Академический Документы
Профессиональный Документы
Культура Документы
Programa
:Transporte Terrestre
Unid. Ejec.
Sub-Programa
:Vas Urbanas
Presupuesto
Proyecto
Dependencia
OBRA
"MEJORAMIENTO DE PISTAS Y VEREDAS DE LA AV. LA VICTORIA (TRAMO: AV. PALIAN - RIO SHULLCAS) Y AV. 2 DE MAYO
(TRAMO: RIO SHULLCAS - AV. 12 DE OCTUBRE) - DEL DISTRITO DE HUANCAYO, PROVINCIA DE HUANCAYO - JUNIN"
19-041-0010-9002-2146103-400084-0049
Mod. Ejec
Fecha Inicio:
Fecha Culm:
Supervisora:
Residente :
:Administracin Directa.
:
:
:Ing. LORENZA BALTAZAR ORE
:Arq. VANESSA N. ORTIZ MEZA
CDIGO
DESCRIPCIN
UND
AVANCE
ANTERIOR
METRADO
P. UNITARIPARCIAL S/.
01.00
MOVIMIENTO DE TIERRAS
35,130.13
1.01
EXCAVACIONES
35,130.13
01.01.01
02.00
ALINEAMIENTO
02.01
ALINEAMIENTO
02.01.01
ALINEAMIENTO DE PREDIOS
03.00
VEREDAS
3.01
MOVIMIENTO DE TIERRAS
3.01.01
3.02
CONCRETO SIMPLE
3.02.01
m3
72.00
12.89
3.02.02
m2
576.00
5.23
m3
1,167.89
30.08
35,130.13
METRADO
VALORIZADO
ACTUAL
%
METRADO
SALDO
ACUMULADO
VALORIZADO
METRADO VALORIZADO
METRADO
SALDO
1167.89
35,130.13
100%
0.00
0%
1,167.89
35,130.13
100%
0.00
0.00
0%
402.12
36,190.80
100%
0.00
0%
402.12
36,190.80
100%
0.00
0.00
0%
2186.89
17,998.10
90%
1,922.53
10%
2,420.49
19,920.63
100%
0.00
0.00
0%
928.08
72.00
928.08
100%
0.00
0%
72.00
928.08
100%
0.00
0.00
0%
3,012.48
576.00
576.00
3,012.48
100%
0.00
36,190.80
36,190.80
m2
402.12
90.00
36,190.80
23,861.19
19,920.63
2,420.49
8.23
19,920.63
233.60
3,940.56
COSTO DIRECTO
95,182.08
3,012.48
100%
0.00
0%
93,259.60
97.98%
1,922.53
2.02%
0.00
0%
95,182.12 100.00%
0.00
0.00%
14,277.31
13,988.94
97.98%
288.38
2.02%
14,277.32 100.00%
0.00
0.00%
SUB TOTAL
109,459.39
107,248.53
97.98%
2,210.91
2.02%
109,459.43 100.00%
0.00
0.00%
TOTAL GENERAL
109,459.39
107,248.53
97.98%
2,210.91
2.02%
109,459.43 100.00%
0.00
0.00%
ACUMULADO
S/.
%
109,459.43 100.00%
SALDO
S/.
%
0.00
0.00%
AVANCE FISICO
Pgina 1
Programa
:Transporte Terrestre
Unid. Ejec.
Sub-Programa
:Vas Urbanas
Presupuesto
Proyecto
Mod. Ejec
:Administracin Directa.
Dependencia
Fecha Inicio:
Fecha Culm:
(TRAMO: RIO SHULLCAS - AV. 12 DE OCTUBRE) - DEL DISTRITO DE HUANCAYO, PROVINCIA DE HUANCAYO - JUNIN"
Supervisora:
19-041-0010-9002-2146103-400084-0049
Residente :
"MEJORAMIENTO DE PISTAS Y VEREDAS DE LA AV. LA VICTORIA (TRAMO: AV. PALIAN - RIO SHULLCAS) Y AV. 2 DE MAYO
OBRA
CDIGO
DESCRIPCIN
UND
METRADO
AVANCE
ANTERIOR
METRADO
1.00 ALINEAMIENTO
26,343.00
1.01
ALINEAMIENTO
26,343.00
1.01.01
ALINEAMIENTO DE PREDIOS
M2
292.70
90.00
26,343.00
TRABAJOS PRELIMINARES
2.01.01
TRAZO Y REPLANTEO
2.01.02
M2
2.01.03
M3
2.02
MOVIMIENTO DE TIERRAS
2.02.01
m3
3.13
2.02.02
m3
3.76
2.02.03
m3
3.76
2.02.04
0.39
79.88
2.03
CONCRETO ARMADO
2.03.01
m2
10.44
13.41
140.00
2.03.02
25.71
339.78
8,735.74
2.03.03
114.10
47.40
5,408.34
2.04
METRADO
VALORIZADO
METRADO VALORIZADO
26,343.00
100%
0.00
0.00
0%
292.70
METRADO
SALDO
26,343.00
100%
0.00
0.00
0%
2,635.95
M2
0.86
8.98
10.44
8.98
100%
0.00
0.00
0%
10.44
8.98
100%
0.00
0.00
0%
10.44
26.89
280.73
10.44
280.73
100%
0.00
0.00
0%
10.44
280.73
100%
0.00
0.00
0%
78.00
30.08
2,346.24
78.00
2,346.24
100%
0.00
0.00
0%
78.00
2,346.24
100%
0.00
0.00
0%
68.55
3.13
68.55
100%
0.00
0.00
0%
3.13
68.55
100%
0.00
0.00
0%
4.24
15.94
3.76
15.94
100%
0.00
0.00
0%
3.76
15.94
100%
0.00
0.00
0%
26.87
101.03
3.76
101.03
100%
0.00
0.00
0%
3.76
101.03
100%
0.00
0.00
0%
31.15
0.39
31.15
100%
0.00
0.00
0%
0.39
31.15
100%
0.00
0.00
0%
10.44
140.00
100%
0.00
0.00
0%
10.44
140.00
100%
0.00
0.00
0%
25.71
8,735.74
100%
0.00
0.00
0%
25.71
8,735.74
100%
0.00
0.00
0%
114.10
5,408.34
100%
0.00
0.00
0%
114.10
5,408.34
100%
0.00
0.00
0%
95.80
3,140.32
100%
0.00
0.00
0%
95.80
3,140.32
100%
0.00
0.00
0%
10.44
216.67
21.90
14,284.08
3,140.32
95.80
32.78
SALDO
ACUMULADO
20,277.03
2.01
2.04.01
292.70
VALORIZADO
ACTUAL
3,140.32
8,054.14
CONCRETO ARMADO
8,054.14
3.01.01
m3
9.44
372.33
3,514.80
9.44
3,514.80
100%
0.00
0.00
0%
9.44
3,514.80
100%
0.00
0.00
0%
3.01.02
ENCOFRADO Y DESENCOFRADO.
m2
42.38
77.40
3,280.21
42.38
3,280.21
100%
0.00
0.00
0%
42.38
3,280.21
100%
0.00
0.00
0%
1,259.13
261.23
1,259.13
100%
0.00
0.00
0%
261.23
1,259.13
100%
0.00
0.00
0%
3.01.03
kg
261.23
4.82
4.00 VEREDAS
20,991.77
4.01
MOVIMIENTO DE TIERRAS
4.01.01
m3
494.40
3.37
20,991.77
1,666.13
494.40
1,666.13
100%
0.00
0.00
0%
494.40
1,666.13
100%
0.00
0.00
0%
4.01.02
m2
136.00
0.60
81.60
136.00
81.60
100%
0.00
0.00
0%
136.00
81.60
100%
0.00
0.00
0%
4.01.03
PERFILADO DE TALUD
m2
293.00
0.75
219.75
293.00
219.75
100%
0.00
0.00
0%
293.00
219.75
100%
0.00
0.00
0%
4.01.04
m3
85.80
45.11
3,870.44
85.80
3,870.44
100%
0.00
0.00
0%
85.80
3,870.44
100%
0.00
0.00
0%
4.01.05
23.77
15,153.85
637.52
15,153.85
100%
0.00
0.00
0%
637.52
15,153.85
100%
0.00
0.00
0%
COSTO DIRECTO
75,665.76
0.00
0.00%
0.00
0.00%
637.52
75,665.93 100.00%
Pgina 2
75,665.76 100.00%
7,566.58
7,566.59 100.00%
0.00
0.00%
7,566.58 100.00%
0.00
0.00%
SUB TOTAL
83,232.34
83,232.53 100.00%
0.00
0.00%
83,232.34 100.00%
0.00
0.00%
TOTAL GENERAL
83,232.34
83,232.53 100.00%
0.00
0.00%
83,232.34 100.00%
0.00
0.00%
AVANCE FISICO
ACUMULADO
S/.
%
83,232.34 100.00%
Pgina 3
SALDO
S/.
0.00
%
0.00%
Programa
:Transporte Terrestre
Unid. Ejec.
Sub-Programa
:Vas Urbanas
Presupuesto
Proyecto
Mod. Ejec
:Administracin Directa.
