Вы находитесь на странице: 1из 176

MWH GLOBAL

DETAIL ENGINEERING DESIGN/PERENCANAAN TEKNIS TERINCI


PALEMBANG TOWN WASTEWATER TREATMENT PLANT PROJECT/PROYEK INSTALASI PENGOLAHAN AIR LIMBAH KOTA PALEMBANG

BASIC PRICE OF WAGES, RENT EQUIPMENT AND BUILDING MATERIAL


HARGA DASAR UPAH, SEWA ALAT DAN BAHAN BANGUNAN
No

Description/Uraian

A
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Basic Price of Wages/Harga Dasar Upah


Chief of Skill Labour/kepala tukang
Handyman/Tukang
Foreman/Mandor
Labour/Pekerja tidak terlatih
Skill Labour/Pekerja terlatih
Machinist/Masinis
Operators/Operator
Driver/Sopir
Machinist helper/Pembantu Masinis
Supervisor
Cookers asphalt/Pemasak aspal
Guard/Penjaga
Driver helper/pembantu Sopir
Mechanics/Mekanik
Surveyor

B
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57

Basic Price of Building Material/Harga Dasar Bahan


Fine aggregate / Agregat Halus
Coarse aggregates / Agregat Kasar
Aluminium Foil
Alcubond
sandpaper Ordinary / Amplas Biasa
sandpaper Niken / Amplas Niken
Roof Aluminium Zinc Coated (zinc) 0.25 mm thick / Atap Aluminium Zink Coated (seng) tebal 0.25 mm
Roof Aluminium Zinc Coated (zinc) 0.3 mm thick / Atap Aluminium Zink Coated (seng) tebal 0.3 mm
Roof Aluminium Zinc Coated (zinc) 0.4 mm thick / Atap Aluminium Zink Coated (seng) tebal 0.4 mm
Aluminium roof Zincalume, 0.25 mm thick / Atap Aluminium Zincalume, tebal 0.25 mm
Aluminium roof Zincalume, 0.3 mm thick / Atap Aluminium Zincalume, tebal 0.3 mm
Aluminium roof Zincalume, 0.4 mm thick / Atap Aluminium Zincalume, tebal 0.4 mm
Aluminium roof Zincalume, 0.5 mm thick / Atap Aluminium Zincalume, tebal 0.5 mm
Fiber roof color "Polycarbonate" thick 4-5mm / Atap Fiber warna "Plycarbonat" tebal 4-5 mm
Local Concrete roof tiles / Atap Genteng Beton Lokal
Concrete roof tiles / Atap Genteng Beton
Concrete roof tiles Cisangka / Atap Genteng Beton Cisangka
Tile roof Buleleng / Atap Genteng Buleleng
Ceramic glazed plain roof tiles / Atap Genteng Keramik biasa berglazur
Ceramic glazed roof tiles Natural / Atap Genteng Keramik berglazur Natural
Glazed ceramic roof tiles similar color / Atap Genteng keramik sejenis Berglazur warna
Ordinary Metal roof tiles (88 cm x 77 cm) / Atap Genteng Metal Biasa (88 cm x 77 cm)
Color Metal roof tiles (120 cm x 76 cm) / Atap Genteng Metal Warna (120 cm x 76 cm)
Zincalume roofing Metal tiles 2x4 (38.5 cm x 80 cm) / Atap Genteng Metal Zincalume 2x4 (38.5 cm x 80 cm)
Sandy Zincalume roofing Metal tiles (77 cm x 100 cm) / Atap Genteng Metal Zincalume berpasir (77 cm x 100 cm)
Metal roof tiles Zincalume sandy plain/Atap Genteng Metal Zincalume berpasir biasa
Roof tiles frog/Atap Genteng kodok
Onduline roof/Atap Onduline
Asbestos Plain 100 x 100 thickness: 4 mm/Asbes polos 100 x 100 tebal : 4 mm
Asbestos Small wave, width 80 cm/Asbes Gelombang kecil, lebar 80 cm
Asbestos Small wave, width 105 cm/Asbes Gelombang kecil, lebar 105 cm
Asbestos Great Wave, a width of 105 cm/Asbes Gelombang Besar, lebar 105 cm
Motive waves asbestos tile/Asbes Gelombang motif genteng
asphalt/Aspal Curah
asphalt Drum/Aspal Drum
Aquaproof
Stainless Steel Sink/Bak Cuci Stainless Steel
Terrazzo Sink/Bak Cuci Teraso
Fibreglass tub/Bak Fibreglass
Terrazzo bathtub/Bak Teraso
Bamboo diameter of 6-8 cm / 6 meter / Bambu diameter 6-8 cm/ 6 meter
brick/Batako
Brownish black aggregates/Batu Andesit hitam kecoklatan
Natural Stone brownish (Sangarong)/Batu Alam kecoklatan (Sangarong)
Bricks hole/Batu Bata lobang
Small Bricks/Batu Bata kecil
Bricks hole/Batu Bata lobang
Stone Temple Black/Batu Candi hitam
stone/Batu Kali
Stone outboard/Batu Kali tempel
Rock Pilang/Batu Karang Pilang
Gravel/Batu Kerikil
Coral Stone broken concrete split 0-5 mm/Batu Koral beton pecah split 0-5 mm
Coral stone and concrete breaking 5-10 split 10-20 mm/Batu Koral beton pecah split 5-10 dan 10-20 mm
Cut stone / gravel/Batu Belah/Kerakal
Stone Palimanan yellow / green/Batu Palimanan kuning/hijau
Stone Palimanan yellow / green + bevel/Batu Palimanan kuning/hijau + bevel

Unit
Satuan

Unit Price
Harga Satuan
(Rp.)

hk/day
hk/day
hk/day
hk/day
hk/day
hk/day
hk/day
hk/day
hk/day
hk/day
hk/day
hk/day
hk/day
hk/day
hk/day

121,000.00
99,000.00
121,000.00
71,500.00
82,500.00
82,500.00
165,000.00
110,000.00
82,500.00
82,500.00
49,500.00
44,000.00
82,500.00
148,500.00
82,500.00

m3
m3
m2
m2
Sheet/Lembar
Sheet/Lembar
Sheet/Lembar
Sheet/Lembar
Sheet/Lembar
Sheet/Lembar
Sheet/Lembar
Sheet/Lembar
Sheet/Lembar
m2
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
m2
m2
m2
m2
m2
Piece/buah
m2
Sheet/Lembar
m2
m2
m2
m2
kg
kg
kg
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Stem/batang
Piece/buah
m2
m2
m3
Piece/buah
Piece/buah
m2
m3
m2
m2
m3
m3
m3
m3
m2
m2

518,850.62
518,850.62
20,350.00
715,000.00
3,850.00
7,150.00
47,300.00
66,000.00
91,300.00
68,200.00
68,750.00
83,600.00
110,000.00
88,000.00
4,620.00
6,270.00
8,250.00
2,530.00
8,800.00
13,200.00
18,700.00
40,700.00
44,000.00
176,000.00
93,500.00
66,000.00
1,100.00
74,800.00
26,400.00
27,500.00
35,200.00
38,500.00
36,850.00
13,200.00
13,200.00
286,000.00
212,300.00
357,500.00
198,000.00
198,000.00
55,000.00
2,860.00
209,000.00
203,500.00
563,200.00
1,375.00
797.50
247,500.00
385,000.00
102,300.00
653,400.00
440,000.00
518,850.62
518,850.62
385,000.00
184,800.00
184,800.00

No

206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270

Description/Uraian

Wood Plank grade IV/Kayu Papan kelas IV


wood Racuk/Kayu Racuk
wood battens/Kayu Reng
Ceramic floor/wall 20 x 20/25 cm plain white / Keramik lantai/dinding 20 x 20/25 cm putih polos
Ceramic floor/wall 20 x 20/25 cm plain white / Keramik lantai/dinding 20 x 20/25 cm putih polos
Ceramic floor / wall 20 x 20 cm color, quality C/Keramik lantai/dinding 20 x 20 cm warna, mutu C
Ceramic floor / wall 20 x 20 cm color, quality C/Keramik lantai/dinding 20 x 20 cm warna, mutu C
Ceramic floor / wall 20 x 20 cm color, quality B/Keramik lantai/dinding 20 x 20 cm warna, mutu B
Ceramic floor / wall 20 x 20 cm color, quality B/Keramik lantai/dinding 20 x 20 cm warna, mutu B
Ceramic wall 20 x 25 cm color/Keramik dinding 20 x 25 cm warna
Ceramic wall 20 x 25 cm color/Keramik dinding 20 x 25 cm warna
Ceramic floor 20 x 25 cm color, quality B/Keramik lantai 20 x 25 cm warna, mutu B
Ceramic floor 20 x 25 cm color, quality B/Keramik lantai 20 x 25 cm warna, mutu B
Ceramic floor 30 x 30 cm color/Keramik lantai 30 x 30 cm warna
Ceramic floor 30 x 30 cm color/Keramik lantai 30 x 30 cm warna
Ceramic floor 30 x 30 cm white plain/Keramik lantai 30 x 30 cm putih polos
Ceramic floor 30 x 30 cm white plain/Keramik lantai 30 x 30 cm putih polos
Ceramic floor 40 x 40 color quality C/Keramik lantai 40 x 40 warna mutu C
Ceramic floor 40 x 40 color quality C/Keramik lantai 40 x 40 warna mutu C
Ceramic floor 40 x 40 color quality B/Keramik lantai 40 x 40 warna mutu B
Ceramic floor 40 x 40 color quality B/Keramik lantai 40 x 40 warna mutu B
Ceramic floors wood motif (rough) quality A/Keramik lantai motif kayu (kasar) mutu A
Gutter Clamps paralon/Klem Talang Paralon
Regular electric cable clamps/Klem kabel listrik biasa
Electric cable clamps/Klem kabel listrik
Korosin
Water faucet/Kran Air
Brush 3 "- 4"/Kuas 3" - 4"
key Padlock/Kunci Gembok
key Cabinets/Kunci Lemari
Bedroom Door Locks (Hotel)/Kunci Pintu Kamar Tidur (Hotel)
The bathroom door lock (lux)/Kunci Pintu KM/WC (lux)
key Slot/Kunci Selot
Planting usual key quality C/Kunci Tanam biasa mutu C
Key Plant 2 regular slaag/Kunci Tanam 2 slaag biasa
Key Plant 2 slaag quality B/Kunci Tanam 2 slaag mutu B
Key Plant Bathroom/Kunci Tanam Kamar Mandi
Elbow electricity/L. bow listrik
lamp Downlight/Lampu Down Light
Hologen 50 watt bulbs/Lampu Hologen 50 watt
Hologen 150 watt bulbs/Lampu Hologen 150 watt
Lights Hologen Box/Lampu Hologen Box
10 watt fluorescent lamp/Lampu TL 10 watt
20 watt fluorescent lamp/Lampu TL 20 watt
40 watt fluorescent lamp (bamboo)/Lampu TL 40 watt (bambu)
25 Watt Incandescent White/Lampu Pijar 25 Watt Putih
40 Watt Incandescent White/Lampu Pijar 40 Watt Putih
Granite Floor 30/30/Lantai Granit 30/30
Granite Floor 40/40Lantai Granit 40/40
Granite Floor 60/60Lantai Granit 60/60
Wood Floor Panil Gracewood/Lantai Kayu Panil Gracewood
Lasdop electricity/Las dop listrik
Wood glue/Lem Kayu
glue Vinyl/Lem Vinyl
Big Gypsum list/List Gypsum Besar
Small Gypsum list/List Gypsum Kecil
Bowl of electric switch/Mangkok Saklar listrik
MCB
MCB Box contents of the 4 groups/MCB Box isi 4 grup
MCB Box contents of the 8 groups/MCB Box isi 8 grup
Melamic Clear
Melamic Gloss/dop (Finishing)
Mill
Formwork oil/Minyak Bekisting
oil Paint/Minyak Cat
Diesel oil for industrial / Oil asphalt/Minyak solar untuk industri / Minyak aspal
Wood mosaic floor size of 30 x 30 cm/Mozaik kayu lantai ukuran 30 x 30 cm
BRC Fence, size 240 cm x 120 cm, diameter 5.5 mm/Pagar BRC, ukuran 240 cm x 120 cm, diameter 5.5 mm
BRC Fence, size 240 cm x 90 cm, diameter 6 mm/Pagar BRC, ukuran 240 cm x 90 cm, diameter 6 mm
Ordinary nails of various sizes 2 "- 5"/Paku Biasa bermacam ukuran 2" - 5"
Ordinary nail 1/2 "- 1"/Paku Biasa 1/2" - 1"
nails Stoppers/Paku Sumbat
Concrete nails/Paku Beton
nails Gypsum/Paku Gypsum

Unit
Satuan

Pieces/Keping
m3
Stem/batang
Box/Kotak
Piece/buah
Box/Kotak
Piece/buah
Box/Kotak
Piece/buah
Box/Kotak
Piece/buah
Box/Kotak
Piece/buah
Box/Kotak
Piece/buah
Box/Kotak
Piece/buah
Box/Kotak
Piece/buah
Box/Kotak
Piece/buah
Box/Kotak
Piece/buah
Piece/buah
Piece/buah
liter
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
m2
Piece/buah
liter
kg
m1
m1
Piece/buah
Piece/buah
Piece/buah
Piece/buah
kg
kg
kg
liter
liter
liter
Piece/buah
unit
unit
kg
kg
Piece/buah
Piece/buah
kg

Unit Price
Harga Satuan
(Rp.)
18,150.00
1,815,000.00
33,000.00
63,800.00
2,552.00
57,200.00
2,288.00
68,200.00
2,728.00
74,800.00
3,740.00
51,260.00
2,563.00
52,800.00
4,752.48
52,800.00
4,752.48
57,200.00
9,152.00
71,500.00
11,440.00
55,000.00
3,025.00
154.00
3,300.00
2,200.00
11,000.00
13,750.00
9,350.00
8,800.00
440,000.00
385,000.00
14,300.00
27,500.00
71,500.00
99,000.00
29,700.00
2,750.00
46,750.00
13,750.00
27,500.00
110,000.00
7,700.00
11,000.00
115,500.00
5,500.00
6,050.00
22,550.00
48,400.00
128,700.00
387,750.00
550.00
22,000.00
9,350.00
24,200.00
13,200.00
1,980.00
48,400.00
27,500.00
60,500.00
66,000.00
66,000.00
36,300.00
13,200.00
6,600.00
6,050.00
8,250.00
379,500.00
412,500.00
16,500.00
19,800.00
660.00
770.00
27,500.00

58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143

stone Marble/Batu Marmer


Stone Roster / Overlay ordinary/Batu Roster/Terawang biasa
Iron diameter of 5 mm/Besi diameter 5 mm
6 mm diameter iron KS/Besi diameter 6 mm KS
Iron diameter of 8 mm KS IT/Besi diameter 8 mm KS TI
Iron diameter of 10 mm KS IT/Besi diameter 10 mm KS TI
Iron diameter of 12 mm KS IT/Besi diameter 12 mm KS TI
Iron diameter of 14 mm KS IT/Besi diameter 14 mm KS TI
Iron diameter of 16 mm KS IT/Besi diameter 16 mm KS TI
Iron diameter of 19 mm KS IT/Besi diameter 19 mm KS TI
Iron Plain Concrete/Besi Beton Polos
Iron Steel Profile WF, I and H/Besi Baja Profil WF, I dan H
Steel Construction (CNP, IVI, and iron L)/Besi Baja Konstruksi (CNP, INP, dan besi L)
Iron Beam Clamp and Plate Elbow/Besi Beam Clamp dan Plat Siku
Hollow iron steel 20 x 40, 2 mm thick/Besi Hollow baja 20 x 40, tebal 2 mm
Hollow iron steel 40 x 40, 2 mm thick/Besi Hollow baja 40 x 40, tebal 2 mm
Hollow iron steel 30 x 60, 2 mm thick/Besi Hollow baja 30 x 60, tebal 2 mm
Hollow Iron Ceiling 2 x 4/Besi Hollow Plafond 2 x 4
iron Strip/Besi Strip
Iron Strip 2 x 3/Besi Strip 2 x 3
Ready Mix Concrete K - 125/Beton Ready Mix K - 125
Ready Mix Concrete K - 175/Beton Ready Mix K - 175
Ready Mix Concrete K - 225/Beton Ready Mix K - 225
Ready Mix Concrete K - 250/Beton Ready Mix K - 250
Ready Mix Concrete K - 275/Beton Ready Mix K - 275
Ready Mix Concrete K - 300/Beton Ready Mix K - 300
Ready Mix Concrete K - 350/Beton Ready Mix K - 350
Ready Mix Concrete K - 400/Beton Ready Mix K - 400
Asbestos ridge Great Wave/Bubungan Asbes Gelombang Besar
Asbestos ridge Small Waves/Bubungan Asbes Gelombang Kecil
Ridge / Nok concrete tiles/Bubungan/Nok Genteng Beton
Ridge tiles Buleleng/Bubungan Genteng Buleleng
Ridge / Nok plain glazed Ceramic Tile/Bubungan/Nok Genteng Keramik biasa berglazur
Ridge / Nok kind of glazed Ceramic Tile/Bubungan/Nok Genteng Keramik sejenis berglazur
Ridge similar color glazed Ceramic Tile/Bubungan Genteng Keramik sejenis warna berglazur
Bubungan/Nok Genteng Metal/aluminium
Ridge tiles Frog/Bubungan Genteng Kodok
Basic paint/Cat Dasar
Between Cat/Cat Antara
Wood and Iron paint Termite/Cat Kayu dan Besi Anti Rayap
Special paint Glassy and Quick Drying/Cat Khusus Glassy dan Quick Drying
Oil paint colors (regular) quality C/Cat Minyak warna (biasa) mutu C
Oil paint quality BOil paint quality B/Cat Minyak mutu B
Oil Paint Spray/Cat Minyak Semprot
Meni paint Iron/Cat Meni Besi
Meni paint Iron / Wood / Flincote/Cat Meni Besi/Kayu/Flincote
Cover paint/Cat Penutup
Wall paint quality C (Vinotex, Q-luc, and the like)/Cat Tembok mutu C (Vinotex, Q-luc, dan sejenis)
Wall paint quality B (Catylac, Vinilex, and similar)/Cat Tembok mutu B (Catylac, Vinilex, dan sejenis)
Wall paint quality B Anti Moss and Mushrooms/Cat Tembok mutu B Anti Lumut dan Jamur
A quality wall paint (Mowilex, Kemtone, Dulux, etc.)/Cat Tembok mutu A (Mowilex, Kemtone, Dulux, dll)
Equivalent closet seat (standard type KIA)Closed duduk Setara (sejenis standar KIA)
Closed sit Standards (Ex kind. TOTOC721FV1)/Closed duduk Standar (sejenis Ex. TOTOC721FV1)
Sitting Closet Halmar/Closet Duduk Halmar
Sitting Closet quality C/Closet Duduk mutu C
Sitting Closet quality A/Closet Duduk mutu A
Sitting Closet quality B/Closet Duduk mutu B
Sitting Closet standards/Closet Duduk standar
Closet Sitting / Monoblock/Closet Duduk / Monoblok
Closet squat Porcelain / regular/Closet jongkok Porselen / biasa
Closet Squatting Terrazzo/Closet Jongkok Teraso
Closet Squatting Standard / type (B quality)/Closet Jongkok Standart / sejenis (mutu B)
Closet Squatting kind (quality A)/Closet Jongkok sejenis (mutu A)
Shower Spray TX 403 SV 3
Conblock usual 6 cm thick/Coneblock biasa tebal 6 cm
Conblock color 6 cm thick/Coneblock warna tebal 6 cm
Conblock usual 8 cm thick/Coneblock biasa tebal 8 cm
Conblock color 8 cm thick/Coneblock warna tebal 8 cm
Cornice (white cement powder for gypsum)/Cornice (bubuk Semen putih untuk gypsum)
Putty ready-made/Dempul Jadi
Ross putty Polac/Dempul Ross Polac
putty Isamu/Dempul Isamu
Wood dolken diameter. 8 - 10/400 cm/Dolken Kayu dia. 8 - 10/400 cm
Door Closer
Door Holder
Door Stoper
Door Stop
black bucket/Ember hitam
Regular hinge/Engsel Biasa
Yellow Hinge 4 "/Engsel Kuning 4"
Door hinge/Engsel Pintu
Epoxi
Plasterboard 100 x 100 2.7 mm thick/Eternit 100 x 100 tebal 2.7 mm
Plasterboard 100 x 100 3.5 mm thick/Eternit 100 x 100 tebal 3.5 mm
Filler
Electrical ceiling fittings/Fitting plafond listrik

m2
Piece/buah
Stem/batang
Stem/batang
Stem/batang
Stem/batang
Stem/batang
Stem/batang
Stem/batang
Stem/batang
kg
kg
kg
m2
Stem/batang
Stem/batang
Stem/batang
Stem/batang
kg
m
m3
m3
m3
m3
m3
m3
m3
m3
m1
m1
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
m1
Piece/buah
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
Units/Unit
Units/Unit
Units/Unit
Units/Unit
Units/Unit
Units/Unit
Units/Unit
Piece/buah
Piece/buah
Piece/buah
Units/Unit
Units/Unit
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
kg
kg
kg
kg
m3
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
kg
Sheet/Lembar
Sheet/Lembar
m3
Piece/buah

330,000.00
4,675.00
24,200.00
27,500.00
56,100.00
88,000.00
121,000.00
203,500.00
214,500.00
302,500.00
20,900.00
18,700.00
16,500.00
24,750.00
154,000.00
176,000.00
209,000.00
27,500.00
11,000.00
5,500.00
880,000.00
935,000.00
990,000.00
1,045,000.00
1,100,000.00
1,155,000.00
1,100,000.00
1,265,000.00
26,400.00
25,850.00
6,600.00
5,720.00
11,000.00
22,000.00
27,500.00
33,000.00
4,400.00
35,200.00
27,500.00
49,500.00
33,000.00
44,000.00
52,800.00
46,200.00
40,700.00
46,200.00
90,200.00
13,750.00
28,600.00
30,250.00
104,500.00
605,000.00
2,475,000.00
3,520,000.00
2,062,500.00
4,840,000.00
2,992,000.00
2,530,000.00
594,000.00
176,000.00
35,200.00
198,000.00
297,000.00
357,500.00
1,980.00
2,640.00
2,695.00
3,300.00
7,700.00
22,000.00
30,800.00
52,800.00
319,000.00
264,000.00
33,000.00
33,000.00
24,200.00
7,150.00
19,800.00
33,000.00
19,800.00
55,000.00
25,300.00
29,700.00
1,375.00
9,900.00

271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333

Nails Zinc, Asbestos/Paku Seng, Asbes


nails Asbestos/Paku Asbes
Nails Screws 3.5 "/Paku Sekrup 3.5"
Nails Screws 3.5 "/Paku Sekrup 3.5"
Teak parquet/Parquet Jati
Concrete Sand / Install/Pasir Beton / Pasang
sand Urug/Pasir Urug
grout colorant/Pewarna nat
Aluminium doors/Pintu Alluminium
Steel Door/Pintu Besi Baja
Fold doors/Pintu Lipat
PVC door + installation complete/Pintu PVC lengkap + pemasangan
Medium iron pipe 2 mm & 1/2 ", length 6 m/Pipa besi medium 2 mm & 1/2", panjang 6 m
Medium iron pipe 2 mm & 3/4 ", length 6 m/Pipa besi medium 2 mm & 3/4", panjang 6 m
Medium iron pipe 2 mm and 1 ", length 6 m/Pipa besi medium 2 mm & 1", panjang 6 m
Medium iron pipe 2 mm & 1.5 ", length 6 m/Pipa besi medium 2 mm & 1.5", panjang 6 m
Medium iron pipe 2 mm & 2 ", length 6 m/Pipa besi medium 2 mm & 2", panjang 6 m
Medium iron pipe 2 mm & 2.5 ", length 6 m/Pipa besi medium 2 mm & 2.5", panjang 6 m
Medium iron pipe 2 mm & 3 ", length 6 m/Pipa besi medium 2 mm & 3", panjang 6 m
Medium iron pipe 2 mm and 4. "Length 6 m/Pipa besi medium 2 mm & 4". Panjang 6 m
Electrical PVC pipe 5/8 "/Pipa paralon listrik 5/8"
PVC pipe and 1/2 "A quality (and similar Wavin)/Pipa PVC & 1/2" mutu A (Wavin dan sejenis)
Ordinary PVC pipe and 1/2 "quality B/Pipa PVC biasa & 1/2" mutu B
PVC pipe & 3/4 "A quality (and similar Wavin)/Pipa PVC & 3/4" mutu A (Wavin dan sejenis)
PVC pipe & 3/4 "quality B/Pipa PVC & 3/4" mutu B
PVC pipe & 1 "A quality (and similar Wavin)/Pipa PVC & 1" mutu A (Wavin dan sejenis)
PVC pipe and 1 "Quality B/Pipa PVC & 1" mutu B
PVC pipe & 1.5 "A quality (and similar Wavin)/Pipa PVC & 1.5" mutu A (Wavin dan sejenis)
PVC pipe & 1.5 "Quality B/Pipa PVC & 1.5" mutu B
PVC pipe & 2 "A quality (and similar Wavin)/Pipa PVC & 2" mutu A (Wavin dan sejenis)
PVC pipe & 2 "Quality B/Pipa PVC & 2" mutu B
PVC pipe & 3 "A quality (and similar Wavin)/Pipa PVC & 3" mutu A (Wavin dan sejenis)
PVC pipe & 3 "quality B/Pipa PVC & 3" mutu B
PVC pipe & 4 "A quality (and similar Wavin)/Pipa PVC & 4" mutu A (Wavin dan sejenis)
PVC pipe & 4 "quality B/Pipa PVC & 4" mutu B
PVC pipe and 6 "(15 cm) A quality (and similar Wavin)/Pipa PVC & 6" (15 cm) mutu A (Wavin dan sejenis)
Stainless Pipe 2 ", 1mm thick/Pipa Stainless 2", tebal 1mm
Stainless Pipe 2 ", 0.8mm thick/Pipa Stainless 2", tebal 0.8mm
Stainless Pipe 2.5 ", 1mm thick/Pipa Stainless 2.5", tebal 1mm
Stainless Pipe 2.5 ", 1.2mm thick/Pipa Stainless 2.5", tebal 1.2mm
plamir Wall/Plamir Tembok
plamir Wood/Plamir Kayu
Stainless plate, 1 mm thick, the size of 244cm x 122cm/Plat Stainless, tebal 1 mm, ukuran 244cm x 122cm
Plint ceramic 10 x 30 cm color/Plint keramik 10 x 30 cm warna
Plint ceramic 10 x 40 cm color/Plint keramik 10 x 40 cm warna
Plint PC Grey Tile 15 x 20 cm/Plint Ubin PC Abu-abu 15 x 20 cm
Plint PC Grey Tile 10 x 30 cm/Plint Ubin PC Abu-abu 10 x 30 cm
Plint PC Grey Tile 10 x 40 cm/Plint Ubin PC Abu-abu 10 x 40 cm
Plywood color / Jabarwood/Plywood warna/Jabarwood
Teak Plywood 3 mm/Plywood Jati 3 mm
Plywood Sungkay 3 mm / Megatick/Plywood Sungkay 3 mm / Megatick
Plywood 3 mm
Plywood 4 mm
Plywood 6 mm
Plywood 9 mm
Plywood 12 mm
Plywood 20 mm
camphor basic/Politur dasar
Camphor ready-made/Politur Jadi
White porcelain 10 x 10 cm/Porselin Putih ukuran 10 x 10 cm
The color porcelain size 10 x 10 cm/Porselin Warna ukuran 10 x 10 cm
Order for light steel roof tile roof, tile/Rangka Atap baja ringan untuk atap genteng, genteng
ceramics, concrete, etc + installation/keramik, beton, dll + pemasangan
Lightweight steel roof framework for zinc metal roofing, roof/Rangka Atap baja ringan untuk atap seng metal, atap
asbestos, aluminum, shingles, etc. + installation/asbes, aluminium, sirap, dll + pemasangan
Lightweight steel roof framework forms joglo / special + stacked installation/Rangka Atap baja ringan bentuk
joglo/bertumpuk khusus + pemasangan

kg
Piece/buah
kg
Piece/buah
m2
m3
m3
bungkus
m2
m2
m2
unit
m1
m1
m1
m1
m1
m1
m1
m1
Stem/batang
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
kg
kg
Sheet/Lembar
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Sheet/Lembar
Sheet/Lembar
Sheet/Lembar
Sheet/Lembar
Sheet/Lembar
Sheet/Lembar
Sheet/Lembar
Sheet/Lembar
Sheet/Lembar
liter
liter
Piece/buah
Piece/buah
m2

24,200.00
660.00
49,500.00
495.00
423,500.00
101,750.00
71,500.00
11,000.00
704,000.00
2,145,000.00
418,000.00
231,000.00
20,350.00
25,740.00
32,092.50
45,870.00
57,750.00
75,350.00
119,350.00
155,540.00
6,600.00
4,400.00
4,125.00
6,050.00
5,060.00
8,250.00
5,225.00
14,300.00
8,800.00
18,012.50
11,550.00
35,337.50
19,250.00
57,200.00
33,000.00
136,125.00
82,500.00
73,920.00
104,720.00
92,400.00
8,800.00
18,700.00
1,870,000.00
4,400.00
14,520.00
880.00
935.00
962.50
121,000.00
121,000.00
121,000.00
46,200.00
74,800.00
96,800.00
137,500.00
176,000.00
231,000.00
53,900.00
58,300.00
770.00
1,100.00
313,500.00

m2

237,820.00

m2

309,870.00

Lightweight steel roof framework "Pryda" for a saddle roof, Metal and Ceramic + installation/Rangka Atap baja ringan
"Pryda" untuk atap Pelana, Metal dan keramik + pemasangan

m2

281,050.00

336

Lightweight steel roof framework "Pryda" for roof Shield, Metal and Ceramic + installation/Rangka Atap baja ringan
"Pryda" untuk atap Perisai, Metal dan keramik + pemasangan

309,870.00

337

Lightweight steel roof framework "Pryda" for Joglo roof, Metal and Ceramic + installation/Rangka Atap baja ringan
"Pryda" untuk atap Joglo, Metal dan keramik + pemasangan
Push the door rails/Rel Pintu Dorong
Rolling Door Standard, t = 4 mm, (minimum of 7 pairs m2)/Rolling Door Standar, t = 4 mm, (minimal pasangan 7 m2)
Rolling Door Standard, t = 5 mm, (minimum of 7 pairs m2)/Rolling Door Standar, t = 5 mm, (minimal pasangan 7 m2)
Sanding Sealer Impra (Primer)/Sanding Sealer Impra (Cat dasar)
Seal Tape
Cement (50 kg)/Semen (50 kg)
Portland cement (PC)/Semen Portland (PC)
White cement (40 kg)/Semen Putih (40 kg)
cement White/Semen Putih
cement Red/Semen Merah
Nat cement/Semen Nat
Zinc Wave, a width of 70 cm/Seng Gelombang, lebar 70 cm
Zinc Plate 120 cm x 240 cm/Seng Plat 120 cm x 240 cm

m2

360,360.00

Units/Unit
m2
m2
kg
Piece/buah
zak
kg
zak
kg
m3
kg
m2
Sheet/Lembar

264,000.00
643,500.00
693,000.00
41,800.00
3,850.00
68,750.00
1,375.00
93,500.00
2,200.00
41,800.00
13,200.00
8,167.50
116,600.00

334
335

338
339
340
341
342
343
344
345
346
347
348
349
350

144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205

1)
2)
3)

