CONTRACTOR MEETING
Date: 3/24/2015
Organizer:
Location:
Herrick Drive,
Construction Trailer
Subject:
Time:
3/24/2015 - 1:30 PM
Attendees:
CC:
Project Notices:
MEETING MINUTES
Actual Start Date:
3/24/2015 1:30 PM
Minutes
Facilities Operations and Development
STEAM AND CONDENSATE DISTIBUTION
SYSTEMS UPGRADES PHASE 3
LOWER W. 12th AVE TUNNEL RECONSTRUCTION
OSU PROJECT NUMBER 138009
Progress Meeting #031
Safety:
o The Ohio State University Campus is Tobacco Free - including E-Cigarettes.
o Submit any updated Material Safety data Sheets (MSDS's).
o Any accident, injury, or near miss must be reported to AE immediately, in
case of emergency: Call University Police at 614-292-2121, or 911.
o Public Protection- protect all open excavations and ensure public safety.
o IGEL is responsible for safety and ensuring that all workers are following
safety procedures.
o Make sure sump pump is active with current rain fall.
o Asbestos containing material on the Postle Hall steam feed was damaged and
is being repaired. Per the documents: all active steam lines must be
encapsulated and protected by a wooden shroud.
o Contractor discovered an existing void under 12th Avenue and filled with CDF.
Will investigate further when this area is excavated for tunnel repair.
o AE observed a contractor standing on an active steam pipe during wall
removal, Contractors were instructed not to stand on these pipes.
3/31/2015
Contractor Meeting
Page 1 of 6
Traffic Control:
o Maintain access to Postle Hall loading dock and dumpsters AT ALL TIMES.
o Contractor must have all maintenance of traffic (MOT) plans reviewed by TTM
prior to implementation.
o Contractor must complete a Traffic Officer request form a minimum of 72
hours prior to any MOT requiring Traffic Officer(s).
o Next switch will be on April 13.
Schedule - Work planned over the next two weeks: See Attached
o Need updated overall schedule
3/31/2015
Contractor Meeting
Page 2 of 6
Pricing received and is under review. - remove credit pricing and turn
over valves already purchased.
AE to submit CO to contractor.
AE to issue to contractor
Proposal Request (PR) 023 - Add Lights within Vault 17 and Postle tunnel
Proposal Request (PR) 024 - Provide Temporary Steam Anchor and Modify
3/31/2015
Contractor Meeting
Page 3 of 6
Tunnel Work
Submittal Status:
o PR-005 Gas meter
o Existing 12th Avenue vault Mezzanine framing
Quality Control:
o QA/QC - Field Issues / Concerns
OCIO cable rack conflict with gas line, contractor to install typical
manhole cable support and turn cable rack over to OCIO for future
installation when conflicting gas line is removed. - Contractor waiting
on material.
Electrical conduit is protruding from the Jennings tunnel into the main
tunnel, Contractor to correct. - AE to send sketch.
3/31/2015
Contractor Meeting
Page 4 of 6
o
o
o
Utilities is proposing to take the steam line down from Neil to B&Z
vault, which will cause an outage to Jennings and Arnoff, Kirk Williams
will verify durations needed. Kevin will coordinate with Jennings to
Arnoff for outage duration. Vault 17 must be set first to perform this
outage. - 6 weeks is okay, Pat
to add to schedule. - Kirk Williams
to send to dates to IGEL. They plan on starting work on 7/13 and
ending work on 8/18.
o Weekly review of AS-BUILTS
o Contractor shall track the use of TTM for MOT, Cc Steve for all requests for
TTM. Allowance Use Authorization form has been submitted to track these
charges. Contractor must submit prior to work for approval.
o Contractor to submit weather delays. Contractor will send out email,
"Weather Day - Note to File" - Kevin added cells within the email to be filled
out.
o What is the status of the trees - AE reviewed PR with subcontractor
(Greenscape) and they will see if the non-performed trees can be recalled
before they are dug.
o Erosion control sheets need to be kept on site. - these sheets are hanging on
the wall of the trailer.
o Is the Contractor waiting for anything from the A/E or Owner?
Comments:
o OSU PM
None
o OSU Utilities
Owner wants the contractor to verify that the gas regulator station is
straight and plumb, Contractor will get with Stevensons.
o OCIO
None
o TTM
None
o OSU Medical Center
None
o Contractors
None
o AE
3/31/2015
Contractor Meeting
Page 5 of 6
None
Next meeting:
o March 31st, 2015 Tuesday - 1:30 PM - 2:30 PM at Herrick Drive, IGEL
Construction Trailer
These minutes are a summary and the writer's interpretation of the proceeding and are not a transcript. Any
changes or clarifications shall be forwarded to the writer within five (5) days of issue. Unless changes are
forwarded, we must assume that all participants are in basic agreement with the above minutes and they will be
recorded in the official record.
