotel, Speciality Restaurant Plant Room #2
3
2
D
2 Supply fan isolator [AHU] 1 D
2
3 D 5
A
3
D 2
A
3
5
2
5
3
P
Activate water feature MCC 1 D 2
Common alarm water feature 2
[Water Feature Entrance]
1
1
2
Supply fan starter [MCC]
Fridge condensing unit common alarm Field 1 D
[Water Meters]
C
-
G
-
M
C
C
-
0
2
4. Numbers of Points and control cable cores are given for guidance. Tenderer to review against written specified requirements and make due allowance for what is required
D 2
Extract fan starter [MCC] 3 D
[AHU]
[AHU]
RE6309/D001369 Rev 0/2003 15910/3 BEMS Point Schedule + MCC Load Diagram
D
e
v
i
c
e
L
o
c
a
t
i
o
n
N
r

o
f

P
o
i
n
t
s
A
n
a
l
o
u
g
e

o
r

D
i
g
i
t
a
l
C
o
n
t
r
o
l

C
a
b
l
e

C
o
r
e
s
C
o
m
p
a
r
t
m
e
n
t

#
S
t
a
r
t
i
n
g

G
e
a
r

T
y
p
e

A
S
t
a
r
t
i
n
g

G
e
a
r

R
a
t
i
n
g
C
a
b
l
e

T
y
p
e
C
a
b
l
e

C
o
r
e
s
C
a
b
l
e

S
i
z
e
L
o
a
d

I
t
e
m

P
o
w
e
r

k
W
L
o
a
d

I
t
e
m
3 1.5 0.2kW Heat Wheel
16
3 2.5 1.5kW Supply fan
1.1kW Extract fan 3
DOL 16 2
DOL 2
DOL 16 2
2
Main Filter DP switch [AHU] 1 D 2
Pre Filter DP switch [AHU] 1 D
2
Rotary wheel isolator [AHU] 1 D 2
Exract fan isolator [AHU] 1 D
5
Supply fan isolator [AHU] 1 D 2
Extract fan starter [MCC] 3 D
3
Supply fan starter [MCC] 3 D 5
Rotary wheel starter [MCC] 2 D
3
Motorised Valve [AHU] 1 A 3
Motorised Valve [AHU] 1 A
3
Motorises damper 2 [AHU] 1 D 3
Motorised damper 1 [AHU] 1 D
Duct IA Hum. detector [AHU] 1 A 2
Duct IA temp. detector [AHU] 1 A
Duct SA Hum. detector [AHU] 1 A 2
2
[C-3-PAH3-02]
Duct SA temp. detector [AHU] 1 A 2
DOL 16 2 3
2
2
[C-3-PAH3-03]
4
DOL 16 2 3 2.5 2.2kW
Heat Wheel 0.2kW
Supply fan
2.5 2.2kW Extract fan
2.5
[C-3-PAH3-02]
Supply fan
3.0kW Extract fan
5.5kW
[C-3-PAH3-01]
2.5
7.5kW Supply fan
2
Duct SA Hum. detector [AHU] 1 A 2
D
[C-3-PAH3-03]
Duct SA temp. detector [AHU] 1 A
Main Filter DP switch [AHU] 1 D
1 D
2
Rotary wheel isolator [AHU] 1 D
Pre Filter DP switch [AHU] 1
2 D
2
Exract fan isolator [AHU] 1 D 2
Supply fan isolator [AHU]
1 A
3
Extract fan starter [MCC] 3 D 5
Rotary wheel starter [MCC]
1 D
3
Motorised Valve [AHU] 1 A 3
Motorised Valve [AHU]
1 A
3
Motorises damper 2 [AHU] 1 D 3
Motorised damper 1 [AHU]
2
2
2
Duct IA Hum. detector [AHU] 1 A 2
Duct IA temp. detector [AHU]
1 A 2
[AHU] 1 A
3
3
3
3
2.5
1.5 DOL 16 2
SD 30 2
DOL 20 2
Duct SA temp. detector [AHU] 1 A 2
2 Duct SA Hum. detector [AHU] 1 A
[C-3-PAH3-01]
2
2
Main Filter DP switch [AHU] 1 D
Pre Filter DP switch [AHU] 1 D
Extract fan starter
5 Supply fan starter [MCC] 3 D
[MCC] 3 D 5
2 Extract fan isolator Field 1 D
A
2
Mixing damper 3 [AHU] 1 A 3
Supply fan isolator Field 1 D
3
3 Mixing damper 1 [AHU]
Mixing damper 2 [AHU] 1 A
1 A
2
Duct RA Air Quality Detector [AHU] 1 A 2
Duct LL temp detector [AHU] 1 A
Duct RA temp. detector SD 40 2
1
C
-
3
-
M
C
C
-
0
1
[AHU]
BEMS POINT SCHEDULE & MCC LOAD DIAGRAM
Castle Hotel, Level 3, Plant Room #1
[C-3-AH2-01] [C-3-AH2-01]
7
Duct RA Hum detector
D 5
3
Motorised Valve [AHU] 1 A
Motorised Valve [AHU] 1
4
3
Supply fan starter [MCC] 3
RE6309/D001369 Rev 0/2003 15910/4 BEMS Point Schedule + MCC Load Diagram
D
e
v
i
c
e
L
o
c
a
t
i
o
n
N
r