Glass Block
Grendel / Slot Plant 4 "/Grendel/Slot Tanam 4"
Grendel ordinary/Grendel biasa
Gypsum Board (120 x 240 x 9) mm
Hordeng Horizontal Blind (aluminium)
Hordeng Vertikal Blind
fibers/Ijuk
Aluminum + Glass Window Reyband 5 mm/Jendela Aluminium + Kaca Reyband 5 mm
Iron window/Jendela Besi
Window Frame Nako 100 cm x 70 cm/Jendela Bingkai Nako 100 cm x 70 cm
Window Frame Nako/Jendela Bingkai Nako
Cable N Y A 1.5 mm/Kabel NYA 1.5 mm
Cable N Y A 2.5 mm/Kabel NYA 2.5 mm
Cable N Y A 4.0 mm/Kabel NYA 4.0 mm
NYM cable 2 x 1.5 mm/Kabel NYM 2 x 1.5 mm
NYM cable 2 x 2.5 mm/Kabel NYM 2 x 2.5 mm
NYM cable 2 x 4.0 mm/Kabel NYM 2 x 4.0 mm
Mirror 3 mm cable/Kabel Cermin 3 mm
Mirror Cable 5 mm/Kabel Cermin 5 mm
Stained Glass/Kaca Patri
Transparent glass 3 mm/Kaca Bening 3 mm
Transparent glass 4 mm/Kaca Bening 4 mm
Transparent glass 5 mm/Kaca Bening 5 mm
Transparent glass 8 mm/Kaca Bening 8 mm
Transparent glass 10 mm/Kaca Bening 10 mm
Transparent glass 12 mm/Kaca Bening 12 mm
Glass Rayband 5 mm/Kaca Rayband 5 mm
Opaque glass / Ice 5 mm/Kaca Buram/Es 5 mm
Glass Frame Nako/Bingkai Kaca Nako
Glass Nako 6 leaf/Kaca Nako 6 daun
Glass Nako 8 leaf/Kaca Nako 8 daun
Nako glass Rayben 5 mm, 6 leaves/Kaca Nako Rayben 5 mm, 6 daun
Nako glass Rayben 5 mm, 8 leaves/Kaca Nako Rayben 5 mm, 8 daun
Hooks wind window/Kait angin Jendela
Kalsiboard 3.5 mm (120 cm x 240 cm)
Kalsiboard 4.5 mm (120 cm x 240 cm)
Lime/Kapur
6 mm thick carpet/Karpet tebal 6 mm
Concrete wire/Kawat Beton
Bird wire/kawat Burung
wire Thorns/Kawat Duri
wire Harmonica/Kawat Harmonika
Net Wire Fence/Kawat Jaring Pagar
wire Gauze/Kawat Kassa
Welding Wire/Kawat Las
wire Mosquitoes/Kawat Nyamuk
Zinc Wire Plain/Kawat Seng Polos
Diameter softwood 6-8/Kayu gelam diameter 6-8
diameter softwood 10-12/kayu gelam diameter 10-12
wood Hek/Kayu Hek
wood Lis/Kayu Lis 1/3
wood Lis/kayu Lis 1/4
Wood Lis Profile Medium/Kayu Lis Profil kecil
Wood Lis Profile Medium/Kayu Lis Profil Sedang
Lis Large Wood Profile/Kayu Lis Profil Besar
Wood Mosaic 30 x 30 cm/Kayu Mosaik 30 x 30 cm
Wooden rafters 5/7 grade III (Meranti and similar)/Kayu Kaso 5/7 kelas III (Meranti dan sejenis)
Wood Class I (Unglen, Teak)/Kayu Kelas I (Unglen, Jati)
Wood Class II (Petanang and similar)/Kayu Kelas II (Petanang dan sejenis)
Class III Wood (Meranti and similar)/Kayu Kelas III (Meranti dan sejenis)
Wood Board 3/20 Class III/Kayu Papan 3/20 Kls. III
Wood Class IV (Racuk and similar)/Kayu Kelas IV (Racuk dan sejenis)

Piece/buah
Piece/buah
Piece/buah
Sheet/Lembar
m2
m3
kg
m2
m2
Units/Unit
m2
m1
m1
m1
m1
m1
m1
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
set
set
set
set
set
Piece/buah
Pieces/Keping
Pieces/Keping
kg
m2
kg
m2
m1
m2
Sheet/Lembar
m2
dos
m2
kg
Stem/batang
Stem/batang
Stem/batang
m1
m1
m1
m1
m1
Piece/buah
Stem/batang
m3
m3
m3
m3
m3

26,400.00
82,500.00
17,600.00
74,800.00
101,200.00
104,500.00
9,900.00
902,000.00
330,000.00
99,000.00
148,500.00
4,290.00
5,720.00
6,600.00
11,000.00
14,300.00
19,800.00
136,400.00
212,300.00
1,760,000.00
71,500.00
82,500.00
121,000.00
220,000.00
260,700.00
429,000.00
110,000.00
118,800.00
15,400.00
59,400.00
68,200.00
59,400.00
67,100.00
16,500.00
60,500.00
63,800.00
6,600.00
82,500.00
19,800.00
22,000.00
16,500.00
42,900.00
30,800.00
16,500.00
110,000.00
19,800.00
20,900.00
8,800.00
9,900.00
9,900.00
11,550.00
12,650.00
2,750.00
3,850.00
8,250.00
6,875.00
60,500.00
9,075,000.00
6,600,000.00
3,630,000.00
3,630,000.00
1,650,000.00

Source : Decree of Mayor of Palembang N0. 518.a Tahun 2013


Sumber : Keputusan Walikota Palembang N0. 518.a Tahun 2013
to antiscipate the price changes of material, wages and equipment rental prices, due to oil price increasing, pricelist above will be added about 15-20%
Untuk mengantisipasi perubahan harga material upah dan sewa alat, akibat kenaikan BBM, daftar harga diatas ditambahkan sekitar 15-20%
For Building Material including transportation cost to the site
Untuk bahan bangunan sudah termasuk biaya transportasi ke lokasi

351
352
353
354
355
356
357
358
359
360
361
362
363
364
365

366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391

Zinc Plate 33 cm/Seng Plat 33 cm


Zinc Plate 38 cm/Seng Plat 38 cm
Zinc Plate 45 cm/Seng Plat 45 cm
Zinc Plate 55 cm/Seng Plat 55 cm
Zinc Plate 88 cm/Seng Plat 88 cm
Zinc Plate 92 cm/Seng Plat 92 cm
soap/Sabun
Caustic Soda/Soda Api
Soft Board (120 x 240) mm
Single switch normal/Saklar Tunggal biasa
Double switch normal/Saklar Ganda biasa
Switches Single National/Saklar Tunggal National
Switch Double National/Saklar Ganda National
Scaffolding tag. 1.77 x 1.77 m/Scafolding tg. 1.77 x 1.77 m
Smartruss Aluminium Magnesium
- Lysaght Smartruss C 75.100
- Lysaght Smartruss C 75.75
- - Batten U T S 40/Reng U T S 40
- Screw / Dynabolt
- Valery Gutter Talang Jurai
- Strap Bracing
Contact Stop usual/Stop Kontak biasa
Contact Stop usual/Stop Kontak AC
Sunscreen Aluminium
T. electric Duss/T. Duss listrik
Gutters gutter, length 4 m/Talang Paralon, panjang 4 m
ropes Ijuk/Tali Ijuk
fibers/Ijuk
Clay / Urug/Tanah Liat / Urug
Soil types Puru/Tanah Puru
Soil types Sirtu/Tanah Sirtu
Teakwood 3 mm
Teakwood 4 mm plain/Teakwood 4 mm biasa
Ter/Residu
Textil Tape
thinner ordinary/Thinner biasa
Glossy Paint Thinner (Cobra and similar)/Thinner Cat Glossy (Cobra dan sejenis)
urinal/Urinoir
A quality urinal/Urinoir mutu A
Vernis
Rock varnish/Vernis Batu
Wallpaper
regular sink/Wastafel biasa
sink Halmar/Wastafel Halmar
A quality sink/Wastafel mutu A
Wood Filler Impra (putty)/Wood Filler Impra (dempul)
Wood Stain Impra (paint color)/Wood Stain Impra (cat pewarna)

C
1
2
3
4
5
6
7
8
9
10

Basic Price of Rent of Equipment/Harga Dasar Sewa Peralatan


Concrete Pump
Dump Truck 3.5 Ton
Dump Truck 10 Ton
Generator/Genset
Flatbed Truck 3.5 ton/ Wheel roller machine /Mesin Gilas Roda
Tools/Alat Bantu
Sprayer, Selfprof
Scaffolding 177cm x 177cm, Tg. 177cm
Concrete Mixer/Pengaduk Beton /Mollen
Water Pump

D
1

Basic Price of Installation/Harga Dasar Instalasi


Electrical Installation/Instalasi Listrik

m1
m1
m1
m1
m1
m1
kg
kg
lebar
Piece/buah
Piece/buah
Piece/buah
Piece/buah
Units/Unit

14,520.00
20,350.00
22,000.00
28,600.00
36,300.00
38,500.00
12,320.00
33,000.00
74,250.00
6,600.00
14,850.00
19,140.00
33,000.00
880,000.00

m1
m1
m1
Piece/buah
m1
m1
Piece/buah
Piece/buah
m2
Piece/buah
batang
kg
m3
m3
m3
m3
m2
m2
liter
roll
liter
liter
Piece/buah
Units/Unit
liter
kg
m2
Piece/buah
Units/Unit
Units/Unit
cans/kaleng
cans/kaleng

24,750.00
20,680.00
17,930.00
2,090.00
137,940.00
13,750.00
18,700.00
82,500.00
412,500.00
1,320.00
52,800.00
12,540.00
26,400.00
55,000.00
60,500.00
88,000.00
39,600.00
44,000.00
49,500.00
7,535.00
13,200.00
38,500.00
154,000.00
181,500.00
27,500.00
71,500.00
308,000.00
291,500.00
308,000.00
495,000.00
35,200.00
66,000.00

hour/jam
hour/jam
hour/jam
hour/jam
hour/jam
hour/jam
hour/jam
sets/Month / set/Bulan
hour/jam
hour/jam

99,187.50
264,500.00
165,312.50
99,187.50
330,625.00
126,500.00
79,350.00
231,437.50
297,562.50
19,837.50

Ls

99,187.50

UNIT PRICES ANALYS/ANALISA HARGA SATUAN PEKERJAAN


A. 2.2.1 PREPARATION WORK UNIT PRICE/ HARGA SATUAN PEKERJAAN PERSIAPAN
A. 2.2.1.1 Preparation of 1 m2 of temporary wooden fence 2 meters high/Pembuatan 1 m2 pagar sementara dari kayu tinggi 2
meter
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.200
82,500
L.02
Manday
0.400
99,000
L.03
Manday
0.020
121,000
L.04
Manday
0.020
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
16,500
39,600
2,420
2,420
60,940

MATERIALS/BAHAN
Batang

319,000

398,750

Kg
1.200
1,375
M3
0.005
101,750
M3
0.009
518,851
M3
0.072
3,630,000
Kg
0.060
16,500
Liter
0.450
49,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,650
509
4,670
261,360
990
22,275
690,203

wood dolken/Dolken kayu 8-10/400 cm


Portland Cement/Semen portland
Concrete sand/Pasir beton
Coral concrete/Koral beton
Wood/Kayu 5/7
common nails/Paku biasa 2" - 5"
Residue/Residu
C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

1.250

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

751,143
112,671.51
863,814.92

A. 2.2.1.2 Preparation of 1 m2 of corrugated iron fence while a height of 2 meters/Pembuatan 1 m2 pagar sementara dari seng
gelombang tinggi 2 meter
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.200
82,500
L.02
Manday
0.400
99,000
L.03
Manday
0.020
121,000
L.04
Manday
0.020
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
16,500
39,600
2,420
2,420
60,940

MATERIALS/BAHAN
wood dolken/Dolken kayu 8-10/400 cm
Portland Cement/Semen portland
Concrete sand/Pasir beton
Coral concrete/Koral beton
Wood/Kayu 5/7
common nails/Paku biasa 2" - 5"
Meni iron/Meni besi

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Batang

319,000

398,750

Kg
1.200
1,375
M3
0.005
101,750
M3
0.009
518,851
M3
0.072
3,630,000
Kg
0.060
16,500
Liter
0.450
46,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1.250

1,650
509
4,670
261,360
990
20,790
688,718

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

749,658
112,448.76
862,107.17

A. 2.2.1.3 Preparation of 1 m2 of temporary fence wire height of 1.8 meters/Pembuatan 1 m2 pagar sementara dari kawat duri
tinggi 1,8 meter
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.200
82,500
L.02
Manday
0.300
99,000
L.03
Manday
0.020
121,000
L.04
Manday
0.020
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

16,500
29,700
2,420
2,420
51,040

MATERIALS/BAHAN
Batang

319,000

319,000

Kg
2.000
1,375
M1
25.000
16,500
M3
0.005
101,750
M3
0.009
518,851
Kg
0.060
16,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

2,750
412,500
509
4,670
990
740,418

wood dolken/Dolken kayu 8-10/400 cm


Portland cement/Semen portland
Wire/Kawat duri
Concrete Sand/Pasir beton
Concrete coral/Koral beton
Common nails/Paku biasa 2" - 5"
C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

1.000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

791,458
118,718.76
910,177.17

15% x D

A. 2.2.1.4 Measurement and installation of 1 m1 Bouwplank/Pengukuran dan pemasangan 1 m1 Bouwplank

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wood beams/Kayu balok 5/7
Nail/Paku 2" - 3"
Saw timber/Kayu papan 3/20

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.100
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

8,250
9,900
1,210
605
19,965

Batang
0.120
60,500
Kg
0.020
16,500
M3
0.007
3,630,000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

7,260
330
25,410
33,000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

52,965
7,944.75
60,909.75

15% x D

A. 2.2.1.5 Preparation of 1 m2 of office floor while plastering/Pembuatan 1 m2 kantor sementara lantai plesteran

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Dolken wood/Dolken kayu diameter 8-10/400 cm
Wood/Kayu
Common nails/Paku biasa
Iron strips/Besi strip
Portland cement/Semen portland
Sand plug/Pasir pasang
Concrete sand/Pasir beton
Coral concrete/Koral beton
Red Brick/Bata merah
Zinc plate/Seng plat
Naco window/Jendela naco
Glass shaft/Kaca polos
Key planting/Kunci tanam
Plywood 4mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
2.000
82,500
L.02
Manday
2.000
99,000
L.02
Manday
1.000
99,000
L.03
Manday
0.300
121,000
L.04
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

165,000
198,000
99,000
36,300
6,050
504,350

Batang
1.250
M3
0.180
1,650,000
Kg
0.080
19,800
Kg
1.100
11,000
Kg
35.000
1,375
M3
0.150
101,750
M3
0.100
101,750
M3
0.150
518,851
Bh
30.000
798
Lbr
0.250
116,600
Bh
0.200
99,000
M2
0.080
Bh
0.150
27,500
Lbr
0.060
74,800
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

297,000
1,584
12,100
48,125
15,263
10,175
77,828
23,925
29,150
19,800
4,125
4,488
543,562

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

1,047,912
157,186.81
1,205,098.91

15% x D

A. 2.2.1.6 Making 1m2 guard house (wood construction)/Pembuatan 1 m2 rumah jaga (konstruksi kayu)

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wood dolken/Dolken kayu 8-10/400 cm
Wood/Kayu
Common nails/Paku biasa
Zinc wave/Seng gelombang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.000
82,500
L.02
Manday
1.500
99,000
L.03
Manday
0.150
121,000
L.04
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

82,500
148,500
18,150
6,050
255,200

Batang
3.000
M3
0.276
1,650,000
Kg
0.700
19,800
Kg
1.500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

455,400
13,860
469,260

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

724,460
108,669.00
833,129.00

15% x D

A. 2.2.1.7 Preparation of 1 m2 warehouse cement and equipment/Pembuatan 1 m2 gudang semen dan peralatan

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wood dolken/Dolken kayu diameter 8-10/400 cm
Wood/Kayu
Common nails/Paku biasa
Portland cement/Semen portland
Concrete sand/Pasir beton
Concrete coral/Koral beton
Zinc wave/Seng gelombang
Zinc plate/Seng plat

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.000
82,500
L.02
Manday
2.000
99,000
L.03
Manday
0.200
121,000
L.04
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

82,500
198,000
24,200
6,050
310,750

Batang
1.700
M3
0.210
1,650,000
Kg
0.300
19,800
Kg
10.500
1,375
M3
0.030
101,750
M3
0.050
518,851
Lbr
1.500
Lbr
0.250
116,600
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

346,500
5,940
14,438
3,053
25,943
29,150
425,023

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

735,773
110,365.88
846,138.41

A. 2.2.1.8 Preparation of 1 m2 plots worker/Pembuatan 1 m2 bedeng pekerja

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wood dolken/Dolken kayu diameter 8-10/400 cm
Wood/Kayu
Common nails/Paku biasa
Portland cement/Semen portland
Concrete sand/Pasir beton
Concrete coral/Koral beton
Zinc Wave/Seng gelombang
Zinc plate/Seng plat

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.000
82,500
L.02
Manday
2.000
99,000
L.03
Manday
0.200
121,000
L.04
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

82,500
198,000
24,200
6,050
310,750

Batang
1.250
M3
0.186
1,650,000
Kg
0.300
19,800
Kg
18.000
1,375
M3
0.030
101,750
M3
0.050
518,851
Lbr
1.500
Lbr
1.350
116,600
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

306,900
5,940
24,750
3,053
25,943
157,410
523,995

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

834,745
125,211.75
959,956.79

A. 2.2.1.9 Cleaning 1 m2 field and leveling/Pembersihan 1 m2 lapangan dan perataan

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.100
82,500
L.04
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

8,250
6,050
14,300

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

14,300
2,145.00
16,445.00

A. 2.2.1.10 Preparation of 1 m2 steger/scaffolding of bamboo / Pembuatan 1 m2 steger/perancah dari bambu

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Labour/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Bamboo/Bambu diameter 6-8/600 cm
Rope ijuk/Tali ijuk

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.000
82,500
L.02
Manday
2.000
99,000
L.03
Manday
0.200
121,000
L.04
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

82,500
198,000
24,200
6,050
310,750

Batang
1.250
55,000
M3
0.186
26,400
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

68,750
4,910
73,660

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

384,410
57,661.56
442,071.96

A. 2.2.1.11 Preparation of 1 piece box 40cm x 50cm x mix 25cm/Pembuatan 1 buah kotak adukan 40cm x 50cm x 25cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
MATERIALS/BAHAN
Wooden board class III/Kayu papan kelas III
Wood beams 5/7 class III/Kayu balok 5/7 kelas III
Common nails/Paku biasa

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.02
Manday
0.300
99,000
L.03
Manday
0.030
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

29,700
3,630
33,330

M3
0.036
3,630,000
M3
Kg
0.080
16,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

130,680

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

1,320
132,000

165,330
24,799.50
190,129.50

A. 2.2.1.12 Preparation of 1 m2 of temporary road/Pembuatan 1 m2 jalan sementara

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
1.000
82,500
L.04
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
82,500
6,050
88,550

MATERIALS/BAHAN
Rock split/Batu belah
Crushed stone/Batu pecah
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

M3
0.150
385,000
M3
0.090
518,851
M3
0.010
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

57,750
46,697
1,018
105,464

194,014
29,102.11
223,116.16

A. 2.2.1.13 Demolition of 1 m3 of reinforced concrete/Pembongkaran 1 m3 beton bertulang

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
13.334
82,500
L.04
0.666
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
1,100,055
80,586
1,180,641

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

1,180,641
177,096.15
1,357,737.15

A. 2.2.1.14 Demolition of concrete walls 1m3/Pembongkaran 1 m3 dinding tembok beton

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
6.667
82,500
L.04
0.333
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
550,028
40,293
590,321

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

590,321
88,548.08
678,868.58

A. 2.2.1.15 Installation of 1 m2 of galvanized mesh fence wire length of 240 cm/Pemasangan 1 m2 pagar kawat jaring galvanis
panjang 240 cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Labour/Tukang
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wire netting/Kawat Jaring

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
0.042
82,500
L.02
0.004
99,000
L.03
0.002
121,000
L.04
0.042
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

3,465
396
242
5,082
9,185

Lbr
0.143
30,800
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

4,417
4,417

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

13,602
2,040.26
15,641.98

A. 2.2.1.16 Installation of 1 m2 of precast concrete panels 5x50x213 cm/Pemasangan 1 m2 panel beton pracetak 5x50x213 cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Skill labour/Tukang
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Precast concrete panels/Panel beton pracetak
Precast concrete columns/ Kolom beton pracetak
Portland cement/Semen PC
Concrete sand/Pasir beton
Coral/Koral

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
0.375
82,500
L.02
0.125
99,000
L.03
0.012
121,000
L.04
0.019
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

30,938
12,375
1,452
2,299
47,064

Lbr
0.986
Btg
0.525
Kg
45
1,375
M3
0.074
101,750
M3
0.146
518,851
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

61,875
7,530
75,752
145,157

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

192,220
28,833.03
221,053.22

A. 2.3.1 GROUND WORK UNIT PRICE/HARGA SATUAN PEKERJAAN TANAH


A. 2.3.1.1 1 m3 of ordinary soil excavation depth of 1 m/Penggalian 1 m3 tanah biasa sedalam 1 m

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.750
82,500
L.04
Manday
0.025
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
61,875
3,025
64,900

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

64,900
9,735.00
74,635.00

A. 2.3.1.2 1 m3 of ordinary soil excavation depth of 2 m/Penggalian 1 m3 tanah biasa sedalam 2 m

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.900
82,500
L.04
Manday
0.045
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
74,250
5,445
79,695

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

79,695
11,954.25
91,649.25

A. 2.3.1.3 1 m3 of ordinary soil excavation depth of 3 m/Penggalian 1 m3 tanah biasa sedalam 3 m

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.050
82,500
L.04
Manday
0.067
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
86,625
8,107
94,732

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

94,732
14,209.80
108,941.80

A. 2.3.1.4 1m3 digging hard soil as deep as 1 m/Menggali 1 m3 tanah keras sedalam 1 m

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.000
82,500
L.04
Manday
0.032
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
82,500
3,872
86,372

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

86,372
12,955.80
99,327.80

A. 2.3.1.5 1m3 Digging deep rocky soil 1m3 1 m/Menggali 1 m3 tanah cadas sedalam 1 m

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.500
82,500
L.04
Manday
0.060
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
123,750
7,260
131,010

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

131,010
19,651.50
150,661.50

A. 2.3.1.6 Digging deep rocky soil 1m3 1 m/Menggali 1 m3 tanah lumpur sedalam 1 m

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.200
82,500
L.04
Manday
0.045
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
99,000
5,445
104,445

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

104,445
15,666.75
120,111.75

A. 2.3.1.7 Work soil stripping 1m2 1 meter high cliff/Pengerjaan stripping 1m2 tanah tebing setinggi 1 meter

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.050
82,500
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
4,125
605
4,730

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

4,730
709.50
5,439.50

A. 2.3.1.8 Disposal of 1m3 of land as far as 30 meters/Pembuangan 1 m3 tanah sejauh 30 meter

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.330
82,500
L.04
Manday
0.010
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
27,225
1,210
28,435

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

28,435
4,265.25
32,700.25

A. 2.3.1.9 Return 1 m3 of excavation backfill soil/Pengurukan kembali 1 m3 galian tanah


1 m3 of excavation backfill back calculated from the third times the coefficient of excavation work/Pengurukan kembali 1 m3
galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.500
82,500
L.04
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
41,250
6,050
47,300

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

47,300
7,095.00
54,395.00

A. 2.3.1.10 1 m3 of soil compaction (per 20 cm)/Pemadatan tanah 1 m3 tanah ( per 20cm )

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.500
82,500
L.04
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
41,250
6,050
47,300

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

47,300
7,095.00
54,395.00

A. 2.3.1.11 Hoarding 1 m3 of sand urug/Pengurugan 1 m3 dengan pasir urug

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.300
82,500
L.04
Manday
0.010
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
24,750
1,210
25,960

MATERIALS/BAHAN
Pasir Urug

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

M3
1.200
71,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

85,800
85,800

111,760
16,764.00
128,524.00

A. 2.3.1.12 Installation of 1 m3 layer poodle mix 1KP: 3PP: 7TL/Pemasangan 1 m3 lapisan pudel campuran 1KP : 3PP : 7TL
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Skill Labour/Tukang
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Lime outages/Kapur Padam
Sand plug/Pasir Pasang
Clay/Tanah Liat

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.800
82,500
L.02
Manday
0.400
99,000
L.03
Manday
0.040
121,000
L.04
Manday
0.080
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

66,000
39,600
4,840
9,680
120,120

M3
0.135
M3
0.400
101,750
M3
0.948
55,000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

40,700
52,140
92,840

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

212,960
31,944.00
244,904.00

A. 2.3.1.13 Installation of 1 m2 10 cm thick layer of fibers for leach field/Pemasangan 1 m2 lapisan ijuk tebal 10 cm untuk
bidang resapan
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor
MATERIALS/BAHAN
Fibers/Ijuk

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.150
82,500
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

12,375
1,815
14,190

M3
6.000
26,400
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

158,400
158,400

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

172,590
25,888.50
198,478.50

A. 2.3.1.14 hoarding 1 m3 of solid gravel/Pengurugan 1 m3 sirtu padat

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor
MATERIALS/BAHAN
Gravel soil/Sirtu

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.250
82,500
L.04
Manday
0.025
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

20,625
3,025
23,650

M3
1.200
88,000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

105,600
105,600

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

129,250
19,387.50
148,637.50

A. 3.2.1 WORK UNIT PRICE FOUNDATION/HARGA SATUAN PEKERJAAN PONDASI


A. 3.2.1.1 Laying the foundation stone of 1 m3 sides mixture 1SP: 3PP/Pemasangan 1 m3 pondasi batu belah campuran 1SP :
3PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Rock split/Batu belah
Portland cement/Semen portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.500
82,500
L.02
Manday
0.750
99,000
L.03
Manday
0.075
121,000
L.04
Manday
0.075
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

123,750
74,250
9,075
9,075
216,150

M3
1.200
385,000
Kg
202.000
1,375
M3
0.485
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

462,000
277,750
49,349
789,099

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

1,005,249
150,787.31
1,156,036.06

A. 3.2.1.2 Laying the foundation stone of 1 m3 sides mixture 1SP: 4PP/Pemasangan 1 m3 pondasi batu belah campuran 1SP :
4PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.500
82,500
L.02
Manday
0.750
99,000
L.03
Manday
0.075
121,000
L.04
Manday
0.075
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Rock split/Batu belah
Portland cement/Semen portland
Sand plug/Pasir pasang

Unit
Satuan

M3
Kg
M3

1.200
385,000
163.000
1,375
0.520
101,750
JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
123,750
74,250
9,075
9,075
216,150
462,000
224,125
52,910
739,035

955,185
143,277.75
1,098,462.75

A. 3.2.1.3 Laying the foundation stone of 1 m3 sides mix 1 SP: 5 PP/Pemasangan 1 m3 pondasi batu belah campuran 1SP :
5PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Rock split/Batu belah
Portland cement/Semen portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.500
82,500
L.02
Manday
0.750
99,000
L.03
Manday
0.075
121,000
L.04
Manday
0.075
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

123,750
74,250
9,075
9,075
216,150

M3
1.200
385,000
Kg
136.000
1,375
M3
0.544
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

462,000
187,000
55,352
704,352

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

920,502
138,075.30
1,058,577.30

A. 3.2.1.4 Laying the foundation stone of 1 m3 sides mixture 1SP: 6PP/Pemasangan 1 m3 pondasi batu belah campuran 1SP :
6PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.500
82,500
L.02
Manday
0.750
99,000
L.03
Manday
0.075
121,000
L.04
Manday
0.075
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
123,750
74,250
9,075
9,075
216,150

MATERIALS/BAHAN
Rock split/Batu belah
Portland cement/Semen portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

M3
1.200
385,000
Kg
117.000
1,375
M3
0.561
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

462,000
160,875
57,082
679,957

896,107
134,416.01
1,030,522.76

A. 3.2.1.5 Laying the foundation stone of 1 m3 sides mixture 1SP: 8PP/Pemasangan 1 m3 pondasi batu belah campuran 1SP :
8PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Rock split/Batu belah
Portland cement/Semen portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.500
82,500
L.02
Manday
0.750
99,000
L.03
Manday
0.075
121,000
L.04
Manday
0.075
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

123,750
74,250
9,075
9,075
216,150

M3
1.200
385,000
Kg
91.000
1,375
M3
0.584
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

462,000
125,125
59,422
646,547

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

862,697
129,404.55
992,101.55

A. 3.2.1.6 Laying the foundation stone of 1 m3 sides mixture 1SP: 1KP: 2PP/Pemasangan 1 m3 pondasi batu belah campuran
1SP : 1KP : 2PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Rock split/Batu belah
Lime/Kapur
Portland cement/Semen portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.500
82,500
L.02
Manday
0.750
99,000
L.03
Manday
0.075
121,000
L.04
Manday
0.075
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

123,750
74,250
9,075
9,075
216,150

M3
1.200
385,000
M3
0.170
Kg
0.170
1,375
M3
0.340
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

462,000
234
34,595
496,829

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

712,979
106,946.81
819,925.56

A. 3.2.1.7 Laying the foundation stone of 1 m3 sides mixture 1SP: 3KP: 10pp/Pemasangan 1 m3 pondasi batu belah campuran
1SP : 3KP : 10PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Rock split/Batu belah
Portland cement/Semen portland
Lime/Kapur
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.500
82,500
L.02
Manday
0.750
99,000
L.03
Manday
0.075
121,000
L.04
Manday
0.075
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

123,750
74,250
9,075
9,075
216,150

M3
1.200
385,000
Kg
61.000
1,375
M3
0.147
M3
0.492
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

462,000
83,875
50,061
595,936

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

812,086
121,812.90
933,898.90

A. 3.2.1.8 Laying the foundation stone of 1 m3 sides mix 1/4 SP: 1 KP: 4PP / Pemasangan 1 m3 pondasi batu belah campuran
1/4SP : 1KP : 4PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Rock split/ Batu belah
Portland cement/Semen portland
Lime/Kapur
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.500
82,500
L.02
Manday
0.750
99,000
L.03
Manday
0.075
121,000
L.04
Manday
0.075
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

123,750
74,250
9,075
9,075
216,150

M3
1.200
385,000
Kg
41.000
1,375
M3
0.131
M3
0.523
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

462,000
56,375
53,215
462,000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

678,150
101,722.50
779,872.50

A. 3.2.1.9 Installation of 1 m3 of empty stone (aanstamping)/Pemasangan 1 m3 batu kosong (anstamping)

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Rock split/Batu belah
Sand pile/Pasir urug

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.780
82,500
L.02
Manday
0.390
99,000
L.03
Manday
0.039
121,000
L.04
Manday
0.039
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

64,350
38,610
4,719
4,719
112,398

M3
1.200
385,000
M3
0.432
71,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

462,000
30,888
492,888

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

605,286
90,792.90
696,078.90

A. 3.2.1.10 Laying the foundation Cyclops 1 m3, 60% of concrete mix 1 SP: 2 PB: 3 Kr and 40% split stone / Pemasangan 1 m3
pondasi siklop, 60% beton campuran 1SP : 2PB : 3 Kr dan 40% batu belah
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Rock split/Batu belah
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil
Concrete steel/Besi beton
Concrete wire/Kawat beton

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.780
82,500
L.02
Manday
0.390
99,000
L.03
Manday
0.039
121,000
L.04
Manday
0.039
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

64,350
38,610
4,719
4,719
112,398

M3
0.480
385,000
Kg
194.000
1,375
M3
0.312
101,750
M3
0.468
440,000
Kg
126.000
20,900
Kg
1.800
19,800
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

184,800
266,750
31,746
205,920
2,633,400
35,640
3,358,256

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

3,470,654
520,598.10
3,991,252.10

A. 3.2.1.11 Laying the foundation sinks 1 m3, diameter 100 cm/Pemasangan 1 m3 pondasi sumuran, diameter 100 cm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.400
82,500
L.02
Manday
0.800
99,000
L.03
Manday
0.080
121,000
L.04
Manday
0.119
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
198,000
79,200
9,680
14,399
301,279

MATERIALS/BAHAN
Rock split/Batu belah
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

M3
0.450
385,000
Kg
194.000
1,375
M3
0.312
101,750
M3
0.468
440,000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

173,250
266,750
31,746
205,920
677,666

978,945
146,841.75
1,125,786.75

A. 4.1.1 CONCRETE WORK UNIT PRICE/HARGA SATUAN PEKERJAAN BETON


A. 4.1.1.1 Makes 1 m3 of concrete quality f'c = 7.4 MPa (K 100), slump (12 2) cm, w / c = 0.87 / Membuat 1 m3 beton mutu f'c =
7,4 Mpa (K 100), slump (12 2) cm, w/c = 0.87
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
gravel/Kerikil (Maks. 30mm)
Water/Air