Dependencia
Fecha Inicio:
Fecha Culm:
(TRAMO: RIO SHULLCAS - AV. 12 DE OCTUBRE) - DEL DISTRITO DE HUANCAYO, PROVINCIA DE HUANCAYO - JUNIN"
Supervisora:
19-041-0010-9002-2146103-400084-0049
Residente :
"MEJORAMIENTO DE PISTAS Y VEREDAS DE LA AV. LA VICTORIA (TRAMO: AV. PALIAN - RIO SHULLCAS) Y AV. 2 DE MAYO
OBRA
CDIGO
DESCRIPCIN
UND
ANTERIOR
METRADO
VALORIZADO
METRADO
VALORIZADO
SALDO
ACUMULADO
%
METRADO VALORIZADO
METRADO
SALDO
ALINEAMIENTO
01.01
ALINEAMIENTO DE POSTES
und
32.00
593.75
19,000.00
01.02
ALINEAMIENTO DE PREDIOS
m2
1,358.18
160.00
217,308.60
0.00
0%
0.00
0.00
1,268.00 202,880.00
0.00
93%
90.18
14,428.80
0%
0.00
0%
32.00
19,000.00
100%
7% 1,358.18 217,308.80
0.00
100%
0.00
0.00
0%
22,817.13
METRADO
ACTUAL
236,308.60
ALINEAMIENTO
01
AVANCE
TRABAJOS PRELIMINARES
01.01
m2
30.00
2.58
77.40
30.00
77.40
100%
0.00
0%
30.00
77.40
100%
0.00
0.00
0%
01.02
m2
30.00
0.87
26.10
30.00
26.10
100%
0.00
0%
30.00
26.10
100%
0.00
0.00
0%
02
MOVIMIENTO DE TIERRAS
02.01
NIVELACION DE TERRENO
m2
30.00
1.81
54.30
30.00
54.30
100%
0.00
0%
30.00
54.30
100%
0.00
0.00
0%
02.02
EXCAVACION
m3
40.00
25.78
1,031.20
40.00
1,031.20
100%
0.00
0%
40.00
1,031.20
100%
0.00
0.00
0%
02.03
m3
40.00
26.87
1,074.80
40.00
1,074.80
100%
0.00
0%
40.00
1,074.80
100%
0.00
0.00
0%
03
CONCRETO SIMPLE
03.01
m3
0.36
369.79
133.12
0.00
0.00
0%
0.36
133.12
100%
0.36
133.12
100%
0.00
0.00
0%
03.02
m2
5.07
92.78
470.39
0.00
0.00
0%
5.07
470.39
100%
5.07
470.39
100%
0.00
0.00
0%
m2
30.00
19.42
582.60
30.00
582.60
100%
0.00
0%
30.00
582.60
100%
0.00
0.00
0%
04
CONCRETO ARMADO
04.01
04.02
ZAPATAS
04.02.01
m3
9.00
337.30
3,035.70
9.00
3,035.70
100%
0.00
0%
9.00
3,035.70
100%
0.00
0.00
0%
04.02.02
kg
618.76
4.86
3,007.17
618.76
3,007.17
100%
0.00
0%
618.76
3,007.17
100%
0.00
0.00
0%
04.03
MUROS
04.03.01
m3
2.94
409.96
1,205.28
2.94
1,205.28
100%
0.00
0%
2.94
1,205.28
100%
0.00
0.00
0%
04.03.02
m2
16.88
68.06
1,148.85
16.88
1,148.85
100%
0.00
0%
16.88
1,148.85
100%
0.00
0.00
0%
04.03.03
kg
1,943.29
4.86
9,478.46
1,943.29
9,444.39
100%
34.07
0% 1,943.29
9,478.46
100%
0.00
0.00
0%
m2
2.76
33.36
91.97
0.00
0.00
0%
m2
60.00
22.93
1,375.80
60.00
1,375.80
100%
m2
2.76
8.69
23.96
0.00
0.00
0%
COSTO DIRECTO
259,125.73
224,943.60
86.81%
25,912.57
22,494.36
86.81%
1,515.84
05
05.01
06
06.01
07
07.01
2.76
91.97
100%
2.76
91.97
100%
0.00
0.00
0%
0.00
0%
60.00
1,375.80
100%
0.00
0.00
0%
0.00
0%
0.00
0.00
0%
2.76
23.96
100%
15,158.36
5.85%
240,101.96
92.66%
19,023.96
7.34%
5.85%
24,010.20
92.66%
1,902.40
7.34%
PISOS Y PAVIMENTOS
FALSO PISO DE 4" DE CONCRETO 1:10
PINTURA
PINTURA LATEX 2 MANOS
Pgina 4
SUB TOTAL
285,038.30
247,437.96
86.81%
16,674.20
5.85%
264,112.16
92.66%
20,926.35
7.34%
SUPERVISION
3,407.85
2,958.31
86.81%
199.35
5.85%
3,157.66
92.66%
250.19
7.34%
TOTAL GENERAL
288,446.15
250,396.26
86.81%
16,873.55
5.85%
267,269.82
92.66%
21,176.54
7.34%
ACUMULADO
S/.
%
267,269.82 92.66%
SALDO
S/.
%
21,176.54
7.34%
AVANCE FISICO
Pgina 5
Programa
Sub-Programa
Proyecto
Dependencia
OBRA
CDIGO
Unid. Ejec.
Presupuesto
Mod. Ejec
:Administracin Directa.
Fecha Inicio:
Fecha Culm:
(TRAMO: RIO SHULLCAS - AV. 12 DE OCTUBRE) - DEL DISTRITO DE HUANCAYO, PROVINCIA DE HUANCAYO - JUNIN"
Supervisora:
19-041-0010-9002-2146103-400084-0049
Residente :
:Transporte Terrestre
:Vas Urbanas
:Construccin de Vas Urbanas
:Gerencia de Obras Pblicas
"MEJORAMIENTO DE PISTAS Y VEREDAS DE LA AV. LA VICTORIA (TRAMO: AV. PALIAN - RIO SHULLCAS) Y AV. 2 DE MAYO
DESCRIPCIN
UND
AVANCE
ANTERIOR
METRADO
P. UNITARI
PARCIAL S/.
METRADO
VALORIZADO
ACTUAL
%
METRADO
VALORIZADO
SALDO
ACUMULADO
%
METRADO
VALORIZADO
METRADO
SALDO
26,321.10
01
01.01
OBRAS PRELIMINARES
01.01.01
TRAZO Y REPLANTEO
213.83
7.67
1640.08
0.00
0.00
0%
213.83
1,640.08
100%
213.83
1,640.08
100%
0.00
0.00
0%
01.01.02
213.83
7.67
1640.08
0.00
0.00
0%
213.83
1,640.08
100%
213.83
1,640.08
100%
0.00
0.00
0%
01.02
MOVIMIENTO DE TIERRAS
01.02.01
m3
86.64
20.30
1758.79
0.00
0.00
0%
86.64
1,758.79
100%
86.64
1,758.79
100%
0.00
0.00
0%
01.02.02
m3
108.30
4.24
459.19
0.00
0.00
0%
108.30
459.19
100%
108.30
459.19
100%
0.00
0.00
0%
01.02.03
NIVELACION Y APISONADO
213.83
2.34
500.36
0.00
0.00
0%
213.83
500.36
100%
213.83
500.36
100%
0.00
0.00
0%
01.02.04
CAMA DE APOYO
213.83
5.51
1178.2
0.00
0.00
0%
213.83
1,178.20
100%
213.83
1,178.20
100%
0.00
0.00
0%
01.02.05
m3
49.27
71.54
3524.78
0.00
0.00
0%
49.27
3,524.78
100%
49.27
3,524.78
100%
0.00
0.00
0%
01.03
OBRAS DE CONCRETO
01.03.01
CONCRETO FC=175KG/CM2
m3
2.24
51.16
114.6
0.00
0.00
0%
2.24
114.60
100%
2.24
114.60
100%
0.00
0.00
0%
01.03.02
m3
3.34
355.46
1187.24
0.00
0.00
0%
1.67
593.62
50%
1.67
593.62
50%
1.67
593.62
50%
01.03.03
ENCOFRADO Y DESENCOFRADO
m2
14.48
55.30
800.74
0.00
0.00
0%
8.50
470.05
59%
8.50
470.05
59%
5.98
330.69
41%
01.03.04
kg
161.04
4.82
776.21
0.00
0.00
0%
100.80
485.86
63%
100.80
485.86
63%
60.24
290.36
37%
01.03.05
m2
13.93
48.73
678.81
0.00
0.00
0%
0.00
0.00
0%
0.00
0.00
0%
13.93
678.81
100%
01.04
01.04.01
213.83
51.44
10999.42
0.00
0.00
0%
213.83
10,999.42
100%
213.83
10,999.42
100%
0.00
0.00
0%
01.05
01.05.01
213.83
1.44
307.92
0.00
0.00
0%
213.83
307.92
100%
213.83
307.92
100%
0.00
0.00
0%
01.06
CARPINTERIA METALICA
01.06.01
COMPUERTA METALICA
3.00
251.56
754.68
0.00
0.00
0%
0.00
0.00
0%
0.00
0.00
0%
3.00
754.68
100%
02
02.01
02.01.01
41.00
830.66
35%
26.31
533.04
22%
67.31
1,363.70
58%
49.68
1,006.52
42%
03
BUZONES H=1.20m
03.01
MOVIMIENTO DE TIERRAS
03.01.01
EXCAVACIONES
und
2,370.22
m2
116.99
20.26
2370.22
3,158.20
m3
3.05
25.78
78.63
3.05
78.63
100%
0.00
0%
3.05
78.63
100%
0.00
0.00
0%
m3
3.66
4.24
15.52
3.66
15.52
100%
0.00
0%
3.66
15.52
100%
0.00
0.00
0%
m3
3.66
5.80
21.23
3.66
21.23
100%
0.00
0%
3.66
21.23
100%
0.00
0.00
0%
m3
3.66
10.78
39.45
3.66
39.45
100%
0.00
0%
3.66
39.45
100%
0.00
0.00
0%
und
2.00
1,417.68
2835.36
2.00
2,835.36
100%
0.00
0%
2.00
2,835.36
100%
0.00
0.00
0%
m3
0.35
30.15
10.55
0.35
10.55
100%
0.00
0%
0.35
10.55
100%
0.00
0.00
0%
und
2.00
78.73
157.46
2.00
157.46
100%
0.00
0%
2.00
157.46
100%
0.00
0.00
0%
03.02
OBRAS DE CONCRETO
03.02.01
BUZONES H=1.20m
COSTO DIRECTO
31,849.52
3,988.86
12.52%
24,205.97 76.00%
28,194.83
88.53%
3,654.67
11.47%
3,184.95
398.89
12.52%
2,420.60 76.00%
2,819.48
88.53%
365.47
11.47%
Pgina 6
SUB TOTAL
SUPERVISION
TOTAL GENERAL
AVANCE FISICO
35,034.47
4,387.75
12.52%
26,626.57 76.00%
31,014.32
88.53%
4,020.14
11.47%
51.85
12.52%
314.67 76.00%
366.53
88.53%
47.51
11.47%
4,439.60
12.52%
26,941.24 76.00%
31,380.85
88.53%
4,067.65
11.47%
414.04
35,448.51
ACUMULADO
S/.
