Академический Документы
Профессиональный Документы
Культура Документы
METHOD STATEMENT
PROJECT
Date: 04-08-2011
BOND INTERIORS
METHOD STATEMENT
INDEX OF CONTENTS
1)
2)
3)
4)
5)
SCOPE
GENERAL
MATERIALS AND MANUFACTURE
FLEXIBLE SHEET TILE FINISHES
PLASTIC OR RUBBER SHEETING OR
TILES
6) CARPETING AND CARPET TILES
7) DRESSING FOR CEMENT FLOORS
8) FLOOR SEAL
9) WORKMANSHIP
10) FLEXIBLE SHEET OR TILE FINISHES
11) PLASTIC OR RUBBER SHEETING OR
TILING
12) CARPETING AND CARPET TILING
13) FLOOR DRESSING
14) FLOOR SEALING
SCOPE
These specifications cover floor and wall cladding intended for use in the Project in accordance with the
Drawings and/or Bills of Quantities and as directed in writing by the Engineer.
GENERAL
The Contractor shall perform all attendance upon other trades and protect all works specified under this
section from damage during subsequent operations, make good any defects, clean throughout and leave all
works in a perfect condition to the satisfaction of the Engineer.
The Contractor shall be responsible for the design and stability of the scaffolding and for all safety
precautions in connection with work specified.
All material and manufactured items that are susceptible to damage shall be delivered in their original
packages, containers, etc. bearing the name of the manufacturer and the brand, and shall be carefully
loaded, transported, unloaded, stored in an approved manner, protected from damage and exposure to
weather or dampness during transit and after delivery to the Site.
Damaged materials and manufactured items shall not be used in the works specified under this Section.
Any materials and manufactured items damaged during and after bedding or setting in position shall be
removed and replaced by and at the Contractor's expense.