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.650
82,500
L.02
Manday
0.275
99,000
L.03
Manday
0.028
121,000
L.04
Manday
0.083
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

136,125
27,225
3,388
10,043
176,781

Kg
247
1,375
Kg
869
Kg
999
Liter
215
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

339,625
339,625

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

516,406
77,460.90
593,866.90

A. 4.1.1.2 Makes 1 m3 of concrete quality f'c = 9.8 MPa (K 125), slump (12 2) cm, w / c = 0.78 / Membuat 1 m3 beton mutu f'c =
9,8 Mpa (K 125), slump (12 2) cm, w/c = 0.78
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil (Maks. 30mm)
Water/Air

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.650
82,500
L.02
Manday
0.275
99,000
L.03
Manday
0.028
121,000
L.04
Manday
0.083
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

136,125
27,225
3,388
10,043
176,781

Kg
276.000
1,375
Kg
828
101,750
Kg
1,012
Liter
215
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

379,500
84,249,000
84,628,500

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

84,805,281
12,720,792.15
97,526,073.15

A. 4.1.1.3 Makes 1 m3 of concrete f'c = 12.2 MPa quality (K150), slump (12 2) cm, w / c = 0.72 / Membuat 1 m3 beton mutu f'c =
12.2 Mpa (K 150), slump (12 2) cm, w/c = 0.72
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
gravel/Kerikil (Maks. 30mm)
Water/Air

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.650
82,500
L.02
Manday
0.275
99,000
L.03
Manday
0.028
121,000
L.04
Manday
0.083
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

136,125
27,225
3,388
10,043
176,781

Kg
299.000
1,375
Kg
799
Kg
1,017
Liter
215
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

411,125
411,125

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

587,906
88,185.90
676,091.90

NOTE/CATATAN
Bulk density = 1400 kg/m3 sand, gravel content Weight = 1350 kg/m3, Buckling factor = 20% sand / Bobot isi pasir = 1400 kg/m3, Bobot isi kerikil =
1350 kg/m3, Buckling factor pasir = 20%

A. A. 4.1.1.4 Makes 1 m3 of concrete floor quality work f'c = 7.4 MPa (K 100), slump (3-6) cm, w / c = 0.87 / Membuat 1 m3 lantai
kerja beton mutu f'c = 7,4 Mpa (K 100), slump (3 - 6)cm, w/c = 0.87
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil (Maks. 30mm)
Water/Air

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.200
82,500
L.02
Manday
0.200
99,000
L.03
Manday
0.020
121,000
L.04
Manday
0.060
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

99,000
19,800
2,420
7,260
128,480

Kg
230.000
1,375
Kg
893
Kg
1,027
Liter
200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

316,250
316,250

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

444,730
66,709.50
511,439.50

A. A. 4.1.1.5 Makes 1 m3 of concrete f'c = 14.5 MPa quality (K 175), slump (12 2) cm, w / c = 0.66 / Membuat 1 m3 beton mutu
f'c = 14.5 Mpa (K 175), slump (12 2)cm, w/c = 0.66
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil (Maks. 30mm)
Water/Air

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.650
82,500
L.02
Manday
0.275
99,000
L.03
Manday
0.028
121,000
L.04
Manday
0.083
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

136,125
27,225
3,388
10,043
176,781

Kg
326.000
1,375
Kg
760
Kg
1,029
Liter
215
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

448,250
448,250

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

625,031
93,754.65
718,785.65

A. A. 4.1.1.6 Makes 1 m3 of concrete f'c = 16.9 MPa quality (K 200), slump (12 2) cm, w / c = 0.61 / Membuat 1 m3 beton mutu
f'c = 16.9 Mpa (K 200), slump (12 2)cm, w/c = 0.61
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil (Maks. 30mm)
Water/Air

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.650
82,500
L.02
Manday
0.275
99,000
L.03
Manday
0.028
121,000
L.04
Manday
0.083
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

136,125
27,225
3,388
10,043
176,781

Kg
352.000
1,375
Kg
731
Kg
1,031
Liter
215
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

484,000
484,000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

660,781
99,117.15
759,898.15

A. 4.1.1.7 Makes 1 m3 of concrete f'c = 19.3 MPa quality (K 225), slump (12 2) cm, w / c = 0:58 / Membuat 1 m3 beton mutu f'c
= 19.3 Mpa (K 225), slump (12 2)cm, w/c = 0.58
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil (Maks. 30mm)
Water/Air

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.650
82,500
L.02
Manday
0.275
99,000
L.03
Manday
0.028
121,000
L.04
Manday
0.083
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

136,125
27,225
3,388
10,043
176,781

Kg
371.000
1,375
Kg
698
Kg
1,047
Liter
215
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

510,125
510,125

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

686,906
103,035.90
789,941.90

A. 4.1.1.8 Makes 1 m3 of concrete f'c = 21.7 MPa quality (K 250), slump (12 2) cm, w / c = 0:56 / Membuat 1 m3 beton mutu f'c
= 21.7 Mpa (K 250), slump (12 2)cm, w/c = 0.56
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil (Maks. 30mm)
Water/Air

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.650
82,500
L.02
Manday
0.275
99,000
L.03
Manday
0.028
121,000
L.04
Manday
0.083
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

136,125
27,225
3,388
10,043
176,781

Kg
384.000
1,375
Kg
692
Kg
1,039
Liter
215
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

528,000
528,000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

704,781
105,717.15
810,498.15

A. 4.1.1.9 Makes 1 m3 of concrete f'c = 24.0 MPa quality (K 275), slump (12 2) cm, w / c = 0:53 / Membuat 1 m3 beton mutu f'c
= 24.0 Mpa (K 275), slump (12 2)cm, w/c = 0.53
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil (Maks. 30mm)
Water/Air

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.650
82,500
L.02
Manday
0.275
99,000
L.03
Manday
0.028
121,000
L.04
Manday
0.083
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

136,125
27,225
3,388
10,043
176,781

Kg
406.000
1,375
Kg
684
Kg
1,026
Liter
215
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

558,250
558,250

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

735,031
110,254.65
845,285.65

A. 4.1.1.10 Makes 1 m3 of concrete f'c = 26.4 MPa quality (K 300), slump (12 2) cm, w / c = 0:52 / Membuat 1 m3 beton mutu
f'c = 26.4 Mpa (K 300), slump (12 2)cm, w/c = 0.52
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil (Maks. 30mm)
Water/Air

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.650
82,500
L.02
Manday
0.275
99,000
L.03
Manday
0.028
121,000
L.04
Manday
0.083
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

136,125
27,225
3,388
10,043
176,781

Kg
413.000
1,375
Kg
681
Kg
1,021
Liter
215
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

567,875
567,875

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

744,656
111,698.40
856,354.40

A. 4.1.1.11 Makes 1 m3 of concrete f'c = 28.8 MPa quality (K 325), slump (12 2) cm, w / c = 0:49 / Membuat 1 m3 beton mutu f'c
= 28.8 Mpa (K 325), slump (12 2)cm, w/c = 0.49
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.100
82,500
L.02
Manday
0.350
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.105
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
173,250
34,650
4,235
12,705
224,840

MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil (Maks. 30mm)
Water/Air

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Kg
439.000
1,375
Kg
670
Kg
1,006
Liter
215
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

603,625
603,625

828,465
124,269.75
952,734.75

A. 4.1.1.12 Makes 1 m3 of concrete f'c = 31.2 MPa quality (K 350), slump (12 2) cm, w / c = 0:48 / Membuat 1 m3 beton mutu
f'c = 31.2 Mpa (K 350), slump (12 2)cm, w/c = 0.48
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil (Maks. 30mm)
Water/Air

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
2.100
82,500
L.02
Manday
0.350
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.105
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

173,250
34,650
4,235
12,705
224,840

Kg
448.000
1,375
Kg
667
Kg
1,000
Liter
215
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

616,000
616,000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

840,840
126,126.00
966,966.00

A. 4.1.1.13 Makes 1 m3 of concrete with a water-resistant strorox - 100 / Membuat 1 m3 beton kedap air dengan strorox - 100
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Labour/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil (2cm / 3cm)
Strorox - 100

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
2.100
82,500
L.02
Manday
0.350
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.105
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

173,250
34,650
4,235
12,705
224,840

Kg
400.000
1,375
m3
0.480
101,750
m3
0.800
518,851
Liter
1.200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

550,000
48,840
415,080
1,013,920

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

1,238,760
185,814.07
1,424,574.57

A. 4.1.1.14 Installation of 1 m PVC. Waterstop width of 150 mm/ Pemasangan 1 m PVC Waterstop lebar 150 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Masons/plumbers/Tukang Batu/Pipa
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

MATERIALS/BAHAN
Width of waterstop/Waterstop lebar 150 mm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.060
82,500
L.02
Manday
0.030
99,000
L.03
Manday
0.003
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
4,950
2,970
363
363
8,646

M
1.050
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

8,646
1,296.90
9,942.90

A. 4.1.1.15 Installation of 1 m width 200 mm PVC waterstop / Pemasangan 1 m PVC Waterstop lebar 200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Masons/plumbers/Tukang Batu/Pipa
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.070
82,500
L.02
Manday
0.035
99,000
L.03
Manday
0.004
121,000
L.04
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
5,775
3,465
484
847
10,571

MATERIALS/BAHAN
Width of waterstop/Waterstop lebar 200 mm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

M
1.050
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

10,571
1,585.65
12,156.65

A. 4.1.1.16 Installation of 1 m PVC waterstop width 230 mm - 320 mm / Pemasangan 1 m PVC Waterstop lebar 230 mm - 320
mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Width of waterstop/Waterstop lebar 230 mm - 320 mm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.080
82,500
L.02
Manday
0.040
99,000
L.03
Manday
0.004
121,000
L.04
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

6,600
3,960
484
484
11,528

M
1.050
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

11,528
1,729.20
13,257.20

A. 4.1.1.17 10 kg of steel reinforcement with plain or threaded iron / Pembesian 10 kg with a plain iron or steel threaded /
Pembesian 10 kg dengan besi polos atau besi ulir
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Vulcan/Tukang Besi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.070
82,500
L.02
Manday
0.070
99,000
L.03
Manday
0.007
121,000
L.04
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

5,775
6,930
847
484
14,036
219,450
2,970
222,420

MATERIALS/BAHAN
Reinforced concrete (plain/threaded)Besi beton (polos/ulir)
Kg
10.500
20,900
Concrete wire/Kawat beton
Kg
0.150
19,800
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN
EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

236,456
35,468.40
271,924.40

A. 4.1.1.18 Installation cable 10 kg presstressed plain / strands / Pemasangan 10 kg kabel presstressed polos/strands
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Labour/Tukang Besi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.050
82,500
L.02
Manday
0.050
99,000
L.03
Manday
0.005
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

4,125
4,950
605
363
10,043
219,450
1,980
221,430

MATERIALS/BAHAN
Reinforced concrete (plain/threaded)/Besi beton (polos/ulir)
Kg
10.500
20,900
Concrete wire/Kawat beton
Kg
0.100
19,800
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN
EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

231,473
34,720.95
266,193.95

A. 4.1.1.19 Installation of 10 kg of steel wire (wiremesh)/Pemasangan 10 kg jaring kawat baja (wiremesh)

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Vulcan/Tukang Besi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Welded steel wire mesh/Jaring kawat baja di las
Concrete wire/Kawat beton

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.025
82,500
L.02
Manday
0.025
99,000
L.03
Manday
0.025
121,000
L.04
Manday
0.001
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

2,063
2,475
3,025
121
7,684

Kg
10.200
Kg
0.050
19,800
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

990
990

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

8,674
1,301.03
9,974.53

A. 4.1.1.20 Installation of 1 m2 of formwork for the foundation/Pemasangan 1 m2 bekisting untuk pondasi

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Timber class III/Wood Kayu kelas III
Nail/Paku 5 - 10 cm
Formwork oil/Minyak bekisting

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.520
82,500
L.02
Manday
0.260
99,000
L.03
Manday
0.026
121,000
L.04
Manday
0.026
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

42,900
25,740
3,146
3,146
74,932

M3
0.040
3,630,000
Kg
0.300
16,500
Liter
0.100
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

145,200
4,950
1,320
151,470

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

226,402
33,960.30
260,362.30

A. 4.1.1.21 Installation of 1 m2 of formwork for sloof/Pemasangan 1 m2 bekisting untuk sloof

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Timber class III/Kayu kelas III
Nail/Paku 5 - 10 cm
Formwork oil/Minyak bekisting

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.520
82,500
L.02
Manday
0.260
99,000
L.03
Manday
0.026
121,000
L.04
Manday
0.026
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

42,900
25,740
3,146
3,146
74,932

M3
0.045
3,630,000
Kg
0.300
16,500
Liter
0.100
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

163,350
4,950
1,320
169,620

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

244,552
36,682.80
281,234.80

A. 4.1.1.22 Installation of 1 m2 of formwork for columns/Pemasangan 1 m2 bekisting untuk kolom

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.660
82,500
L.02
Manday
0.330
99,000
L.03
Manday
0.033
121,000
L.04
Manday
0.033
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

54,450
32,670
3,993
3,993
95,106
145,200
6,600
2,640
99,000
48,125
301,565

MATERIALS/BAHAN
Timber class/Kayu kelas III
M3
0.040
3,630,000
Nail/Paku 5 - 12 cm
Kg
0.400
16,500
Formwork oli/Minyak bekisting
Liter
0.200
13,200
Wooden blocks class II/Balok kayu kelas II
M3
0.015
6,600,000
Plywood tebal 9 mm
Lbr
0.350
137,500
Wood dolken/Dolken kayu 8-10cm long/panjang 4 meter
Batang
2.000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN
EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

396,671
59,500.65
456,171.65

A. 4.1.1.23 Installation of 1 m2 of formwork for the beams/Pemasangan 1 m2 bekisting untuk balok

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.660
82,500
L.02
Manday
0.330
99,000
L.03
Manday
0.033
121,000
L.04
Manday
0.033
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
54,450
32,670
3,993
3,993
95,106

MATERIALS/BAHAN
Timber class/Kayu kelas III
Nail/Paku 5 - 12 cm
Formwork oil/Minyak bekisting
Wooden blocks class/Balok kayu kelas II
Plywood tebal 9 mm
Galam wood dolken/Dolken kayu galam 8-10cm
long/panjang 4 meter
EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

M3
0.040
3,630,000
Kg
0.400
16,500
Liter
0.200
13,200
M3
0.018
6,600,000
Lbr
0.350
137,500
Batang
2.000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

145,200
6,600
2,640
118,800
48,125
321,365

416,471
62,470.65
478,941.65

A. 4.1.1.24 Installation of 1 m2 of formwork for floor/Pemasangan 1 m2 bekisting untuk lantai

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

MATERIALS/BAHAN
Timber class/Kayu kelas III
Nail/Paku 5 - 12 cm
Formwork oil/Minyak bekisting
Wooden blocks class/Balok kayu kelas II
Plywood tebal 9 mm
Galam wood dolken/Dolken kayu galam 8-10cm
long/panjang 4 meter
EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.660
82,500
L.02
Manday
0.330
99,000
L.03
Manday
0.033
121,000
L.04
Manday
0.033
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

54,450
32,670
3,993
3,993
95,106

M3
0.040
3,630,000
Kg
0.400
16,500
Liter
0.200
13,200
M3
0.015
6,600,000
Lbr
0.350
137,500
Batang
6.000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

145,200
6,600
2,640
99,000
48,125
301,565

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

396,671
59,500.65
456,171.65

A. 4.1.1.25 Installation of 1 m2 of formwork for walls / Pemasangan 1 m2 bekisting untuk dinding

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Labour/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

MATERIALS/BAHAN
Timber class/Kayu kelas III
Nail/Paku 5 - 12 cm
Formwork oil/Minyak bekisting
Wooden blocks class/Balok kayu kelas II
Plywood tebal 9 mm
Dolken wood/Dolken kayu, 8-10cm
long/panjang 4 meter
Distance formwork guard/spacer / Penjaga jarak
bekisting/spacer
EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.660
82,500
L.02
Manday
0.330
99,000
L.03
Manday
0.033
121,000
L.04
Manday
0.033
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M3
Kg
Liter
M3
Lbr

0.030
0.400
0.200
0.020
0.350

Batang

3.000

3,630,000
16,500
13,200
6,600,000
137,500

Total Price
Total Harga
(RP.)
54,450
32,670
3,993
3,993
95,106
108,900
6,600
2,640
132,000
48,125
-

Buah
4.000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

298,265

393,371
59,005.65
452,376.65

A. 4.1.1.26 Installation of 1 m2 of formwork for stairs/Pemasangan 1 m2 bekisting untuk tangga

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Timber class/Kayu kelas III
Nail/Paku 5 - 12 cm
Formwork oil/Minyak bekisting
Wooden block class/Balok kayu kelas II
Plywood tebal 9 mm
Dolken wood/Dolken kayu, 8-10cm
long/panjang 4 meter

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.660
82,500
L.02
Manday
0.330
99,000
L.03
Manday
0.033
121,000
L.04
Manday
0.033
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M3
Kg
Liter
M3
Lbr

0.030
0.400
0.150
0.015
0.350

Batang

2.000

3,630,000
16,500
13,200
6,600,000
137,500

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

Total Price
Total Harga
(RP.)
54,450
32,670
3,993
3,993
95,106
108,900
6,600
1,980
99,000
48,125
264,605

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

359,711
53,956.65
413,667.65

15% x D

A. 4.1.1.27 Installation of 1 m2 for casting concrete bridge/Pemasangan 1 m2 jembatan untuk pengecoran beton

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.150
82,500
L.02
Manday
0.050
99,000
L.03
Manday
0.005
121,000
L.04
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Timber class/Kayu kelas III (papan)
Nail/Paku 5 - 12 cm
Dolken wood/Dolken kayu, 8-10cm
long/panjang 4 meter

M3
Kg

0.026
0.600

Batang

0.500

3,630,000
16,500

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

12,375
4,950
605
968
18,898
95,832
9,900
-

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Total Price
Total Harga
(RP.)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

105,732

124,630
18,694.50
143,324.50

A. 4.1.1.28 Makes 1 m3 of reinforced concrete foundation (150 kg iron + formwork)/Membuat 1 m3 pondasi beton bertulang
(150 kg besi + bekisting)
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Carpenter/Tukang Kayu
Vulcan/Tukang Besi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Timber class/Kayu kelas III
Nail/Paku 5 - 12 cm
Formwork oil/Minyak bekisting
Plain concrete iron/Besi beton polos
Concrete wire/Kawat beton
Portlan cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
5.300
82,500
L.02
Manday
0.275
99,000
L.02
Manday
1.300
99,000
L.02
Manday
1.050
99,000
L.03
Manday
0.262
121,000
L.04
Manday
0.265
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

437,250
27,225
128,700
103,950
31,702
32,065
760,892

M3
0.200
3,630,000
Kg
1.500
16,500
Liter
0.400
13,200
Kg
157.500
20,900
Kg
2.250
19,800
Kg
336.000
1,375
M3
0.540
101,750
M3
0.810
440,000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

726,000
24,750
5,280
3,291,750
44,550
462,000
54,945
356,400
4,965,675

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

5,726,567
858,985.05
6,585,552.05

A. 4.1.1.29 Makes 1 sloof m3 of reinforced concrete (200 kg iron + formwork)/Membuat 1 m3 sloof beton bertulang (200 kg besi
+ bekisting)
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Carpenter/Tukang Kayu
Vulcan/Tukang Besi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Timber class/Kayu kelas III
Nail/Paku 5 - 12 cm
Formwork oil/Minyak bekisting
Plain concrete iron/Besi beton polos
Concrete wire/Kawat beton
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
5.650
82,500
L.02
Manday
0.275
99,000
L.02
Manday
1.580
99,000
L.02
Manday
1.400
99,000
L.03
Manday
0.323
121,000
L.04
Manday
0.283
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

466,125
27,225
156,420
138,600
39,083
34,243
861,696

M3
0.270
3,630,000
Kg
2.000
16,500
Liter
0.600
13,200
Kg
210.000
20,900
Kg
3.000
19,800
Kg
336.000
1,375
M3
0.540
101,750
M3
0.810
440,000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

980,100
33,000
7,920
4,389,000
59,400
462,000
54,945
356,400
6,342,765

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

7,204,461
1,080,669.15
8,285,130.15

A. 4.1.1.30 Makes 1 m3 of reinforced concrete columns (300 kg iron + formwork)/Membuat 1 m3 kolom beton bertulang (300 kg
besi + bekisting)
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Carpenter/Tukang Kayu
Vulcan/Tukang Besi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
7.050
82,500
L.02
Manday
0.275
99,000
L.02
Manday
1.650
99,000
L.02
Manday
2.100
99,000
L.03
Manday
0.403
121,000
L.04
Manday
0.353
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

581,625
27,225
163,350
207,900
48,763
42,713
1,071,576
1,452,000
66,000
26,400
6,583,500
89,100
462,000
54,945
356,400
990,000
481,250
10,561,595

MATERIALS/BAHAN
Timber class/Kayu kelas III
M3
0.400
3,630,000
Nail/Paku 5 - 12 cm
Kg
4.000
16,500
Formwork oil/Minyak bekisting
Liter
2.000
13,200
Plain concrete iron/Besi beton polos
Kg
315.000
20,900
Concrete wire/Kawat beton
Kg
4.500
19,800
Portland cement/Semen portland
Kg
336.000
1,375
Concrete sand/Pasir beton
M3
0.540
101,750
Gravel/Kerikil
M3
0.810
440,000
Wooden block class/Kayu kelas II balok
M3
0.150
6,600,000
Plywood 9 mm
Lbr
3.500
137,500
Dolken wood/Dolken kayu, 8-10cm long/panjang 4 meter
Batang
20.000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN
EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

11,633,171
1,744,975.65
13,378,146.65

A. 4.1.1.31 Makes 1 m3 of reinforced concrete beams (200 kg iron + formwork) / Membuat 1 m3 balok beton bertulang (200 kg
besi + bekisting)
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Carpenter/Tukang Kayu
Vulcan/Tukang Besi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
6.350
82,500
L.02
Manday
0.275
99,000
L.02
Manday
1.650
99,000
L.02
Manday
1.400
99,000
L.03
Manday
0.333
121,000
L.04
Manday
0.318
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

523,875
27,225
163,350
138,600
40,293
38,478
931,821
1,161,600
52,800
21,120
4,389,000
59,400
462,000
54,945
356,400
924,000
385,000
7,866,265

MATERIALS/BAHAN
Timber class/Kayu kelas III
M3
0.320
3,630,000
Nail/Paku 5 - 12 cm
Kg
3.200
16,500
Formwork oil/Minyak bekisting
Liter
1.600
13,200
Plain concrete iron/Besi beton polos
Kg
210.000
20,900
Concrete wire/Kawat beton
Kg
3.000
19,800
Portland cement/Semen portland
Kg
336.000
1,375
Concrete sand/Pasir beton
M3
0.540
101,750
Gravel/Kerikil
M3
0.810
440,000
Wooden block class/Kayu kelas II balok
M3
0.140
6,600,000
Plywood 9 mm
Lembar
2.800
137,500
Dolken wood/Dolken kayu, 8-10cm long/panjang 4 meter
Batang
16.000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN
EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

8,798,086
1,319,712.90
10,117,798.90

A. 4.1.1.32 Makes 1 m3 of reinforced concrete beams (150 kg iron + formwork)/Membuat 1 m3 balok beton bertulang (150 kg
besi + bekisting)
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Carpenter/Tukang Kayu
Vulcan/Tukang Besi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
5.300
82,500
L.02
Manday
0.275
99,000
L.02
Manday
1.300
99,000
L.02
Manday
1.050
99,000
L.03
Manday
0.265
121,000
L.04
Manday
0.265
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

437,250
27,225
128,700
103,950
32,065
32,065
761,255

MATERIALS/BAHAN
Timber class/Kayu kelas III
M3
0.320
3,630,000
Nail/Paku 5 - 12 cm
Kg
3.200
16,500
Formwork oil/Minyak bekisting
Liter
1.600
13,200
Plain concrete iron/Besi beton polos
Kg
157.500
20,900
Concrete wire/Kawat beton
Kg
2.250
19,800
Portland cement/Semen portland
Kg
336.000
1,375
Concrete sand/Pasir beton
M3
0.540
101,750
Gravel/Kerikil
M3
0.810
440,000
Wooden block class/Kayu kelas II balok
M3
0.120
6,600,000
Plywood 9 mm
Lembar
2.800
137,500
Dolken wood/Dolken kayu, 8-10cm long/panjang 4 meter
Batang
32.000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,161,600
52,800
21,120
3,291,750
44,550
462,000
54,945
356,400
792,000
385,000
6,622,165

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

7,383,420
1,107,513.00
8,490,933.00

A. 4.1.1.33 Makes 1 m3 of reinforced concrete walls (150 kg iron + formwork) / Membuat 1 m3 dinding beton bertulang (150 kg
besi + bekisting)
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Carpenter/Tukang Kayu
Vulcan/Tukang Besi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
5.300
82,500
L.02
Manday
0.275
99,000
L.02
Manday
1.300
99,000
L.02
Manday
1.050
99,000
L.03
Manday
0.262
121,000
L.04
Manday
0.265
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

437,250
27,225
128,700
103,950
31,702
32,065
760,892
871,200
52,800
21,120
3,291,750
44,550
462,000
54,945
356,400
1,056,000
385,000
6,595,765

MATERIALS/BAHAN
Timber class/Kayu kelas III
M3
0.240
3,630,000
Nail/Paku 5 - 12 cm
Kg
3.200
16,500
Formwork oil/Minyak bekisting
Liter
1.600
13,200
Plain concrete iron/Besi beton polos
Kg
157.500
20,900
Concrete wire/Kawat beton
Kg
2.250
19,800
Portland cement/Semen portland
Kg
336.000
1,375
Concrete sand/Pasir beton
M3
0.540
101,750
Gravel/Kerikil
M3
0.810
440,000
Wooden block class/Kayu kelas II balok
M3
0.160
6,600,000
Plywood 9 mm
Lembar
2.800
137,500
Dolken wood/Dolken kayu, 8-10cm long/panjang 4 meter
Batang
24.000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN
EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

7,356,657
1,103,498.55
8,460,155.55

A. 4.1.1.34 Makes 1 m3 of reinforced concrete walls (200 kg iron + formwork) / Membuat 1 m3 dinding beton bertulang (200 kg
besi + bekisting)
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Carpenter/Tukang Kayu
Vulcan/Tukang Besi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
5.650
82,500
L.02
Manday
0.275
99,000
L.02
Manday
1.560
99,000
L.02
Manday
1.400
99,000
L.03
Manday
0.323
121,000
L.04
Manday
0.283
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

466,125
27,225
154,440
138,600
39,083
34,243
859,716
907,500
49,500
15,840
4,389,000
59,400
462,000
54,945
356,400
693,000
343,750
7,331,335

MATERIALS/BAHAN
Timber class/Kayu kelas III
M3
0.250
3,630,000
Nail/Paku 5 - 12 cm
Kg
3.000
16,500
Formwork oil/Minyak bekisting
Liter
1.200
13,200
Plain concrete iron/Besi beton polos
Kg
210.000
20,900
Concrete wire/Kawat beton
Kg
3.000
19,800
Portland cement/Semen portland
Kg
336.000
1,375
Concrete sand/Pasir beton
M3
0.540
101,750
Gravel/Kerikil
M3
0.810
440,000
Wooden block class/Kayu kelas II balok
M3
0.105
6,600,000
Plywood 9 mm
Lembar
2.500
137,500
Dolken wood/Dolken kayu, 8-10cm long/panjang 4 meter
Batang
14.000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN
EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

8,191,051
1,228,657.65
9,419,708.65

A. 4.1.1.35 Makes 1 m1 practical reinforced concrete columns (11 x 11) cm / Membuat 1 m1 kolom praktis beton bertulang (11 x
11) cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Carpenter/Tukang Kayu
Vulcan/Tukang Besi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Timber class/Kayu kelas III
Nail/Paku 5 - 12 cm
Formwork oil/Minyak bekisting
Plain concrete iron/Besi beton polos
Concrete wire/Kawat beton
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.180
82,500
L.02
Manday
0.020
99,000
L.02
Manday
0.020
99,000
L.02
Manday
0.020
99,000
L.03
Manday
0.006
121,000
L.04
Manday
0.009
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

14,850
1,980
1,980
1,980
726
1,089
22,605

M3
0.002
3,630,000
Kg
0.010
16,500
Liter
Kg
3.000
20,900
Kg
0.450
19,800
Kg
4.000
1,375
M3
0.006
101,750
M3
0.009
440,000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

7,260
165
62,700
8,910
5,500
611
3,960
89,106

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

A. 4.1.1.36 Makes 1 m1 reinforced concrete ring beam (10 x 15) cm / Membuat 1 m1 ring balok beton bertulang
cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Carpenter/Tukang Kayu
Vulcan/Tukang Besi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Timber class/Kayu kelas III
Nail/Paku 5 - 12 cm
Formwork oil/Minyak bekisting
Plain concrete iron/Besi beton polos
Concrete wire/Kawat beton
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

111,711
16,756.58
128,467.08

(10 x 15)
Total Price
Total Harga
(RP.)

