PEKERJAAN PERSIAPAN
1 LAND CLEARING
P : 9m, L : 10m
LUAS : 9X10 = 90m

2 PEMASANGAN BOUWPLANK
P : 9m, L : 8m(jarak 1m dari dinding fasad rumah)
KELL : 2x9 + 2x8 = 34m

3 GALIAN TANAH UNTUK PONDASI


S1 : 1m, S2 : 0.8m, T :0.7m, Panjang galian : 70m
LUAS : (1+0.8)x0.7 /2 = 0.63m
VOLUM : 70m x LUAS = 44.1m
4 URUGAN PASIR BAWAH PONDASI
S1 : 0.83m, S2 : 0.8m, T : 0.1m, Panjang galian : 70m
LUAS : (0.83+0.8)x0.1 /2 = 0.0815m
VOLUM : 70m x LUAS = 5.705m
5 URUGAN PASIR BAWAH LANTAI
10cm : 35.25m, 5cm : 18.25m
VOLUM 1 : 35.25 x 0.1 = 3.525m
VOLUM 2 : 18.25 x 0.05 = 0.9375m
TOTAL : 3.525 + 0.9375 = 4.4625m
6 URUGAN TANAH KEMBALI SISI PONDASI
VOLUM : x VOLUM Urugan Total
VOLUM : x 44.1 = 11.025m
7 URUGAN TANAH UNTUK PENINGGIAN LANTAI
Tidak dipakai karena peninggian lt. sudah dibedakan pada
urugan pasir.
II

PEKERJAAN PONDASI
1 PONDASI BATU KALI
S1 : 0.3m, S2 : 0.6m, T : 0.6m, panjang pondasi
total : 70m
LUAS : (0.3+0.6)x0.6 /2 = 0.36m
VOLUM : 70 x LUAS = 25.2m

III

PEKERJAAN BETON
1 SLOOF BETON

Ukuran sloof : 15/20


Total panjang : 70m
VOLUM = (0.15 x 0.2) x 70 = 2.1m
2 KOLOM BETON
Kolom 1 : @ T : 3.5 m, Kolom 15/15, 26bh
Kolom 2 : @ T : 1.5 m, Kolom 15/15, 5bh
VOLUM 1 : (0.15 x 0.15) x 3.5 = 0.07875m
VOLUM 2 : (0.15 x 0.15) x 1.5 = 0.03375m
3 RING BALK BETON
Ukuran ring balk : 8/12
Total panjang : 59 m
VOLUM : (0.08 x 0.12) x 59 = 0.5664m
4 MEJA DAPUR
P : 2 m, L : 0.75 m, T : 0.1 m
VOLUM : 2 x 0.75 x 0.1 = 0.15m
5 LIST PLANK
Ukuran : 15/20
Total panjang : 19 m
VOLUM : (0.15 x 0.2) x 19 = 0.57m
6 TOPI TERAS
P : 3 m, L : 1.5 m, T : 0.15 m
VOLUM : 3 x 1.5 x 0.15 = 0.675m
7 LANTAI KERJA
Luas lantai : 54m
Tebal : 0.1 m
VOLUM : 54 x 0.1 = 5.4m
IV

PEKERJAAN PASANGAN DINDING DAN


PLESTERAN
1 PASANGAN DINDING BATA MERAH ( 1:2 )
Total panjang dinding : 59 m
Tinggi dinding : 3 m
Luas : 59 x 3 = 177m
2 PASANGAN BATU ROLLAG ( 1:4 )

Total panjang : 5 m
3 PLESTERAN DAN ACI ( 1:2, TEBAL 15mm)
Total panjang dinding : 59 m
V

