BUILT-UP RATE FOR METAL DECK HOARDING

PROJECT :
LOCATION :
SUPPLIER :
SUB-CONTRACTOR :
QUOTATION DATE :

Metal Decking Hoarding ( 3.60m High @ 2.40m c/c/)


Allow for 50% scrap value for structural steel & metal hoarding
Footing
Vertical Struct
Horizontal Struct
Metal hoarding

Profit & Overhead @


Tender Price / m

1200mm x 600mm x 600mm deep


100mm x 50mm x 3mm thk ( 2nos.)
100mm x 50mm x 3mm thk ( 3nos.)
2.40m x 3.60m

Inclusived

Metal Decking Hoarding ( 2.40m High @ 2.40m c/c/)


Allow for 50% scrap value for structural steel & metal hoarding
Footing
Vertical Struct
Horizontal Struct
Metal hoarding

Profit & Overhead @


Tender Price / m

1200mm x 600mm x 600mm deep


100mm x 50mm x 3mm thk ( 2nos.)
100mm x 50mm x 3mm thk ( 3nos.)
2.40m x 3.60m

Inclusived

Cost / m

90.00
26.49
52.99
63.00
232.48
232.48

Cost / m

90.00
17.66
52.99
42.00
202.65
202.65