L.01
Manday
0.297
82,500
L.02
Manday
0.033
99,000
L.02
Manday
0.033
99,000
L.02
Manday
0.033
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

24,503
3,267
3,267
3,267
1,210
1,815
37,329

M3
0.003
3,630,000
Kg
0.020
16,500
Liter
Kg
3.600
20,900
Kg
0.050
19,800
Kg
5.500
1,375
M3
0.009
101,750
M3
0.015
440,000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

10,890
330
75,240
990
7,563
916
6,600
102,528

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

139,857
20,978.51
160,835.26

A. 4.1.2 PRECAST CONCRETE WORK UNIT PRICE/HARGA SATUAN PEKERJAAN BETON PRACETAK
A. 4.1.2.1 Preparation of 1 m2 of production area 8cm thick concrete f'c = 14.5 MPa (K 175), slump (12 2) cm/Pembuatan 1 m2
lahan produksi tebal 8cm beton f'c = 14,5 Mpa (K 175), slump (12 2) cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil (Maks. 30mm)
Water/Air

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.132
82,500
L.02
Manday
0.022
99,000
L.03
Manday
0.002
121,000
L.04
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

10,890
2,178
242
847
14,157

Kg
26.080
1,375
Kg
60.80
Kg
82.32
Liter
17.20
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

35,860
35,860

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

50,017
7,502.55
57,519.55

A. 4.1.2.2 Preparation of 1 m2 of production area of 10cm thick concrete f'c = 14.5 MPa (K 175), slump (12 2) cm/Pembuatan 1
m2 lahan produksi tebal 10cm beton f'c = 14,5 Mpa (K 175), slump (12 2) cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil (Maks. 30mm)
Water/Air

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.165
82,500
L.02
Manday
0.028
99,000
L.03
Manday
0.003
121,000
L.04
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

13,613
2,772
363
968
17,716

Kg
32.600
1,375
Kg
76.00
Kg
102.90
Liter
21.50
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

44,825
44,825

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

62,541
9,381.08
71,921.58

A. 4.1.2.3 Preparation of 1 m2 of production area 12cm thick concrete f'c = 14.5 MPa (K 175), slump (12 2) cm/Pembuatan 1
m2 lahan produksi tebal 12cm beton f'c = 14,5 Mpa (K 175), slump (12 2) cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil (Maks. 30mm)
Water/Air

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.198
82,500
L.02
Manday
0.033
99,000
L.03
Manday
0.003
121,000
L.04
Manday
0.010
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

16,335
3,267
363
1,210
21,175

Kg
32.120
1,375
Kg
91.20
Kg
123.48
Liter
25.80
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

44,165
44,165

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

65,340
9,801.00
75,141.00

A. 4.1.2.4 Preparation of 1 m2 of production area 15cm thick concrete f'c = 14.5 MPa (K 175), slump (12 2) cm/Pembuatan 1
m2 lahan produksi tebal 15cm beton f'c = 14,5 Mpa (K 175), slump (12 2) cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Portland cement/Semen portland
Concrete sand/Pasir beton
Gravel/Kerikil (Maks. 30mm)
Water/Air

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.248
82,500
L.02
Manday
0.041
99,000
L.03
Manday
0.004
121,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

20,460
4,059
484
1,573
26,576

Kg
48.900
1,375
Kg
114
Kg
154.35
Liter
32.25
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

67,238
67,238

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

93,814
14,072.03
107,885.53

A. 4.1.2.5 Preparation of 1 m2 of formwork for the precast concrete slab (5 times)/Pembuatan 1 m2 bekisting untuk plat beton
pracetak ( 5 kali pakai)
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Floorspace thick/Lantai kerja tebal 10cm
Hollow steel/Besi hollow 50.50.3
Wooden rafters/Kayu kaso 5/7
Phenol film 12mm
Formwork oil/Minyak bekisting
Dinabolt dia 12mm (10-15cm)

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.007
82,500
L.02
Manday
0.076
99,000
L.03
Manday
0.008
121,000
L.04
Manday
0.001
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

578
7,524
968
121
9,191

M3
0.080
Kg
9.394
M3
0.005
3,630,000
Lembar
0.08
Liter
0.20
13,200
Bh
3.882
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

18,150
2,640
20,790

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

29,981
4,497.08
34,477.58

A. 4.1.2.6 Preparation of 1 m2 of formwork for the precast concrete slab (10-12 times)/Pembuatan 1 m2 bekisting untuk plat
beton pracetak ( 10-12 kali pakai)
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wooden rafters/Kayu kaso 5/7
Phenol film 12mm
Formwork oil/Minyak bekisting
Dinabolt dia 12mm (10-15cm)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.004
82,500
L.02
Manday
0.038
99,000
L.03
Manday
0.004
121,000
L.04
Manday
0.001
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

330
3,762
484
121
4,697

M3
0.005
3,630,000
Lebar
0.043
Liter
0.20
13,200
Bh
0.693
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

18,150
2,640
20,790

EQUIPMENT/PERALATAN
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

25,487
3,823.05
29,310.05

15% x D

A. 4.1.2.7 Preparation of 1 m2 of formwork for precast concrete columns (10-12 times)/Pembuatan 1 m2 bekisting untuk kolom
beton pracetak ( 10-12 kali pakai)
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wooden rafters/Kayu kaso 5/7
Phenol film 12mm
Formwork oil/Minyak bekisting
Dinabolt dia 12mm (10-15cm)

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.004
82,500
L.02
Manday
0.038
99,000
L.03
Manday
0.004
121,000
L.04
Manday
0.001
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

330
3,762
484
121
4,697

M3
0.005
3,630,000
Lebar
0.043
Liter
0.20
13,200
Bh
0.693
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

18,150
2,640
20,790

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

25,487
3,823.05
29,310.05

A. 4.1.2.8 Installation and opening formwork Plate 1 piece precast concrete components/Pemasangan dan membuka bekisting
1 buah komponen Plat beton pracetak
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.053
82,500
L.02
Manday
0.018
99,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

4,373
1,782
605
6,760

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

6,760
1,013.93
7,773.43

A. 4.1.2.9 Installation and open beam formwork 1 piece precast concrete components/Pemasangan dan membuka bekisting 1
buah komponen Balok beton pracetak
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.089
82,500
L.02
Manday
0.030
99,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,343
2,970
605
10,918

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

10,918
1,637.63
12,555.13

A. 4.1.2.10 Installation and opening Column formwork 1 piece precast concrete components/Pemasangan dan membuka
bekisting 1 buah komponen Kolom beton pracetak
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.071
82,500
L.02
Manday
0.024
99,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
5,858
2,376
605
8,839

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

8,839
1,325.78
10,164.28

A. 4.1.2.11 Pouring / spread for 1 piece plate precast components / Penuangan/menebar untuk 1 buah komponen plat pracetak
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Artisan vibrator/Tukang vibrator
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.064
82,500
L.02
Manday
0.244
99,000
L.02
Manday
0.128
99,000
L.03
Manday
0.034
121,000
L.04
Manday
0.073
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

5,280
24,156
12,672
4,114
8,833
55,055

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

55,055
8,258.25
63,313.25

A. 4.1.2.12 Pouring / spread for 1 piece precast beam components / Penuangan/menebar untuk 1 buah komponen balok
pracetak
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Artisan vibrator/Tukang vibrator
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.069
82,500
L.02
Manday
0.242
99,000
L.02
Manday
0.138
99,000
L.03
Manday
0.037
121,000
L.04
Manday
0.073
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
5,693
23,958
13,662
4,477
8,833
56,623

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

56,623
8,493.38
65,115.88

A. 4.1.2.13 Pouring / spread for 1 piece precast column components / Penuangan/menebar untuk 1 buah komponen kolom
pracetak
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Artisan vibrator/Tukang vibrator
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.069
82,500
L.02
Manday
0.242
99,000
L.02
Manday
0.138
99,000
L.03
Manday
0.037
121,000
L.04
Manday
0.073
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
5,693
23,958
13,662
4,477
8,833
56,623

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

56,623
8,493.38
65,115.88

A. 4.1.2.14 1 pcs plate set up precast components / Mendirikan 1 buah komponen plat pracetak

Nr./No.
A

D
E
F

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Artisan vibrator/Tukang vibrator
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Diesel Fuel/Solar
EQUIPMENT/PERALATAN
Crane rental/Sewa crane
Rent/Sewa pipe support
Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.067
82,500
L.02
Manday
0.067
99,000
L.02
Manday
0.134
99,000
L.03
Manday
0.067
121,000
L.04
Manday
0.067
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Liter
6.676
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN
UH
0.067
UH
1.100
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT
15% x D

Total Price
Total Harga
(RP.)
5,528
6,633
13,266
8,107
8,107
41,641
-

41,641
6,246.08
47,886.58

A. 4.1.2.15 Establishing 1 piece precast beam components/Mendirikan 1 buah komponen balok pracetak

Nr./No.

Description/Uraian

MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Artisan Erection/Tukang Erection
Crane operator/Operator Crane
Crane operator helper/Pembantu operator Crane
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

D
E
F

MATERIALS/BAHAN
Diesel fuel/Solar
EQUIPMENT/PERALATAN
Crane rental/Sewa crane
Rent pipe support/Sewa pipe support

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
L.02
L.02

Manday
0.061
82,500
Manday
0.061
99,000
Manday
0.122
99,000
Manday
0.061
Manday
0.061
L.03
Manday
0.061
121,000
L.04
Manday
0.061
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

5,033
6,039
12,078
7,381
7,381
37,912

Liter
6.11
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

UH
0.061
UH
1.100
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

6,039
905.85
6,944.85

15% x D

A. 4.1.2.16 Establishing 1 piece precast column components / Mendirikan 1 buah komponen kolom pracetak

Nr./No.

Description/Uraian

MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Artisan Erection/Tukang Erection
Crane operator/Operator Crane
Crane operator helper/Pembantu operator Crane
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

D
E
F

MATERIALS/BAHAN
Diesel fuel/Solar
EQUIPMENT/PERALATAN
Crane rental/Sewa crane
Rent pipe support/Sewa pipe support

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
L.02
L.02

Manday
0.083
82,500
Manday
0.083
99,000
Manday
0.166
99,000
Manday
0.083
Manday
0.083
L.03
Manday
0.083
121,000
L.04
Manday
0.083
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

6,848
8,217
16,434
10,043
10,043
51,585

Liter
8.277
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

UH
0.083
UH
2.20
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

51,585
7,737.68
59,322.18

15% x D

A. 4.1.2.17 1 piece shunt plate precast component ( 20m) / Melangsir 1 buah komponen plat pracetak ( 20m)

Nr./No.

Description/Uraian

MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Crane operator/Operator Crane
Crane operator helper/Pembantu operator Crane

MATERIALS/BAHAN
Diesel fuel/Solar

EQUIPMENT/PERALATAN
Crane rental/Sewa crane

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
L.02

Manday
0.019
82,500
Manday
0.038
99,000
Manday
0.019
Manday
0.019
MANPOWER TOTAL / JUMLAH TENAGA KERJA

1,568
3,762
5,330

Liter
1.897
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

UH
0.019
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

5,330
799.43
6,128.93

15% x D

A. 4.1.2.18 Shunt 1 piece precast beam components ( 20m)/Melangsir 1 buah komponen balok pracetak ( 20m)

Nr./No.

Description/Uraian

MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Crane operator/Operator Crane
Crane operator helper/Pembantu operator Crane

MATERIALS/BAHAN
Diesel fuel/Solar

EQUIPMENT/PERALATAN
Crane rental/Sewa crane

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
L.02

Manday
0.019
82,500
Manday
0.038
99,000
Manday
0.019
Manday
0.019
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Liter
1.897
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN
UH
0.019
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT
15% x D

Total Price
Total Harga
(RP.)
1,568
3,762
5,330
-

5,330
799.43
6,128.93

A. 4.1.2.19 1 piece shunt component precast column ( 20m)/Melangsir 1 buah komponen kolom pracetak ( 20m)

Nr./No.

Description/Uraian

MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Crane operator/Operator Crane
Crane operator helper/Pembantu operator Crane

MATERIALS/BAHAN
Diesel fuel/Solar

EQUIPMENT/PERALATAN
Crane rental/Sewa crane

D
E
F

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
L.02

Manday
0.019
82,500
Manday
0.038
99,000
Manday
0.019
Manday
0.019
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
1,568
3,762
5,330

Liter
1.897
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN
UH
0.019
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

5,330
799.43
6,128.93

A. 4.1.2.20 Ingredients 1 m3 grouting mixture/Bahan 1 m3 grouting campuran

Nr./No.

Description/Uraian

MANPOWER/TENAGA

MATERIALS/BAHAN
Cement grout/Semen grout
Screening
Water/Air

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

MANPOWER TOTAL / JUMLAH TENAGA KERJA

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Kg
1200
Kg
650
Liter
350
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

15% x D

A. 4.1.2.21 1 m3 grouting materials do not mix/Bahan 1 m3 grouting tidak campuran

Nr./No.

Description/Uraian

MANPOWER/TENAGA

MATERIALS/BAHAN
Cement grout/Semen grout
Water/Air

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

MANPOWER TOTAL / JUMLAH TENAGA KERJA

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Kg
1850
Liter
400
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

15% x D

A. 4.1.2.22 Wages do 1 at a join point grouting precast/Upah melakukan 1 titik grouting pada join pracetak

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.02
Manday
0.367
99,000
L.03
Manday
0.074
121,000
L.04
Manday
0.037
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
36,333
8,954
4,477
49,764

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

49,764
7,464.60
57,228.60

A. 4.1.2.23 Installation of 1 point Formwork join precast/Pemasangan 1 titik Bekisting join pracetak

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wooden rafters/Kayu kaso 5/7
Board cast/Papan cor
Nail/Paku 5 - 7cm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.147
82,500
L.02
Manday
0.147
99,000
L.03
Manday
0.015
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

12,128
14,553
1,815
605
29,101

M3
0.012
3,630,000
M3
0.004
1,650,000
Kg
0.264
16,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

43,560
6,600
4,356
54,516

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

83,617
12,542.48
96,158.98

15% x D

A. 4.1.2.24 Wages 1 point Join with Sling/Upah 1 titik Join dengan Sling

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Vulcan/Tukang Besi
Foreman/Mandor

MATERIALS/BAHAN

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.220
82,500
L.02
Manday
0.220
99,000
L.02
Manday
0.220
99,000
L.04
Manday
0.011
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

18,150
21,780
21,780
1,331
63,041

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

63,041
9,456.15
72,497.15

15% x D

A. 4.2.1 WORK UNIT PRICE IRON AND ALUMINIUM/HARGA SATUAN PEKERJAAN BESI DAN ALUMINIUM
A. 4.2.1.1 Installation of 1 kg of iron profile/Pemasangan 1 kg besi profil

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Construction welder/Tukang Las Konstruksi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Iron propile/Besi Profil

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.060
82,500
L.03
Manday
0.060
121,000
L.03
Manday
0.006
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

4,950
7,260
726
363
13,299

Kg
1.150
18,700
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

21,505
21,505

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

34,804
5,220.60
40,024.60

A. 4.2.1.2 Installation of 1 kg steel frame easel IWF/Pemasangan 1 kg rangka kuda-kuda baja IWF

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Construction welder/Tukang Las Konstruksi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
IWF steel/Besi Baja IWF

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.060
82,500
L.03
Manday
0.060
121,000
L.03
Manday
0.006
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Kg
1.150
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
4,950
7,260
726
363
13,299
18,700
18,700

31,999
4,799.85
36,798.85

A. 4.2.1.3 Workmanship 100kg assembly jobs/Pengerjaan 100kg pekerjaan perakitan

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Construction welder/Tukang Las Konstruksi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Diesel fuel/Solar
Lubricant/Minyak pelumas

EQUIPMENT/PERALATAN
1. Rental tool/Sewa alat

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.100
82,500
L.03
Manday
0.100
121,000
L.03
Manday
0.001
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Liter
1.000
Liter
0.100
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN
Jam
0.800
126,500.00
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT
15% x D

Total Price
Total Harga
(RP.)
8,250
12,100
121
605
21,076
101,200
101,200
122,276
18,341.40
140,617.40

A. 4.2.1.4 Preparation of 1 m2 metal doors double 2mm thick steel plate, steel frame elbow/Pembuatan 1 m2 pintu besi plat
baja tebal 2mm rangkap, rangka baja siku
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Ordinary welder/Tukang Las biasa
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Brackets/Besi siku L.30.30.3
Iron steel plate/Besi plat baja
Welding wire/Kawat las

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.050
82,500
L.03
Manday
1.050
121,000
L.03
Manday
0.105
121,000
L.04
Manday
0.052
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

86,625
127,050
12,705
6,292
232,672

Kg
15.000
16,500
Kg
32.800
Kg
0.050
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

247,500
247,500

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

480,172
72,025.80
552,197.80

A. 4.2.1.5 The execution of 10cm electric welding with welding/Pengerjaan 10cm pengelasan dengan las listrik

Nr./No.

Description/Uraian

MANPOWER/TENAGA
Labour/Pekerja
Blacksmith construction/Tukang Besi Konstruksi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

D
E
F

MATERIALS/BAHAN
Electric welding wire/Kawat las listrik
Diesel fuel/Solar
Lubricant/Minyak pelumas
EQUIPMENT/PERALATAN
Rental tool/Sewa alat

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.040
82,500
L.03
Manday
0.020
121,000
L.03
Manday
0.002
121,000
L.04
Manday
0.002
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
3,300
2,420
242
242
6,204

Kg
0.400
Liter
0.300
Liter
0.040
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN
Jam
0.170
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

6,204
930.60
7,134.60

A. 4.2.1.6 Preparation of 1 m2 scuare iron window frame tube (25 x 5) cm/Pembuatan 1 m2 rangka jendela besi scuare tube (25
x 5) cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Ordinary welder/Tukang Las Biasa
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Scuare iron tube/Besi scuare tube
Lis iron glass/Besi lis kaca (1 x 1)cm
Welding/Pengelasan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.650
82,500
L.03
Manday
0.650
121,000
L.03
Manday
0.065
121,000
L.04
Manday
0.032
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
53,625
78,650
7,865
3,872
144,012

M
4.760
M
4.522
cm
20
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

144,012
21,601.80
165,613.80

A. 4.2.1.7 Installation of 1 m2 iron door rolling door/Pemasangan 1 m2 pintu rolling door besi

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Ordinary welder/Tukang Las Biasa
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Metal roll door/Pintu gulung besi

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.200
82,500
L.03
Manday
1.200
121,000
L.03
Manday
0.120
121,000
L.04
Manday
0.006
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M2
1.000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
99,000
145,200
14,520
726
259,446
-

259,446
38,916.90
298,362.90

A. 4.2.1.8 Installation of 1 m2 folding doors (folding door) plastic/PVC / Pemasangan 1 m2 pintu lipat (folding door) bahan
plastik/PVC
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Skill Labour/Tukang
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

MATERIALS/BAHAN
Folding doors/Pintu lipat

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.440
82,500
L.03
Manday
0.440
121,000
L.03
Manday
0.440
121,000
L.04
Manday
0.022
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

36,300
53,240
53,240
2,662
145,442

M2
1.000
418,000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

418,000
418,000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

563,442
84,516.30
647,958.30

A. 4.2.1.9 Installation of 1 m2 sunscreen alluminium/Pemasangan 1 m2 sunscreen alluminium

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Skill Labour/Tukang
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

MATERIALS/BAHAN
Sunscreen alluminium

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.080
82,500
L.03
Manday
0.800
121,000
L.03
Manday
0.080
121,000
L.04
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

6,600
96,800
9,680
484
113,564

M2
1.000
412,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

412,500
412,500

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

526,064
78,909.60
604,973.60

A. 4.2.1.10 Installation of 1 m2 rolling door alluminium/Pemasangan 1 m2 rolling door alluminium

Nr./No.

Description/Uraian

MANPOWER/TENAGA
Labour/Pekerja
Handyman special /Tukang khusus Alluminium
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

MATERIALS/BAHAN
Rolling door alluminium

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.000
82,500
L.03
Manday
1.000
121,000
L.03
Manday
0.100
121,000
L.04
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
82,500
121,000
12,100
6,050
221,650

M2
1.000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

221,650
33,247.50
254,897.50

A. 4.2.1.11 Installation of 1 m alluminium door frames/Pemasangan 1 m kusen pintu alluminium

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Handyman special/Tukang khusus Alluminium
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Rolling door alluminium
Skrup fixer
Sealant

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.043
82,500
L.03
Manday
0.043
121,000
L.03
Manday
0.0043
121,000
L.04
Manday
0.0021
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M
1.100
Buah
2.000
Tube
0.060
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
3,548
5,203
520
254
9,525
-

9,525
1,428.74
10,953.64

A. 4.2.1.12 Installation of 1 m2 alluminium door 8cm wide strips/Pemasangan 1 m2 pintu alluminium strip lebar 8cm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Handyman special/Tukang khusus Alluminium
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Alluminium profiles/Propil alluminium
Alluminium strip

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.085
82,500
L.03
Manday
0.085
121,000
L.03
Manday
0.0085
121,000
L.04
Manday
0.0042
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
7,013
10,285
1,029
508
18,834

M
4.400
M
14.600
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

18,834
2,825.13
21,659.33

A. 4.2.1.13 Installation of 1 m2 glass door frame alluminium/Pemasangan 1 m2 pintu kaca rangka alluminium

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Alluminium/glass artisan / Tukang
Alluminium/Kaca
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Alluminium Profiles/Propil alluminium
Glass profiles/Profil kaca
Sealant

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

L.01
L.03

Manday
Manday

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

0.085
0.085

Total Price
Total Harga
(RP.)

82,500
121,000

7,013
10,285

L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

1,089
605
18,992

M
4.400
M
4.500
Tube
0.270
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

18,992
2,848.73
21,840.23

A. 4.2.1.14 Installation of 1 m2 venetions blinds and vertical blinds/Pemasangan 1 m2 venetions blinds dan vertical blinds
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Skill Labour/Tukang
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.350
82,500
L.03
Manday
0.350
121,000
L.03
Manday
0.035
121,000
L.04
Manday
0.018
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Venetions blinds dan vertical blinds
(curtain/tirai)

M2

Total Price
Total Harga
(RP.)
28,875
42,350
4,235
2,178
77,638

1.000

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

77,638
11,645.70
89,283.70

A. 4.2.1.15 Installation of 1 m2 strip bars (2 x 3) mm/Pemasangan 1 m2 terali besi strip (2 x 3) mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Chief of Skill Labour/Tukang Las
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Iron strips/Besi strip
Welding/Pengelasan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.670
82,500
L.03
Manday
1.670
121,000
L.03
Manday
0.167
121,000
L.04
Manday
0.083
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

137,775
202,070
20,207
10,043
370,095

Kg
6.177
11,000
cm
27.080
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

67,947
67,947

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

438,042
65,706.30
503,748.30

A. 4.2.1.16 Installation of 1 m2 of mosquito nets/Pemasangan 1 m2 kawat nyamuk

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Skill Labour/Tukang
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Mosquito net/Kawat nyamuk
Welding/Pengelasan
Steel strip/Baja strip (0.2 x 2) cm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.670
82,500
L.03
Manday
1.670
121,000
L.03
Manday
0.167
121,000
L.04
Manday
0.083
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

137,775
202,070
20,207
10,043
370,095

M2
1.100
19,800
cm
11.11
Kg
1.716
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

21,780
21,780

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

391,875
58,781.25
450,656.25

A. 4.2.1.17 Installation of 1 m2 window Naco & tralis/Pemasangan 1 m2 jendela naco & tralis

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Skill Labour/Tukang
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Nako window/Jendela nako (rangka + kaca 5 mm)
Nail screw/Paku skrup 1cm - 2.5cm
Steel strip/Baja strip

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.200
82,500
L.03
Manday
0.200
121,000
L.03
Manday
0.020
121,000
L.04
Manday
0.001
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

16,500
24,200
2,420
121
43,241

M2
1.100
902,000
Buah
10.00
M
7.000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

992,200
992,200

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

1,035,441
155,316.15
1,190,757.15

A. 4.2.1.18 Pemasangan 1 m2 talang datar/jurai seng bjls 28 lebar 90cm/Pemasangan 1 m2 talang datar/jurai seng bjls 28 lebar
90cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Skill Labour/Tukang
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Zinc plate/Seng plat
Nail/Paku 1cm - 2.5 cm
Class Wooden board/Papan kayu kelas II or/atau III

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.200
82,500
L.03
Manday
0.200
121,000
L.03
Manday
0.020
121,000
L.04
Manday
0.001
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

16,500
24,200
2,420
121
43,241

M
1.050
38,500
Kg
0.015
19,800
M3
0.019
3,630,000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

40,425
297
68,970
109,692

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

152,933
22,939.95
175,872.95

A. 4.2.1.19 Installation of 1 m gutters half circle D-15cm, width 30 BjLS zinc plate 45cm/Pemasangan 1 m talang 1/2 lingkaran
D-15cm, seng plat bjls 30 lebar 45cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Skill Labour/Tukang
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Zinc plate/Seng plat
Nail/Paku 1cm - 2.5 cm
Iron strips/besi strip

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.150
82,500
L.03
Manday
0.300
121,000
L.03
Manday
0.030
121,000
L.04
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

12,375
36,300
3,630
968
53,273

M
1.050
22,000
Kg
0.010
19,800
Kg
0.500
11,000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

23,100
198
5,500
28,798

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

82,071
12,310.65
94,381.65

A. 4.2.1.20 Installation of 1 m2 1x40.40.2mm hollow steel frame, 60 x 120 cm modules, partition walls/Pemasangan 1 m2
rangka besi hollow 1x40.40.2mm, modul 60 x 120 cm, dinding partisi
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Vulcan/Tukang Besi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.250
82,500
L.03
Manday
0.250
121,000
L.03
Manday
0.025
121,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Hollow metal frame/Rangka metal hollow 40.40.2 mm
Accessories/Aksesoris (cultivation, weld
etc./perkuatan, las dll)

M
Kg

Total Price
Total Harga
(RP.)
20,625
30,250
3,025
1,573
55,473

3.500
100% x rangka

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

55,473
8,320.95
63,793.95

A. 4.2.1.21 Installation of 1 m2 1x40.40.2mm hollow steel frame, 60 x 60 cm modules, ceiling/Pemasangan 1 m2 rangka besi
hollow 1x40.40.2mm, modul 60 x 60 cm, plafon
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Vulcan/Tukang Besi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.350
82,500
L.02
Manday
0.350
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.018
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Hollow metal frame/Rangka metal hollow 40.40.2 mm
Accessories/Assesoris (cultivation, weld
etc./perkuatan, las dll)

M1
Ls

Total Price
Total Harga
(RP.)
28,875
34,650
4,235
2,178
69,938

4.000
100% x rangka

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

69,938
10,490.70
80,428.70

A. 4.4.1 WALL UNIT PRICE WORK SPOUSE/HARGA SATUAN PEKERJAAN PASANGAN DINDING
A. 4.4.1.1 Installation of 1 m2 red brick wall (5x11x22) 1 cm thick stone mix 1SP: 2PP/Pemasangan 1 m2 dinding bata merah
(5x11x22) cm tebal 1 batu campuran 1SP : 2PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.600
82,500
L.02
Manday
0.200
99,000
L.03
Manday
0.020
121,000
L.04
Manday
0.030
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

49,500
19,800
2,420
3,630
75,350

M3
140.000
Kg
43.50
1,375
M3
0.08
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

59,813
8,140
67,953

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

143,303
21,495.38
164,797.88

A. 4.4.1.2 Installation of 1 m2 red brick wall (5x11x22) 1 cm thick stone mix 1SP: 3PP/Pemasangan 1 m2 dinding bata merah
(5x11x22) cm tebal 1 batu campuran 1SP : 3PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.600
82,500
L.02
Manday
0.200
99,000
L.03
Manday
0.020
121,000
L.04
Manday
0.030
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

49,500
19,800
2,420
3,630
75,350

M3
140.000
Kg
32.950
1,375
M3
0.091
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

45,306
9,259
54,566

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

129,916
19,487.33
149,402.83

A. 4.4.1.3 Installation of 1 m2 red brick wall (5x11x22) 1 cm thick stone mix 1SP: 4PP/Pemasangan 1 m2 dinding bata merah
(5x11x22) cm tebal 1 batu campuran 1SP : 4PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.600
82,500
L.02
Manday
0.200
99,000
L.03
Manday
0.020
121,000
L.04
Manday
0.030
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

49,500
19,800
2,420
3,630
75,350

M3
140.000
Kg
26.550
1,375
M3
0.093
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

36,506
9,463
45,969

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

121,319
18,197.85
139,516.85

A. 4.4.1.4 Installation of 1 m2 red brick wall (5x11x22) 1 cm thick stone mix 1SP: 5PP/Pemasangan 1 m2 dinding bata merah
(5x11x22) cm tebal 1 batu campuran 1SP : 5PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.600
82,500
L.02
Manday
0.200
99,000
L.03
Manday
0.020
121,000
L.04
Manday
0.030
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

49,500
19,800
2,420
3,630
75,350

M3
140.000
Kg
22.200
1,375
M3
0.102
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

30,525
10,379
40,904

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

116,254
17,438.03
133,691.53

A. 4.4.1.5 Installation of 1 m2 red brick wall (5x11x22) 1 cm thick stone mix 1SP: 6PP/Pemasangan 1 m2 dinding bata merah
(5x11x22) cm tebal 1 batu campuran 1SP : 6PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.600
82,500
L.02
Manday
0.200
99,000
L.03
Manday
0.020
121,000
L.04
Manday
0.030
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

49,500
19,800
2,420
3,630
75,350

M3
140.000
Kg
18.500
1,375
M3
0.122
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

25,438
12,414
37,851

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

113,201
16,980.15
130,181.15

A. 4.4.1.6 Installation of 1 m2 red brick wall (5x11x22) 1 cm thick stone mix 1SP: 3KP: 10pp/Pemasangan 1 m2 dinding bata
merah (5x11x22) cm tebal 1 batu campuran 1SP : 3KP : 10PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen Portland
Lime outages/Kapur Padam
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.600
82,500
L.02
Manday
0.200
99,000
L.03
Manday
0.020
121,000
L.04
Manday
0.030
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

49,500
19,800
2,420
3,630
75,350

M3
140.000
Kg
10.080
1,375
M3
0.0275
M3
0.0925
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

13,860
9,412
23,272

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

98,622
14,793.28
113,415.16

A. 4.4.1.7 Installation of 1 m2 red brick wall (5x11x22) cm thick half stone mix 1SP: 2PP/Pemasangan 1 m2 dinding bata merah
(5x11x22) cm tebal 1/2 batu campuran 1SP : 2PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

24,750
9,900
1,210
1,815
37,675

M3
70.000
Kg
18.950
1,375
M3
0.0380
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

26,056
3,867
29,923

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

67,598
10,139.66
77,737.41

A. 4.4.1.8 Installation of 1 m2 red brick wall (5x11x22) cm thick half stone mix 1SP: 3PP/Pemasangan 1 m2 dinding bata merah
(5x11x22) cm tebal 1/2 batu campuran 1SP : 3PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

24,750
9,900
1,210
1,815
37,675

M3
70.000
Kg
14.370
1,375
M3
0.040
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

19,759
4,070
23,829

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

61,504
9,225.56
70,729.31

A. 4.4.1.9 Installation of 1 m2 red brick wall (5x11x22) cm thick half stone mix 1SP: 4PP/Pemasangan 1 m2 dinding bata merah
(5x11x22) cm tebal 1/2 batu campuran 1SP : 4PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

24,750
9,900
1,210
1,815
37,675

M3
70.000
Kg
11.500
1,375
M3
0.043
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

15,813
4,375
20,188

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

57,863
8,679.41
66,542.16

A. 4.4.1.10 Installation of 1 m2 red brick wall (5x11x22) cm thick half stone mix 1SP: 5PP/Pemasangan 1 m2 dinding bata
merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 5PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

24,750
9,900
1,210
1,815
37,675

M3
70.000
Kg
9.680
1,375
M3
0.045
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

13,310
4,579
17,889

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

55,564
8,334.56
63,898.31

A. 4.4.1.11 Installation of 1 m2 red brick wall (5x11x22) cm thick half stone mix 1SP: 6PP/Pemasangan 1 m2 dinding bata
merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 6PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

24,750
9,900
1,210
1,815
37,675

M3
70.000
Kg
8.320
1,375
M3
0.049
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

11,440
4,986
16,426

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

54,101
8,115.11
62,215.86

A. 4.4.1.12 Installation of 1 m2 red brick wall (5x11x22) cm thick half stone mix 1SP: 8PP/Pemasangan 1 m2 dinding bata
merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 8PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

24,750
9,900
1,210
1,815
37,675

M3
70.000
Kg
6.500
1,375
M3
0.050
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

8,938
5,088
14,025

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

51,700
7,755.00
59,455.00

A. 4.4.1.13 Installation of 1 m2 red brick wall (5x11x22) cm thick half stone mix 1SP: 3KP: 10pp/Pemasangan 1 m2 dinding bata
merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 3KP : 10PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen Portland
Lime outages/Kapur Padam
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

24,750
9,900
1,210
1,815
37,675

M3
70.000
Kg
4.500
1,375
M3
0.015
M3
0.050
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

6,188
5,088
11,275

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

48,950
7,342.50
56,292.50

A. 4.4.1.14 Installation of 1 m2 red brick wall (5x11x22) cm thick half stone mix 1SM: 1KP: 1PP/Pemasangan 1 m2 dinding bata
merah (5x11x22) cm tebal 1/2 batu campuran 1SM : 1KP : 1PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata Merah
Red cement/Semen Merah
Lime outages/Kapur Padam
Sand plugPasir Pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

24,750
9,900
1,210
1,815
37,675

M3
70.000
Kg
0.018
M3
0.018
M3
0.018
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,832
1,832

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

39,507
5,925.98
45,432.48

A. 4.4.1.15 Installation of 1 m2 red brick wall (5x11x22) cm thick half stone mix 1SM: 1KP: 2PP/Pemasangan 1 m2 dinding bata
merah (5x11x22) cm tebal 1/2 batu campuran 1SM : 1KP : 2PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata Merah
Red cement/Semen Merah
Lime outages/Kapur Padam
Sand plugPasir Pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

24,750
9,900
1,210
1,815
37,675

M3
70.000
Kg
0.014
M3
0.014
M3
0.028
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

2,849
2,849

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

40,524
6,078.60
46,602.60

A. 4.4.1.16 1 m2 of wall mounting conblock HB20 mix 1 SP: 3PP/Pemasangan 1 m2 dinding conblock HB20 campuran 1 SP :
3PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
HB-20
Portland cement/Semen Portland
Sand plugPasir Pasang
Iron anchor/Besi angkur diameter 8

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.350
82,500
L.02
Manday
0.150
99,000
L.03
Manday
0.015
121,000
L.04
Manday
0.018
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

28,875
14,850
1,815
2,178
47,718

M3
12.500
Kg
30.320
1,375
M3
0.728
101,750
Kg
0.280
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