3/31/2015
Contractor Meeting
Page 6 of 6
3 Week Schedule
Date:
3/24/2015
Name: Steam & Condensate
3/23/2015
3/16/2015
Sched ID
A1610
Work Description
3/30/2015
4/6/2015
M T W T F S S M T W T F S S M T W T F S S M T W T F
Demo Pavement
100%
A1640
Sump Concrete
A1650
Wall Concrete
A1652
Wall Waterproofing
A1654
Wall Backfill
A1660
A1680
A1700
Notes /
Status / %
Complete Resources
X
X X
X X
0%
X X X X
X X X X X
50%
X X X
X X
0%
30%
X X
90%
X X X X
40%
X X X
10%
X X
Kirk Williams
Place Supports in Tunnel
80%
90%
Phase A3-B
0%
60%
Phase A3-A
30%
Phase A3-A
75%
Obstructed
40%
80%
100%
Tunnel Top
Material
X X X
X X X
X
X X X X
X X X X X
Phase A3-B
Lithko
Epoxy Inject Cracks
Knight Electric
Install new electric
Install new cable tray
Install new Bucket
Activity ID
Original
Duration
A0010
A0020
100% Submittals
30
A0030
15
A0040
McCracken Complete
A0050
A0060
A0070
A1010
A1020
Excavate Sidewalk
A1030
Stone Sidewalk
A1040
Form/Pour Sidewalk
A1050
100% Topsoil
Topsoil
A1100
A1110
Install Storm
A1120
100% Seed
Seed
A1130
Remove MOT
A1140
100%
A1210
A1220
100% 15-Sep-14 A
Begin Phase A
A1230
A1310
A1320
10
A1322
20
A1324
Install Regulators
A1326
A1328
A1330
100% Abatement
10
Abatement
A1345
Phase A1 Complete
A1420
A1422
A1424
A1425
A1426
A1428
Pavement Restoration
A1430
Phase A2 Complete
A1432
A1442
A1444
A1446
A1450
A1452
A1460
A1462
A1464
A1466
20
10
Finish
Predecessors
19-Mar-15 14:07
08-Sep-14 AA1130
Phase A2 MOT
Shoring & Excavation in Neil Ave
Wall Repair
Tunnel Top Replacement
Summary
Milestone
Remaining Work
% Complete
Submittals
Project Award
Actual Work
100% 27-Aug-14 A
15
10
A1464
Original
Duration
Schedule % Start
Complete
Finish
Predecessors
19-Mar-15 14:07
O
10
A1470
A1472
A1474
A1480
A1490
A1500
A1510
A1512
A1514
A1516
Wall Backfill
A1520
10
A1530
10
A1540
20
A1542
10
A1544
A1552
A1560
A1570
A1580
A1590
A1592
10
A1600
A1610
Demo Pavement
A1620
100% 21-Feb-15
02-Mar-15 A1630
Sump Concrete
A1630
A1640
0% Sump Concrete
50
15
Phase A3 Complete
A1652
Wall waterproofing
A1654
A1660
A1670
Wall backfill
Remove Tunnel top
Load Pipe Ph B
15
KW - Ph B Mechanical Work
0% KW - Test Seq 2
10
100% 10-Mar-15
18-Mar-15 A1672
KW - Test Seq 2
A1676
0% KW - Insulate Seq 2
20
0% 19-Mar-15
06-Apr-15 A1674
A1680
16
A1690
50% Waerproofing
Waerproofing
A1700
0% Road Replacement
A1720
A1730
KW - Insulate Seq 2
Tunnel top replaced
10
0% 03-Apr-15
13-Apr-15 A1700
Road Replacement
0% 13-Apr-15
0% 13-Apr-15
15-Apr-15 A1720
A1740
0% Demo Road
0% 15-Apr-15
16-Apr-15 A1730
Demo Road
A1750
0% 16-Apr-15
18-Apr-15 A1740
A1760
0% 18-Apr-15
23-Apr-15 A1750
A1770
0% Exc Vault 17
0% 23-Apr-15
28-Apr-15 A1760
Actual Work
% Complete
Remaining Work
Milestone
Summary
A1710
A1674
A1650
A1672
A1468
15
A1780
A1790
0% Vault Walls
A1800
0% Wall waterproofing
A1810
0% Partial Backfill
A1820
A1830
A1840
0% Test Vault 17
A1850
Original
Duration
Schedule % Start
Complete
Finish
Predecessors
19-Mar-15 14:07
O
0% 28-Apr-15
02-May-15 A1770
15
0% 02-May-15
16-May-15 A1780
Vault Walls
0% 16-May-15
21-May-15 A1790
Wall waterproofing
0% 21-May-15
22-May-15 A1800
Partial Backfill
10
0% 23-May-15
01-Jun-15 A1810
10
0% 02-Jun-15
10-Jun-15 A1820
0% 11-Jun-15
15-Jun-15 A1830
0% Insulate Vault 17
10
0% 16-Jun-15
24-Jun-15 A1840
A1860
10
0% 25-Jun-15
03-Jul-15
A1850
A1870
0% Backfill Vault 17
