ALLEN

INDEPENDENT SCHOOL DISTRICT

Board Meeting May 2015


Construction Update for the Stadium Repairs

May 2015

ALLEN
INDEPENDENT SCHOOL DISTRICT

Summary of Stadium Repairs


Phase
of Work
Phase 1
Phase 2
Phase 3
Phase 4
Phase 5
Phase 6

Description
of Work
Scoreboard
Low Rise Lateral
Retaining Walls
Press Box Repairs
Exp. Joints,
One-Story Gravity
Concourse Structure

Phase 7

Traffic Topping

Complete
Complete
Complete
Complete
Complete
Complete at
Home side/In Progress
In Progress

Stadium Repairs Scoreboard Phase 1 - Complete

ALLEN
INDEPENDENT SCHOOL DISTRICT

Stadium Repairs
Phase 2 One Story Lateral Load Buildings on Concourse
Level.
The structural repairs are complete
Concession Stands complete
Entry towers are reconstructed
Beams over gate ramps are complete

Allen ISD Eagle Stadium Concession Repairs 5-2015

Allen ISD Eagle Stadium Towers at Ramp Entries 5-2015

Allen ISD Eagle Stadium Ramped Entry at D 4-2015

ALLEN
INDEPENDENT SCHOOL DISTRICT

Stadium Repairs
Phase 3 Retaining Wall Repairs
Shotcrete complete
Geo-foam complete
Rock Anchors complete

Eagle Stadium Shotcrete on Retaining Wall Phase 3

Eagle Stadium Retaining Wall Soil Nails Phase 3

ALLEN
INDEPENDENT SCHOOL DISTRICT

Stadium Repairs
Phase 4 Press Box Repairs
Structural Steel Repairs complete from the Press box
to the foundation
Press box repairs are complete

Allen ISD Eagle Stadium Press box repairs complete

Allen ISD Eagle Stadium Press box repairs complete

Allen ISD Eagle Stadium Press box repairs

ALLEN
INDEPENDENT SCHOOL DISTRICT

Stadium Repairs
Phase 5 Expansion Joints, Transfer Girders, and One
Story Gravity Repairs
Structural Steel Repairs complete
Water shed metal roof is complete

Allen ISD Eagle Stadium Phase 5

Allen ISD Eagle Stadium Phase 5

ALLEN
INDEPENDENT SCHOOL DISTRICT

Stadium Repairs
Phase 6 Concourse Structural Repairs
Installation of FRP Composite System to concrete
joists on-going
Home side joists and beams has been wrapped and
installation is underway on the visitor side

Concrete Joists repaired with FRP Application

ALLEN
INDEPENDENT SCHOOL DISTRICT

Stadium Repairs
Phase 7 Traffic Topping
Installation of a coating over the concrete concourse
walking surface
Installation has started and we are waiting on a break
in the weather

Traffic Topping Installed at home side of Stadium

Traffic Topping Installed at the visitor side of Stadium

ALLEN
INDEPENDENT SCHOOL DISTRICT

Questions?