Task Name

Production Requirements Analysis


Selecting Plant Manager
Purchase Orders for Necessary Equipment
Deliveryof Purchased Quipment to Atlant HQ
Safety and Quality Control Modifications
Building Selection
Lease Execution
Development of Equipment Layout
Electrical Modifications
Delivery of Purchased Equipment to New Plant
Installation of the Equipment
Releasing Purchase Orders for Initial Stock Materials
Delivery of Purchased Initial Stock Materials
Relocation of New Plant Manager
Advertisement for operation and maintenance personnel
Interviewing and selecting plant personnel
Operational training

Duration
3 days
3 days
1 day
25 days
10 days
5 days
10 days
5 days
10 days
1 day
2 days
1 days
10 days
21 days
7 days
15 days
10 days

Start
25-May
27-May
30-May
31-May
26-Jun
1-Jul
7-Jul
20-Jul
28-Jul
8-Aug
9-Aug
12-Aug
13-Aug
1-Jun
5-Jun
1-Aug
20-Aug

Finish
27-May
29-May
30-May
24-Jun
5-Jul
5-Jul
17-Jul
25-Jul
7-Aug
8-Aug
10-Aug
12-Aug
22-Aug
22-Jun
11-Jun
16-Aug
30-Aug

Task Owner
Industrial Engineering staff
VP of Operations
Purchasing Department
Contractor Transportation Company
Corporate Maintenance Department
VP Facilities
VP of Operations
Industrial Engineering staff
Local Contractor
Contractor Transportation Company
Industrial Engineering staff
Atlanta Warehouse staff
Contractor Transportation Company
Plant Manager
Human Resources
Plant Manager
Corporate Training representative