0% 04-Jul-15
08-Jul-15
A1860
Backfill Vault 17
A1880
0% 09-Jul-15
11-Jul-15
A1870
A1890
0% 11-Jul-15
13-Jul-15
A1880
A1900
0% 14-Jul-15
17-Jul-15
A1890
A1910
0% 18-Jul-15
22-Jul-15
A1900
A1920
0% 09-Jul-15
13-Jul-15
A1870
A1930
0% 14-Jul-15
17-Jul-15
A1920
A1940
0% 18-Jul-15
20-Jul-15
A1930
A1950
30
0% 20-Jul-15
17-Aug-15 A1940
A1960
10
0% 17-Aug-15
26-Aug-15 A1950
A1970
10
0% 26-Aug-15
04-Sep-15 A1960
A1972
0% 04-Sep-15
09-Sep-15 A1970
A1980
0% Restoration Seq 3
20
0% 09-Sep-15
A1990
10
0% 25-Jun-15
03-Jul-15
A1850
A2000
0% 04-Jul-15
08-Jul-15
A1990
A2010
0% 09-Jul-15
13-Jul-15
A2000
A2020
0% 26-Aug-15
28-Aug-15 A1960
A2030
0% Seq 3 Compete
0% 28-Sep-15
A2040
0% Punch List
10
0% 28-Sep-15
07-Oct-15
A2050
30
0% 07-Oct-15
04-Nov-15 A2040
A2060
0% Alt 5 Landscaping
30
0% 04-Nov-15
02-Dec-15 A2050
A2070
0% Closeout
12
0% 02-Dec-15
14-Dec-15 A2060
A2080
0% Project Complete
Actual Work
% Complete
Remaining Work
Milestone
Summary
Test Vault 17
Insulate Vault 17
A2030
Punch List
Atl 4 Trees along John Herrick
Alt 5 Landscaping
Page 3 of 3
OSU138009SteamandCondensateDistributionSystemUpgradesPhase3
BasisofChange
StartDate ChangeOrder
C/OTitle
Comment
Order
OwnerRequest
8/19/2014 001101
Shift&reducesidewalk
Other
ReplacesumppumpwithintheNeilAvenue
OwnerRequest
1/6/2015 004101
Tunnel
Other
OwnerRequest
10/24/2014 005101
PostleHallGasMeter
Other
9/26/2014 006101
10/13/2014 007101
1/6/2015 008101
10/14/2014 009101
11/10/2014 010101
AESign
PrjMgr
Approval
Sign
DOP
Approval
Fixed
APPLIED
Fixed
12/16/2014 12/16/2014
APPLIED
Fixed
ProperlyAbandonedWaterline
DifferingCondition APPLIED
TM
11/18/2014
2/17/2015
2/20/2015
Provide6"TemporaryCondenstateReturn
DifferingCondition
OwnerRequest
Other
OwnerRequest
Other
OwnerRequest
Other
APPLIED
Fixed
11/17/2014
12/3/2014
APPLIED
Fixed
1/27/2015
1/7/2015
1/30/2015
1/30/2015
2/2/2015
APPLIED
TM
1/27/2015
1/7/2015
1/30/2015
1/30/2015
2/2/2015
2/11/2015
2/11/2015
12/9/2014
9/9/2014
Contract
Admin.
Approval
APPLIED
NaturalGasDistrictRegulatorwithMonitor
TestpitstocompletePsychologysteam
replacementdesign
9/9/2014
Contractor
Approval
1/15/2015
1/16/2015
2/24/2015
APPLIED
Fixed
11/17/2014
11/3/2014 11/19/2014
11/3/2014 011101
12thAvenueTreeRemoval
AdditionalwalladjacenttoNeilAvenue
Tunnel.
DifferingCondition APPLIED
Fixed
11/18/2014
1/16/2015 012101
PipeDropandVaultAccess
Error/OmissionAE
Fixed
1/19/2015
1/19/2015
1/20/2015
1/23/2015
1/26/2015
2/10/2015 013101
AdditionalWallRepair
Fixed
2/17/2015
2/10/2015
2/20/2015
2/23/2015
2/24/2015
3/10/2015 014101
NonPerformSteamBlow
1/22/2015 015101
WaterlineRepairNorthofPostal
DifferingCondition APPLIED
Y
OwnerRequest
Other
SUBMITTED N
OwnerRequest
Other
SUBMITTED N
Fixed
3/24/2015 015A101
WaterlineTemporaryRepairNorthofPostal
DifferingCondition
OwnerRequest
Other
OwnerRequest
Other
OwnerRequest
Other
OwnerRequest
Other
SUBMITTED N
Fixed
APPLIED
Fixed
2/3/2015
2/3/2015
2/5/2015
2/6/2015
2/16/2015
SUBMITTED N
Fixed
SUBMITTED N
Fixed
3/3/2015
2/24/2015
3/5/2015
NEW
Fixed
DifferingCondition NEW
Fixed
2/3/2015 016101
ElectricalClaimResolution
3/24/2015 017101
ShutoffandCheckValves
2/24/2015 018101
PostleHallSigns
3/16/2015 021101
SodSubstitution
TemporarySteamAnchorandModify
TunnelWork
3/17/2015 024101
Totals
Executed
Potential
Total
APPLIED
CMAgent
Approval
Fixed
1/14/2015