o
f

P
o
i
n
t
s
A
n
a
l
o
u
g
e

o
r

D
i
g
i
t
a
l
C
o
n
t
r
o
l

C
a
b
l
e

C
o
r
e
s
C
o
m
p
a
r
t
m
e
n
t

#
S
t
a
r
t
i
n
g

G
e
a
r

T
y
p
e

A
S
t
a
r
t
i
n
g

G
e
a
r

R
a
t
i
n
g
C
a
b
l
e

T
y
p
e
C
a
b
l
e

C
o
r
e
s
C
a
b
l
e

S
i
z
e
L
o
a
d

I
t
e
m

P
o
w
e
r

k
W
L
o
a
d

I
t
e
m
BEMS POINT SCHEDULE & MCC LOAD DIAGRAM
Castle Hotel, Level 3, Plant Room #1
1. A = Analogue; D = Digital; C = Communication
2. Starters: DOL = Direct On Line; SD = Star/Delta; AT = Auto Transformer; Inv = Inverter
3 Cable Type :1 = Xlpe/Swa/LSF, 2 = PVC/PVC, 3 = PVC single conductors in conduit
Rotary wheel isolator
Main Filter DP switch [AHU] 1 D 2
Pre Filter DP switch [AHU] 1 D 2
DOL 16 2 3
DOL 16 2 3
4
0.2kW Heat Wheel
2.5 2.2kW Extract fan
[AHU] 1 D
2
2
2
Supply fan isolator [AHU] 1 D
Exract fan isolator [AHU] 1 D
5
Extract fan starter [MCC] 3 D 5
Supply fan starter [MCC] 3 D
3
Motorised Valve [AHU] 1 A 3
Motorised Valve [AHU] 1 A
3
Motorises damper 2 [AHU] 1 D 3
Motorised damper 1 [AHU] 1 D
2
Duct IA Hum. detector [AHU] 1 A 2
Duct IA temp. detector [AHU] 1 A
Duct SA Hum. detector [AHU] 1 A 2
2.5
4. Numbers of Points and control cable cores are given for guidance. Tenderer to review against written specified requirements and make due allowance for what is required
MCC 1 D
[Fire Alarm]
2 Fire Alarm Interface Unit, zone 2
3 Rotary wheel starter [MCC] 2 D
RE6309/D001369 Rev 0/2003 15910/5 BEMS Point Schedule + MCC Load Diagram
D
e
v
i
c
e
L
o
c
a
t
i
o
n
N
r