41,690
74,074
115,764

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

163,482
24,522.30
188,004.30

A. 4.4.1.17 1 m2 of wall mounting conblock HB20 mix 1 SP: 4PP/Pemasangan 1 m2 dinding conblock HB20 campuran 1 SP :
4PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
HB-20
Portland cement/Semen Portland
Sand plugPasir Pasang
Iron anchor/Besi angkur diameter 8

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.350
82,500
L.02
Manday
0.150
99,000
L.03
Manday
0.015
121,000
L.04
Manday
0.018
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

28,875
14,850
1,815
2,178
47,718

M3
12.500
Kg
24.260
1,375
M3
0.772
101,750
Kg
0.280
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

33,358
78,551
111,909

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

159,627
23,943.98
183,570.48

A. 4.4.1.18 1 m2 of wall mounting conblock HB15 mix 1 SP: 3PP/Pemasangan 1 m2 dinding conblock HB15 campuran 1 SP :
3PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
HB-15
Portland cement/Semen Portland
Sand plugPasir Pasang
Iron anchor/Besi angkur diameter 8

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.320
82,500
L.02
Manday
0.120
99,000
L.03
Manday
0.012
121,000
L.04
Manday
0.016
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

26,400
11,880
1,452
1,936
41,668

M3
12.500
Kg
22.740
1,375
M3
0.550
101,750
Kg
0.280
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

31,268
55,963
87,230

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

128,898
19,334.70
148,232.70

A. 4.4.1.19 1 cm2 wall mounting conblock HB15 mix 1 SP: 4PP/Pemasangan 1 cm2 dinding conblock HB15 campuran 1 SP :
4PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
HB-15
Portland cement/Semen Portland
Sand plugPasir Pasang
Iron anchor/Besi angkur diameter 8

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.320
82,500
L.02
Manday
0.120
99,000
L.03
Manday
0.012
121,000
L.04
Manday
0.016
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

26,400
11,880
1,452
1,936
41,668

M3
12.500
Kg
18.200
1,375
M3
0.582
101,750
Kg
0.280
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

25,025
59,219
84,244

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

125,912
18,886.73
144,798.23

A. 4.4.1.20 1 cm2 wall mounting conblock HB10 mix 1 SP: 3PP/Pemasangan 1 cm2 dinding conblock HB10 campuran 1 SP :
3PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
HB-10
Portland cement/Semen Portland
Sand plugPasir Pasang
Iron anchor/Besi angkur diameter 8

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

24,750
9,900
1,210
1,815
37,675

M3
12.500
Kg
15.160
1,375
M3
0.364
101,750
Kg
0.280
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

20,845
37,037
57,882

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

95,557
14,333.55
109,890.55

A. 4.4.1.21 1 cm2 wall mounting conblock HB10 mix 1 SP: 4PP/Pemasangan 1 cm2 dinding conblock HB10 campuran 1 SP :
4PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
HB-10
Portland cement/Semen Portland
Sand plugPasir Pasang
Iron anchor/Besi angkur diameter 8

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

24,750
9,900
1,210
1,815
37,675

M3
12.500
Kg
12.130
1,375
M3
0.388
101,750
Kg
0.280
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

16,679
39,479
56,158

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

93,833
14,074.91
107,907.66

A. 4.4.1.22 Installation of 1 cm2 wall overlay (rooster) 12x11x24 mix 1 SP: 3PP/Pemasangan 1 cm2 dinding terawang (rooster)
12x11x24 campuran 1 SP : 3PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Brick Rooster/Bata Rooster
Portland cement/Semen Portland
Sand plug/Pasir Pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

24,750
9,900
1,210
1,815
37,675

M3
30.000
Kg
11.000
1,375
M3
0.035
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

3,561
3,561

41,236
6,185.44
47,421.69

A. 4.4.1.23 Installation of 1 cm2 wall overlay (rooster) 12x11x24 mix 1 SP: 4PP/Pemasangan 1 cm2 dinding terawang (rooster)
12x11x24 campuran 1 SP : 4PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Hollow brick/Bata Berongga
Potland cement/Semen Portland
Sand plug/Pasir Pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

24,750
9,900
1,210
1,815
37,675

M3
30.000
Kg
11.000
1,375
M3
0.035
18,013
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

15,125
630
15,755

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

53,430
8,014.57
61,445.00

15% x D

A. 4.4.1.24 Installation of 1 cm2 hollow brick walls exposes 12x11x24 mix 1 SP: 3PP/Pemasangan 1 cm2 dinding bata
berongga ekspose 12x11x24 campuran 1 SP : 3PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Brick rooster/Bata Rooster
Portland cement/Semen Portland
Sand plug/Pasir Pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.02
Manday
0.150
99,000
L.03
Manday
0.015
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

24,750
14,850
1,815
1,815
43,230

M3
70.000
Kg
14.000
1,375
M3
0.032
96,800
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

19,250
3,098
22,348

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

65,578
9,836.64
75,414.24

15% x D

A. 4.4.2 WORK UNIT PRICE PLASTERING/HARGA SATUAN PEKERJAAN PLESTERAN


A. 4.4.2.1 Installation of 1 m2 of stucco 1SP: 15mm thick 1PP/Pemasangan 1 m2 plesteran 1SP : 1PP tebal 15mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.03
Manday
0.150
121,000
L.03
Manday
0.015
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Kg
M3

15.504
0.016

24,750
18,150
1,815
1,815
46,530

1,375
101,750

21,318
1,628

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

22,946

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

69,476
10,421.40
79,897.40

15% x D

A. 4.4.2.2 Installation of 1 m2 of stucco 1SP: 2PP, 15mm thick/Pemasangan 1 m2 plesteran 1SP : 2PP tebal 15mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.300
82,500
L.03
Manday
0.150
121,000
L.03
Manday
0.015
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Kg
M3

10.224
0.020

1,375
101,750

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
24,750
18,150
1,815
1,815
46,530
14,058
2,035
16,093

62,623
9,393.45
72,016.45

A. 4.4.2.3 Installation of 1 m2 of stucco 1SP: 3PP, 15mm thick/Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.03
Manday
0.150
121,000
L.03
Manday
0.015
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Kg
M3

7.776
0.023

24,750
18,150
1,815
1,815
46,530

1,375
101,750

10,692
2,340

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

13,032

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

59,562
8,934.34
68,496.59

15% x D

A. 4.4.2.4 Installation of 1 m2 of stucco 1SP: 4PP, 15mm thick/Pemasangan 1 m2 plesteran 1SP : 4PP, tebal 15mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.03
Manday
0.150
121,000
L.03
Manday
0.015
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Kg
M3

6.240
0.024

24,750
18,150
1,815
1,815
46,530

1,375
101,750

8,580
2,442

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

11,022

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

57,552
8,632.80
66,184.80

15% x D

A. 4.4.2.5 Installation of 1 m2 of stucco 1SP: 5PP, 15mm thick/Pemasangan 1 m2 plesteran 1SP : 5PP, tebal 15mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.03
Manday
0.150
121,000
L.03
Manday
0.015
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Kg
M3

5.184
0.026

24,750
18,150
1,815
1,815
46,530

1,375
101,750

7,128
2,646

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

9,774

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

56,304
8,445.53
64,749.03

15% x D

A. 4.4.2.6 Installation of 1 m2 of stucco 1SP: 6PP, 15mm thick/Pemasangan 1 m2 plesteran 1SP : 6PP, tebal 15mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.300
82,500
L.03
Manday
0.150
121,000
L.03
Manday
0.015
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Kg
M3

4.416
0.027

1,375
101,750

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
24,750
18,150
1,815
1,815
46,530
6,072
2,747
8,819

55,349
8,302.39
63,651.64

A. 4.4.2.7 Installation of 1 m2 of stucco 1SP: 7PP, 15mm thick/Pemasangan 1 m2 plesteran 1SP : 7PP tebal 15mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.03
Manday
0.150
121,000
L.03
Manday
0.015
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Kg
M3

3.936
0.028

24,750
18,150
1,815
1,815
46,530

1,375
101,750

5,412
2,849

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

8,261

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

54,791
8,218.65
63,009.65

15% x D

A. 4.4.2.8 Installation of 1 m2 of stucco 1SP: 8PP, 15mm thick/Pemasangan 1 m2 plesteran 1SP : 8PP, tebal 15mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.300
82,500
L.03
Manday
0.150
121,000
L.03
Manday
0.015
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Kg
M3

3.456
0.029

Total Price
Total Harga
(RP.)
24,750
18,150
1,815
1,815
46,530

1,375
101,750

4,752
2,951

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

7,703

54,233
8,134.91
62,367.66

A. 4.4.2.9 Installation of 1 m2 of stucco 1SP: 1/2KP: 3PP, 15mm thick/Pemasangan 1 m2 plesteran 1SP : 1/2KP : 3PP tebal
15mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Lime outages/Kapur Padam
3. Sand plug/Pasir Pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.360
82,500
L.03
Manday
0.120
121,000
L.03
Manday
0.012
121,000
L.04
Manday
0.018
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

29,700
14,520
1,452
2,178
47,850

Kg
5.760
1,375
M3
0.003
M3
0.013
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

7,920
1,323
9,243

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

57,093
8,563.91
65,656.66

A. 4.4.2.10 Installation of 1 m2 of stucco 1SP: 2KP: 8PP, 15mm thick/Pemasangan 1 m2 plesteran 1SP : 2KP : 8PP tebal 15mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Lime outages/Kapur Padam
3. Sand plug/Pasir Pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.360
82,500
L.03
Manday
0.120
121,000
L.03
Manday
0.012
121,000
L.04
Manday
0.018
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

29,700
14,520
1,452
2,178
47,850

Kg
3.000
1,375
M3
0.005
M3
0.020
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

4,125
2,035
6,160

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

54,010
8,101.50
62,111.50

A. 4.4.2.11 Installation of 1 m2 of stucco 1SM: 1KP: 1PP, 15mm thick/Pemasangan 1 m2 plesteran 1SM : 1KP : 1PP tebal 15mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
1. Red cement/Semen Merah
2. Lime outages/Kapur Padam
3. Sand plug/Pasir Pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.360
82,500
L.03
Manday
0.120
121,000
L.03
Manday
0.012
121,000
L.04
Manday
0.018
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

29,700
14,520
1,452
2,178
47,850

M3
0.009
41,800
M3
0.009
M3
0.009
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

376
916
1,292

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

49,142
7,371.29
56,513.24

15% x D

A. 4.4.2.12 Installation of 1 m2 of stucco 1SM: 1KP: 2PP, 15mm thick/Pemasangan 1 m2 plesteran 1SM : 1KP : 2PP tebal 15mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
1. Red cement/Semen Merah
2. Lime outages/Kapur Padam
3. Sand plug/Pasir Pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.360
82,500
L.03
Manday
0.120
121,000
L.03
Manday
0.012
121,000
L.04
Manday
0.018
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

29,700
14,520
1,452
2,178
47,850

M3
0.007
41,800
M3
0.007
M3
0.015
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

293
1,526
1,819

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

49,669
7,450.33
57,119.18

15% x D

A. 4.4.2.13 Installation of 1 m2 of stucco 1SP: 1PP, 20mm thick/Pemasangan 1 m2 plesteran 1SP : 1PP tebal 20mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.400
82,500
L.03
Manday
0.200
121,000
L.03
Manday
0.020
121,000
L.04
Manday
0.022
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Kg
M3

13.632
0.027

33,000
24,200
2,420
2,662
62,282

1,375
101,750

18,744
2,747

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

21,491

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

83,773
12,565.99
96,339.24

15% x D

A. 4.4.2.14 Installation of 1 m2 of stucco 1SP: 3PP, 20mm thick/Pemasangan 1 m2 plesteran 1SP : 3PP tebal 20mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.260
82,500
L.03
Manday
0.200
121,000
L.03
Manday
0.020
121,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Kg
M3

10.368
0.031

1,375
101,750

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
21,450
24,200
2,420
1,573
49,643
14,256
3,154
17,410

67,053
10,057.99
77,111.24

A. 4.4.2.15 Installation of 1 m2 of stucco 1SP: 4PP, 20mm thick/Pemasangan 1 m2 plesteran 1SP : 4PP tebal 20mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.400
82,500
L.03
Manday
0.200
121,000
L.03
Manday
0.020
121,000
L.04
Manday
0.022
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Kg
M3

8.320
0.032

33,000
24,200
2,420
2,662
62,282

1,375
101,750

11,440
3,256

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

14,696

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

76,978
11,546.70
88,524.70

15% x D

A. 4.4.2.16 Installation of 1 m2 of stucco 1SP: 5PP, 20mm thick/Pemasangan 1 m2 plesteran 1SP : 5PP tebal 20mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.400
82,500
L.03
Manday
0.200
121,000
L.03
Manday
0.020
121,000
L.04
Manday
0.022
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Kg
M3

6.912
0.035

33,000
24,200
2,420
2,662
62,282

1,375
101,750

9,504
3,561

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

13,065

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

75,347
11,302.09
86,649.34

15% x D

A. 4.4.2.17 Installation of 1 m2 of stucco 1SP: 6PP, 20mm thick/Pemasangan 1 m2 plesteran 1SP : 6PP tebal 20mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.400
82,500
L.03
Manday
0.200
121,000
L.03
Manday
0.020
121,000
L.04
Manday
0.022
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Kg
M3

5.888
0.036

1,375
101,750

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
33,000
24,200
2,420
2,662
62,282
8,096
3,663
11,759

74,041
11,106.15
85,147.15

A. 4.4.2.18 Installation of 1 m2 of stucco 1SM: 1KP: 2PP, 20mm thick/Pemasangan 1 m2 plesteran 1SM : 1KP : 2PP tebal 20mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
1. Red cement/Semen Merah
2. Lime outages/Kapur Padam
3. Sand plug/Pasir Pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.440
82,500
L.03
Manday
0.220
121,000
L.03
Manday
0.022
121,000
L.04
Manday
0.022
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

36,300
26,620
2,662
2,662
68,244

M3
0.009
41,800
M3
0.009
M3
0.018
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

376
1,832
2,208

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

70,452
10,567.76
81,019.46

A. 4.4.2.19 Installation of 1 m2 Berapen 1SP: 5PP, 15 mm thick/Pemasangan 1 m2 Berapen 1SP : 5PP tebal 15 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.150
82,500
L.03
Manday
0.075
121,000
L.03
Manday
0.008
121,000
L.04
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Kg
M3

5.184
0.026

1,375
101,750

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
12,375
9,075
968
968
23,386
7,128
2,646
9,774

33,160
4,973.93
38,133.43

15% x D

A. 4.4.2.20 Installation of 1 m1 Plaster skoning 1SP: 3PP, 10 cm thick/Pemasangan 1 m1 Plesteran skoning 1SP : 3PP tebal 10
cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.080
82,500
L.03
Manday
0.400
121,000
L.03
Manday
0.040
121,000
L.04
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Kg
M3

0.500
0.013

1,375
101,750

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
6,600
48,400
4,840
484
60,324
688
1,323
2,010

62,334
9,350.14
71,684.39

15% x D

A. 4.4.2.21 Installation of granite 1SP 1 m2 Plastering: 2 granite, 1cm thick/Pemasangan 1 m2 Plesteran granit 1SP : 2 granit
tebal 1cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.450
82,500
L.03
Manday
0.225
121,000
L.03
Manday
0.023
121,000
L.04
Manday
0.023
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Granite/Batu Granit

Kg
Kg

10.000
15.000

1,375

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
37,125
27,225
2,783
2,783
69,916
13,750
13,750

83,666
12,549.90
96,215.90

15% x D

A. 4.4.2.22 Installation of 1 m2 Plastering traso 1SP: 2 traso, 1cm thick/Pemasangan 1 m2 Plesteran traso 1SP : 2 traso tebal
1cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Terrazzo stone/Batu Traso

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.450
82,500
L.03
Manday
0.225
121,000
L.03
Manday
0.023
121,000
L.04
Manday
0.023
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Kg
Kg

10.000
15.000

1,375

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
37,125
27,225
2,783
2,783
69,916
13,750
13,750

83,666
12,549.90
96,215.90

A. 4.4.2.23 Installation of 1 m2 Plastering Splash 1SP: 2PP/Pemasangan 1 m2 Plesteran ciprat 1SP : 2PP

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.300
82,500
L.03
Manday
0.100
121,000
L.03
Manday
0.010
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Kg
Kg

4.320
0.006

24,750
12,100
1,210
1,815
39,875

1,375
101,750

5,940
611

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

6,551

46,426
6,963.83
53,389.33

15% x D

A. 4.4.2.24 Installation of 1 m2 finish broadcasting red masonry/Pemasangan 1 m2 finishing siar pasangan bata merah
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.150
82,500
L.03
Manday
0.075
121,000
L.03
Manday
0.008
121,000
L.04
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland

Kg

3.108

12,375
9,075
968
968
23,386

1,375

4,274

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

4,274

27,660
4,148.93
31,808.43

15% x D

A. 4.4.2.25 Installation of 1 m2 finish broadcasting partner exposes conblock/Pemasangan 1 m2 finishing siar pasangan
conblock ekspose
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.070
82,500
L.03
Manday
0.035
121,000
L.03
Manday
0.004
121,000
L.04
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland

Kg

1.600

1,375

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
5,775
4,235
484
484
10,978
2,200
2,200

13,178
1,976.70
15,154.70

A. 4.4.2.26 Installation of 1 m2 finishing masonry broadcast times, mix 1SP: 2PP/Pemasangan 1 m2 finishing siar pasangan
batu kali, campuran 1SP : 2PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
1. Portland cement/Semen Portland
2. Sand plug/Pasir Pasang

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.300
82,500
L.03
Manday
0.150
121,000
L.03
Manday
0.015
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Kg
M3

6.340
0.012

1,375
101,750

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
24,750
18,150
1,815
1,815
46,530
8,718
1,221
9,939

56,469
8,470.28
64,938.78

A. 4.4.2.27 Installation of 1 m2 acian/Pemasangan 1 m2 acian

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.200
82,500
L.03
Manday
0.100
121,000
L.03
Manday
0.010
121,000
L.04
Manday
0.010
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
1. Portland cement/Semen Portland

Kg

3.250

1,375

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
16,500
12,100
1,210
1,210
31,020
4,469
4,469

35,489
5,323.31
40,812.06

A. 4.4.3 WORK UNIT PRICE, FLOOR AND FINAL CLOSING WALLS/HARGA SATUAN PEKERJAAN PENUTUP LANTAI
DAN PENUTUP DINDING
A. 4.4.3.1 Installation of 1 m2 of floor tiles gray PC size 40cm x 40cm/Pemasangan 1 m2 Lantai ubin PC abu-abu ukuran 40cm
x 40cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Gray tiles/Ubin abu-abu
Portland cement/Semen Portland
Sand plug/Pasir Pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.250
82,500
L.02
Manday
0.125
99,000
L.03
Manday
0.013
121,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

20,625
12,375
1,573
1,573
36,146

Bh
6.630
Kg
9.800
1,375
M3
0.05
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

13,475
4,579
18,054

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

54,200
8,129.96
62,329.71

A. 4.4.3.2 Installation of 1 m2 of floor tiles gray PC size 30cm x 30cm/Pemasangan 1 m2 Lantai ubin PC abu-abu ukuran 30cm
x 30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Gray tiles/Ubin abu-abu
Portland cement/Semen Portland
Sand plug/Pasir Pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.250
82,500
L.02
Manday
0.125
99,000
L.03
Manday
0.013
121,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

20,625
12,375
1,573
1,573
36,146

Bh
11.870
Kg
10.000
1,375
M3
0.045
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

13,750
4,579
18,329

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

54,475
8,171.21
62,645.96

A. 4.4.3.3 Installation of 1 m2 of floor tiles gray PC size 20cm x 20cm/Pemasangan 1 m2 Lantai ubin PC abu-abu ukuran 20cm
x 20cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Gray tiles/Ubin abu-abu
Portland cement/Semen Portland
Sand plug/Pasir Pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.270
82,500
L.02
Manday
0.135
99,000
L.03
Manday
0.014
121,000
L.04
Manday
0.014
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

22,275
13,365
1,694
1,694
39,028

Bh
26.500
Kg
10.400
1,375
M3
0.045
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

14,300
4,579
18,879

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

18,879
2,831.81
21,710.56

A. 4.4.3.4 Installation of 1 m2 of floor tile size 40cm x 40cm color/Pemasangan 1 m2 Lantai ubin warna ukuran 40cm x 40cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Tile color/Ubin warna
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.250
82,500
L.02
Manday
0.125
99,000
L.03
Manday
0.013
121,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

20,625
12,375
1,573
1,573
36,146

Bh
6.63
Kg
9.80
1,375
Kg
1.30
13,200
M3
0.045
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

13,475
17,160
4,579
35,214

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

71,360
10,703.96
82,063.71

A. 4.4.3.5 Installation of 1 m2 of floor tile size 30cm x 30cm color/Pemasangan 1 m2 Lantai ubin warna ukuran 30cm x 30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Tile color/Ubin warna
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.260
82,500
L.02
Manday
0.130
99,000
L.03
Manday
0.013
121,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

21,450
12,870
1,573
1,573
37,466

Bh
11.87
Kg
10.00
1,375
Kg
1.50
13,200
M3
0.045
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

13,750
19,800
4,579
38,129

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

75,595
11,339.21
86,933.96

A. 4.4.3.6 Installation of 1 m2 of floor tile size 20cm x 20cm color/Pemasangan 1 m2 Lantai ubin warna ukuran 20cm x 20cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Tile color/Ubin warna
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.270
82,500
L.02
Manday
0.135
99,000
L.03
Manday
0.014
121,000
L.04
Manday
0.014
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

22,275
13,365
1,694
1,694
39,028

Bh
26.50
Kg
10.40
1,375
Kg
1.62
13,200
M3
0.045
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

14,300
21,384
4,579
40,263

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

79,291
11,893.61
91,184.36

A. 4.4.3.7 Installation of 1 m2 of floor tile size 40cm x 40cm terrazzo/Pemasangan 1 m2 Lantai ubin teraso ukuran 40cm x 40cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Terrazzo tile/Ubin teraso
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.250
82,500
L.02
Manday
0.125
99,000
L.03
Manday
0.013
121,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

20,625
12,375
1,573
1,573
36,146

Bh
6.63
Kg
9.80
1,375
Kg
1.30
13,200
M3
0.045
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

13,475
17,160
4,579
35,214

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

71,360
10,703.96
82,063.71

A. 4.4.3.8 Installation of 1 m2 of floor tile size 30cm x 30cm terrazzo/Pemasangan 1 m2 Lantai ubin teraso ukuran 30cm x 30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Terrazzo tile/Ubin teraso
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.260
82,500
L.02
Manday
0.130
99,000
L.03
Manday
0.013
121,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

21,450
12,870
1,573
1,573
37,466

Bh
11.87
Kg
10.00
1,375
Kg
1.50
13,200
M3
0.045
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

13,750
19,800
4,579
38,129

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

75,595
11,339.21
86,933.96

A. 4.4.3.9 Installation of 1 m2 of floor tile size 40cm x 40cm granite/Pemasangan 1 m2 Lantai ubin granit ukuran 40cm x 40cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Granite tiles/Ubin granit
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.250
82,500
L.02
Manday
0.125
99,000
L.03
Manday
0.013
121,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

20,625
12,375
1,573
1,573
36,146

Bh
6.63
48,400
Kg
9.80
1,375
Kg
1.30
13,200
M3
0.045
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

320,892
13,475
17,160
4,579
356,106

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

392,252
58,837.76
451,089.51

A. 4.4.3.10 Installation of 1 m2 of floor tile size 30cm x 30cm granite/Pemasangan 1 m2 Lantai ubin granit ukuran 30cm x 30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Granite tiles/Ubin granit
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.260
82,500
L.02
Manday
0.130
99,000
L.03
Manday
0.013
121,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

21,450
12,870
1,573
1,573
37,466

Bh
11.87
22,550
Kg
10.00
1,375
Kg
1.50
13,200
M3
0.045
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

267,669
13,750
19,800
4,579
305,797

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

343,263
51,489.49
394,752.74

A. 4.4.3.11 Installation of 1 m2 marble floor tile size 40cm x teralux 40cm/Pemasangan 1 m2 Lantai ubin teralux marmer ukuran
40cm x 40cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Tile teralux/Ubin teralux
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.250
82,500
L.02
Manday
0.125
99,000
L.03
Manday
0.013
121,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

20,625
12,375
1,573
1,573
36,146

Bh
6.63
Kg
9.80
1,375
Kg
1.30
13,200
M3
0.045
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

13,475
17,160
4,579
35,214

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

71,360
10,703.96
82,063.71

A. 4.4.3.12 Installation of 1 m2 of floor tile size 30cm x 30cm teralux/Pemasangan 1 m2 Lantai ubin teralux ukuran 30cm x
30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Tile teralux/Ubin teralux
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.260
82,500
L.02
Manday
0.130
99,000
L.03
Manday
0.013
121,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

21,450
12,870
1,573
1,573
37,466

Bh
11.87
Kg
10.00
1,375
Kg
1.50
13,200
M3
0.045
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

13,750
19,800
4,579
38,129

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

75,595
11,339.21
86,933.96

A. 4.4.3.13 Installation of 1 m2 of floor tile size 60cm x 60cm teralux/Pemasangan 1 m2 Lantai ubin teralux ukuran 60cm x
60cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Teralux marble tiles/Ubin teralux marmer
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.240
82,500
L.02
Manday
0.120
99,000
L.03
Manday
0.012
121,000
L.04
Manday
0.012
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

19,800
11,880
1,452
1,452
34,584

Bh
3.10
Kg
9.60
1,375
Kg
1.50
13,200
M3
0.045
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

13,200
19,800
4,579
37,579

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

72,163
10,824.41
82,987.16

A. 4.4.3.14 Installation of 1 m2 marble floor tile size 40cm x teralux 40cm/Pemasangan 1 m2 Lantai ubin teralux marmer ukuran
40cm x 40cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Teralux marble tiles/Ubin teralux marmer
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.250
82,500
L.02
Manday
0.125
99,000
L.03
Manday
0.013
121,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

20,625
12,375
1,573
1,573
36,146

Bh
6.63
Kg
9.80
1,375
Kg
1.30
13,200
M3
0.045
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

13,475
17,160
4,579
35,214

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

71,360
10,703.96
82,063.71

A. 4.4.3.15 Installation of 1 m2 of floor tile marble teralux size 30 x 30cm/Pemasangan 1 m2 Lantai ubin teralux marmer ukuran
30cm x 30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Teralux marble tiles/Ubin teralux marmer
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.260
82,500
L.02
Manday
0.130
99,000
L.03
Manday
0.013
121,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

21,450
12,870
1,573
1,573
37,466

Bh
11.87
Kg
10.00
1,375
Kg
1.50
13,200
M3
0.045
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

13,750
19,800
4,579
38,129

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

75,595
11,339.21
86,933.96

A. 4.4.3.16 Installation of 1 m1 Plint PC gray tile size 15cm x 20cm/Pemasangan 1 m1 Plint ubin PC abu-abu ukuran 15cm x
20cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint tile PC/Plint ubin PC
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
1,089
605
18,029

Bh
5.30
880
Kg
1.65
1,375
M3
0.004
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

4,664
2,269
407
7,340

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

25,369
3,805.31
29,174.06

A. 4.4.3.17 Installation of 1 m1 Plint PC gray tile size 10cm x 30cm/Pemasangan 1 m1 Plint ubin PC abu-abu ukuran 10cm x
30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint tile PC/Plint ubin PC
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
1,089
605
18,029

Bh
3.53
935
Kg
1.24
1,375
M3
0.003
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

3,301
1,705
305
5,311

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

23,340
3,500.97
26,840.77

A. 4.4.3.18 Installation of 1 m1 Plint PC gray tile size 10cm x 40cm/Pemasangan 1 m1 Plint ubin PC abu-abu ukuran 10cm x
40cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint tile PC/Plint ubin PC
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
1,089
605
18,029

Bh
2.65
963
Kg
1.24
1,375
M3
0.003
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

2,551
1,705
305
4,561

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

22,590
3,388.48
25,978.36

A. 4.4.3.19 Installation of 1 m1 Plint tile size 10cm x 20cm color/Pemasangan 1 m1 Plint ubin warna ukuran 10cm x 20cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint color tiles/Plint ubin warna
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
1,089
605
18,029

Bh
2.65
Kg
1.14
1,375
Kg
0.10
13,200
M3
0.003
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,568
1,320
305
3,193

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

21,222
3,183.26
24,405.01

A. 4.4.3.20 Installation of 1 m1 Plint tile size 10cm x 30cm color/Pemasangan 1 m1 Plint ubin warna ukuran 10cm x 30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint color tiles/Plint ubin warna
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
1,089
605
18,029

Bh
3.53
Kg
1.14
1,375
Kg
0.10
13,200
M3
0.003
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,568
1,320
305
3,193

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

21,222
3,183.26
24,405.01

A. 4.4.3.21 Installation of 1 m1 Plint tile size 10cm x 40cm color/Pemasangan 1 m1 Plint ubin warna ukuran 10cm x 40cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint color tiles/Plint ubin warna
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
1,089
605
18,029

Bh
2.65
Kg
1.14
1,375
Kg
0.10
13,200
M3
0.003
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,568
1,320
305
3,193

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

21,222
3,183.26
24,405.01

A. 4.4.3.22 Installation of 1 m1 Plint terrazzo tile size 10cm x 30cm/Pemasangan 1 m1 Plint ubin teraso ukuran 10cm x 30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint terrazzo tiles/Plint ubin teraso
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
1,089
605
18,029

Bh
3.53
Kg
1.14
1,375
Kg
0.10
13,200
M3
0.003
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,568
1,320
305
3,193

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

21,222
3,183.26
24,405.01

A. 4.4.3.23 Installation of 1 m1 Plint terrazzo tile size 10cm x 40cm/Pemasangan 1 m1 Plint ubin teraso ukuran 10cm x 40cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint terrazzo tiles/Plint ubin teraso
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
1,089
605
18,029

Bh
2.65
Kg
1.14
1,375
Kg
0.10
13,200
M3
0.003
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,568
1,320
305
3,193

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

21,222
3,183.26
24,405.01

A. 4.4.3.24 Installation of 1 m1 Plint granite tile size 10cm x 40cm/Pemasangan 1 m1 Plint ubin granit ukuran 10cm x 40cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint granite tiles/Plint ubin granit
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
1,089
605
18,029

Bh
2.65
Kg
1.14
1,375
Kg
0.10
13,200
M3
0.003
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,568
1,320
305
3,193

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

21,222
3,183.26
24,405.01

A. 4.4.3.25 Installation of 1 m1 Plint granite tile size 10cm x 30cm/Pemasangan 1 m1 Plint ubin granit ukuran 10cm x 30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint granite tiles/Plint ubin granit
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
1,089
605
18,029

Bh
3.53
Kg
1.14
1,375
Kg
0.10
13,200
M3
0.003
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,568
1,320
305
3,193

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

21,222
3,183.26
24,405.01

A. 4.4.3.26 Installation of 1 m1 Plint teralux tile shells, size 10cm x 40cm/Pemasangan 1 m1 Plint ubin teralux kerang ukuran
10cm x 40cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint teralux shells/Plint teralux kerang
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
1,089
605
18,029

Bh
2.63
Kg
1.14
1,375
Kg
0.10
13,200
M3
0.003
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,568
1,320
305
3,193

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

21,222
3,183.26
24,405.01

A. 4.4.3.27 Installation of 1 m1 Plint teralux tile shells, size 10cm x 30cm/Pemasangan 1 m1 Plint ubin teralux kerang ukuran
10cm x 30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint teralux shells/Plint teralux kerang
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
1,089
605
18,029

Bh
3.53
Kg
1.14
1,375
Kg
0.10
13,200
M3
0.003
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,568
1,320
305
3,193

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

21,222
3,183.26
24,405.01

A. 4.4.3.28 Installation of 1 m1 Plint teralux marble tile size 10cm x 60cm/Pemasangan 1 m1 Plint ubin teralux marmer ukuran
10cm x 60cm

A. 4.4.3.28 Installation of 1 m1 Plint teralux marble tile size 10cm x 60cm/Pemasangan 1 m1 Plint ubin teralux marmer ukuran
10cm x 60cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint teralux marble/Plint teralux marmer
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
1,089
605
18,029

Bh
1.70
Kg
1.14
1,375
Kg
0.10
13,200
M3
0.003
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,568
1,320
305
3,193

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

21,222
3,183.26
24,405.01

A. 4.4.3.29 Installation of 1 m1 Plint teralux marble tile size 10cm x 40cm/Pemasangan 1 m1 Plint ubin teralux marmer ukuran
10cm x 40cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint teralux marble/Plint teralux marmer
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
1,089
605
18,029

Bh
2.65
Kg
1.14
1,375
Kg
0.10
13,200
M3
0.003
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,568
1,320
305
3,193

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

21,222
3,183.26
24,405.01

A. 4.4.3.30 Installation of 1 m1 Plint teralux marble tile size 10cm x 30cm/Pemasangan 1 m1 Plint ubin teralux marmer ukuran
10cm x 30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint teralux marble/Plint teralux marmer
Portland cement/Semen Portland
Cement color/Semen warna
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
1,089
605
18,029

Bh
3.53
Kg
1.14
1,375
Kg
0.10
13,200
M3
0.003
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,568
1,320
305
3,193

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

21,222
3,183.26
24,405.01

A. 4.4.3.31 Installation of 1 m2 cast terrazzo floor in place, 3cm thick/Pemasangan 1 m2 lantai teraso cor di tempat, tebal 3cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
cast terrazzo/Teraso cor
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.360
82,500
L.02
Manday
0.180
99,000
L.03
Manday
0.018
121,000
L.04
Manday
0.018
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

29,700
17,820
2,178
2,178
51,876

M3
0.036
Kg
0.100
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,320
1,320

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

53,196
7,979.40
61,175.40

A. 4.4.3.32 Installation of 1 m2 of floor tile artistic, 10cm x 20cm/Pemasangan 1 m2 lantai keramik artistik 10cm x 20cm
Nr./No.