%
31,380.85
88.53%
Pgina 7
SALDO
S/.
%
4,067.65
11.47%
Programa
Sub-Programa
:Transporte Terrestre
:Vas Urbanas
Proyecto
Dependencia
OBRA
CDIGO
Unid. Ejec.
Presupuesto
Mod. Ejec
Fecha Inicio:
Fecha Culm:
Supervisora:
Residente :
DESCRIPCIN
UND
AVANCE
ANTERIOR
METRADO
P. UNITARIO
PAVIMENTOS FLEXIBLES
PARCIAL S/.
METRADO
VALORIZADO
ACTUAL
%
METRADO
METRADO
S/. 37,452.55
2,306,660.91
SALDO
ACUMULADO
VALORIZADO
VALORIZADO
METRADO
VALORIZADO
S/. 849,086.17
01
OBRAS PROVISIONALES
01.01
mes
12.00
400.00
10,284.78
4,800.00
12.00
S/. 4,800.00
100%
0.00
S/. 0.00
0%
12.00
S/. 4,800.00
100%
0.00
S/. 0.00
0%
01.02
und
2.00
1,742.90
3,485.80
1.00
S/. 1,742.90
50%
0.00
S/. 0.00
0%
1.00
S/. 1,742.90
50%
1.00
S/. 1,742.90
50%
01.03
1.00
1,998.98
1,998.98
1.00
S/. 1,998.98
100%
0.00
S/. 0.00
0%
1.00
S/. 1,998.98
100%
0.00
S/. 0.00
0%
02
TRABAJOS PRELIMINARES
02.01
21,627.36
0.87
18,815.80
5947.36
S/. 5,174.20
27%
5,120.00
S/. 4,454.40
24% 11,067.36
S/. 9,628.60
51% 10,560.00
S/. 9,187.20
49%
02.02
21,627.36
1.24
26,817.93
5947.36
S/. 7,374.73
27%
5,120.00
S/. 6,348.80
24% 11,067.36
S/. 13,723.53
51% 10,560.00
S/. 13,094.40
49%
02.03
1.00
1,463.22
1,463.22
1.00
S/. 1,463.22
100%
0.00
S/. 0.00
0%
1.00
S/. 1,463.22
100%
0.00
S/. 0.00
0%
02.04
270.34
6.40
1,730.18
270.34
S/. 1,730.18
100%
0.00
S/. 0.00
0%
270.34
S/. 1,730.18
100%
0.00
S/. 0.00
0%
02.05
50.00
224.40
11,220.00
48.00
S/. 10,771.20
96%
2.00
S/. 448.80
4%
50.00
S/. 11,220.00
100%
0.00
S/. 0.00
0%
03
EXPLANACIONES
03.01
MOVIMIENTO DE TIERRAS
03.01.01
m3
11,852.00
15.61
185,009.72
11852.00
S/. 185,009.72
100%
0.00
S/. 0.00
0% 11,852.00
S/. 185,009.72
100%
0.00
S/. 0.00
0%
03.01.02
m3
592.60
7.92
4,693.39
175.60
S/. 1,390.75
30%
0.00
S/. 0.00
0%
175.60
S/. 1,390.75
30%
417.00
S/. 3,302.64
70%
03.01.03
m3
592.60
30.08
17,825.41
137.84
S/. 4,146.23
23%
0.00
S/. 0.00
0%
137.84
S/. 4,146.23
23%
454.76
S/. 13,679.18
77%
03.01.04
m3
239.80
25.78
6,182.04
138.80
S/. 3,578.26
58%
0.00
S/. 0.00
0%
138.80
S/. 3,578.26
58%
101.00
S/. 2,603.78
42%
03.01.05
m3
6.67
30.08
200.63
3.55
S/. 106.78
53%
0.00
S/. 0.00
0%
3.55
S/. 106.78
53%
3.12
S/. 93.85
47%
03.01.06
m3
44.81
25.78
1,155.20
11.86
S/. 305.75
26%
0.00
S/. 0.00
0%
11.86
S/. 305.75
26%
32.95
S/. 849.45
74%
03.01.07
m3
14,222.40
4.24
60,302.98
9002.14
S/. 38,169.07
63%
5120.26
S/. 21,709.90
36% 14,122.40
S/. 59,878.98
99%
100.00
S/. 424.00
1%
03.01.08
m3
14,222.40
2.20
31,289.28
13648.04
S/. 30,025.69
96%
474.36
S/. 1,043.59
3% 14,122.40
S/. 31,069.28
99%
100.00
S/. 220.00
1%
03.01.09
m3
14,222.40
5.11
72,676.46
13648.04
S/. 69,741.48
96%
474.36
S/. 2,423.98
3% 14,122.40
S/. 72,165.46
99%
100.00
S/. 511.00
1%
03.01.10
m2
15,550.70
2.73
42,453.41
4390.99
S/. 11,987.40
28%
0.00
S/. 0.00
0%
4,390.99
S/. 11,987.40
28% 11,159.71
S/. 30,466.01
72%
03.02
03.02.01
m3
2,145.90
4.74
10,171.57
47.20
S/. 223.73
2%
0.00
S/. 0.00
0%
47.20
S/. 223.73
2%
2,098.70
S/. 9,947.84
98%
03.02.02
m3
2,145.90
26.27
56,372.79
47.20
S/. 1,239.94
2%
0.00
S/. 0.00
0%
47.20
S/. 1,239.94
2%
2,098.70
S/. 55,132.85
98%
03.02.03
m3
2,575.08
5.81
14,961.21
47.20
S/. 274.23
2%
0.00
S/. 0.00
0%
47.20
S/. 274.23
2%
2,527.88
S/. 14,686.98
98%
03.02.04
2,575.80
10.78
27,767.12
47.20
S/. 508.82
2%
0.00
S/. 0.00
0%
47.20
S/. 508.82
2%
2,528.60
S/. 27,258.31
98%
03.02.05
15,247.29
2.58
39,338.01
94.40
S/. 243.55
1%
0.00
S/. 0.00
0%
94.40
S/. 243.55
1% 15,152.89
S/. 39,094.46
99%
04
PAVIMENTOS
04.01
04.01.01
m3
3,970.40
4.97
19,732.89
915.87
S/. 4,551.87
23%
0.00
S/. 0.00
0%
915.87
S/. 4,551.87
23%
3,054.53
S/. 15,181.01
77%
04.01.02
m3
3,970.40
29.67
117,801.77
915.87
S/. 27,173.86
23%
0.00
S/. 0.00
0%
915.87
S/. 27,173.86
23%
3,054.53
S/. 90,627.91
77%
04.01.03
m3
4,764.48
5.66
26,966.96
915.87
S/. 5,183.82
19%
0.00
S/. 0.00
0%
915.87
S/. 5,183.82
19%
3,848.61
S/. 21,783.13
81%
04.01.04
m3
4,764.48
10.74
51,170.52
915.87
S/. 9,836.44
19%
0.00
S/. 0.00
0%
915.87
S/. 9,836.44
19%
3,848.61
S/. 41,334.07
81%
04.01.05
m2
15,247.29
3.58
54,585.30
4579.35
S/. 16,394.07
30%
0.00
S/. 0.00
0%
4,579.35
S/. 16,394.07
30% 10,667.94
S/. 38,191.23
70%
04.02
BASE GRANULAR
04.02.01
m3
3,970.40
4.96
19,693.18
915.87
S/. 4,542.72
23%
0.00
S/. 0.00
0%
915.87
S/. 4,542.72
23%
3,054.53
S/. 15,150.47
77%
04.02.02
m3
3,970.40
29.67
117,801.77
915.87
S/. 27,173.86
23%
0.00
S/. 0.00
0%
915.87
S/. 27,173.86
23%
3,054.53
S/. 90,627.91
77%
04.02.03
CARGUIO (BASE)
m3
4,764.48
2.29
10,910.66
915.87
S/. 2,097.34
19%
0.00
S/. 0.00
0%
915.87
S/. 2,097.34
19%
3,848.61
S/. 8,813.32
81%
04.02.04
m3
4,764.48
5.11
24,346.49
915.87
S/. 4,680.10
19%
0.00
S/. 0.00
0%
915.87
S/. 4,680.10
19%
3,848.61
S/. 19,666.40
81%
04.02.05
m2
15,247.29
3.58
54,585.30
4579.35
S/. 16,394.07
30%
0.00
S/. 0.00
0%
4,579.35
S/. 16,394.07
30% 10,667.94
S/. 38,191.23
70%
04.03
CARPETA ASFALTICA
04.03.01
IMPRIMACION ASFALTICA
m2
15,881.59
13.43
213,289.75
4143.81
S/. 55,651.37
26%
0.00
S/. 0.00
0%
4,143.81
S/. 55,651.37
26% 11,737.78
S/. 157,638.39
74%
04.03.02
m2
15,881.59
53.53
850,141.51
4143.81
S/. 221,818.15
26%
0.00
S/. 0.00
0%
4,143.81
S/. 221,818.15
26% 11,737.78
S/. 628,323.36
74%
05
CONCRETO ARMADO
60,047.13
570,399.24
421,788.53
148,610.71
1,561,026.09
270,257.43
227,337.40
1,063,431.27
62,706.67
Programa
Sub-Programa
:Transporte Terrestre
:Vas Urbanas
Proyecto
Dependencia
OBRA
CDIGO
Unid. Ejec.