o
f

P
o
i
n
t
s
A
n
a
l
o
u
g
e

o
r

D
i
g
i
t
a
l
C
o
n
t
r
o
l

C
a
b
l
e

C
o
r
e
s
C
o
m
p
a
r
t
m
e
n
t

#
S
t
a
r
t
i
n
g

G
e
a
r

T
y
p
e
S
t
a
r
t
i
n
g

G
e
a
r

R
a
t
i
n
g
C
a
b
l
e

T
y
p
e
C
a
b
l
e

C
o
r
e
s
C
a
b
l
e

S
i
z
e
L
o
a
d

I
t
e
m

P
o
w
e
r

K
w
L
o
a
d

I
t
e
m
1
1. A = Analogue; D = Digital; C = Communication
2. Starters: DOL = Direct On Line; SD = Star/Delta; AT = Auto Transformer; Inv = Inverter
3 Cable Type :1 = Xlpe/Swa/LSF, 2 = PVC/PVC, 3 = PVC single conductors in conduit
1 A 3
Field 1 D 2
[AHU]
2
3
2
4. Numbers of Points and control cable cores are given for guidance. Tenderer to review against written specified requirements and make due allowance for what is required
3
C-3-AH2-01
2.2kW Supply fan
[Fire Alarm]
[AHU] 1 D
2 Pre Filter DP switch [AHU] 1 D
Main Filter DP switch 2
5
Supply fan starter [MCC] 3 D
Extract fan starter [MCC] 3 D
5
Extract fan isolator
Motorised Valve
Supply fan isolator Field 1 D
1 A 3
3 Mixing damper 2 [AHU] 1 A
Duct LL temp detector [AHU] 1 A
Duct RA Air Quality Detector [AHU] 1
1
BEMS POINT SCHEDULE & MCC LOAD DIAGRAM
16
Castle Hotel, Level 3, Plant Room #2
2 6
1
A
C
-
3
-
M
C
C
-
0
2
DOL
2
2 2.5
C-3-AH2-02
Duct RA temp. detector
[AHU]
[AHU] 1
Motorised Valve [AHU] 1 A
Duct RA Hum detector
A
Mixing damper 1 [AHU] 1
2 Fire Alarm Interface Unit, zone 2 MCC 1 D
A 2
A
Mixing damper 3 [AHU]
RE6309/D001369 Rev 0/2003 15910/6 BEMS Point Schedule + MCC Load Diagram
D
e
v
i
c
e
L
o
c
a
t
i
o
n
N
r