Description/Uraian

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
ceramic tiles/Ubin keramik
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

L.01
Manday
0.700
82,500
L.02
Manday
0.350
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.035
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

57,750
34,650
4,235
4,235
100,870

Bh
53.00
Kg
8.19
1,375
M3
0.045
101,750
Kg
2.75
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

11,261
4,579
36,300
52,140

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

153,010
22,951.50
175,961.50

15% x D

A. 4.4.3.33 Installation of 1 m2 of floor tile artistic, 10cm x 10cm or 20cm x 5cm/Pemasangan 1 m2 lantai keramik artistik 10cm
x 10cm atau 5cm x 20cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Ceramic tiles/Ubin keramik
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.700
82,500
L.02
Manday
0.350
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.035
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

57,750
34,650
4,235
4,235
100,870

Bh
106.00
Kg
8.19
1,375
M3
0.045
101,750
Kg
3.20
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

11,261
4,579
42,240
58,080

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

158,950
23,842.50
182,792.50

15% x D

A. 4.4.3.34 Installation of 1 m2 of floor tile size 33cm x 33cm/Pemasangan 1 m2 lantai keramik ukuran 33cm x 33cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Ceramic tiles/Ubin keramik
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.700
82,500
L.02
Manday
0.350
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.035
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

57,750
34,650
4,235
4,235
100,870

Bh
10.00
Kg
8.19
1,375
M3
0.045
101,750
Kg
1.62
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

11,261
4,579
21,384
37,224

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

138,094
20,714.10
158,808.10

15% x D

A. 4.4.3.35 Installation of 1 m2 of floor tile size 30cm x 30cm/Pemasangan 1 m2 lantai keramik ukuran 30cm x 30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Ceramic tiles/Ubin keramik
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.700
82,500
L.02
Manday
0.350
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.035
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

57,750
34,650
4,235
4,235
100,870

Bh
11.87
4,752
Kg
10.00
1,375
M3
0.045
101,750
Kg
1.50
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

56,412
13,750
4,579
19,800
94,541

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

195,411
29,311.60
224,722.29

15% x D

A. 4.4.3.36 Installation of 1 m2 of floor tile size 20cm x 20cm/Pemasangan 1 m2 lantai keramik ukuran 20cm x 20cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja

Code
Kode

Unit
Satuan

L.01

Manday

Coefficient
Koefisien

0.700

Unit Price
Harga Satuan
(Rp.)
82,500

Total Price
Total Harga
(RP.)
57,750

Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
B

MATERIALS/BAHAN
Ceramic tiles/Ubin keramik
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

L.02
Manday
0.350
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.035
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

34,650
4,235
4,235
100,870

Bh
26.50
2,728
Kg
10.40
1,375
M3
0.045
101,750
Kg
1.62
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

72,292
14,300
4,579
21,384
112,555

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

213,425
32,013.71
245,438.46

15% x D

A. 4.4.3.37 Installation of 1 m2 of floor tile size 10cm x 33cm for variations/border / Pemasangan 1 m2 lantai keramik ukuran
10cm x 33cm untuk variasi/border
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Ceramic tiles/Ubin keramik
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.050
82,500
L.02
Manday
0.525
99,000
L.03
Manday
0.053
121,000
L.04
Manday
0.053
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

86,625
51,975
6,413
6,413
151,426

Bh
33.00
Kg
9.80
1,375
M3
0.045
101,750
Kg
4.37
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

13,475
4,579
57,684
75,738

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

227,164
34,074.56
261,238.31

15% x D

A. 4.4.3.38 Installation of 1 m2 of floor tile size 30cm x 30cm/Pemasangan 1 m2 lantai keramik ukuran 30cm x 30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Ceramic tiles/Ubin keramik
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.700
82,500
L.02
Manday
0.350
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.035
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

57,750
34,650
4,235
4,235
100,870

Bh
11.87
4,752
Kg
14.15
1,375
M3
0.039
101,750
Kg
2.00
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

56,412
19,456
3,968
26,400
106,236

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

207,106
31,065.97
238,172.40

A. 4.4.3.39 Installation of 1 m1 Plint ceramic, size 10cm x 20cm/Pemasangan 1 m1 plint keramik ukuran 10cm x 20cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint ceramics/Plint keramik
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
4,235
605
21,175

Bh
5.30
Kg
1.14
1,375
M3
0.003
101,750
Kg
0.025
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,568
305
330
2,203

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

23,378
3,506.66
26,884.41

15% x D

A. 4.4.3.40 Installation of 1 m1 Plint ceramic size 10cm x 10cm/Pemasangan 1 m1 plint keramik ukuran 10cm x 10cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang

Code
Kode

Unit
Satuan

L.01
L.02
L.03

Manday
Manday
Manday

Coefficient
Koefisien

0.090
0.090
0.035

Unit Price
Harga Satuan
(Rp.)
82,500
99,000
121,000

Total Price
Total Harga
(RP.)
7,425
8,910
4,235

Foreman/Mandor
B

MATERIALS/BAHAN
Plint ceramics/Plint keramik
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

605
21,175

Bh
10.60
Kg
1.14
1,375
M3
0.003
101,750
Kg
0.050
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,568
305
660
2,533

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

23,708
3,556.16
27,263.91

15% x D

A. 4.4.3.41 Installation of 1 m1 Plint ceramic, size 5cm x 20cm/Pemasangan 1 m1 plint keramik ukuran 5cm x 20cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plint ceramics/Plint keramik
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.090
82,500
L.02
Manday
0.090
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

7,425
8,910
4,235
605
21,175

Bh
5.30
Kg
0.57
1,375
M3
0.0015
101,750
Kg
0.013
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

784
153
172
1,108

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

22,283
3,342.45
25,625.42

A. 4.4.3.42 Installation of 1 m1 internal Plint artistic cove. 5cm x 5cm x 20cm/Pemasangan 1 m1 plint internal cove artistik 5cm
x 5cm x 20cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
internal cove/Internal cove
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.750
82,500
L.02
Manday
0.750
99,000
L.03
Manday
0.075
121,000
L.04
Manday
0.038
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

61,875
74,250
9,075
4,598
149,798

Bh
5.30
Kg
1.14
1,375
M3
0.0030
101,750
Kg
0.100
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,568
305
1,320
3,193

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

152,991
22,948.61
175,939.36

A. 4.4.3.43 Installation of 1 m2 marble flooring, size 100cm x 100cm/Pemasangan 1 m2 lantai marmer ukuran 100cm x 100cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
marble/Marmer
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.700
82,500
L.02
Manday
0.350
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.035
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

57,750
34,650
4,235
4,235
100,870

Bh
1.06
Kg
8.19
1,375
M3
0.045
101,750
Kg
0.65
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

11,261
4,579
8,580
24,420

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

125,290
18,793.50
144,083.50

A. 4.4.3.44 Installation of 1 m2 of floor carpet/Pemasangan 1 m2 lantai karpet


Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.170
82,500
L.02
Manday
0.170
99,000
L.03
Manday
0.017
121,000
L.04
Manday
0.009
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
14,025
16,830
2,057
1,089
34,001

MATERIALS/BAHAN
carpet/Karpet
glue/Lem

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

M2
1.05
82,500
Kg
0.35
9,350
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

86,625
3,273
89,898

123,899
18,584.78
142,483.28

A. 4.4.3.45 Installation of 1 m2 underlayer (under carpet upholstery)/Pemasangan 1 m2 underlayer (pelapis bawah karpet)
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Underlayer
Glue/Lem

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.120
82,500
L.02
Manday
0.120
99,000
L.03
Manday
0.012
121,000
L.04
Manday
0.006
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

9,900
11,880
1,452
726
23,958

M2
1.05
Kg
0.35
9,350
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

3,273
3,273

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

27,231
4,084.58
31,315.08

15% x D

A. 4.4.3.46 Installation of 1 m2 wooden parquet flooring/Pemasangan 1 m2 lantai parquet kayu


Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Parquet
Glue/Lem

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.70
82,500
L.02
Manday
0.35
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.035
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

57,750
34,650
4,235
4,235
100,870

M2
1.05
423,500
Kg
0.60
9,350
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

444,675
5,610
450,285

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

551,155
82,673.25
633,828.25

15% x D

A. 4.4.3.47 Installation of 1 m2 wood floors gymfloor/Pemasangan 1 m2 lantai kayu gymfloor


Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang Kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Parquet
Glue/Lem

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.70
82,500
L.02
Manday
0.35
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.035
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

57,750
34,650
4,235
4,235
100,870

M2
1.05
423,500
Kg
0.60
9,350
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

444,675
5,610
450,285

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

551,155
82,673.25
633,828.25

15% x D

A. 4.4.3.48 1 m2 of wall mounting porslen, 11cm x 11cm/Pemasangan 1 m2 dinding porslen 11cm x 11cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Porcelain/Porselen
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.00
82,500
L.02
Manday
0.50
99,000
L.03
Manday
0.050
121,000
L.04
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

82,500
49,500
6,050
6,050
144,100

Bh
86.00
Kg
9.30
1,375
M3
0.018
101,750
Kg
1.50
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

12,788
1,832
19,800
34,419

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

178,519
26,777.85
205,296.85

15% x D

A. 4.4.3.49 1 m2 of wall mounting porslen, 10cm x 20cm/Pemasangan 1 m2 dinding porslen 10cm x 20cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu

Code
Kode

Unit
Satuan

L.01
L.02

Manday
Manday

Coefficient
Koefisien

0.90
0.45

Unit Price
Harga Satuan
(Rp.)
82,500
99,000

Total Price
Total Harga
(RP.)
74,250
44,550

Chief of Skill Labour/Kepala Tukang


Foreman/Mandor
B

MATERIALS/BAHAN
Porcelain/Porselen
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

L.03
Manday
0.045
121,000
L.04
Manday
0.045
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

5,445
5,445
129,690

Bh
53.00
Kg
9.30
1,375
M3
0.018
101,750
Kg
2.75
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

12,788
1,832
36,300
50,919

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

180,609
27,091.35
207,700.35

A. 4.4.3.50 1 m2 of wall mounting porslen, 20cm x 20cm/Pemasangan 1 m2 dinding porslen 20cm x 20cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Porcelain/Porselen
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.90
82,500
L.02
Manday
0.45
99,000
L.03
Manday
0.045
121,000
L.04
Manday
0.045
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

74,250
44,550
5,445
5,445
129,690

Bh
26.00
Kg
9.30
1,375
M3
0.018
101,750
Kg
1.94
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

12,788
1,832
25,608
40,227

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

169,917
25,487.55
195,404.55

A. 4.4.3.51 Installation of 1 m2 artistic ceramic wall, 10cm x 20cm/Pemasangan 1 m2 dinding keramik artistik 10cm x 20cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
artistic ceramics/Keramik artistik
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.90
82,500
L.02
Manday
0.45
99,000
L.03
Manday
0.045
121,000
L.04
Manday
0.045
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

74,250
44,550
5,445
5,445
129,690

Bh
53.00
Kg
9.30
1,375
M3
0.018
101,750
Kg
2.75
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

12,788
1,832
36,300
50,919

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

180,609
27,091.35
207,700.35

A. 4.4.3.52 Installation of 1 m2 artistic ceramic wall, 5cm x 20cm/Pemasangan 1 m2 dinding keramik artistik 5cm x 20cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
artistic ceramics/Keramik artistik
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.90
82,500
L.02
Manday
0.45
99,000
L.03
Manday
0.045
121,000
L.04
Manday
0.045
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

74,250
44,550
5,445
5,445
129,690

Bh
106.00
Kg
9.30
1,375
M3
0.018
101,750
Kg
2.90
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

12,788
1,832
38,280
52,899

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

182,589
27,388.35
209,977.35

A. 4.4.3.53 Installation of 1 m2 artistic ceramic wall, 10cm x 20cm/Pemasangan 1 m2 dinding keramik artistik 10cm x 20cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

L.01
L.02
L.03
L.04

Manday
Manday
Manday
Manday

Coefficient
Koefisien

0.90
0.45
0.045
0.045

Unit Price
Harga Satuan
(Rp.)
82,500
99,000
121,000
121,000

Total Price
Total Harga
(RP.)
74,250
44,550
5,445
5,445

MANPOWER TOTAL / JUMLAH TENAGA KERJA


B

MATERIALS/BAHAN
artistic ceramics/Keramik artistik
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Bh
53.00
Kg
9.30
1,375
M3
0.018
101,750
Kg
2.75
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

129,690
12,788
1,832
36,300
50,919

180,609
27,091.35
207,700.35

A. 4.4.3.54 Installation of 1 m2 of wall tile, 20cm x 20cm/Pemasangan 1 m2 dinding keramik 20cm x 20cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
artistic ceramics/Keramik artistik
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.90
82,500
L.02
Manday
0.45
99,000
L.03
Manday
0.045
121,000
L.04
Manday
0.045
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

74,250
44,550
5,445
5,445
129,690

Bh
26.50
Kg
9.30
1,375
M3
0.018
101,750
Kg
1.94
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

12,788
1,832
25,608
40,227

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

169,917
25,487.55
195,404.55

A. 4.4.3.55 Installation of 1 m2 marble wall, 100cm x 100cm/Pemasangan 1 m2 dinding marmer 100cm x 100cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
marble/Marmer
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna
Nail/Paku 12cm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.30
82,500
L.02
Manday
0.65
99,000
L.03
Manday
0.065
121,000
L.04
Manday
0.065
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

107,250
64,350
7,865
7,865
187,330

Bh
1.06
Kg
12.44
1,375
M3
0.025
101,750
Kg
0.65
13,200
Bh
3.03
16,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

17,105
2,544
8,580
49,995
78,224

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

265,554
39,833.06
305,386.81

A. 4.4.3.56 Installation of 1 m2 brick wall coatings, 3cm x 7cm x 24cm/Pemasangan 1 m2 dinding bata pelapis 3cm x 7cm x
24cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
brick linings/Bata pelapis
Portland cement/Semen Portland
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.00
82,500
L.02
Manday
0.50
99,000
L.03
Manday
0.050
121,000
L.04
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

82,500
49,500
6,050
6,050
144,100

Bh
63.00
Kg
12.44
1,375
M3
0.025
101,750
Kg
2.75
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

17,105
2,544
36,300
55,949

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

200,049
30,007.31
230,056.06

A. 4.4.3.57 Installation of 1 m2 sandstone wall/Pemasangan 1 m2 dinding batu paras


Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.70
82,500
L.02
Manday
0.35
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.035
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
57,750
34,650
4,235
4,235
100,870

MATERIALS/BAHAN
sandstone/Batu paras
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Bh
1.10
Kg
11.75
1,375
M3
0.035
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

16,156
3,561
19,718

120,588
18,088.13
138,675.63

15% x D

A. 4.4.3.58 Installation of 1 m2 black paste stone wall/Pemasangan 1 m2 dinding batu tempel hitam
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Black paste stones/Batu tempel hitam
Portland cement/Semen Portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.70
82,500
L.02
Manday
0.35
99,000
L.03
Manday
0.035
121,000
L.04
Manday
0.035
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

57,750
34,650
4,235
4,235
100,870

Bh
1.10
Kg
11.75
1,375
M3
0.035
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

16,156
3,561
19,718

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

120,588
18,088.13
138,675.63

15% x D

A. 4.4.3.59 Installation of 1 m2 of vinyl flooring, size 30cm x 30cm/Pemasangan 1 m2 lantai vynil ukuran 30cm x 30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.15
82,500
L.02
Manday
0.15
99,000
L.03
Manday
0.015
121,000
L.04
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Vynil
Glue/Lem

Bh
Kg

11.87
0.35

9,350

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
12,375
14,850
1,815
968
30,008
3,273
3,273

33,281
4,992.08
38,272.58

A. 4.4.3.60 Installation of 1 m2 wallpaper, width 50cm/Pemasangan 1 m2 wallpaper lebar 50cm


Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.35
82,500
L.02
Manday
0.175
99,000
L.03
Manday
0.017
121,000
L.04
Manday
0.002
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Wallpaper
Glue/Lem

m
Kg

2.20
0.25

308,000
9,350

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
28,875
17,325
2,057
242
48,499
677,600
2,338
679,938

728,437
109,265.48
837,701.98

A. 4.4.3.61 Installation of 1 m2 of floor hardener/Pemasangan 1 m2 floor hardener


Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Floor hardener

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.12
82,500
L.02
Manday
0.12
99,000
L.03
Manday
0.012
121,000
L.04
Manday
0.006
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
m

5.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

Total Price
Total Harga
(RP.)
9,900
11,880
1,452
726
23,958
-

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

23,958
3,593.70
27,551.70

15% x D

A. 4.4.3.62 Installation of 1 m1 Plint vinyl, 15cm x 30cm/Pemasangan 1 m1 plint vynil 15cm x 30cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.08
82,500
L.02
Manday
0.08
99,000
L.03
Manday
0.008
121,000
L.04
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Vynil
Glue/Lem

Bh
Kg

1.76
0.08

6,600
7,920
968
484
15,972
748

9,350

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

748

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

16,720
2,508.00
19,228.00

15% x D

A. 4.4.3.63 Installation of 1 m1 Plint wood, 2cm thick 10cm wide/Pemasangan 1 m1 plint kayu tebal 2cm lebar 10cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang Batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.12
82,500
L.02
Manday
0.12
99,000
L.03
Manday
0.012
121,000
L.04
Manday
0.006
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Wooden board class 1/Papan kayu kelas 1
Nails / screws 5cm / Paku/Skrup 5cm

M3
Kg

Total Price
Total Harga
(RP.)
9,900
11,880
1,452
726
23,958

0.003
0.05

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

23,958
3,593.70
27,551.70

15% x D

A. 4.5.1 WORK UNIT PRICE CEILING /HARGA SATUAN PEKERJAAN LANGIT-LANGIT(PLAFOND)


A. 4.5.1.1 Installation of 1 m2 of asbestos cement ceilings, thick 4mm, 5mm and 6mm/Pemasangan 1 m2 langit-langit asbes
semen, tebal 4mm, 5mm dan 6mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.030
82,500
L.02
Manday
0.070
99,000
L.03
Manday
0.007
121,000
L.04
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Asbestos cement / Asbes semen
nail plywood/Paku tripleks

M2
Kg

1.100
0.010

Total Price
Total Harga
(RP.)
2,475
6,930
847
484
10,736
198

19,800

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

198

10,934
1,640.10
12,574.10

15% x D

A. 4.5.1.2 Installation of 1 m2 of acoustic ceiling, the size (30 x 30) cm/Pemasangan 1 m2 langit-langit akustik ukuran (30 x 30)
cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
acoustic/ Akustik
nail plywood/Paku tripleks

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.120
82,500
L.02
Manday
0.120
99,000
L.03
Manday
0.012
121,000
L.04
Manday
0.006
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Lembar
Kg

12.000
0.050

19,800

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
9,900
11,880
1,452
726
23,958
990
990

24,948
3,742.20
28,690.20

A. 4.5.1.3 Installation of 1 m2 of acoustic ceiling, the size (30 x 60) cm/Pemasangan 1 m2 langit-langit akustik ukuran (30 x 60)
cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.120
82,500
L.02
Manday
0.120
99,000
L.03
Manday
0.012
121,000
L.04
Manday
0.006
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
acoustic/ Akustik
nail plywood/Paku tripleks

Lembar
Kg

5.800
0.050

Total Price
Total Harga
(RP.)
9,900
11,880
1,452
726
23,958
990

19,800

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

990

24,948
3,742.20
28,690.20

15% x D

A. 4.5.1.4 Installation of 1 m2 of acoustic ceiling, the size (60 x 120) cm/Pemasangan 1 m2 langit-langit akustik ukuran (60 x
120) cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.100
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
acoustic/ Akustik
nail plywood/Paku tripleks

Lembar
Kg

1.500
0.050

Total Price
Total Harga
(RP.)
8,250
9,900
1,210
605
19,965
990

19,800

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

990

20,955
3,143.25
24,098.25

15% x D

A. 4.5.1.5 Installation of 1 m2 of ceiling plywood size (120 x 240) cm, thickness 3mm, 4mm, & 6mm/Pemasangan 1 m2 langitlangit tripleks ukuran (120 x 240) cm, tebal 3mm, 4mm, & 6mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.100
82,500
L.02
Manday
0.100
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
acoustic/ Akustik
nail plywood/Paku tripleks

Lembar
Kg

0.375
0.030

Total Price
Total Harga
(RP.)
8,250
9,900
1,210
605
19,965
594

19,800

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

594

20,559
3,083.85
23,642.85

15% x D

A. 4.5.1.6 Installation of 1 m2 wooden ceiling lambrisering, 9mm thick/Pemasangan 1 m2 langit-langit lambrisering kayu, tebal
9mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.800
82,500
L.02
Manday
0.800
99,000
L.03
Manday
0.080
121,000
L.04
Manday
0.040
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
saw timber/ Kayu papan
nail plywood/Paku tripleks

M3
Kg

0.015
0.010

Total Price
Total Harga
(RP.)
66,000
79,200
9,680
4,840
159,720
198

19,800

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

198

159,918
23,987.70
183,905.70

A. 4.5.1.7 Installation of 1 m2 gypsum ceiling board size (120x240x9) mm, 9mm thick/Pemasangan 1 m2 langit-langit gypsum
board ukuran (120x240x9) mm, tebal 9mm
Nr./No.

Description/Uraian

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan

Total Price
Total Harga

Nr./No.

Description/Uraian
(Rp.)

MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

L.01
Manday
0.100
82,500
L.02
Manday
0.050
99,000
L.03
Manday
0.005
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Gypsum board
nail screw/Paku skrup

Lembar
Kg

0.364
0.110

74,800

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

(RP.)
8,250
4,950
605
605
14,410
27,227
27,227

41,637
6,245.58
47,882.78

A. 4.5.1.8 Installation of 1 m2 of acoustic ceiling size (60 x 120) cm, following the framework of alluminium/Pemasangan 1 m2
langit-langit akustik ukuran (60 x 120) cm berikut rangka alluminium
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Vulcan/Tukang besi
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.500
82,500
L.02
Manday
0.500
99,000
L.03
Manday
0.050
121,000
L.04
Manday
0.025
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Alluminium Profile "T"/ Profil Alluminium "T"
4mm diameter wire/Kawat diameter 4mm
Ramset
Acoustic 60 x 120/Akustik 60 x 120

M
Kg
Buah
Lembar

Total Price
Total Harga
(RP.)
41,250
49,500
6,050
3,025
99,825

3.600
0.150
1.050
1.500

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

99,825
14,973.75
114,798.75

A. 4.5.1.9 Installation of 1 m1 list wooden ceiling profile/Pemasangan 1 m1 list langit-langit kayu profil

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.050
82,500
L.02
Manday
0.050
99,000
L.03
Manday
0.005
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
List of timber profiles/ List kayu profil
Nail/Paku

M
Kg

Total Price
Total Harga
(RP.)
4,125
4,950
605
363
10,043

1.050
0.010

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

10,043
1,506.45
11,549.45

A. 4.5.1.10 Installation of 1 m2 framework of hollow steel ceiling 40.40/Pemasangan 1 m2 Rangka langit-langit besi hollow
40.40
Look at Iron Works and Aluminium group (A.9.21)/Lihat pada kelompok Pekerjaan Besi dan Alluminium (A.9.21)

A. 4.5.2 CLOSING ROOF WORK UNIT PRICE/HARGA SATUAN PEKERJAAN PENUTUP ATAP
A. 4.5.2.1 Installation of 1 m2 of roof tile small Plentong/Pemasangan 1 m2 atap genteng palentong kecil

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
tile Plentong/Genteng plentong

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.15
82,500
L.03
Manday
0.075
121,000
L.11
Manday
0.0075
121,000
L.15
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Bh

25.000

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

A. 4.5.2.2 Installation of 1 m2 of roof tile frog glazuur/Pemasangan 1 m2 atap genteng kodok glazuur

Total Price
Total Harga
(RP.)
12,375
9,075
908
968
23,326
-

23,326
3,498.83
26,824.33

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.15
82,500
L.03
Manday
0.075
121,000
L.11
Manday
0.008
121,000
L.15
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
tile frog/Genteng kodok

Bh

12,375
9,075
968
968
23,386

25.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

23,386
3,507.90
26,893.90

A. 4.5.2.3 Installation of 1 m2 of roof tile Plentong large/super /Pemasangan 1 m2 atap genteng plentong besar/super
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.15
82,500
L.03
Manday
0.075
121,000
L.11
Manday
0.008
121,000
L.15
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
tile Plentong/Genteng Plentong

Bh

Total Price
Total Harga
(RP.)
12,375
9,075
968
968
23,386

12.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

23,386
3,507.90
26,893.90

A. 4.5.2.4 Installation of 1 m1 ridge tile Plentong/Pemasangan 1 m1 bubung genteng plentong

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
ridge tile/Genteng bubung
Portland cement/Semen Portland
Sand Plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.40
82,500
L.03
Manday
0.20
121,000
L.11
Manday
0.02
121,000
L.15
Manday
0.002
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

33,000
24,200
2,420
242
59,862

Bh
5.00
Kg
8.00
1,375
M3
0.032
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

11,000
3,256
14,256

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

74,118
11,117.70
85,235.70

A. 4.5.2.5 Installation of 1 m1 ridge tile frog glazuur/Pemasangan 1 m1 bubung genteng kodok glazuur

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
ridge tile/Genteng bubung
Portland cement/Semen Portland
Sand Plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.40
82,500
L.03
Manday
0.20
121,000
L.11
Manday
0.02
121,000
L.15
Manday
0.002
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

33,000
24,200
2,420
242
59,862

Bh
5.00
Kg
8.00
1,375
M3
0.032
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

11,000
3,256
14,256

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

74,118
11,117.70
85,235.70

A. 4.5.2.6 Installation of 1 m1 ridge tile large palentong/Pemasangan 1 m1 bubung genteng palentong besar

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

L.01
L.03
L.11
L.15

Manday
Manday
Manday
Manday

Coefficient
Koefisien

0.40
0.20
0.02
0.002

Unit Price
Harga Satuan
(Rp.)
82,500
121,000
121,000
121,000

Total Price
Total Harga
(RP.)
33,000
24,200
2,420
242

MANPOWER TOTAL / JUMLAH TENAGA KERJA


B

MATERIALS/BAHAN
ridge tile/Genteng bubung
Portland cement/Semen Portland
Sand Plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Bh
4.00
Kg
8.00
1,375
M3
0.032
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

59,862
11,000
3,256
14,256

74,118
11,117.70
85,235.70

15% x D

A. 4.5.2.7 Installation of rooflight 1 m2 fiberglass, 90 x 180/Pemasangan 1 m2 roof light fibreglass 90 x 180

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.14
82,500
L.03
Manday
0.067
121,000
L.11
Manday
0.007
121,000
L.15
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Rooflight 90 x 180
Common nails/Paku biasa 1/2" - 1"

Lembar
Kg

0.60
0.05

Total Price
Total Harga
(RP.)
11,550
8,107
847
847
21,351
990

19,800

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

990

22,341
3,351.15
25,692.15

15% x D

A. 4.5.2.8 1 m2 of roof mounting wave of asbestos 0.92m x 2.5m x 5mm/Pemasangan 1 m2 atap asbes gelombang 0.92m x
2.5m x 5mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.14
82,500
L.03
Manday
0.075
121,000
L.11
Manday
0.008
121,000
L.15
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Asbestos wave /Asbes gelombang 92 x 250
nail rod 6 x 23/paku pancing 6 x 23

Lembar
Kg

0.50
0.12

24,200

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
11,550
9,075
968
968
22,561
2,904
2,904

25,465
3,819.75
29,284.75

15% x D

A. 4.5.2.9 1 m2 of roof mounting wave of asbestos 0.92m x 2.25m x 5mm/Pemasangan 1 m2 atap asbes gelombang 0.92m x
2.25m x 5mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.14
82,500
L.03
Manday
0.075
121,000
L.11
Manday
0.008
121,000
L.15
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Asbestos wave /Asbes gelombang 92 x 250
nail rod 6 x 23/paku pancing 6 x 23

Lembar
Kg

0.60
0.12

24,200

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
11,550
9,075
968
968
22,561
2,904
2,904

25,465
3,819.75
29,284.75

15% x D

A. 4.5.2.10 1 m2 of roof mounting wave of asbestos 0.92m x 2.00m x 5mm/Pemasangan 1 m2 atap asbes gelombang 0.92m x
2.00m x 5mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Asbestos wave /Asbes gelombang 92 x 250
nail rod 6 x 23/paku pancing 6 x 23

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.14
82,500
L.03
Manday
0.070
121,000
L.11
Manday
0.007
121,000
L.15
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Lembar
Kg

0.60
0.12

24,200

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

Total Price
Total Harga
(RP.)
11,550
8,470
847
847
21,714
2,904
2,904

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

24,618
3,692.70
28,310.70

15% x D

A. 4.5.2.11 1 m2 of roof mounting wave of asbestos 0.92m x 1.80m x 5mm/Pemasangan 1 m2 atap asbes gelombang 0.92m x
1.80m x 5mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.14
82,500
L.03
Manday
0.070
121,000
L.11
Manday
0.007
121,000
L.15
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Asbestos wave /Asbes gelombang 92 x 250
nail rod 6 x 23/paku pancing 6 x 23

Lembar
Kg

0.75
0.12

24,200

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
11,550
8,470
847
847
21,714
2,904
2,904

24,618
3,692.70
28,310.70

15% x D

A. 4.5.2.12 1 m2 of roof mounting wave of asbestos 1.05m x 3.00m x 4mm/Pemasangan 1 m2 atap asbes gelombang 1.05m x
3.00m x 4mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.14
82,500
L.03
Manday
0.070
121,000
L.11
Manday
0.007
121,000
L.15
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Asbestos wave /Asbes gelombang 92 x 250
nail rod 6 x 23/paku pancing 6 x 23

Lembar
Kg

0.35
0.12

24,200

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
11,550
8,470
847
847
21,714
2,904
2,904

24,618
3,692.70
28,310.70

15% x D

A. 4.5.2.13 1 m2 of roof mounting wave of asbestos 1.05m x 2.70m x 4mm/Pemasangan 1 m2 atap asbes gelombang 1.05m x
2.70m x 4mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.14
82,500
L.03
Manday
0.070
121,000
L.11
Manday
0.007
121,000
L.15
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Asbestos wave /Asbes gelombang 92 x 250
nail rod 6 x 23/paku pancing 6 x 23

Lembar
Kg

0.42
0.12

24,200

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
11,550
8,470
847
847
21,714
2,904
2,904

24,618
3,692.70
28,310.70

15% x D

A. 4.5.2.14 1 m2 of roof mounting wave of asbestos 1.05m x 2.40m x 4mm/Pemasangan 1 m2 atap asbes gelombang 1.05m x
2.40m x 4mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Asbestos wave /Asbes gelombang 92 x 250
nail rod 6 x 23/paku pancing 6 x 23

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.14
82,500
L.03
Manday
0.070
121,000
L.11
Manday
0.007
121,000
L.15
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Lembar
Kg

0.44
0.12

24,200

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
11,550
8,470
847
847
21,714
2,904
2,904

24,618
3,692.70
28,310.70

A. 4.5.2.15 1 m2 of roof mounting wave of asbestos 1.05m x 2.10m x 4mm/Pemasangan 1 m2 atap asbes gelombang 1.05m x
2.10m x 4mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.14
82,500
L.03
Manday
0.070
121,000
L.11
Manday
0.007
121,000
L.15
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Asbestos wave /Asbes gelombang 92 x 250
nail rod 6 x 23/paku pancing 6 x 23

Lembar
Kg

0.51
0.12

24,200

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
11,550
8,470
847
847
21,714
2,904
2,904

24,618
3,692.70
28,310.70

15% x D

A. 4.5.2.16 1 m2 of roof mounting wave of asbestos 1.05m x 1.50m x 4mm/Pemasangan 1 m2 atap asbes gelombang 1.05m x
1.50m x 4mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.14
82,500
L.03
Manday
0.070
121,000
L.11
Manday
0.007
121,000
L.15
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Asbestos wave /Asbes gelombang 92 x 250
nail rod 6 x 23/paku pancing 6 x 23

Lembar
Kg

0.80
0.12

24,200

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
11,550
8,470
847
847
21,714
2,904
2,904

24,618
3,692.70
28,310.70

15% x D

A. 4.5.2.17 1 m2 of roof mounting wave of asbestos 1.08m x 3.00m x 6mm/Pemasangan 1 m2 atap asbes gelombang 1.08m x
3.00m x 6mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.14
82,500
L.03
Manday
0.070
121,000
L.11
Manday
0.007
121,000
L.15
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Asbestos wave /Asbes gelombang 92 x 250
nail rod 6 x 23/paku pancing 6 x 23

Lembar
Kg

0.37
0.12

24,200

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
11,550
8,470
847
847
21,714
2,904
2,904

24,618
3,692.70
28,310.70

15% x D

A. 4.5.2.18 1 m2 of roof mounting wave of asbestos 1.08m x 2.70m x 6mm/Pemasangan 1 m2 atap asbes gelombang 1.08m x
2.70m x 6mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.14
82,500
L.03
Manday
0.070
121,000
L.11
Manday
0.007
121,000
L.15
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Asbestos wave /Asbes gelombang 92 x 250
nail rod 6 x 23/paku pancing 6 x 23

Lembar
Kg

0.38
0.12

24,200

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
11,550
8,470
847
847
21,714
2,904
2,904

24,618
3,692.70
28,310.70

A. 4.5.2.19 1 m2 of roof mounting wave of asbestos 1.08m x 2.40m x 6mm/Pemasangan 1 m2 atap asbes gelombang 1.08m x
2.40m x 6mm
Nr./No.