Presupuesto
Mod. Ejec
Fecha Inicio:
Fecha Culm:
Supervisora:
Residente :
05.01
DRENAJE
05.01.01
m2
249.64
29.12
34,163.91
7,269.52
171.25
S/. 4,986.80
69%
0.00
S/. 0.00
0%
171.25
S/. 4,986.80
69%
78.39
S/. 2,282.72
31%
05.01.02
m3
69.90
352.87
24,665.61
47.95
S/. 16,920.12
69%
0.00
S/. 0.00
0%
47.95
S/. 16,920.12
69%
21.95
S/. 7,745.50
31%
05.01.03
ACABADO DE CUNETAS
m2
449.35
4.96
2,228.78
308.25
S/. 1,528.92
69%
0.00
S/. 0.00
0%
308.25
S/. 1,528.92
69%
141.10
S/. 699.86
31%
05.02
BADEN
05.02.01
m2
95.50
39.68
3,789.44
27.52
S/. 1,091.99
29%
0.00
S/. 0.00
0%
27.52
S/. 1,091.99
29%
67.98
S/. 2,697.45
71%
05.02.02
m3
45.36
336.78
15,276.34
8.34
S/. 2,808.75
18%
0.00
S/. 0.00
0%
8.34
S/. 2,808.75
18%
37.02
S/. 12,467.60
82%
05.02.03
ACABADO DE BADEN
m2
303.20
4.96
1,503.87
70.18
S/. 348.09
23%
0.00
S/. 0.00
0%
70.18
S/. 348.09
23%
233.02
S/. 1,155.78
77%
05.03
SARDINEL DE CONFINAMIENTO
05.03.01
m2
107.02
37.93
4,059.27
27.00
S/. 1,024.11
25%
0.00
S/. 0.00
0%
27.00
S/. 1,024.11
25%
80.02
S/. 3,035.16
75%
05.03.02
m3
10.70
365.78
3,913.85
2.70
S/. 987.61
25%
0.00
S/. 0.00
0%
2.70
S/. 987.61
25%
8.00
S/. 2,926.24
75%
06
JUNTAS
06.01
85.00
S/. 305.15
51%
0.00
S/. 0.00
0%
85.00
S/. 305.15
51%
81.43
S/. 292.33
49%
07
SEALIZACION
07.01
SEALIZACION HORIZONTAL
07.01.01
1,351.71
5.92
8,002.12
131.71
S/. 779.72
10%
0.00
S/. 0.00
0%
131.71
S/. 779.72
10%
1,220.00
S/. 7,222.40
90%
07.01.02
m2
28.80
18.78
540.86
5.00
S/. 93.90
17%
0.00
S/. 0.00
0%
5.00
S/. 93.90
17%
23.80
S/. 446.96
83%
07.01.03
m2
255.00
27.96
7,129.80
44.00
S/. 1,230.24
17%
0.00
S/. 0.00
0%
44.00
S/. 1,230.24
17%
211.00
S/. 5,899.56
83%
07.01.04
2,703.42
4.12
11,138.09
0.00
S/. 0.00
0%
0.00
S/. 0.00
0%
0.00
S/. 0.00
0%
2,703.42
S/. 11,138.09
100%
08
IMPACTO AMBIENTAL
08.01
21,627.36
0.29
1766.00
S/. 512.14
8%
960.00
S/. 278.40
4%
2,726.00
S/. 790.54
13% 18,901.36
S/. 5,481.39
87%
09
VARIOS
09.01
29% 15,360.00
09.02
PLACA RECORDATORIA
20,569.65
7,973.11
597.48
m
166.43
3.59
597.48
26,810.88
26,810.88
6,271.93
6,271.93
8,516.72
m2
u
21,627.36
0.36
7,785.85
4198.81
S/. 1,511.57
19%
2,068.55
S/. 744.68
10%
6,267.36
S/. 2,256.25
1.00
730.87
730.87
0.00
S/. 0.00
0%
0.00
S/. 0.00
0%
0.00
S/. 0.00
VEREDAS
S/. 55,318.77
554,982.15
S/.
0%
S/. 5,529.60
71%
1.00
S/. 730.87
100%
408,472.83
01
TRABAJOS PRELIMINARES
17,884.29
01.01
TRAZOS Y REPLANTEOS
m2
3,814.27
0.87
3,318.41
3287.74
S/. 2,860.33
86%
301.00
S/. 261.87
8%
3,588.74
S/. 3,122.20
94%
225.53
S/. 196.21
6%
01.02
3,814.27
1.24
4,729.69
3093.34
S/. 3,835.74
81%
495.40
S/. 614.30
13%
3,588.74
S/. 4,450.04
94%
225.53
S/. 279.66
6%
01.03
304.62
32.29
9,836.18
304.62
S/. 9,836.18
100%
0.00
S/. 0.00
0%
304.62
S/. 9,836.18
100%
0.00
S/. 0.00
0%
02
MOVIMIENTO DE TIERRAS
02.01
EXCAVACIONES
02.01.01
m3
576.59
30.08
17,343.83
576.59
S/. 17,343.83
100%
0.00
S/. 0.00
0%
576.59
S/. 17,343.83
100%
0.00
S/. 0.00
0%
02.01.02
m3
186.27
30.08
5,603.00
101.58
S/. 3,055.53
55%
84.69
S/. 2,547.48
45%
186.27
S/. 5,603.00
100%
0.00
S/. 0.00
0%
02.01.03
m3
217.84
30.08
6,552.63
132.03
S/. 3,971.46
61%
82.52
S/. 2,482.20
38%
214.55
S/. 6,453.66
98%
3.29
S/. 98.96
2%
02.02
02.02.01
m3
1,176.84
4.24
4,989.80
1097.65
S/. 4,654.04
93%
79.19
S/. 335.77
7%
1,176.84
S/. 4,989.80
100%
0.00
S/. 0.00
0%
02.02.02
m3
1,481.46
5.80
8,592.47
1391.38
S/. 8,070.00
94%
90.08
S/. 522.46
6%
1,481.46
S/. 8,592.47
100%
0.00
S/. 0.00
0%
02.02.03
m3
1,481.46
10.78
15,970.14
1391.38
S/. 14,999.08
94%
90.08
S/. 971.06
6%
1,481.46
S/. 15,970.14
100%
0.00
S/. 0.00
0%
03
CONCRETO SIMPLE
03.01
SARDINEL EXPUESTO
03.01.01
m2
1,806.97
34.70
62,701.86
1241.81
S/. 43,090.81
69%
322.20
S/. 11,180.34
18%
1,564.01
S/. 54,271.15
87%
242.96
S/. 8,430.71
13%
03.01.02
m3
216.84
349.31
75,744.38
149.62
S/. 52,263.76
69%
49.00
S/. 17,116.19
23%
198.62
S/. 69,379.95
92%
18.22
S/. 6,364.43
8%
03.01.03
m2
1,714.72
4.96
8,505.01
1221.96
S/. 6,060.92
71%
310.50
S/. 1,540.08
18%
1,532.46
S/. 7,601.00
89%
182.26
S/. 904.01
11%
03.02
VEREDAS
03.02.01
m2
2,882.94
1.87
5,391.10
2277.74
S/. 4,259.37
79%
62.90
S/. 117.62
2%
2,340.64
S/. 4,377.00
81%
542.30
S/. 1,014.10
19%
03.02.02
m2
2,743.74
9.68
26,559.40
2624.84
S/. 25,408.45
96%
40.87
S/. 395.62
1%
2,665.71
S/. 25,804.07
97%
78.03
S/. 755.33
3%
03.02.03
m2
337.89
20.26
6,845.65
337.89
S/. 6,845.65
100%
0.00
S/. 0.00
0%
337.89
S/. 6,845.65
100%
0.00
S/. 0.00
0%
03.02.04
m3
2,882.94
44.45
128,146.68
2192.28
S/. 97,446.85
76%
148.54
S/. 6,602.60
5%
2,340.82
S/. 104,049.45
81%
542.12
S/. 24,097.23
19%
03.03
MARTILLOS
m3
59,051.86
29,499.46
29,552.41
344,949.77
146,951.25
166,942.84
29,803.43
Programa
Sub-Programa
:Transporte Terrestre
:Vas Urbanas
Proyecto
Dependencia
OBRA
CDIGO
Unid. Ejec.