o
f

P
o
i
n
t
s
A
n
a
l
o
u
g
e

o
r

D
i
g
i
t
a
l
C
o
n
t
r
o
l

C
a
b
l
e

C
o
r
e
s
C
o
m
p
a
r
t
m
e
n
t

#
S
t
a
r
t
i
n
g

G
e
a
r

T
y
p
e
S
t
a
r
t
i
n
g

G
e
a
r

R
a
t
i
n
g

A
C
a
b
l
e

T
y
p
e
C
a
b
l
e

C
o
r
e
s
C
a
b
l
e

S
i
z
e
L
o
a
d

I
t
e
m

P
o
w
e
r

k
W
L
o
a
d

I
t
e
m
1. A = Analogue; D = Digital; C = Communication
2. Starters: DOL = Direct On Line; SD = Star/Delta; AT = Auto Transformer; Inv = Inverter
3 Cable Type :1 = Xlpe/Swa/LSF, 2 = PVC/PVC, 3 = PVC single conductors in conduit
4.0 kW Extract fan
3 1.5 0.2 kW Heat Wheel
3 2.5 2.2 kW Extract fan
4
C
-
5
-
M
C
C
-
0
1
C-5-KEF-01
C-4-KEF-02
DOL 20 3 4
[C-5-PAH3-01]
[C-5-AH2-01]
Supply fan
12 10 11.0kW Supply fan
1
SD 63 2
2
DOL 16 2
3 4 3.0 kW DOL 20 2
DOL 16 2
2 Main Filter DP switch [AHU] 1 D
2
2
Pre Filter DP switch [AHU] 1 D 2
Rotary wheel isolator [AHU] 1 D
2
Exract fan isolator [AHU] 1 D 2
Supply fan isolator [AHU] 1 D
5
Extract fan starter [MCC] 3 D 5
Supply fan starter [MCC] 3 D
3
Rotary wheel starter [MCC] 2 D 3
Motorised Valve [AHU] 1 A
3
Motorised Valve [AHU] 1 A 3
Motorises damper 2 [AHU] 1 D
2
Motorised damper 1 [AHU] 1 D 3
Duct IA Hum. detector [AHU] 1 A
2
Duct IA temp. detector [AHU] 1 A 2
Duct SA Hum. detector [AHU] 1 A
2
[C-5-PAH3-01]
Duct SA temp. detector [AHU] 1 A 2
Main Filter DP switch [AHU] 1 D
5
Pre Filter DP switch [AHU] 1 D 2
Extract fan starter [MCC] 3 D
3
Supply fan starter [MCC] 3 D 5
Motorised Valve [AHU] 1 A
2
Motorised Valve [AHU] 1 A 3
Extract fan isolator [AHU] 1 D
3
Supply fan isolator [AHU] 1 D 2
Mixing damper 3 [AHU] 1 A
3
Mixing damper 2 [AHU] 1 A 3
Mixing damper 1 [AHU] 1 A
2
Room hum detector Room 1 A 2
Room temp. detector Room 1 A
2
Duct LL temp detector [AHU] 1 A 2
Duct RA Air Quality Detector [AHU] 1
2
Duct RA Hum detector [AHU] 1 A 2
[C-5-AH2-01]
Duct RA temp. detector [AHU] 1
A
A
Extract fan 16 2 3 2 0.55 kW DOL
2
[Fire Alarm]
Fire Alarm Interface Unit, zone 1 MCC 1 D
3
DOL 16 4
2
2
3 2.2 kW Extract fan
Electrostatic filter 1 kW 2
2 Extract fan isolator Field
D 5
1 D
C-5-KEF-01
D 2
2
C-4-KEF-02
Extract fan starter [MCC] 3
Electrostatic filter isolator
D 5
Field
Field
Extract fan isolator Field 1
D 2
4. Numbers of Points and control cable cores are given for guidance. Tenderer to review against written specified requirements and make due allowance for what is required
12
Extract fan starter
Electrostatic Filter enable
D
1
1 Electrostatic filter alarm
[MCC] 3
BEMS POINT SCHEDULE & MCC LOAD DIAGRAM
Castle Hotel, Level 5, Plant Room #1
Field 1 D 2
3
DOL 16
RE6309/D001369 Rev 0/2003 15910/7 BEMS Point Schedule + MCC Load Diagram
D
e
v
i
c
e
L
o
c
a
t
i
o
n
N
r

o
f

P
o
i
n
t
s
A
n
a
l
o
u
g
e

o
r

D
i
g
i
t
a
l
C
o
n
t
r
o
l

C
a
b
l
e

C
o
r
e
s
C
o
m
p
a
r
t
m
e
n
t

#
S
t
a
r
t
i
n
g

G
e
a
r

T
y
p
e
S
t
a
r
t
i
n
g

G
e
a
r

R
a
t
i
n
g

A
C
a
b
l
e

T
y
p
e
C
a
b
l
e

C
o
r
e
s
C
a
b
l
e

S
i
z
e
L
o
a
d

I
t
e
m

P
o
w
e
r

L
o
a
d

I
t
e
m
1. A = Analogue; D = Digital; C = Communication
2. Starters: DOL = Direct On Line; SD = Star/Delta; AT = Auto Transformer; Inv = Inverter
3 Cable Type :1 = Xlpe/Swa/LSF, 2 = PVC/PVC, 3 = PVC single conductors in conduit
D
Castle Hotel, Zone 1, Level 4, Plant Room #1
D
2
1
[AHU]
Main Filter DP switch
3
BEMS POINT SCHEDULE & MCC LOAD DIAGRAM
2 [AHU] 1 D
Fire Alarm Interface Unit, zone 1 MCC 1
1
[Fire Alarm]
[AHU]
3 D
Extract fan starter [MCC] 3
Supply fan isolator
D
Rotary wheel starter [MCC] 2 D
Exract fan isolator [AHU] D
Supply fan starter [MCC]
2
3
Motorised Valve [AHU] 1 A 3
2
DOL 16
Duct SA temp. detector [AHU] 1 A 2 3.0 kW
1
DOL 20
Duct IA Hum. detector
[C-4-PAH3-01]
[AHU] 1 A
[AHU] 1 A 2
Motorised Valve [AHU]
2
[AHU] 1 A 2
Duct SA Hum. detector
Duct IA temp. detector
D 2
4. Numbers of Points and control cable cores are given for guidance. Tenderer to review against written specified requirements and make due allowance for what is required
2
2 Pre Filter DP switch [AHU] 1 D
Rotary wheel isolator
Extract fan
20
5
2
1 A
2.2 kW
3
5
1
3 Supply fan
3 Heat Wheel 0.2kW
4
2
2 3
C
-
4
-
M
C
C
-
0
1
DOL 16
RE6309/D001369 Rev 0/2003 15910/8 BEMS Point Schedule + MCC Load Diagram
D
e
v
i
c
e
L
o
c
a
t
i
o
n
C
a
b
l
e
A
n
a
l
o
u
g
e

