ID Task Name Duration Start Finish Predecessors

1 Site Activity 37 days? Mon 02/06/14 Tue 08/07/14


2 Permit clearance 1 day? Mon 02/06/14 Mon 02/06/14
3 Site Survey & Visual inspection 3 days Tue 03/06/14 Thu 05/06/142
4 NDT (onshore) 3 days Fri 06/06/14 Sun 08/06/143
5 Equipment and diver mobilization 3 days Mon 09/06/14 Wed 11/06/14
6 Offshore inspection (Visual +NDT) 6 days Thu 12/06/14 Tue 17/06/145
7 Additional site inspection (if required) 7 days Wed 18/06/14 Tue 24/06/146
8 Site visit with migas personnel 2 days Mon 07/07/14 Tue 08/07/1411
9 Migas Administration 37 days? Mon 02/06/14 Tue 08/07/14
10 Migas Appointment Letter 21 days Mon 02/06/14 Sun 22/06/14
11 Invitation Letter for Migas visit 1 day? Mon 30/06/14 Mon 30/06/1410
12 Migas visit 2 days Mon 07/07/14 Tue 08/07/1411
13 Reporting 51 days Wed 18/06/14 Thu 07/08/14
14 Re-engineering/Assessment report 30 days Wed 18/06/14 Thu 17/07/146
15 Certification Report 7 days Fri 18/07/14 Thu 24/07/1414
16 Issuing SKPP (include Migas Review) 14 days Fri 25/07/14 Thu 07/08/1415
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
02 J un '14 09 J un '14 16 J un '14 23 J un '14 30 J un '14 07 J ul '14 14 J ul '14 21 J ul '14 28 J ul '14 04 Aug '14
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
SUBSEA LOADING LINE INSPECTION
PT. PERTAMINA EP ASSET 5 TARAKAN FIELD
Page 1
Project: Schedule SUbsea Inspection
Date: Sun 01/06/14