Presupuesto
Mod. Ejec
Fecha Inicio:
Fecha Culm:
Supervisora:
Residente :
03.03.01
m2
931.33
3.00
2,793.99
507.91
S/. 1,523.73
55%
44.24
S/. 132.72
5%
552.15
S/. 1,656.45
59%
379.18
S/. 1,137.54
41%
03.03.02
m2
441.16
9.68
4,270.43
256.85
S/. 2,486.31
58%
44.24
S/. 428.24
10%
301.09
S/. 2,914.55
68%
140.07
S/. 1,355.88
32%
03.03.03
m2
138.65
36.03
4,995.56
79.23
S/. 2,854.66
57%
12.80
S/. 461.18
9%
92.03
S/. 3,315.84
66%
46.62
S/. 1,679.72
34%
03.03.04
m2
441.16
40.22
17,743.46
256.85
S/. 10,330.51
58%
44.24
S/. 1,779.33
10%
301.09
S/. 12,109.84
68%
140.07
S/. 5,633.62
32%
03.04
RAMPAS
03.04.01
m2
7.00
36.30
254.10
6.10
S/. 221.43
87%
0.90
S/. 32.67
13%
7.00
S/. 254.10
100%
0.00
S/. 0.00
0%
03.04.02
m3
2.38
369.79
880.10
1.97
S/. 728.49
83%
0.41
S/. 151.61
17%
2.38
S/. 880.10
100%
0.00
S/. 0.00
0%
03.04.03
ACABADO DE RAMPA
m2
23.80
4.96
118.05
20.90
S/. 103.66
88%
2.90
S/. 14.38
12%
23.80
S/. 118.05
100%
0.00
S/. 0.00
0%
04
JUNTAS
1,252.25
5,425.75
Programa
Sub-Programa
:Transporte Terrestre
:Vas Urbanas
Proyecto
Dependencia
OBRA
CDIGO
04.01
RELLENO DE JUNTAS
05
AREAS VERDES
1,511.35
3.59
5,425.75
05.01
m2
2,402.45
2.23
5,357.46
05.02
m3
480.49
98.63
47,390.73
05.03
COLOCADO DE GRASS
m2
2,402.45
8.81
05.04
COLOCADO DE PLANTONES
900.00
10.86
06
SEALIZACION
06.01
SEALIZACION HORIZONTAL
06.01.01
06.02
SEALIZACION VERTICAL
06.02.01
3.00
388.19
06.02.02
SEALIZACIONES TIPO P
6.00
388.19
06.02.03
SEALIZACIONES TIPO F
6.00
06.02.04
2.00
07
RECONEXIONES
07.01
pto
111.00
40.36
07.02
pto
111.00
35.69
07.03
pto
111.00
07.04
pto
111.00
08
VARIOS
08.01
08.02
908.70
Unid. Ejec.
Presupuesto
Mod. Ejec
Fecha Inicio:
Fecha Culm:
Supervisora:
Residente :
S/. 3,262.23
60%
0.00
S/. 0.00
0%
908.70
S/. 3,262.23
60%
602.65
S/. 2,163.51
40%
398.79
S/. 889.30
17%
393.75
S/. 878.06
16%
792.54
S/. 1,767.36
33%
79.76
S/. 7,866.73
17%
0.00
S/. 0.00
0%
79.76
S/. 7,866.73
17%
1,609.91
S/. 3,590.10
67%
400.73
S/. 39,524.00
21,165.58
398.79
S/. 3,513.34
17%
0.00
S/. 0.00
0%
398.79
S/. 3,513.34
83%
17%
2,003.66
S/. 17,652.24
9,774.00
0.00
S/. 0.00
0%
0.00
S/. 0.00
0%
0.00
83%
S/. 0.00
0%
900.00
S/. 9,774.00
100%
62.00
S/. 162.44
2%
0.00
S/. 0.00
0%
62.00
S/. 162.44
2%
3,551.94
S/. 9,306.08
98%
1,164.57
0.00
S/. 0.00
0%
0.00
S/. 0.00
2,329.14
0.00
S/. 0.00
0%
0.00
S/. 0.00
0%
0.00
S/. 0.00
0%
3.00
S/. 1,164.57
100%
0%
0.00
S/. 0.00
0%
6.00
S/. 2,329.14
388.19
2,329.14
0.00
S/. 0.00
0%
0.00
100%
S/. 0.00
0%
0.00
S/. 0.00
0%
6.00
S/. 2,329.14
501.93
1,003.86
0.00
S/. 0.00
0%
100%
0.00
S/. 0.00
0%
0.00
S/. 0.00
0%
2.00
S/. 1,003.86
100%
4,479.96
65.00
S/. 2,623.40
3,961.59
67.00
S/. 2,391.23
59%
39.00
S/. 1,574.04
35%
104.00
S/. 4,197.44
94%
7.00
S/. 282.52
6%
60%
37.00
S/. 1,320.53
33%
104.00
S/. 3,711.76
94%
7.00
S/. 249.83
21.72
2,410.92
65.00
6%
S/. 1,411.80
59%
39.00
S/. 847.08
35%
104.00
S/. 2,258.88
94%
7.00
S/. 152.04
35.87
3,981.57
6%
68.00
S/. 2,439.16
61%
36.00
S/. 1,291.32
32%
104.00
S/. 3,730.48
94%
7.00
S/. 251.09
6%
83,687.78
16,295.23
9,468.52
m
3,613.94
2.62
9,468.52
6,826.71
14,834.04
12,853.44
m2
u
3,347.90
2.15
7,197.99
2424.44
S/. 5,212.55
72%
800.00
S/. 1,720.00
24%
3,224.44
S/. 6,932.55
96%
123.46
S/. 265.44
4%
15.00
377.03
5,655.45
3.00
S/. 1,131.09
20%
0.00
S/. 0.00
0%
3.00
S/. 1,131.09
20%
12.00
S/. 4,524.36
80%
ALINEAMIENTO
S/. 0.00
177,793.00
S/.
161,253.00
01
ALINEAMIENTO
177,793.00
01.01
ALINEAMIENTO DE POSTES
32.00
500.00
16,000.00
0.00
S/. 0.00
0%
0.00
S/. 0.00
0%
0.00
S/. 0.00
0%
32.00
S/. 16,000.00
100%
01.02
ALINEAMIENTO DE PREDIOS
1,797.70
90.00
161,793.00
1,791.70
S/. 161,253.00
100%
0.00
S/. 0.00
0%
1,791.70
S/. 161,253.00
100%
6.00
S/. 540.00
0%
DESAGUE PLUVIAL
S/. 8,822.63
212,426.29
S/.