o
r

D
i
g
i
t
a
l
C
o
n
t
r
o
l

C
a
b
l
e

C
o
r
e
s
C
o
m
p
a
r
t
m
e
n
t

#
S
t
a
r
t
i
n
g

G
e
a
r

T
y
p
e
S
t
a
r
t
i
n
g

G
e
a
r

R
a
t
i
n
g
C
a
b
l
e

T
y
p
e
C
a
b
l
e

C
o
r
e
s
C
a
b
l
e

s
i
z
e
L
o
a
d

I
t
e
m

P
o
w
e
r
L
o
a
d

I
t
e
m
1. A = Analogue; D = Digital; C = Communication
2. Starters: DOL = Direct On Line; SD = Star/Delta; AT = Auto Transformer; Inv = Inverter
3 Cable Type :1 = Xlpe/Swa/LSF, 2 = PVC/PVC, 3 = PVC single conductors in conduit
5
2
1
3
3
3 D
3 D
0.2kW 3
3.0 kW 3
4
1.5
2.5
4. Numbers of Points and control cable cores are given for guidance. Tenderer to review against written specified requirements and make due allowance for what is required
D 2
D 2
D 2
D 2
D
[Fire Alarm]
2
C
-
4
-
M
C
C
-
0
2
2 Fire Alarm Interface Unit, zone 1 MCC
1
1
1
20 2 DOL
5
3
2
Extract fan
3 4.0 kW
1 A
Supply fan
Heat Wheel
20 2
16 2 DOL
Exract fan isolator [AHU] 1
1
[AHU]
Pre Filter DP switch [AHU]
Rotary wheel isolator [AHU]
Main Filter DP switch
[AHU]
Extract fan starter [MCC]
Supply fan starter [MCC]
Duct IA Hum. detector [AHU]
1 A
1 A
Duct SA Hum. detector 1 2
2 D
Motorised Valve [AHU] 1 A
A
[AHU]
Supply fan isolator 1 D
Motorised Valve [AHU]
Duct IA temp. detector [AHU]
Rotary wheel starter [MCC]
BEMS POINT SCHEDULE & MCC LOAD DIAGRAM
Castle Hotel, Zone 1, Level 4, Plantroom #2
[C-4-PAH3-02]
Duct SA temp. detector [AHU] DOL 1 A 2
RE6309/D001369 Rev 0/2003 15910/9 BEMS Point Schedule + MCC Load Diagram
D
e
v
i
c
e
L
o
c
a
t
i
o
n
N
r

