JK Lakshmi Cement Limited: Deshuttering Period

Deshuttering period relates to the maturity of concrete and depends on the


ambient temperature. Forms shall not s truck until the concrete has reached
strength at least twice the stress of which the concrete may be subjected at the
time of removal of form work.
Assuming standard conditions of workmanship and quality of materials, you can
refer to the following time-frames for the removal of forms.
Form

Summers

Winters (Temp <18 C )

Walls, columns and vertical faces


of structural members

24 hrs.

48 hrs.

Removal of props under slab


Spanning up to 4.5 m

7 days

14 days

Removal of props under beams


and arches spanning up to 6 m

14 days

28 days

www.jklakshmi.com/deshuttering_period.html