197,191.19
01
TRABAJOS PRELIMINARES
01.01
1,117.34
1.38
3,083.86
1,541.93
1066.90
S/. 1,472.32
95%
50.44
S/. 69.61
5%
1,117.34
S/. 1,541.93
100%
0.00
S/. 0.00
0%
01.02
1,117.34
1.38
1,541.93
1117.34
S/. 1,541.93
100%
0.00
S/. 0.00
0%
1,117.34
S/. 1,541.93
100%
0.00
S/. 0.00
0%
02
MOVIMIENTO DE TIERRAS
03
EXCAVACIONES
03.01
m3
27.14
25.78
699.67
27.14
S/. 699.67
100%
0.00
S/. 0.00
0%
27.14
S/. 699.67
100%
0.00
S/. 0.00
0%
03.02
1,117.34
5.42
6,055.98
1066.00
S/. 5,777.72
95%
22.00
S/. 119.24
2%
1,088.00
S/. 5,896.96
97%
29.34
S/. 159.02
3%
03.03
m3
39.15
25.78
1,009.29
33.95
S/. 875.23
87%
0.00
S/. 0.00
0%
33.95
S/. 875.23
87%
5.20
S/. 134.06
13%
03.04
1,117.34
2.34
2,614.58
1066.00
S/. 2,494.44
95%
22.00
S/. 51.48
2%
1,088.00
S/. 2,545.92
97%
29.34
S/. 68.66
3%
04
CAMAS DE APOYO
04.01
1066.00
S/. 5,873.66
95%
22.00
S/. 121.22
2%
1,088.00
S/. 5,994.88
97%
29.34
S/. 161.66
3%
05
RELLENOS
05.01
m3
1,072.65
4.74
5,084.36
1007.85
S/. 4,777.20
94%
30.00
S/. 142.20
3%
1,037.85
S/. 4,919.40
97%
34.80
S/. 164.96
3%
05.02
m3
1,072.65
4.74
5,084.36
1007.85
S/. 4,777.20
94%
30.00
S/. 142.20
3%
1,037.85
S/. 4,919.40
97%
34.80
S/. 164.96
3%
05.03
CARGUIO P/RELLENO
m3
1,072.65
5.98
6,414.45
1007.85
S/. 6,026.93
94%
30.00
S/. 179.40
3%
1,037.85
S/. 6,206.33
97%
34.80
S/. 208.12
3%
05.04
m3
1,072.65
10.76
11,541.71
1007.85
S/. 10,844.44
94%
30.00
S/. 322.80
3%
1,037.85
S/. 11,167.24
97%
34.80
S/. 374.47
3%
05.05
1,117.34
27.41
30,626.29
1066.00
S/. 29,219.06
95%
22.00
S/. 603.02
2%
1,088.00
S/. 29,822.08
97%
29.34
S/. 804.21
3%
06
10,379.51
10,379.51
6,156.54
m
1,117.34
5.51
6,156.54
58,751.17
28,455.32
Programa
Sub-Programa
:Transporte Terrestre
:Vas Urbanas
Proyecto
Dependencia
OBRA
CDIGO
Unid. Ejec.
Presupuesto
Mod. Ejec
Fecha Inicio:
Fecha Culm:
Supervisora:
Residente :
06.01
m3
1,366.73
4.24
5,794.94
1265.93
S/. 5,367.54
93%
53.25
S/. 225.78
4%
1,319.18
S/. 5,593.32
97%
47.55
S/. 201.61
3%
06.02
m3
1,366.73
5.80
7,927.03
1265.93
S/. 7,342.39
93%
53.25
S/. 308.85
4%
1,319.18
S/. 7,651.24
97%
47.55
S/. 275.79
3%
06.03
1,366.73
10.78
14,733.35
1265.93
S/. 13,646.73
93%
53.25
S/. 574.04
4%
1,319.18
S/. 14,220.76
97%
47.55
S/. 512.59
3%
Programa
Sub-Programa
:Transporte Terrestre
:Vas Urbanas
Proyecto
Dependencia
OBRA
CDIGO
Unid. Ejec.
Presupuesto
Mod. Ejec
Fecha Inicio:
Fecha Culm:
Supervisora:
Residente :
07
CONCRETO ARMADO
07.01
BUZONES
42,764.57
07.01.01
11.00
1,436.08
15,796.88
11.00
S/. 15,796.88
100%
0.00
S/. 0.00
0%
11.00
S/. 15,796.88
100%
0.00
S/. 0.00
0%
07.01.02
2.00
1,557.18
3,114.36
2.00
S/. 3,114.36
100%
0.00
S/. 0.00
0%
2.00
S/. 3,114.36
100%
0.00
S/. 0.00
0%
07.01.03
26.00
78.73
2,046.98
26.00
S/. 2,046.98
100%
0.00
S/. 0.00
0%
26.00
S/. 2,046.98
100%
0.00
S/. 0.00
0%
07.02
ENCIMADO DE BUZONES
07.02.01
4.00
S/. 3,485.00
80%
0.00
S/. 0.00
0%
4.00
S/. 3,485.00
80%
1.00
S/. 871.25
20%
07.03
SUMIDEROS
07.03.01
CONSTRUCCION DE SUMIDEROS
30.00
449.31
13,479.30
23.00
S/. 10,334.13
77%
0.00
S/. 0.00
0%
23.00
S/. 10,334.13
77%
7.00
S/. 3,145.17
23%
07.03.02
30.00
132.36
3,970.80
23.00
S/. 3,044.28
77%
0.00
S/. 0.00
0%
23.00
S/. 3,044.28
77%
7.00
S/. 926.52
23%
08
08.01
228.21
56.63
12,923.53
159.00
S/. 9,004.17
70%
0.00
S/. 0.00
0%
159.00
S/. 9,004.17
70%
69.21
S/. 3,919.36
30%
08.02
889.13
46.19
41,068.91
761.70
S/. 35,182.92
86%
127.43
S/. 5,885.99
14%
889.13
S/. 41,068.91
100%
0.00
S/. 0.00
0%
08.03
30.00
57.51
1,725.30
18.00
S/. 1,035.18
60%
0.00
S/. 0.00
0%
18.00
S/. 1,035.18
60%
12.00
S/. 690.12
40%
09
PRUEBA HIDRAULICA
09.01
1,012.34
1.44
959.00
S/. 1,380.96
95%
53.34
S/. 76.81
5%
1,012.34
S/. 1,457.77
100%
0.00
S/. 0.00
0%
10
CARPINTERIA METALICA
10.01
VENTANA METALICA
30.00
112.46
3,373.80
17.00
S/. 1,911.82
57%
0.00
S/. 0.00
0%
17.00
S/. 1,911.82
57%
13.00
S/. 1,461.98
43%
10.02
REJILLA METALICA
30.00
76.20
2,286.00
17.00
S/. 1,295.40
57%
0.00
S/. 0.00
0%
17.00
S/. 1,295.40
57%
13.00
S/. 990.60
43%
20,958.22
4,356.25
u
5.00
871.25
4,356.25
17,450.10
55,717.75
1,457.77
1,457.77
5,659.80
S/. 0.00
94,416.48
S/.
94,416.48
01
TRABAJOS PRELIMINARES
01.01
TRAZO Y REPLANTEO
m2
102.00
0.87
17,647.90
88.74
102.00
S/. 88.74
100%
0.00
S/. 0.00
0%
102.00
S/. 88.74
100%
0.00
S/. 0.00
0%
01.02
m2
102.00
2.58
263.16
102.00
S/. 263.16
100%
0.00
S/. 0.00
0%
102.00
S/. 263.16
100%
0.00
S/. 0.00
0%
01.03
m2
800.00
21.62
17,296.00
800.00
S/. 17,296.00
100%
0.00
S/. 0.00
0%
800.00
S/. 17,296.00
100%
0.00
S/. 0.00
0%
02
MOVIMIENTO DE TIERRAS
02.01
14.00
35.02
490.28
14.00
S/. 490.28
100%
0.00
S/. 0.00
0%
14.00
S/. 490.28
100%
0.00
S/. 0.00
0%
02.02
71.28
5.45
388.48
71.28
S/. 388.48
100%
0.00
S/. 0.00
0%
71.28
S/. 388.48
100%
0.00
S/. 0.00
0%
03
CONCRETO SIMPLE
03.01
m3
53.21
324.44
17,263.45
53.21
S/. 17,263.45
100%
0.00
S/. 0.00
0%
53.21
S/. 17,263.45
100%
0.00
S/. 0.00
0%
03.02
m2
54.00
42.16
2,276.64
54.00
S/. 2,276.64
100%
0.00
S/. 0.00
0%
54.00
S/. 2,276.64
100%
0.00
S/. 0.00
0%
04
CONCRETO ARMADO
04.01
48.00
19.42
932.16
48.00
S/. 932.16
100%
0.00
S/. 0.00
0%
48.00
S/. 932.16
100%
0.00
S/. 0.00
0%
04.02
m3
56.06
372.33
20,872.82
56.06
S/. 20,872.82
100%
0.00
S/. 0.00
0%
56.06
S/. 20,872.82
100%
0.00
S/. 0.00
0%
04.03
ENCOFRADO Y DESENCOFRADO
m2
118.22
77.40
9,150.23
118.22
S/. 9,150.23
100%
0.00
S/. 0.00
0%
118.22
S/. 9,150.23
100%
0.00
S/. 0.00
0%
04.04
kg
4,517.56
4.82
21,774.64
4,517.56
S/. 21,774.64
100%
0.00
S/. 0.00
0%
4,517.56
S/. 21,774.64
100%
0.00
S/. 0.00
0%
05
ESTRUCTURAS METALICA
05.01
14.60
S/. 2,941.75
100%
0.00
S/. 0.00
0%
14.60
S/. 2,941.75
100%
0.00
S/. 0.00
0%
06
JUNTAS
06.01
JUNTAS ASFALTICAS
5.40
5.61
30.29
5.40
S/. 30.29
100%
0.00
S/. 0.00
0%
5.40
S/. 30.29
100%
0.00
S/. 0.00
0%
06.02
16.00
40.49
647.84
16.00
S/. 647.84
100%
0.00
S/. 0.00
0%
16.00
S/. 647.84
100%
0.00
S/. 0.00
0%
878.76
m3
19,540.09
52,729.85
2,941.75
m
14.60
201.49
2,941.75
678.13
MUROS DE CONTENCION
S/. 0.00
228,205.68
S/.