o
f

P
o
i
n
t
s
A
n
a
l
o
u
g
e

o
r

D
i
g
i
t
a
l
C
o
n
t
r
o
l

C
a
b
l
e

C
o
r
e
s
C
o
m
p
a
r
t
m
e
n
t

#
S
t
a
r
t
i
n
g

G
e
a
r

T
y
p
e
S
t
a
r
t
i
n
g

G
e
a
r

R
a
t
i
n
g
C
a
b
l
e

T
y
p
e

C
a
b
l
e

C
o
r
e
s
C
a
b
l
e

S
i
z
e
L
o
a
d

I
t
e
m

P
o
w
e
r

k
W
L
o
a
d

I
t
e
m
1. A = Analogue; D = Digital; C = Communication
2. Starters: DOL = Direct On Line; SD = Star/Delta; AT = Auto Transformer; Inv = Inverter
3 Cable Type :1 = Xlpe/Swa/LSF, 2 = PVC/PVC, 3 = PVC single conductors in conduit
5. Cable sizes are in mm2. CPC sizes shall be as BS7671 (IEE Regulations)
[C-4-PAH3-03]
C
-
4
-
M
C
C
-
0
3
5.5 kW
16 2 Duct SA temp. detector 0.2kW [AHU] 1.5
Duct SA Hum. detector [AHU] 1 A
Duct IA temp. detector [AHU] 1 A
1 A
1 A
3 3.0 kW
2
2 DOL 16 2 2.5
Motorised Valve [AHU] 1 A 3
Supply fan starter [MCC] 3 D
Rotary wheel starter [MCC] 2 D
Exract fan isolator [AHU] 1 D
[AHU] 1 D
Rotary wheel isolator [AHU] 1 D
Pre Filter DP switch [AHU] 1 D
Main Filter DP switch
[Fire Alarm]
Fire Alarm Interface Unit, zone 1 MCC 1 D 2
BEMS POINT SCHEDULE & MCC LOAD DIAGRAM
Castle Hotel, Zone 1 , Level 4, Plant Room 1
2
2
2
2
5
3
2 [AHU]
D
3. Numbers of Points and control cable cores are given for guidance. Tenderer to review against written specified requirements and make due allowance for what is required
5
Supply fan isolator [AHU] 1 D 2
Extract fan starter [MCC] 3
Supply fan
DOL 2 3 Heat Wheel
SD 30 7 2 6
Extract fan
Motorised Valve [AHU] 1 A 3
1
Duct IA Hum. detector
RE6309/D001369 Rev 0/2003 15910/10 BEMS Point Schedule + MCC Load Diagram
D
e
v
i
c
e
L
o
c
a
t
i
o
n
N
r

o
f

P
o
i
n
t
s
A
n
a
l
o
u
g
e

o
r

D
i
g
i
t
a
l
C
o
n
t
r
o
l

C
a
b
l
e

C
o
r
e
s
1. A = Analogue; D = Digital; C = Communication
2. Starters: DOL = Direct On Line; SD = Star/Delta; AT = Auto Transformer; Inv = Inverter
3 Cable Type :1 = Xlpe/Swa/LSF, 2 = PVC/PVC, 3 = PVC single conductors in conduit
3
Activate water feature
Common alarm water feature
MCC 1 D 2
MCC
1 A
1 D
Return immersion detector spa 2 Field 1 A
1 D 2
1 D 2
3
Return immersion detector spa 1 Field 1 A 3
Common alarm spa 1
Common alarm spa 2
MCC
MCC
MCC
1
LTHW motorised Valve Field 1 A 3
Common alarm pool D 2
Return immersion detector pool Field
3
Chilled water motorised Valve Field 1 A 3
LTHW motorised Valve Field 1 A
A 3
Chilled water motorised Valve Field 1 A 3
Chilled water motorised Valve
LTHW motorised Valve Field 1
Field 1 A 3
2
C
-
G
-
M
C
C
-
0
3
BEMS POINT SCHEDULE & MCC LOAD DIAGRAM
4. Numbers of Points and control cable cores are given for guidance. Tenderer to review against written specified requirements and make due allowance for what is required
Castle Hotel; Pool Plant Room
RE6309/D001369 Rev 0/2003 15910/11 BEMS Point Schedule + MCC Load Diagram
D
e
v
i
c
e
L
o
c
a
t
i
o
n
N
r