Description/Uraian

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan

Total Price
Total Harga

Nr./No.

Description/Uraian
(Rp.)

MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

(RP.)

L.01
Manday
0.14
82,500
L.03
Manday
0.070
121,000
L.11
Manday
0.007
121,000
L.15
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Asbestos wave /Asbes gelombang 92 x 250
nail rod 6 x 23/paku pancing 6 x 23

Lembar
Kg

0.46
0.12

24,200

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

11,550
8,470
847
847
21,714
2,904
2,904

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

24,618
3,692.70
28,310.70

15% x D

A. 4.5.2.20 1 m2 of roof mounting wave of asbestos 1.08m x 2.10m x 6mm/Pemasangan 1 m2 atap asbes gelombang 1.08m x
2.10m x 6mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.14
82,500
L.03
Manday
0.070
121,000
L.11
Manday
0.007
121,000
L.15
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Asbestos wave /Asbes gelombang 92 x 250
nail rod 6 x 23/paku pancing 6 x 23

Lembar
Kg

0.49
0.12

24,200

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Total Price
Total Harga
(RP.)
11,550
8,470
847
847
21,714
2,904
2,904

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

24,618
3,692.70
28,310.70

15% x D

A. 4.5.2.21 1 m2 of roof mounting wave of asbestos 1.08m x 1.80m x 6mm/Pemasangan 1 m2 atap asbes gelombang 1.08m x
1.80m x 6mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.14
82,500
L.03
Manday
0.070
121,000
L.11
Manday
0.007
121,000
L.15
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Asbestos wave /Asbes gelombang 92 x 250
nail rod 6 x 23/paku pancing 6 x 23

Lembar
Kg

0.57
0.12

24,200

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Total Price
Total Harga
(RP.)
11,550
8,470
847
847
21,714
2,904
2,904

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

24,618
3,692.70
28,310.70

15% x D

A. 4.5.2.22 1 m1 steel mounting wave ridge 0.92m/Pemasangan 1 m1 bubung steel gelombang 0.92m

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.084
82,500
L.03
Manday
0.125
121,000
L.11
Manday
0.013
121,000
L.15
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Stainless ridge wave/Bubungan steel gelombang
nail screw/Paku skrup 3.5"

Lembar
Bh

2.40
6.00

495

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
6,930
15,125
1,573
484
24,112
2,970
2,970

27,082
4,062.30
31,144.30

A. 4.5.2.23 1 m1 steel mounting wave ridge 1.05m/Pemasangan 1 m1 bubung steel gelombang 1.05m

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

L.01
L.03
L.11
L.15

Manday
Manday
Manday
Manday

Coefficient
Koefisien

0.084
0.125
0.013
0.004

Unit Price
Harga Satuan
(Rp.)
82,500
121,000
121,000
121,000

Total Price
Total Harga
(RP.)
6,930
15,125
1,573
484

MANPOWER TOTAL / JUMLAH TENAGA KERJA


B

MATERIALS/BAHAN
Stainless ridge wave/Bubungan steel gelombang
nail screw/Paku skrup 3.5"

Lembar
Bh

2.10
6.00

24,112

495

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

2,970
2,970

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

27,082
4,062.30
31,144.30

15% x D

A. 4.5.2.24 Installation of 1 m1 steel ridge wave 1.08m/Pemasangan 1 m1 bubung steel gelombang 1.08m

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.084
82,500
L.03
Manday
0.125
121,000
L.11
Manday
0.013
121,000
L.15
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Stainless ridge wave/Bubungan steel gelombang
nail screw/Paku skrup 3.5"

Lembar
Bh

2.05
6.00

495

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Total Price
Total Harga
(RP.)
6,930
15,125
1,573
484
24,112
2,970
2,970

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

27,082
4,062.30
31,144.30

15% x D

A. 4.5.2.25 Installation of 1 m1 nok patent 0.92m/Pemasangan 1 m1 nok paten 0.92m

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.084
82,500
L.03
Manday
0.125
121,000
L.11
Manday
0.013
121,000
L.15
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Nok patent 92cm/Nok paten 92cm
nail screw/Paku skrup 3.5"

Lembar
Bh

1.20
6.00

495

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Total Price
Total Harga
(RP.)
6,930
15,125
1,573
484
24,112
2,970
2,970

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

27,082
4,062.30
31,144.30

15% x D

A. 4.5.2.26 Installation of 1 m1 nok patent 1.05m/Pemasangan 1 m1 nok paten 1.05m

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.084
82,500
L.03
Manday
0.125
121,000
L.11
Manday
0.013
121,000
L.15
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Nok patent 92cm/Nok paten 92cm
nail screw/Paku skrup 3.5"

Lembar
Bh

1.20
6.00

495

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Total Price
Total Harga
(RP.)
6,930
15,125
1,573
484
24,112
2,970
2,970

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

27,082
4,062.30
31,144.30

15% x D

A. 4.5.2.27 Installation of 1 m1 nok patent 1.08m/Pemasangan 1 m1 nok paten 1.08m

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Nok patent 92cm/Nok paten 92cm
nail screw/Paku skrup 3.5"

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.084
82,500
L.03
Manday
0.125
121,000
L.11
Manday
0.013
121,000
L.15
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Lembar
Bh

1.20
6.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

495

Total Price
Total Harga
(RP.)
6,930
15,125
1,573
484
24,112
2,970
2,970

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

27,082
4,062.30
31,144.30

15% x D

A. 4.5.2.28 Installation of 1 m1 stainless nok average 0.92m/Pemasangan 1 m1 nok steel rata 0.92m

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.100
82,500
L.03
Manday
0.150
121,000
L.11
Manday
0.013
121,000
L.15
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Nok patent 92cm/Nok paten 92cm
nail screw/Paku skrup 3.5"

Lembar
Bh

1.10
6.00

495

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Total Price
Total Harga
(RP.)
8,250
18,150
1,573
484
28,457
2,970
2,970

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

31,427
4,714.05
36,141.05

15% x D

A. 4.5.2.29 Installation of 1 m1 stainless nok average 1.05m/Pemasangan 1 m1 nok steel rata 1.05m

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.084
82,500
L.03
Manday
0.125
121,000
L.11
Manday
0.013
121,000
L.15
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Nok patent 92cm/Nok paten 92cm
nail screw/Paku skrup 3.5"

Lembar
Bh

1.10
6.00

495

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
6,930
15,125
1,573
484
24,112
2,970
2,970

27,082
4,062.30
31,144.30

15% x D

A. 4.5.2.30 Installation of 1 m2 of concrete tile/Pemasangan 1 m2 genteng beton

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.200
82,500
L.03
Manday
0.100
121,000
L.11
Manday
0.010
121,000
L.15
Manday
0.010
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
concrete tile/Genteng beton
Common Nails/Paku biasa 2"-5"

Bh
Kg

11.00
0.03

6,270
16,500

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
16,500
12,100
1,210
1,210
31,020
68,970
495
69,465

100,485
15,072.75
115,557.75

A. 4.5.2.31 Installation of 1 m2 of asphalt tile/Pemasangan 1 m2 genteng aspal

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
asphalt tile/Genteng aspal
Plywood 6mm
Common nails/Paku biasa 1/2"-1"
Plastic aerator

EQUIPMENT/PERALATAN

D
E

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.200
82,500
L.03
Manday
0.300
121,000
L.11
Manday
0.003
121,000
L.15
Manday
0.010
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

16,500
36,300
363
1,210
54,373

Bh
6.90
lembar
0.35
96,800
Kg
0.03
19,800
Bh
0.500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

33,880
594
34,474

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

88,847
13,327.05

Unit Price Work/Harga Satuan Pekerjaan (D+E)

102,174.05

A. 4.5.2.32 Installation of 1 m2 metal roof/Pemasangan 1 m2 genteng metal

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.200
82,500
L.03
Manday
0.100
121,000
L.11
Manday
0.010
121,000
L.15
Manday
0.001
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
metal roof/Genteng metal
Common nails/Paku biasa 1/2"-1"

Bh
Kg

1.02
0.20

19,800

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
16,500
12,100
1,210
121
29,931
3,960
3,960

33,891
5,083.65
38,974.65

15% x D

A. 4.5.2.33 Installation of 1 m2 wood shingle roof/Pemasangan 1 m2 atap sirap kayu

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.166
82,500
L.03
Manday
0.250
121,000
L.11
Manday
0.025
121,000
L.15
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
wood shingle/Sirap kayu
Common nails/Paku biasa 1/2"-1"

Bh
Kg

30.00
0.20

19,800

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
13,695
30,250
3,025
968
47,938
3,960
3,960

51,898
7,784.70
59,682.70

A. 4.5.2.34 Installation of concrete tile nok 1 m1/Pemasangan 1 m1 nok genteng beton

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Nok concrete tile/Nok genteng beton
Common nails/Paku biasa 1/2"-1"
Portland cement/Semen PC
Sand plug/Pasir pasang
Cement color/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.400
82,500
L.03
Manday
0.200
121,000
L.11
Manday
0.020
121,000
L.15
Manday
0.020
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

33,000
24,200
2,420
2,420
62,040

Bh
3.50
6,600
Kg
0.05
19,800
Kg
10.80
1,375
M3
0.032
101,750
Kg
1.00
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

23,100
990
14,850
3,256
13,200
55,396

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

117,436
17,615.40
135,051.40

A. 4.5.2.35 Installation of asphalt tile rooftop 1 m1/Pemasangan 1 m1 nok genteng aspal

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Nok asphalt tile/Nok genteng aspal
Common nails/Paku biasa 1/2"-1"
Wood beams borneo/Kayu balok borneo

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.125
82,500
L.03
Manday
0.250
121,000
L.11
Manday
0.025
121,000
L.15
Manday
0.006
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

10,313
30,250
3,025
726
44,314

Bh
2.00
Kg
0.05
19,800
M3
0.0035
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

990
990

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

A. 4.5.2.36 nstallation of metal roof nok 1 m1/Pemasangan 1 m1 nok genteng metal

45,304
6,795.53
52,099.03

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.250
82,500
L.03
Manday
0.150
121,000
L.11
Manday
0.015
121,000
L.15
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Nok metal roof/Nok genteng metal
Common nails/Paku biasa 1/2"-1"

Bh
Kg

1.10
0.05

33,000
19,800

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
20,625
18,150
1,815
1,573
42,163
36,300
990
37,290

79,453
11,917.95
91,370.95

15% x D

A. 4.5.2.37 Installation of rooftop shingle 1 m1/Pemasangan 1 m1 nok sirap

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.125
82,500
L.03
Manday
0.250
121,000
L.11
Manday
0.025
121,000
L.15
Manday
0.006
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Zinc plate/Seng plat 3 x 6"
Common nails/Paku biasa 1/2"-1"
Common nails/Paku biasa 2"-5"

Lembar
Kg
Kg

0.40
0.05
0.05

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

10,313
30,250
3,025
726
44,314
990
825

19,800
16,500

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Total Price
Total Harga
(RP.)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

1,815

46,129
6,919.28
53,047.78

15% x D

A. 4.5.2.38 Installation of 1 m2 of corrugated iron roof/Pemasangan 1 m2 atap seng gelombang

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.120
82,500
L.03
Manday
0.060
121,000
L.11
Manday
0.006
121,000
L.15
Manday
0.006
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
zinc wave/Seng gelombang 3 x 6"
Common nails/Paku biasa 1/2"-1"

Lembar
Kg

0.70
0.02

Total Price
Total Harga
(RP.)
9,900
7,260
726
726
18,612
396

19,800

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

396

19,008
2,851.20
21,859.20

15% x D

A. 4.5.2.39 Installation of 1 m1 nok tin roof/Pemasangan 1 m1 nok atap seng

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.150
82,500
L.03
Manday
0.070
121,000
L.11
Manday
0.007
121,000
L.15
Manday
0.006
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
zinc wave/Seng gelombang 3 x 6" bjls28
Common nails/Paku biasa 1/2"-1"

Lembar
Kg

0.30
0.04

Total Price
Total Harga
(RP.)
12,375
8,470
847
726
22,418
792

19,800

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

792

23,210
3,481.50
26,691.50

A. 4.5.2.40 Installation of 1 m2 aluminum roof/Pemasangan 1 m2 atap aluminium

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
B

L.01
Manday
0.150
82,500
L.03
Manday
0.750
121,000
L.11
Manday
0.080
121,000
L.15
Manday
0.006
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Aluminum wave, thickness 0.55/Almn gel. Tebal 0.55
Long nails right/Paku hak panj. 15cm

Lembar
Kg

1.05
0.02

12,375
90,750
9,680
726
113,531

110,000

115,500
-

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

115,500

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

229,031
34,354.65
263,385.65

15% x D

A. 4.5.2.41 Installation of 1 m1 nok aluminum/Pemasangan 1 m1 nok aluminium

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.100
82,500
L.03
Manday
1.000
121,000
L.11
Manday
0.100
121,000
L.15
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Nok standard /Nok standar 40x18
Nails the right length, 15 cm/Paku hak panj. 15cm

Bh
Kg

8,250
121,000
12,100
6,050
147,400

1.20
0.04

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

147,400
22,110.00
169,510.00

15% x D

A. 4.5.2.42 Installation of 1 m2 aluminum foil/sisalation / Pemasangan 1 m2 aluminium foil/sisalation

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.150
82,500
L.03
Manday
0.050
121,000
L.11
Manday
0.005
121,000
L.15
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Alluminium foil

M2

1.05

12,375
6,050
605
968
19,998

20,350

21,368

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

21,368

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

41,366
6,204.83
47,570.33

15% x D

A. 4.6.1 WOOD WORK UNIT PRICE/HARGA SATUAN PEKERJAAN KAYU


A. 4.6.1.1 Manufacture and installation of 1 m3 door frame and window frame, wooden class I/Pembuatan dan pemasangan 1
m3 kusen pintu dan kusen jendela, kayu kelas I
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
wood beams/Balok kayu
Nail/Paku 10 cm
Wood glue/Lem kayu

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
7.00
82,500
L.03
Manday
21.000
121,000
L.03
Manday
2.1000
121,000
L.04
Manday
0.350
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

577,500
2,541,000
254,100
42,350
3,414,950

M3
1.100
9,075,000
Kg
1.250
16,500
Kg
1.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

9,982,500
20,625
10,003,125

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

13,418,075
2,012,711.25
15,430,786.25

A. 4.6.1.2 Manufacture and installation of 1 m3 door frame and window frame, wooden class II or III/Pembuatan dan
pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
6.00
82,500
L.03
Manday
18.000
121,000
L.03
Manday
1.8000
121,000
L.04
Manday
0.300
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
495,000
2,178,000
217,800
36,300
2,927,100

MATERIALS/BAHAN
wood beams/Balok kayu
Nail/Paku 10 cm
Wood glue/Lem kayu

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

M3
1.200
6,600,000
Kg
1.250
16,500
Kg
1.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

7,920,000
20,625
7,940,625

10,867,725
1,630,158.75
12,497,883.75

A. 4.6.1.3 Manufacture and installation of 1 m2 standard Klamp door, wooden class II/Pembuatan dan pemasangan 1 m2 pintu
klamp standar, kayu kelas II
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.350
82,500
L.03
Manday
1.050
121,000
L.03
Manday
0.105
121,000
L.04
Manday
0.018
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
wooden board/Papan kayu
Nail/Paku 5 - 7cm

M3
Kg

0.040
0.050

6,600,000
16,500

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
28,875
127,050
12,705
2,178
170,808
264,000
825
264,825

435,633
65,344.95
500,977.95

A. 4.6.1.4 Manufacture and installation of 1 m2 door Klamp simple, wooden class III/Pembuatan dan pemasangan 1 m2 pintu
klamp sederhana, kayu kelas III
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.350
82,500
L.03
Manday
1.050
121,000
L.03
Manday
0.105
121,000
L.04
Manday
0.018
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
wooden board/Papan kayu
Nail/Paku 5 - 7cm

M3
Kg

0.040
0.050

3,630,000
16,500

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
28,875
127,050
12,705
2,178
170,808
145,200
825
146,025

316,833
47,524.95
364,357.95

A. 4.6.1.5 Manufacture and installation of 1 m2 panel doors, wooden class I or II/Pembuatan dan pemasangan 1 m2 daun pintu
panel, kayu kelas I atau II
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.000
82,500
L.03
Manday
3.000
121,000
L.03
Manday
0.300
121,000
L.04
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
wooden board/Papan kayu
Wood glue/Lem kayu

M3
Kg

0.040
0.500

6,600,000

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
82,500
363,000
36,300
6,050
487,850
264,000
264,000

751,850
112,777.50
864,627.50

A. 4.6.1.6 Manufacture and installation of 1 m2 glass doors and windows, wood grade I or II/Pembuatan dan pemasangan 1 m2
daun pintu dan jendela kaca, kayu kelas I atau II
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
wooden board/Papan kayu
Wood glue/Lem kayu

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.800
82,500
L.03
Manday
2.400
121,000
L.03
Manday
0.240
121,000
L.04
Manday
0.040
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M3
Kg

0.024
0.300

6,600,000

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

Total Price
Total Harga
(RP.)
66,000
290,400
29,040
4,840
390,280
158,400
158,400

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

548,680
82,302.00
630,982.00

15% x D

A. 4.6.1.7 Manufacture and installation of 1 m2 leaf wooden door and window jalousie class I or II/Pembuatan dan
pemasangan 1 m2 daun pintu dan jendela jalusi kayu kelas I atau II
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
wooden board/Papan kayu
Wood glue/Lem kayu

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.000
82,500
L.03
Manday
3.000
121,000
L.03
Manday
0.300
121,000
L.04
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M3
Kg

0.064
0.500

6,600,000

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
82,500
363,000
36,300
6,050
487,850
422,400
422,400

910,250
136,537.50
1,046,787.50

A. 4.6.1.8 Preparation of 1 m2 of double doors plywood, wood frame covered in class II (width up to 90cm)/Pembuatan 1 m2
daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90cm)
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wooden board/Papan kayu
Nail/Paku 1cm - 2.5cm
Wood glue/Lem kayu
Plywood tebal 4mm ukuran(90x220) cm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.700
82,500
L.03
Manday
2.100
121,000
L.03
Manday
0.210
121,000
L.04
Manday
0.035
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

57,750
254,100
25,410
4,235
341,495

M3
0.025
6,600,000
Kg
0.030
19,800
Kg
0.500
Lembar
1.00
74,800
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

165,000
594
74,800
240,394

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

581,889
87,283.35
669,172.35

15% x D

A. 4.6.1.9 Preparation of 1 m2 of double doors plywood, wood frame expose class I or II/Pembuatan 1 m2 daun pintu plywood
rangkap, rangka expose kayu kelas I atau II
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wooden board/Papan kayu
Nail/Paku 1cm - 2.5cm
Wood glue/Lem kayu
Plywood tebal 4mm ukuran(90x220) cm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.800
82,500
L.03
Manday
2.400
121,000
L.03
Manday
0.240
121,000
L.04
Manday
0.040
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

66,000
290,400
29,040
4,840
390,280

M3
0.0256
6,600,000
Kg
0.030
19,800
Kg
0.500
Lembar
1.00
74,800
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

168,960
594
74,800
244,354

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

634,634
95,195.10
729,829.10

15% x D

A. 4.6.1.10 Installation of 1 m2 jalousie frame, timber class I or II/Pemasangan 1 m2 jalusi kusen, kayu kelas I atau II
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.670
82,500
L.03
Manday
2.000
121,000
L.03
Manday
0.200
121,000
L.04
Manday
0.335
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Wooden board/Papan kayu
Nail/Paku 1cm - 2.5cm

M3
Kg

0.060
0.150

6,600,000
19,800

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
55,275
242,000
24,200
40,535
362,010
396,000
2,970

398,970

760,980
114,147.00
875,127.00

A. 4.6.1.11 Installation of 1 m2 double teak, wood frame expose class I/Pemasangan 1 m2 teakwood rangkap, rangka expose
kayu kelas I
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wooden board/Papan kayu
Nail/Paku 1cm - 2.5cm
Wood glue/Lem kayu
teakwood tebal 4mm ukuran(90x220) cm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.800
82,500
L.03
Manday
2.400
121,000
L.03
Manday
0.240
121,000
L.04
Manday
0.040
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

66,000
290,400
29,040
4,840
390,280

M3
0.025
9,075,000
Kg
0.030
19,800
Kg
0.300
Lembar
1.00
74,800
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

226,875
594
74,800
302,269

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

692,549
103,882.35
796,431.35

A. 4.6.1.12 Installation of 1 m2 double teak plywood formica, wood frame expose class II/Pemasangan 1 m2 teakwood rangkap
lapis formika, rangka expose kayu kelas II

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wooden board/Papan kayu
Nail/Paku 1cm - 2.5cm
Wood glue/Lem kayu
Teakwood 4mm (90 x 220cm)
Formica/Formika

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.850
82,500
L.03
Manday
2.550
121,000
L.03
Manday
0.255
121,000
L.04
Manday
0.043
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

70,125
308,550
30,855
5,203
414,733

M3
0.025
6,600,000
Kg
0.030
19,800
Kg
0.800
Lembar
1.00
74,800
Lembar
0.50
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

165,000
594
74,800
240,394

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

655,127
98,269.05
753,396.05

A. 4.6.1.13 Installation of 1 m3 horses conventional construction, timber class I, II and III spans 6 meters/Pemasangan 1 m3
konstruksi kuda-kuda konvensional, kayu kelas I, II dan III bentang 6 meter
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
wood beams/Balok kayu
Thick iron strips, 5 mm/Besi strip tebal 5mm
Nail/Paku 12cm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
4.000
82,500
L.03
Manday
12.000
121,000
L.03
Manday
1.200
121,000
L.04
Manday
0.200
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

330,000
1,452,000
145,200
24,200
1,951,400

M3
1.100
9,075,000
Kg
15.000
11,000
Kg
5.600
16,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

9,982,500
165,000
92,400
10,239,900

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

12,191,300
1,828,695.00
14,019,995.00

A. 4.6.1.14 Installation of 1 m3 construction expose horses, wooden class I/Pemasangan 1 m3 konstruksi kuda-kuda expose,
kayu kelas I
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
wood beams/Balok kayu
Thick iron strips, 5 mm/Besi strip tebal 5mm
Nail/Paku 12cm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
6.700
82,500
L.03
Manday
20.100
121,000
L.03
Manday
2.010
121,000
L.04
Manday
0.335
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

552,750
2,432,100
243,210
40,535
3,268,595

M3
1.200
9,075,000
Kg
15.000
11,000
Kg
5.600
16,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

10,890,000
165,000
92,400
11,147,400

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

14,415,995
2,162,399.25
16,578,394.25

A. 4.6.1.15 Installation of 1 m3 gordeng construction, timber class II/Pemasangan 1 m3 konstruksi gordeng, kayu kelas II
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
wood beams/Balok kayu
Thick iron strips, 5 mm/Besi strip tebal 5mm
Nail/Paku 12cm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
6.700
82,500
L.03
Manday
20.100
121,000
L.03
Manday
2.010
121,000
L.04
Manday
0.335
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

552,750
2,432,100
243,210
40,535
3,268,595

M3
1.100
6,600,000
Kg
15.000
11,000
Kg
3.000
16,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

7,260,000
165,000
49,500
7,474,500

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

10,743,095
1,611,464.25
12,354,559.25

A. 4.6.1.16 Installation of 1 m2 of ceramic tile roof truss, timber class II/Pemasangan 1 m2 rangka atap genteng keramik, kayu
kelas II
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
B

MATERIALS/BAHAN
Rafter/Kaso-kaso 5 x 7cm
Lath/Reng 2 x 3cm
Nail/Paku 5 dan 10 cm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

L.01
Manday
0.100
82,500
L.03
Manday
0.100
121,000
L.03
Manday
0.010
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

8,250
12,100
1,210
605
22,165

M3
0.014
6,600,000
m3
0.036
6,600,000
Kg
0.250
16,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

92,400
237,600
4,125
334,125

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

356,290
53,443.50
409,733.50

15% x D

A. 4.6.1.17 Installation of 1 m2 of concrete tile roof truss, timber class II/Pemasangan 1 m2 rangka atap genteng beton, kayu
kelas II
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Rafter/Kaso-kaso 5 x 7cm
Lath/Reng 2 x 3cm
Nail/Paku 5 dan 10 cm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.100
82,500
L.03
Manday
0.100
121,000
L.03
Manday
0.010
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

8,250
12,100
1,210
605
22,165

M3
0.014
6,600,000
m3
0.057
6,600,000
Kg
0.250
16,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

92,400
376,200
4,125
472,725

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

494,890
74,233.50
569,123.50

15% x D

A. 4.6.1.18 Installation of 1 m2 frame roof shingles, wood class II/Pemasangan 1 m2 rangka atap sirap, kayu kelas II

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
timber class II/kayu kelas II
Nail/Paku 5 dan 10 cm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.120
82,500
L.03
Manday
0.120
121,000
L.03
Manday
0.012
121,000
L.04
Manday
0.006
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

9,900
14,520
1,452
726
26,598

M3
0.014
6,600,000
M3
0.057
16,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

92,400
941
93,341

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

119,939
17,990.78
137,929.28

A. 4.6.1.19 Installation of 1 m2 of the ceiling frame (50 x 100) cm, wooden class II or III/Pemasangan 1 m2 rangka langit-langit
(50 x 100)cm, kayu kelas II atau III
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Rafter/Kaso-kaso 5 x 7cm
Nail/Paku 7cm - 10cm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.150
82,500
L.03
Manday
0.300
121,000
L.03
Manday
0.030
121,000
L.04
Manday
0.075
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

12,375
36,300
3,630
9,075
61,380

M3
0.0154
6,600,000
Kg
0.200
16,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

101,640
3,300
104,940

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

166,320
24,948.00
191,268.00

A. 4.6.1.20 Installation of 1 m2 of the ceiling frame (60 x 60) cm, wooden class II or III/Pemasangan 1 m2 rangka langit-langit
(60 x 60)cm, kayu kelas II atau III
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Rafter/Kaso-kaso 5 x 7cm
Nail/Paku 7cm - 10cm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.200
82,500
L.03
Manday
0.300
121,000
L.03
Manday
0.030
121,000
L.04
Manday
0.010
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M3
Kg

0.0163
0.250

6,600,000
16,500

Total Price
Total Harga
(RP.)
16,500
36,300
3,630
1,210
57,640
107,580
4,125

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

111,705

169,345
25,401.75
194,746.75

A. 4.6.1.21 Installation of 1 m1 lisplank size (3 x 20) cm, wooden class I or class II/Pemasangan 1 m1 lisplank ukuran (3 x
20)cm, kayu kelas I atau kelas II
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wooden board/Papan kayu
Nail/Paku 5cm - 7cm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.100
82,500
L.03
Manday
0.200
121,000
L.03
Manday
0.020
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

8,250
24,200
2,420
605
35,475

M3
0.0108
6,600,000
Kg
0.100
16,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

71,280
1,650
72,930

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

108,405
16,260.75
124,665.75

A. 4.6.1.22 Installation of 1 m1 lisplank size (3 x 30) cm, wooden class I or class II/Pemasangan 1 m1 lisplank ukuran (3 x
30)cm, kayu kelas I atau kelas II
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wooden board/Papan kayu
Nail/Paku 5cm - 7cm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.100
82,500
L.03
Manday
0.200
121,000
L.03
Manday
0.020
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

8,250
24,200
2,420
605
35,475

M3
0.011
6,600,000
Kg
0.050
16,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

72,600
825
73,425

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

108,900
16,335.00
125,235.00

A. 4.6.1.23 Installation of 1 m2 frame separating wall (60 x 120) cm timber class II or III/Pemasangan 1 m2 rangka dinding
pemisah (60 x 120) cm kayu kelas II atau III
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wood beams/Balok kayu
Nail/Paku 5cm - 7cm

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.150
82,500
L.03
Manday
0.450
121,000
L.03
Manday
0.045
121,000
L.04
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

12,375
54,450
5,445
968
73,238

M3
0.028
6,600,000
Kg
0.150
16,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

184,800
2,475
187,275

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

260,513
39,076.95
299,589.95

A. 4.6.1.24 Installation of 1 m2 of wall dividers double teak, wood frame class II/Pemasangan 1 m2 dinding pemisah teakwood
rangkap, rangka kayu kelas II
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
wood beams/Balok kayu, 6 x 12
Nail/Paku 5 dan 10
Teakwood 4mm, 120 x 240
Wood glue/Lem kayu

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.150
82,500
L.03
Manday
0.450
121,000
L.03
Manday
0.045
121,000
L.04
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

12,375
54,450
5,445
968
73,238

M3
0.028
6,600,000
Kg
0.150
16,500
Lembar
0.860
74,800
Kg
0.560
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

184,800
2,475
64,328
251,603

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

324,841
48,726.15
373,567.15

A. 4.6.1.25 Installation of 1 m2 duplex separation wall plywood, wood frame class II/Pemasangan 1 m2 dinding pemisah
plywood rangkap, rangka kayu kelas II
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Wood beams/Balok kayu, 6 x 12
Nail/Paku 5 dan 10
Plywood 4mm, 120 x 240
Wood glue/Lem kayu

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.200
82,500
L.03
Manday
0.600
121,000
L.03
Manday
0.060
121,000
L.04
Manday
0.010
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