64,841.81
01
TRABAJOS PRELIMINARES
01.01
TRAZOS Y REPLANTEOS
m2
90.00
0.87
2,558.70
78.30
27.00
S/. 23.49
30%
0.00
S/. 0.00
0%
27.00
S/. 23.49
30%
63.00
S/. 54.81
70%
01.02
m2
90.00
27.56
2,480.40
27.00
S/. 744.12
30%
0.00
S/. 0.00
0%
27.00
S/. 744.12
30%
63.00
S/. 1,736.28
70%
Programa
Sub-Programa
:Transporte Terrestre
:Vas Urbanas
Proyecto
Dependencia
OBRA
CDIGO
Unid. Ejec.
Presupuesto
Mod. Ejec
Fecha Inicio:
Fecha Culm:
Supervisora:
Residente :
02
MOVIMIENTO DE TIERRAS
02.01
m3
140.40
21.90
12,054.56
3,074.76
42.12
S/. 922.43
30%
0.00
S/. 0.00
0%
42.12
S/. 922.43
30%
98.28
S/. 2,152.33
70%
02.02
m3
168.48
4.24
714.36
50.54
S/. 214.29
30%
0.00
S/. 0.00
0%
50.54
S/. 214.29
30%
117.94
S/. 500.07
70%
02.03
168.48
26.87
4,527.06
50.54
S/. 1,358.01
30%
0.00
S/. 0.00
0%
50.54
S/. 1,358.01
30%
117.94
S/. 3,169.05
70%
02.04
46.80
79.88
3,738.38
14.04
S/. 1,121.52
30%
0.00
S/. 0.00
0%
14.04
S/. 1,121.52
30%
32.76
S/. 2,616.87
70%
Programa
Sub-Programa
:Transporte Terrestre
:Vas Urbanas
Proyecto
Dependencia
OBRA
CDIGO
Unid. Ejec.
Presupuesto
Mod. Ejec
Fecha Inicio:
Fecha Culm:
Supervisora:
Residente :
03
CONCRETO ARMADO
03.01
m2
156.00
13.41
211,103.93
2,091.96
46.80
S/. 627.59
30%
0.00
S/. 0.00
0%
46.80
S/. 627.59
30%
109.20
S/. 1,464.37
70%
03.02
m3
141.00
810.33
114,256.53
42.30
S/. 34,276.96
30%
0.00
S/. 0.00
0%
42.30
S/. 34,276.96
30%
98.70
S/. 79,979.57
70%
03.03
m2
420.00
112.72
47,342.40
126.00
S/. 14,202.72
30%
0.00
S/. 0.00
0%
126.00
S/. 14,202.72
30%
294.00
S/. 33,139.68
70%
03.04
kg
10,002.75
4.74
47,413.04
2237.16
S/. 10,604.14
22%
0.00
S/. 0.00
0%
2,237.16
S/. 10,604.14
22%
7,765.59
S/. 36,808.90
78%
04
VARIOS
04.01
JUNTAS ASFALTICAS
35.00
5.61
196.35
10.50
S/. 58.91
30%
0.00
S/. 0.00
0%
10.50
S/. 58.91
30%
24.50
S/. 137.45
70%
04.02
35.00
65.49
2,292.15
10.50
S/. 687.65
30%
0.00
S/. 0.00
0%
10.50
S/. 687.65
30%
24.50
S/. 1,604.51
70%
2,488.50
S/. 1,683.26
42,268.20
S/.
42,201.03
01
TRABAJOS PRELIMINARES
01.01
m2
78.40
2.58
270.48
202.27
78.40
S/. 202.27
100%
0.00
S/. 0.00
0%
78.40
S/. 202.27
100%
0.00
S/. 0.00
0%
01.02
m2
78.40
0.87
68.21
78.40
S/. 68.21
100%
0.00
S/. 0.00
0%
78.40
S/. 68.21
100%
0.00
S/. 0.00
0%
02
MOVIMIENTO DE TIERRAS
02.01
NIVELACION DE TERRENO
m2
78.40
1.81
141.90
78.40
S/. 141.90
100%
0.00
S/. 0.00
0%
78.40
S/. 141.90
100%
0.00
S/. 0.00
0%
02.02
EXCAVACION
m3
99.20
25.78
2,557.38
99.20
S/. 2,557.38
100%
0.00
S/. 0.00
0%
99.20
S/. 2,557.38
100%
0.00
S/. 0.00
0%
02.03
99.20
26.87
2,665.50
83.40
S/. 2,240.96
84%
15.80
S/. 424.55
16%
99.20
S/. 2,665.50
100%
0.00
S/. 0.00
0%
03
CONCRETO SIMPLE
03.01
m3
1.47
369.79
543.59
0.87
S/. 321.72
59%
0.60
S/. 221.87
41%
1.47
S/. 543.59
100%
0.00
S/. 0.00
0%
03.02
m2
20.50
92.78
1,901.99
13.83
S/. 1,283.15
67%
6.67
S/. 618.84
33%
20.50
S/. 1,901.99
100%
0.00
S/. 0.00
0%
04
CONCRETO ARMADO
04.01
78.40
S/. 1,522.53
100%
0.00
S/. 0.00
0%
78.40
S/. 1,522.53
100%
0.00
S/. 0.00
0%
04.02
ZAPATAS
04.02.01
m3
23.52
337.30
7,933.30
23.52
S/. 7,933.30
100%
0.00
S/. 0.00
0%
23.52
S/. 7,933.30
100%
0.00
S/. 0.00
0%
04.02.02
kg
2,597.57
4.86
12,624.19
2,597.57
S/. 12,624.19
100%
0.00
S/. 0.00
0%
2,597.57
S/. 12,624.19
100%
0.00
S/. 0.00
0%
04.03
MUROS
04.03.01
m3
8.82
409.96
3,615.85
8.82
S/. 3,615.85
100%
0.00
S/. 0.00
0%
8.82
S/. 3,615.85
100%
0.00
S/. 0.00
0%
04.03.02
m2
50.64
68.06
3,446.56
50.64
S/. 3,446.56
100%
0.00
S/. 0.00
0%
50.64
S/. 3,446.56
100%
0.00
S/. 0.00
0%
04.03.03
kg
559.74
4.86
2,720.34
559.74
S/. 2,720.34
100%
0.00
S/. 0.00
0%
559.74
S/. 2,720.34
100%
0.00
S/. 0.00
0%
05
05.01
TARRAJEO EN EXTERIORES
0.00
S/. 0.00
0%
12.53
S/. 418.00
100%
12.53
S/. 418.00
100%
0.00
S/. 0.00
0%
06
PISOS Y PAVIMENTOS
06.01
78.40
S/. 1,797.71
100%
0.00
S/. 0.00
0%
78.40
S/. 1,797.71
100%
0.00
S/. 0.00
0%
07
PINTURA
07.01
0.00
4.80
S/. 41.71
38%
7.73
5,364.78
2,445.58
31,862.76
m2
78.40
19.42
1,522.53
20,557.49
9,782.74
418.00
m2
12.53
33.36
418.00
1,797.71
m2
78.40
22.93
1,797.71
108.89
m2
S/. 41.71
38%
S/. 0.00
0%
S/. 67.17
62%
COSTO DIRECTO
12.53
8.69
3,616,752.73
108.89
4.80
1,714,185.28
47.40%
103,277.22
2.86%
1,817,462.50 50.25%
1,799,290.24
49.75%
SUPERVICION 1.33 %
48,000.00
22,749.94
47.40%
1,370.65
2.86%
24,120.59 50.25%
23,879.41
49.75%
10,000.00
4,739.57
47.40%
285.55
2.86%
5,025.12 50.25%
4,974.88
49.75%
GASTOS GENERALES 10 %
361,675.27
171,418.53
47.40%
10,327.72
2.86%
181,746.25 50.25%
179,929.02
49.75%
SUB TOTAL
4,036,428.00
1,913,093.31
47.40%
115,261.15
2.86%
2,028,354.46 50.25%
2,008,073.55
49.75%
TOTAL GENERAL
4,036,428.00
1,913,093.31
47.40%
115,261.15
2.86%
2,028,354.46 50.25%
2,008,073.55
49.75%
RESUMEN DE PRESUPUESTO
DESCRIPCION
PRESUPUESTO
DE EXPEDIENTE
PRESUPUESTO
EJECUTADO
%
EJECUTADO
PRESUPUESTO
QUE FALTA
EJECUTAR
% POR
EJECUTAR
EXPEDIENTE TCNICO
PAVIMENTO FLEXIBLE
S/. 2,306,660.91
S/. 849,086.17
36.81%
S/. 1,457,574.74
63.19%
VEREDAS PEATONALES
S/. 554,982.15
S/. 408,472.83
73.60%
S/. 146,509.33
26.40%
ALINEAMIENTO
S/. 177,793.00
S/. 161,253.00
90.70%
S/. 16,540.00
9.30%
DESAGUE PLUVIAL
S/. 212,426.29
S/. 197,191.19
92.83%
S/. 15,235.11
7.17%
S/. 94,416.48
S/. 94,416.48
100.00%
S/. 0.00
0.00%
S/. 228,205.68
S/. 64,841.81
28.41%
S/. 163,363.87
S/. 42,268.20
S/. 42,201.03
S/. 3,616,752.73
S/. 1,817,462.50
S/. 48,000.00
S/. 24,120.59
S/. 10,000.00
S/. 5,025.12
S/. 361,675.27
S/. 181,746.25
### S/. 2,028,354.46
99.84%
S/. 67.17
S/. 1,799,290.23
S/. 23,879.41
S/. 4,974.88
S/. 179,929.02
S/. 2,008,073.54
REHABILITACION DE ESTRIBOS
MURO DE CONTENCION
REHABILITACION DE PONTONES PARA
CANAL
RIEGO
COSTO DE
DIRECTO
SUPERVICION 1.33 %
EXP. TECNICO 0.28 %
GASTOS GENERALES 10 %
TOTAL GENERAL
50.25%
71.59%
0.16%
49.75%
ADICIONALES DE OBRA
ADICIONAL N 01
S/. 109,459.39
S/. 109,459.43
100.00%
S/. 0.00
0.00%
ADICIONAL N 02
S/. 83,232.34
S/. 83,232.34
100.00%
S/. 0.00
0.00%
ADICIONAL N 03
S/. 288,446.15
S/. 267,269.82
92.66%
S/. 21,176.33
7.34%
ADICIONAL N 04
S/. 35,448.51
S/. 31,380.85
88.53%
S/. 4,067.67
S/. 516,586.39
S/. 491,342.44
95.11%
S/. 25,244.00
4.89%
###
###
55.34%
2,033,317.49
44.66%
TOTAL GENERAL
PIP ACTUALIZADO
PRESUPUESTO
AVANZADO
AVANCE
TOTAL
S/. 2,519,696.89
55.34%
Pgina 16
11.47%
MENSUAL ABRIL-2013
Programa
:Transporte Terrestre
Sub-Programa
:Vas Urbanas
:2013
Proyecto
:Administracin Directa.