PEKERJAAN LANTAI DAN DINDING


1 LANTAI KERAMIK 30X30cm
Luas lantai dengan keramik 30x30 : 35.25m

LANTAI KERAMIK 20X20cm


Luas lantai dengan keramik 20x20 : 22.75m
2 DINDING KERAMIK 20X25cm
LUAS : 4 x s x t : 4 x 1.5 m x 3 m = 18m
3 PLIN KERAMIK
Total panjang plin keramik = 71 m
VI

PEKERJAAN ATAP
1 KUDA-KUDA ATAP RUMAH
balok kayu : 8/12
luas : 0.08 x 0.12 = 0.0096 m
alas : p x L = 5 x 0.0096 = 0.048 m
sisi : 2 x p x L = 2 x 2.8 x 0.0096 = 0.054 m
under : p x L = 1.4 x 0.0096 = 0.014 m
balok penyangga : 2 x p x L = 2 x 1.4 x 0.0096 =
0.027 m
volume kuda-kuda = 0.143 m
jumlah kuda-kuda = 4 bh
total = 4 x 0.0143 = 0.572 m
2 GORDING KAYU
balok kayu : 8/12
luas : 0.08 x 0.12 = 0.0096 m
gording 1 : p = 6 m, jumlah = 2 bh
gording 2 : p = 3 m, jumlah = 2 bh
volume g1 : 2 x p x L = 2 x 6 x 0.0096 = 0.1152 m
volume g2 : 2 x p x L = 2 X 3 x 0.0096 = 0.0576 m
total = 0.1152 + 0.0576 = 0.1728 m
3 KASO DAN RENG
kaso : 5/7, jumlah = 18 bh, jarak antara = 50 cm
reng : 3/4, jumlah = 14 bh, jarak antara = 20 cm
panjang kaso : 1.4 m
panjang reng : 9 m
kaso : 18 x p x L = 18 x 1.4 = 25.2 m
reng : 14 x p x L = 14 x 9 = 126 m
total : kaso + reng = 25.2 + 126 = 151.2 m
4 LISTPLANK KAYU
balok : 3/20

panjang listplank = 9 + 3 + 4 = 16 m
5 PASANG ATAP GENTENG PRESS BETON
luas penampang atap : 9 x 2.8 = 25.2 m

6 PASANG NOK GENTENG PRESS BETON


panjang nok : 9 m
7 PEKERJAAN TALANG AIR
volume : 16 x 0.20 x 0.25 = 0.8 m
VII

PEKERJAAN PLAFOND
1 RANGKA PLAFOND
luas bangunan = 58 m
2 PLAFOND ETERNIT
luas bangunan = 58 m

VIII

PEKERJAAN KUSEN, PINTU DAN JENDELA


1 KUSEN PINTU
kell : 2.1 + 0.9 + 2.1 = 5.1 m
jumlah pintu = 6 bh
total : 6 x 5.1 = 30.6 m
2 DAUN PINTU
luas : 2.1 x 0.9 = 1.89 m
jumlah pintu = 6 bh
total : 6 x 1.89 = 11.34 m
3 KUSEN JENDELA
kell : 2 x ( 1.5 + 1 ) = 5 m
jumlah jendela = 3.5 bh
total : 3.5 x 5 = 17.5 m
4 KACA JENDELA
luas : 0.5 x 1.5 = 0.75 m
jumlah kaca = 7 bh
total : 7 x 0.75 = 5.25 m

IX

PEKERJAAN CAT
1 CAT KAYU
total : daun pintu + kusen pintu + kusen jendela = 30.6 + 11.34 + 17.5
= 59.44 m
tebal kusen = 0.035 m
59.44 x 0.035= 2.0804 m
2 CAT INTERIOR
dinding = p = 77 m, t = 3 m
luas = 77 x 3 = 231 m

plafond = 58 m
total = 231 + 58 = 289 m

3 CAT EKSTERIOR
dinding 1 = p : 24 m, t = 3 m
dinding 2 = p : 11 m, t = 1.5 m
total = (24 x 3) + (11 x 1.5) = 72 + 16.5 = 88.5 m