o
f

P
o
i
n
t
s
A
n
a
l
o
u
g
e

o
r

D
i
g
i
t
a
l
C
o
n
t
r
o
l

C
a
b
l
e

C
o
r
e
s
C
o
m
p
a
r
t
m
e
n
t

#
S
t
a
r
t
i
n
g

G
e
a
r

T
y
p
e
S
t
a
r
t
i
n
g

G
e
a
r

R
a
t
i
n
g
C
a
b
l
e

T
y
p
e
C
a
b
l
e

C
o
r
e
s
C
a
b
l
e

S
i
z
e
L
o
a
d

I
t
e
m

P
o
w
e
r
L
o
a
d

I
t
e
m
1. A = Analogue; D = Digital; C = Communication
2. Starters: DOL = Direct On Line; SD = Star/Delta; AT = Auto Transformer; Inv = Inverter, I = isolator
3 Cable Type :1 = Xlpe/Swa/LSF, 2 = PVC/PVC, 3 = PVC single conductors in conduit
4. Numbers of Points and control cable cores are given for guidance. Tenderer to review against written specified requirements and make due allowance for what is required
[C-4-PAH2-01]
Duct SA temp. detector [AHU] 1 A 2
Room temp. detector Room 1 A
C
-
4
-
M
C
C
-
0
4
BEMS POINT SCHEDULE & MCC LOAD DIAGRAM
LEVEL 4 PLANTROOM 4
2
3
Motorised Valve [AHU] 1 A 3
Motorised damper 1 [AHU] 1 A
5
Supply fan isolator [AHU] 1 D 2
Supply fan starter [MCC] 3 D
2
Main Filter DP switch [AHU] 1 D 2
Pre Filter DP switch [AHU] 1 D
[C-4-PAH2-02]
Duct SA temp. detector [AHU] 1 A 2
Room temp. detector Room 1 A 2
Motorised damper 1 [AHU] 1 A
Motorised Valve [AHU] 1 A
[AHU] 1 D
Supply fan starter [MCC] 3 D
Main Filter DP switch [AHU] 1 D
Pre Filter DP switch [AHU]
[C-4-PAH2-01]
1
DOL 20 2 3 4 4.0kW Supply fan
[C-4-PAH2-02]
2
DOL 20 2 3 4 4.0 Kw Supply fan
2
2
5
2
3
3
Extract fan starter [MCC] 3 D
[C-4-KEF-01]
1 D
Supply fan isolator
Electrostatic filter alarm Field 1 D
5
Electrostatic Filter enable Field 1 D 2
Electrostatic filter isolator Field 1 D
2
Extract fan isolator Field 1 D 2
Extract fan isolator Field 1 D
2
[C-4-KEF-02]
Extract fan starter [MCC] 3 D
[C-4-KEF-01]
3
DOL 16 2 3 2.5 2.2 kW Extract fan
DOL 16 4 1.5 3
2
5
1 kW Electrostatic filter
[C-4-KEF-02]
4
DOL 16 2 3 1.5 0.55 kW Extract fan
Fire Alarm Interface Unit, zone 1 MCC 1 D 2
[Fire Alarm]
RE6309/D001369 Rev 0/2003 15910/12 BEMS Point Schedule + MCC Load Diagram
D
e
v
i
c
e
L
o
c
a
t
i
o
n
N
r

o
f

P
o
i
n
t
s
A
n
a
l
o
u
g
e

o
r

D
i
g
i
t
a
l
C
o
n
t
r
o
l

C
a
b
l
e

C
o
r
e
s
C
o
m
p
a
r
t
m
e
n
t

#
S
t
a
r
t
i
n
g

G
e
a
r

T
y
p
e
S
t
a
r
t
i
n
g

G
e
a
r

R
a
t
i
n
g

A
C
a
b
l
e

T
y
p
e
C
a
b
l
e

C
o
r
e
s
C
a
b
l
e

S
i
z
e
L
o
a
d

I
t
e
m

P
o
w
e
r

k
W
L
o
a
d

I
t
e
m
1. A = Analogue; D = Digital; C = Communication
2. Starters: DOL = Direct On Line; SD = Star/Delta; AT = Auto Transformer; Inv = Inverter
3 Cable Type : 1 Xlpe/Swa/Pvc
BEMS POINT SCHEDULE & MCC LOAD DIAGRAM
Town Hotel, Level 2, Plant Room #3
4. Numbers of Points and control cable cores are given for guidance. Tenderer to review against written specified requirements and make due allowance for what is required
RE6332/D001240 Rev 0/2002 15910/13 BEMS Point Schedule + MCC Load Diagram

Вам также может понравиться