Dependencia
META PRESP.
OBRA
CDIGO 19-041-0010-0108-2133482-400084-0015
ITEM
DESCRIPCIN
UND
METRADO
ABRIL
P. UNITARIPARCIAL S/.
MAYO
PROG
%
EJEC
MET
JUNIO
PROG
MET
EJEC
MET
JULIO
PROG
MET
EJEC
MET
AGOSTO
PROG
MET
EJEC
MET
PROG
MET
MET
OBRAS PROVICIONALES
01
OBRAS PROVICIONALES
01.01
MES
8.00
400.00
3,200.00
0.0375
01.02
01.03
1.00
1,784.01
1,784.01
GLB
1.00
3,137.52
3,137.52
02
TRABAJOS PRELIMINARES
02.01
TRAZO Y REPLANTEO
M2
14,379.35
0.75
10,784.51
0.8
0.2
02.02
M2
14,379.35
1.00
14,379.35
0.0375
0.1666667
02.03
M3
45.41
45.99
2,088.41
0.3
03
EXPLANACIONES
03.01
M3
5,154.55
4.73
24,381.02
03.02
EXCAVACION MANUAL
M3
428.93
22.05
9,457.91
03.03
M3
6,700.17
10.96
73,433.86
03.04
M2
8,874.89
1.93
17,128.54
04
ESTRUCTURA DE PAVIMENTO
04.01
SUB RASANTE
04.01.01
M2
2,291.20
7.30
16,725.76
04.02
04.02.01
M2
8,852.60
7.57
67,014.18
04.03
04.03.01
M2
8,169.53
8.76
71,565.08
04.04
CARPETA ASFALTICA
04.04.01
IMPRIMACION ASFALTICA
M2
8,169.53
4.06
33,168.29
04.04.02
M2
8,169.53
46.29
378,167.54
04.05
CUNETAS
04.05.01
M2
199.36
27.28
5,438.54
04.05.02
M3
174.44
291.49
50,847.52
04.05.03
ACABADOS DE CUNETAS
M2
622.99
19.54
12,173.22
05
VEREDAS PEATONALES
05.01
SARDINEL EXPUESTO
05.01.01
M2
2,970.22
29.95
88,958.09
05.01.02
M3
222.77
294.68
65,645.86
05.01.03
M2
990.07
12.89
12,762.00
05.02
SARDINEL INEXPUESTO
05.02.01
M2
1,057.40
29.95
31,669.13
05.02.02
M3
79.31
294.68
23,371.07
05.02.03
M2
352.47
12.89
4,543.34
05.03
SARDINEL DE CONFINAMIENTO
05.03.01
M2
174.81
18.29
3,197.27
05.03.02
M3
10.73
333.98
3,583.61
05.04
VEREDAS
05.04.01
M3
794.59
22.05
17,520.71
05.04.02
M2
3,972.97
2.54
10,091.34
05.04.03
M3
953.51
10.96
10,450.47
05.04.04
M2
3,972.97
7.97
05.04.05
M2
86.73
27.11
2,351.25
05.04.06
M2
3,972.97
34.66
137,703.14
05.04.07
ACABADO DE VEREDAS
M2
3,972.97
14.81
58,839.69
05.05
05.05.01
M2
50.40
19.67
991.37
BASE GRANULAR
31,664.57
0.1666667
0.2916667
0.4208333
0.55
0.2916667
0.4208333
0.55
0.5
05.05.02
M2
16.20
34.91
565.54
05.05.03
ACABADO DE RAMPAS
M2
108.00
26.11
2,819.88
06
JUNTAS
06.01
ML
1,551.70
3.75
5,818.88
07
TRATAMIENTO DE JARDINERIA
07.01
M2
1,250.90
0.43
537.89
07.02
M3
188.46
56.07
10,566.95
07.03
M2
1,250.90
10.67
13,347.10
07.04
PLANTADO DE ARBUSTOS
UN D
588.00
7.38
4,339.44
08
SEALIZACION HORIZONTAL
08.01
ML
2,475.18
3.09
7,648.31
08.02
ML
1,124.52
3.23
3,632.20
08.03
M2
50.40
17.47
880.49
08.04
M2
440.40
19.23
8,468.89
09
VARIOS
09.01
M2
14,379.35
0.18
2,588.28
09.02
PTO
167.00
27.79
09.03
PTO
167.00
21.38
3,570.46
09.04
PTO
167.00
61.93
10,342.31
09.05
PTO
167.00
21.22
3,543.74
09.06
ALINEAMIENTO DE POSTES
UND
47.00
1,200.00
56,400.00
09.07
M2
99.77
400.00
39,908.00
M2
12,825.57
0.22
2,821.63
4,640.93
10 MITIGACION AMBIENTAL
10.01 MITIGACION DE POLVO EN EJECUCION
01
DESAGUE PLUVIAL
01.01
TRABAJOS PRELIMINARES
01.01.01
ML
1,435.00
0.69
990.15
01.01.02
1,435.00
0.85
1,219.75
01.02
MOVIMIENTO DE TIERRAS
01.02.01
M3
45.15
29.40
1,327.41
01.02.02
M3
162.69
25.20
4,099.79
01.02.03
M3
855.72
4.12
3,525.57
01.02.04
M3
89.90
22.05
1,982.30
01.02.05
ML
1,435.00
2.28
3,271.80
01.02.06
ML
1,435.00
4.63
6,644.05
01.03
01.03.01
M3
559.65
42.39
23,723.56
01.03.02
M3
394.63
63.86
25,201.07
01.03.03
M3
431.11
10.96
4,724.97
01.04
01.04.01
BUZONES
01.04.01.01
UND
21.00
1,679.97
35,279.37
01.04.02
SUMIDEROS
01.04.02.01
CONSTRUCCION DE SUMIDERO
UND
58.00
771.34
44,737.72
01.04.03
DADOS DE CONCRETO
01.04.03.01
UND
42.00
119.23
5,007.66
01.05
01.05.01
ML
246.50
42.25
10,414.63
01.05.02
ML
1,188.50
55.53
65,997.41
01.05.03
UND
43.00
30.97
1,331.71
01.06
INSTALACIONES METALICAS
01.06.01
M2
58.00
95.33
5,529.14
01.07
PRUEBA HIDRAULICA
01.07.01
ML
1,435.00
1.43
2,052.05
01
MURO DE CONTENCION
01.01
OBRAS PRELIMINARES
01.01.01
TRAZO Y REPLANTEO
M2
46.53
0.75
34.90
01.01.02
M2
46.53
1.00
46.53
01.02
MOVIMIENTO DE TIERRAS
01.02.01
M3
116.33
24.72
2,875.68
01.02.02
M2
46.53
4.17
194.03
01.02.03
M3
82.49
43.67
3,602.34
01.02.04
M3
33.84
10.96
370.89
01.03
CONCRETO ARMADO
01.03.01
M2
112.80
43.79
4,939.51
01.03.02
SOLADO E=4"
M2
46.53
21.98
1,022.73
01.03.03
M3
18.61
324.84
6,045.27
01.03.04
M3
15.51
361.43
5,605.78
01.03.05
KG
2,721.48
6.90
18,778.21
01.04
OTROS
01.04.01
15.00
5.58
83.70
01.04.02
M2
56.40
33.38
1,882.63
01.04.03
ML
36.00
9.79
352.44
COSTO DIRECTO
1,773,553.84
AGOSTO
SEPTIEMBRE
EJEC
%
PROG
MET
0.675
OCTUBRE
EJEC
MET
PROG
MET
0.8041667
NOVIEMBRE
EJEC
MET
PROG
MET
0.9291667
DICIEMBRE
EJEC
MET
PROG
MET
1
1
0.675
0.8041667
0.9291667
EJEC
MET