16,500
72,600
7,260
1,210
97,570

M3
0.028
6,600,000
Kg
0.150
16,500
Lembar
0.860
74,800
Kg
0.560
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

184,800
2,475
64,328
251,603

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

349,173
52,375.95
401,548.95

15% x D

A. 4.6.1.26 Installation of 1 m2 of wall of wooden planks lambrisering class I/Pemasangan 1 m2 dinding lambrisering dari
papan kayu kelas I
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.600
82,500
L.03
Manday
1.800
121,000
L.03
Manday
0.180
121,000
L.04
Manday
0.030
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Wooden board/Papan kayu
Nail/Paku 5 dan 10
Paku skrup 10 cm

M3
Kg
Kg

0.007
0.100
0.150

9,075,000
16,500

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
49,500
217,800
21,780
3,630
292,710
63,525
1,650
65,175

357,885
53,682.75
411,567.75

15% x D

A. 4.6.1.27 1 m2 of wall mounting lambrisering of plywood size (120 x 240) cm/Pemasangan 1 m2 dinding lambrisering dari
plywood ukuran (120 x 240) cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.025
82,500
L.03
Manday
0.075
121,000
L.03
Manday
0.008
121,000
L.04
Manday
0.001
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Plywood 4mm
Nail/Paku 1 dan 2.5

M3
Kg

0.400
0.050

Total Price
Total Harga
(RP.)
2,063
9,075
968
121
12,227
990

19,800

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

990

13,217
1,982.48
15,198.98

A. 4.6.1.28 Installation of 1 m2 cubicle walls, wood frame class III or IV/Pemasangan 1 m2 dinding bilik, rangka kayu kelas III
atau IV
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
bamboo booths/Bilik bambu
Rafter/Kaso-kaso 5 x 7
Nail/Paku
list of timber / List kayu 2/4

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.100
82,500
L.03
Manday
0.050
121,000
L.03
Manday
0.005
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M2
M3
Kg
M3

1.500
0.014
0.012
0.003

3,630,000
3,630,000

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

A. 4.6.2 KEY WORK UNIT PRICE AND GLASS /HARGA SATUAN PEKERJAAN KUNCI DAN KACA

Total Price
Total Harga
(RP.)
8,250
6,050
605
605
15,510
50,820
10,890
61,710

77,220
11,583.00
88,803.00

A. 4.6.2.1 Installation 1 key pieces of antique planting/Pemasangan 1 buah kunci tanam antik

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Planting antique key/Kunci tanam antik

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.06
82,500
L.02
Manday
0.60
99,000
L.03
Manday
0.06
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
4,950
59,400
7,260
363
71,973

Bh
1.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

71,973
10,795.95
82,768.95

A. 4.6.2.2 Installation 1 key pieces usual planting/Pemasangan 1 buah kunci tanam biasa

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Key usual planting/Kunci tanam biasa

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.01
82,500
L.02
Manday
0.50
99,000
L.03
Manday
0.05
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
825
49,500
6,050
605
56,980

Bh
1.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

56,980
8,547.00
65,527.00

A. 4.6.2.3 Installation 1 piece bathroom lock/Pemasangan 1 buah kunci kamar mandi

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Planting key KM/Kunci tanam KM

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.005
82,500
L.02
Manday
0.50
99,000
L.03
Manday
0.05
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

413
49,500
6,050
363
56,326

Bh
1.00
29,700
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

29,700
29,700

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

86,026
12,903.83
98,929.33

A. 4.6.2.4 Installation 1 piece lock cylinder/Pemasangan 1 buah kunci silinder

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Lock cylinder/Kunci silinder

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.005
82,500
L.02
Manday
0.50
99,000
L.03
Manday
0.05
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
413
49,500
6,050
363
56,326

Bh
1.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

56,326
8,448.83
64,774.33

A. 4.6.2.5 Installation of door hinges 1 piece/Pemasangan 1 buah engsel pintu

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.015
82,500
L.02
Manday
0.15
99,000
L.03
Manday
0.015
121,000
L.04
Manday
0.0008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
1,238
14,850
1,815
97
17,999

door hinges/Engsel pintu


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Bh
1.00
19,800
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

19,800
19,800

37,799
5,669.90
43,469.20

A. 4.6.2.6 Installation 1 piece window butterfly hinge/Pemasangan 1 buah engsel jendela kupu-kupu

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Butterfly hinges/Engsel kupu-kupu

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.01
82,500
L.02
Manday
0.10
99,000
L.03
Manday
0.010
121,000
L.04
Manday
0.0005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
825
9,900
1,210
61
11,996

Bh
1.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

11,996
1,799.33
13,794.83

A. 4.6.2.7 1 piece hinge mounting wind/Pemasangan 1 buah engsel angin

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
hinge wind/Engsel angin

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.10
82,500
L.02
Manday
0.20
99,000
L.03
Manday
0.020
121,000
L.04
Manday
0.0005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
8,250
19,800
2,420
61
30,531

Bh
1.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

30,531
4,579.58
35,110.08

A. 4.6.2.8 Installation 1 piece spring KNIP/Pemasangan 1 buah spring knip

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Spring knip

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.015
82,500
L.02
Manday
0.15
99,000
L.03
Manday
0.015
121,000
L.04
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
1,238
14,850
1,815
968
18,871

Bh
1.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

18,871
2,830.58
21,701.08

A. 4.6.2.9 1 piece mounting hooks wind/Pemasangan 1 buah kait angin

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
wind hooks/kait angin

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.015
82,500
L.02
Manday
0.15
99,000
L.03
Manday
0.015
121,000
L.04
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

1,238
14,850
1,815
968
18,871

Bh
1.00
16,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

16,500
16,500

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

35,371
5,305.58
40,676.08

A. 4.6.2.10 Installation of 1 piece of door closer/Pemasangan 1 buah door closer

Nr./No.

Description/Uraian

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan

Total Price
Total Harga

Nr./No.

Description/Uraian
(Rp.)

MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Door closer

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

(RP.)

L.01
Manday
0.05
82,500
L.02
Manday
0.5
99,000
L.03
Manday
0.05
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

4,125
49,500
6,050
363
60,038

Set
1.00
264,000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

264,000
264,000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

324,038
48,605.70
372,643.70

A. 4.6.2.11 1 piece lock mounting slots/Pemasangan 1 buah kunci slot

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Lock slot/Kunci slot

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.02
82,500
L.02
Manday
0.2
99,000
L.03
Manday
0.02
121,000
L.04
Manday
0.001
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

1,650
19,800
2,420
121
23,991

Bh
1.00
14,300
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

14,300
14,300

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

38,291
5,743.65
44,034.65

A. 4.6.2.12 1 piece mounting Door holder/Pemasangan 1 buah Door holder

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Door holder

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.05
82,500
L.02
Manday
0.5
99,000
L.03
Manday
0.05
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

4,125
49,500
6,050
363
60,038

Bh
1.00
33,000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

33,000
33,000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

93,038
13,955.70
106,993.70

A. 4.6.2.13 1 piece mounting Door stop/Pemasangan 1 buah Door stop

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Door stop

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.01
82,500
L.02
Manday
0.1
99,000
L.03
Manday
0.01
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

825
9,900
1,210
605
12,540

Bh
1.00
24,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

24,200
24,200

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

36,740
5,511.00
42,251.00

A. 4.6.2.14 1 piece mounting rail sliding door/Pemasangan 1 buah Rel pintu sorong

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Sliding door rails/Rel pintu sorong

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.06
82,500
L.02
Manday
0.6
99,000
L.03
Manday
0.06
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

4,950
59,400
7,260
363
71,973

Set
1.00
264,000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

264,000
264,000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

335,973

E
F

15% x D

Overhead & Profit (Contoh 15%)


Unit Price Work/Harga Satuan Pekerjaan (D+E)

50,395.95
386,368.95

A. 4.6.2.15 Installation 1 piece cabinet lock/Pemasangan 1 buah kunci lemari

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
key cabinets/Kunci lemari

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.03
82,500
L.02
Manday
0.3
99,000
L.03
Manday
0.03
121,000
L.04
Manday
0.0013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

2,063
24,750
3,025
157
29,995

Set
1.00
8,800
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

8,800
8,800

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

38,795
5,819.22
44,614.02

A. 4.6.2.16 Installation of 1 m2 glass 3mm thick/Pemasangan 1 m2 kaca tebal 3mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
3mm thick glass/Kaca tebal 3mm
Sealant

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.03
82,500
L.02
Manday
0.3
99,000
L.03
Manday
0.03
121,000
L.04
Manday
0.0013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

2,063
24,750
3,025
157
29,995

M2
1.00
71,500
Kg
0.05
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

71,500
71,500

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

101,495
15,224.22
116,719.02

A. 4.6.2.17 Installation of 1 m2 glass 5mm thick/Pemasangan 1 m2 kaca tebal 5mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
5mm thick glass/Kaca tebal 5mm
Sealant

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.015
82,500
L.02
Manday
0.15
99,000
L.03
Manday
0.015
121,000
L.04
Manday
0.0008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

1,238
14,850
1,815
97
17,999

M2
1.10
121,000
Kg
0.05
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

133,100
133,100

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

151,099
22,664.90
173,764.20

A. 4.6.2.22 Installation of 1 m2 glass 5 mm thick wireglass/Pemasangan 1 m2 kaca wireglassed tebal 5mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.015
82,500
L.02
Manday
0.15
99,000
L.03
Manday
0.015
121,000
L.04
Manday
0.0008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
glass wireglass/Kaca wireglassed tebal 5mm

M2

Total Price
Total Harga
(RP.)
1,238
14,850
1,815
97
17,999

1.10

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

17,999
2,699.90
20,699.20

A. 4.6.2.23 Installation of 1 m2 of stained glass 5mm thick/Pemasangan 1 m2 kaca patri tebal 5mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

Labour/Pekerja
Carpenter/Tukang kayu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
B

MATERIALS/BAHAN
Stained glass 5mm/Kaca patri 5mm
Sealant

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

L.01
Manday
0.075
82,500
L.02
Manday
0.15
99,000
L.03
Manday
0.015
121,000
L.04
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

6,188
14,850
1,815
484
23,337

M2
1.10
1,760,000
Kg
0.05
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,936,000
1,936,000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

1,959,337
293,900.48
2,253,236.98

15% x D

A. 4.7.1 PAINTING WORK UNIT PRICE/HARGA SATUAN PEKERJAAN PENGECATAN


A. 4.7.1.1 1 m2 erosion / scraping old paint surface/ 1 m2 Pengikisan/pengerokan permukaan cat lama

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor
MATERIALS/BAHAN
caustic soda/Soda api

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.15
82,500
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

12,375
363
12,738

Kg
0.050
33,000
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

1,650
1,650

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

14,388
2,158.20
16,546.20

15% x D

A. 4.7.1.2 1 m2 surface area Laundering ever painted wall/ 1 m2 Pencucian bidang permukaan tembok yang pernah dicat
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

MATERIALS/BAHAN
Soap/Sabun

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.15
82,500
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

12,375
363
12,738

Kg
0.050
12,320
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

616
616

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

13,354
2,003.10
15,357.10

15% x D

A. 4.7.1.3 1 m2 of surface rust on the steel scraping manually/ 1 m2 Pengerokan karat pada permukaan baja cara manual
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

MATERIALS/BAHAN
Soap/Sabun

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.15
82,500
L.04
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

12,375
968
13,343

Kg
0.050
12,320
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

616
616

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

13,959
2,093.85
16,052.85

15% x D

A. 4.7.1.4 1 m2 field painting new wood (1 plamir layer, 1 layer of basecoat, 2 coats of paint cover)/ 1 m2 Pengecatan bidang
kayu baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
paint menie/Cat menie
Plamir
priming/Cat dasar
paint cover/Cat penutup
brush/Kuas
diluent/Pengencer
sandpaper/Amplas

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.070
82,500
L.02
Manday
0.009
99,000
L.03
Manday
0.006
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Kg
Kg
Kg
Kg
Bh
Kg
Lembar

0.20
0.15
0.17
0.26
0.01
0.03
0.20

46,200
18,700
35,200
90,200
13,750
3,850

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

Total Price
Total Harga
(RP.)
5,775
891
726
363
7,755
9,240
2,805
5,984
23,452
138
770
42,389

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

50,144
7,521.53
57,665.03

15% x D

A. 4.7.1.5 Painting 1 m2 field of new wood (1 plamir layer, 1 layer of base paint, 3 layers of paint cover)/ Pengecatan 1 m2
bidang kayu baru (1 lapis plamir, 1 lapis cat dasar, 3 lapis cat penutup)
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.070
82,500
L.02
Manday
0.105
99,000
L.03
Manday
0.004
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
paint menie/Cat menie
Plamir
priming/Cat dasar
paint cover/Cat penutup
brush/Kuas
diluent/Pengencer
sandpaper/Amplas

Kg
Kg
Kg
Kg
Bh
Kg
Lembar

0.20
0.15
0.17
0.35
0.01
0.03
0.20

46,200
18,700
35,200
90,200
13,750
3,850

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
5,775
10,395
484
363
17,017
9,240
2,805
5,984
31,570
138
770
50,507

67,524
10,128.53
77,652.03

A. 4.7.1.6 Resurfacing 1 m2 wood with teak oil field/ Pelaburan 1 m2 bidang kayu dengan teak oil

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.040
82,500
L.02
Manday
0.063
99,000
L.03
Manday
0.063
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Teak oil

Liter

Total Price
Total Harga
(RP.)
3,300
6,237
7,623
363
17,523

0.36

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

17,523
2,628.45
20,151.45

A. 4.7.1.7 Resurfacing 1 m2 field with camphor wood/ Pelaburan 1 m2 bidang kayu dengan politur

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
camphor/Politur
Camphor ready-made/Politur jadi
sandpaper/Ampelas

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.04
82,500
L.02
Manday
0.06
99,000
L.03
Manday
0.016
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

3,300
5,940
1,936
363
11,539

Liter
0.15
53,900
Liter
0.372
58,300
Lembar
2.00
3,850
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

8,085
21,688
7,700
37,473

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

49,012
7,351.74
56,363.34

A. 4.7.1.8 Resurfacing 1 m2 areas of wood with paint residue and tar/ Pelaburan 1 m2 bidang kayu dengan cat residu dan ter
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor
MATERIALS/BAHAN
Residue or tar/Residu atau ter

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.10
82,500
L.04
Manday
0.006
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

8,250
726
8,976

Liter
0.35
49,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

17,325
17,325

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

26,301
3,945.15
30,246.15

A. 4.7.1.9 Resurfacing 1 m2 areas of wood with varnish/ Pelaburan 1 m2 bidang kayu dengan vernis

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
varnish/Vernis
putty/Dempul
sandpaper/Ampelas

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.16
82,500
L.02
Manday
0.16
99,000
L.03
Manday
0.016
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

13,200
15,840
1,936
363
31,339

Liter
0.15
27,500
Kg
0.05
22,000
Lembar
0.10
3,850
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

4,125
1,100
385
5,610

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

36,949
5,542.35
42,491.35

15% x D

A. 4.7.1.10 New wall painting 1 m2 (1 plamir layer, 1 layer of basecoat, 2 coats of paint cover)/ Pengecatan 1 m2 tembok baru
( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Plamir
priming/Cat dasar
paint cover/Cat penutup

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.02
82,500
L.02
Manday
0.063
99,000
L.03
Manday
0.0063
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

1,650
6,237
762
363
9,012

Kg
0.10
8,800
Kg
0.10
35,200
Kg
0.26
90,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

880
3,520
23,452
27,852

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

36,864
5,529.65
42,393.95

15% x D

A. 4.7.1.11 Old wall painting 1 m2 (1 layer of basecoat, 2 coats of paint cover)/ Pengecatan 1 m2 tembok lama ( 1 lapis cat
dasar, 2 lapis cat penutup )
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.028
82,500
L.02
Manday
0.042
99,000
L.03
Manday
0.0042
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
priming/Cat dasar
paint cover/Cat penutup

Kg
Kg

0.12
0.18

35,200
90,200

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
2,310
4,158
508
363
7,339
4,224
16,236
20,460

27,799
4,169.88
31,969.08

15% x D

A. 4.7.1.12 Resurfacing 1 m2 wall with kalkarium/ Pelaburan 1 m2 tembok dengan kalkarium

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.028
82,500
L.02
Manday
0.042
99,000
L.03
Manday
0.0042
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
kalkarium

Kg

Total Price
Total Harga
(RP.)
2,310
4,158
508
363
7,339

0.10

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

7,339
1,100.88
8,440.08

15% x D

A. 4.7.1.13 Resurfacing 1 m2 wall with whiting/ Pelaburan 1 m2 tembok dengan kapur sirih

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja

Code
Kode

Unit
Satuan

L.01

Manday

Coefficient
Koefisien

0.15

Unit Price
Harga Satuan
(Rp.)
82,500

Total Price
Total Harga
(RP.)
12,375

Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
B

MATERIALS/BAHAN
whiting/Kapur sirih
Sandpaper/Ampelas
Reed/Alang-alang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

L.02
Manday
0.001
99,000
L.03
Manday
0.0001
121,000
L.04
Manday
0.0025
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

99
12
303
12,789

Kg
0.15
Lembar
0.10
3,850
Ikat
0.25
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

385
385

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

13,174
1,976.04
15,149.64

15% x D

A. 4.7.1.14 1 m2 wall resurfacing old with whiting (maintenance)/ Pelaburan 1 m2 tembok lama dengan kapur sirih
(pemeliharaan)
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
whiting/Kapur sirih
Sandpaper/Ampelas
Reed/Alang-alang
EQUIPMENT/PERALATAN

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.04
82,500
L.02
Manday
0.005
99,000
L.03
Manday
0.0005
121,000
L.04
Manday
0.0025
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

3,300
495
61
303
4,158

Kg
0.30
Lembar
0.20
3,850
Ikat
0.25
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

770
770

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

4,928
739.20
5,667.20

15% x D

A. 4.7.1.15 Installation of 1 m2 wallpaper/ Pemasangan 1 m2 wallpaper

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.02
82,500
L.02
Manday
0.2
99,000
L.03
Manday
0.02
121,000
L.04
Manday
0.0025
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Wallpaper
Glue/Lem

M2
Kg

1.20
0.20

1,650
19,800
2,420
303
24,173

308,000
9,350

369,600
1,870

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

371,470

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

395,643
59,346.38
454,988.88

15% x D

A. 4.7.1.16 Painting 1 m2 surface of steel with iron menie/ Pengecatan 1 m2 permukaan baja dengan menie besi

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.02
82,500
L.02
Manday
0.2
99,000
L.03
Manday
0.02
121,000
L.04
Manday
0.0025
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Menie iron/Menie besi
brush/Kuas

Kg
Bh

0.10
0.01

40,700
13,750

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

Total Price
Total Harga
(RP.)
1,650
19,800
2,420
303
24,173
4,070
138
4,208

28,380
4,257.00
32,637.00

A. 4.7.1.17 Painting 1 m2 surface of steel with iron menie with scaffolding/ Pengecatan 1 m2 permukaan baja dengan menie
besi dengan perancah
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Menie iron/Menie besi
diluent/Pengencer
Brush/Kuas
wooden scaffold/Perancah kayu

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.25
82,500
L.02
Manday
0.225
99,000
L.03
Manday
0.0225
121,000
L.04
Manday
0.0075
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

20,625
22,275
2,723
908
46,530

Kg
0.10
40,700
Liter
0.01
Bh
0.01
13,750
M3
0.002
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

4,070
138
4,208

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

50,738
7,610.63
58,348.13

A. 4.7.1.18 1 m2 painting galvanized steel surfaces manually 4 ply/ Pengecatan 1 m2 permukaan baja galvanis secara manual 4
lapis
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Menie A
Manie B
Paint/Cat
Brush/Kuas
diluent/Pengencer

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.25
82,500
L.02
Manday
0.25
99,000
L.03
Manday
0.025
121,000
L.04
Manday
0.0013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

20,625
24,750
3,025
157
48,557

Kg
0.10
Kg
0.10
Kg
0.08
Bh
0.01
13,750
Liter
0.01
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

138
138

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

48,695

E
F

Overhead & Profit (Contoh 15%)


Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

7,304.22
55,999.02

A. 4.7.1.19 1 m2 painting galvanized steel surfaces manually 1 layer paint system edge/ Pengecatan 1 m2 permukaan baja
galvanis secara manual sistem 1 lapis cat mutakhir
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Paint/Cat
Brush/Kuas
diluent/Pengencer

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.06
82,500
L.02
Manday
0.06
99,000
L.03
Manday
0.012
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

4,950
5,940
1,452
363
12,705

Kg
0.30
Bh
0.01
13,750
Liter
0.01
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

138
138

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

12,843
1,926.38
14,768.88

A. 4.7.1.20 Painting 1 m2 surface of galvanized steel 3 tier system manually/ Pengecatan 1 m2 permukaan baja galvanis secara
manual sistem 3 lapis
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
priming/Cat dasar
paint between/Cat antara
paint cover/Cat penutup
Brush/Kuas
Diluent/Pengencer

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.40
82,500
L.02
Manday
0.80
99,000
L.03
Manday
0.08
121,000
L.04
Manday
0.02
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

33,000
79,200
9,680
2,420
124,300

Kg
0.11
35,200
Kg
0.17
27,500
Kg
0.08
90,200
Bh
0.01
13,750
Liter
0.01
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

3,872
4,675
7,216
138
15,901

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

140,201
21,030.08
161,230.58

A. 4.7.1.21 1 m2 painting galvanized steel surface 3 layers of paint spray system edge/ Pengecatan 1 m2 permukaan baja
galvanis secara semprot sistem 3 lapis cat mutakhir
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Painter/Tukang cat
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Priming/Cat dasar
Diluent/Pengencer

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.40
82,500
L.02
Manday
0.70
99,000
L.03
Manday
0.07
121,000
L.04
Manday
0.02
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

33,000
69,300
8,470
2,420
113,190

Kg
0.30
35,200
Liter
0.01
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

10,560
10,560

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

123,750
18,562.50
142,312.50

A. 5.1.1 SANITATION WORK UNIT PRICE IN BUILDING/HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
A. 5.1.1.1 Installation of closet seat 1 piece/monoblock / Pemasangan 1 buah closet duduk/monoblock

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Closet sitting/Closet duduk
equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
3.30
82,500
L.02
Manday
1.10
99,000
L.03
Manday
0.01
121,000
L.04
Manday
0.16
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

272,250
108,900
1,210
19,360
401,720

Unit
1.00
594,000
Ls
6% x closet
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

594,000
594,000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

A. 5.1.1.2 Installation 1 piece closet squatting porslen/Pemasangan 1 buah closet jongkok porslen

995,720
149,358.00
1,145,078.00

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Closet squat/Closet jongkok
Portland cement/Semen portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.00
82,500
L.02
Manday
1.50
99,000
L.03
Manday
0.15
121,000
L.04
Manday
0.16
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

82,500
148,500
18,150
19,360
268,510

Unit
1.00
176,000
Kg
6.00
1,375
M3
0.01
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

176,000
8,250
1,018
185,268

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

453,778
68,066.63
521,844.13

A. 5.1.1.3 Installation 1 piece closet squatting terrazzo/Pemasangan 1 buah closet jongkok teraso

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Closet squat/Closet jongkok
Portland cement/Semen portland
Sand plug/Pasir pasang
red brick/Bata merah

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.00
82,500
L.02
Manday
1.50
99,000
L.03
Manday
0.15
121,000
L.04
Manday
0.05
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

82,500
148,500
18,150
6,050
255,200

Unit
1.00
35,200
Kg
6.00
1,375
M3
0.01
101,750
Bh
7.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

35,200
8,250
1,018
44,468

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

299,668
44,950.13
344,617.63

A. 5.1.1.4 1 piece Urinal Installation/Pemasangan 1 buah Urinoir

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
urinal/Urinoir
Portland cement/Semen portland
Sand plug/Pasir pasang
equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.00
82,500
L.02
Manday
1.00
99,000
L.03
Manday
0.10
121,000
L.04
Manday
0.05
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

82,500
99,000
12,100
6,050
199,650

Unit
1.00
154,000
Kg
6.00
1,375
M3
0.01
101,750
%
30.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

154,000
8,250
1,018
163,268

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

362,918
54,437.63
417,355.13

A. 5.1.1.5 Installation 1 piece sink/Pemasangan 1 buah wastafel

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
sink/Wastafel
Portland cement/Semen portland
Sand plug/Pasir pasang
equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
1.20
82,500
L.02
Manday
1.45
99,000
L.03
Manday
0.15
121,000
L.04
Manday
0.06
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

99,000
143,550
18,150
7,260
267,960

Unit
1.20
291,500
Kg
6.00
1,375
M3
0.01
101,750
%
12.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

349,800
8,250
1,018
359,068

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

627,028
94,054.13
721,081.63

A. 5.1.1.6 Installation 1 piece porcelain bathcuip/Pemasangan 1 buah bathcuip porselen

Nr./No.

Description/Uraian

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Bathcuip
equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

L.01
Manday
0.075
82,500
L.02
Manday
0.75
99,000
L.03
Manday
0.075
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

6,188
74,250
9,075
363
89,876

Unit
1.00
%
20.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

89,876
13,481.33
103,356.83

15% x D

A. 5.1.1.7 Installation 1 piece fiberglass tub, vol 1 m3/Pemasangan 1 buah bak fibreglass vol 1 m3

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
fiberglass tub/bak fibreglass
equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
3.00
82,500
L.02
Manday
4.50
99,000
L.03
Manday
0.05
121,000
L.04
Manday
0.90
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

247,500
445,500
6,050
108,900
807,950

Unit
1.00
198,000
Ls
12% bak
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

198,000
198,000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

1,005,950
150,892.50
1,156,842.50

15% x D

A. 5.1.1.8 Installation 1 piece bath brick, 0.30 m3 volume/Pemasangan 1 buah bak mandi batu bata volume 0.30 m3

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen portland
Sand plug/Pasir pasang
Porcelain 11 x 11/Porselen 11 x 11
Color cement/Semen warna

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
6.00
82,500
L.02
Manday
3.00
99,000
L.03
Manday
0.30
121,000
L.04
Manday
0.03
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

495,000
297,000
36,300
3,630
831,930

M3
150.00
Kg
120.00
1,375
M3
0.30
101,750
Bh
360.00
Kg
6.00
13,200
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

165,000
30,525
79,200
274,725

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

1,106,655
165,998.25
1,272,653.25

A. 5.1.1.9 Installation of terrazzo bathtub 1 piece volume 0.30 m3/Pemasangan 1 buah bak mandi teraso volume 0,30 m3
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
fiberglass tub/bak mandi teraso
equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
3.00
82,500
L.02
Manday
4.50
99,000
L.03
Manday
0.05
121,000
L.04
Manday
0.90
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

247,500
445,500
6,050
108,900
807,950

Unit
1.00
198,000
Ls
12% x bak
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

198,000
198,000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

1,005,950
150,892.50
1,156,842.50

A. 5.1.1.10 Installation 1 piece fiberglass tub tubs volume of 1 m3/Pemasangan 1 buah bak bak air fibreglass volume 1 m3
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.30
82,500
L.02
Manday
0.45
99,000
L.03
Manday
0.045
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
24,750
44,550
5,445
1,815
76,560

fiberglass tub/bak fibreglass


equipment/Perlengkapan
C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Unit
1.00
198,000
%
12.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

198,000
198,000

274,560
41,184.00
315,744.00

A. 5.1.1.11 Installation of 1 unit volume of 1 m3 concrete tank/Pemasangan 1 buah bak beton volume 1 m3

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Concrete/Beton 1 : 2 : 3
steel reinforcement/Baja tulangan
timber formwork/Kayu bekisting
porcelain tile/Ubin porselen
equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
3.50
82,500
L.02
Manday
4.50
99,000
L.03
Manday
0.05
121,000
L.04
Manday
0.018
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

288,750
445,500
6,050
2,178
742,478

M3
0.90
Kg
180.00
20,900
M2
8.00
Bh
500.00
%
10.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

3,762,000
3,762,000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

4,504,478
675,671.70
5,180,149.70

A. 5.1.1.12 Installation 1 piece sink stainlessteel/Pemasangan 1 buah bak cuci piring stainlessteel

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Sink/Bak cuci piring
Water drain

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.03
82,500
L.02
Manday
0.30
99,000
L.03
Manday
0.03
121,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

2,475
29,700
3,630
1,815
37,620

Unit
1.00
212,300
Bh
1.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

212,300
212,300

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

249,920
37,488.00
287,408.00

A. 5.1.1.13 Installation 1 piece sink terrazzo/Pemasangan 1 buah bak cuci piring teraso

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Sink/Bak cuci piring
Water drain
Portland cement/Semen portland
Sand plug/Pasir pasang

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.05
82,500
L.02
Manday
0.50
99,000
L.03
Manday
0.05
121,000
L.04
Manday
0.025
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

4,125
49,500
6,050
3,025
62,700

Unit
1.00
357,500
Bh
1.00
Kg
20.00
1,375
M3
0.05
101,750
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

357,500
27,500
5,088
390,088

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

452,788
67,918.13
520,705.63

A. 5.1.1.14 Installation 1 piece floor drain/Pemasangan 1 buah floor drain

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor

MATERIALS/BAHAN
Floor drain

EQUIPMENT/PERALATAN

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.01
82,500
L.02
Manday
0.10
99,000
L.03
Manday
0.01
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
825
9,900
1,210
605
12,540

Unit
1.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

12,540
1,881.00
14,421.00

15% x D

A. 5.1.1.15 Installation of 1 piece of masonry control boxes 30x30cm 35cm high/Pemasangan 1 buah bak kontrol pasangan
bata 30x30cm tinggi 35cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen portland
Sand plug/Pasir pasang
Sand concrete/Pasir beton
Gravel/Kerikil
steel reinforcement/Baja tulangan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
2.16
82,500
L.02
Manday
0.72
99,000
L.03
Manday
0.072
121,000
L.04
Manday
0.011
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

178,200
71,280
8,712
1,331
259,523

Bh
40.00
Kg
44.00
1,375
M3
0.07
101,750
M3
0.06
101,750
M3
0.07
440,000
Kg
1.60
20,900
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

60,500
7,123
6,105
30,800
33,440
137,968

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

397,491
59,623.58
457,114.08

A. 5.1.1.16 Installation of 1 piece of masonry control boxes 45x45cm 50cm high/Pemasangan 1 buah bak kontrol pasangan
bata 45x45cm tinggi 50cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen portland
Sand plug/Pasir pasang
Sand concrete/Pasir beton
Gravel/Kerikil
steel reinforcement/Baja tulangan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
3.20
82,500
L.02
Manday
1.15
99,000
L.03
Manday
0.011
121,000
L.04
Manday
0.016
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

264,000
113,850
1,331
1,936
381,117

Bh
70.00
Kg
77.00
1,375
M3
0.13
101,750
M3
0.09
101,750
M3
0.02
440,000
Kg
2.60
20,900
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

105,875
13,228
9,158
8,800
54,340
191,400

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

572,517
85,877.55
658,394.55

A. 5.1.1.17 Installation of 1 piece of masonry control boxes 60x60cm 65cm high/Pemasangan 1 buah bak kontrol pasangan
bata 60x60cm tinggi 65cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Red brick/Bata merah
Portland cement/Semen portland
Sand plug/Pasir pasang
Sand concrete/Pasir beton
Gravel/Kerikil
steel reinforcement/Baja tulangan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
3.20
82,500
L.02
Manday
1.15
99,000
L.03
Manday
0.011
121,000
L.04
Manday
0.016
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

264,000
113,850
1,331
1,936
381,117

Bh
70.00
Kg
77.00
1,375
M3
0.13
101,750
M3
0.09
101,750
M3
0.02
440,000
Kg
2.60
20,900
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

105,875
13,228
9,158
8,800
54,340
191,400

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

572,517
85,877.55
658,394.55

A. 5.1.1.18 Installation of 1 m1 diameter galvanized pipe 1/2 "/Pemasangan 1 m1 pipa galvanis diameter 1/2"

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Galvanized pipe /Pipa galvanis 1/2"
Equipment/Perlengkapan
EQUIPMENT/PERALATAN

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.054
82,500
L.02
Manday
0.09
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.027
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M
1.20
Ls
35% x pipa
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

Total Price
Total Harga
(RP.)
4,455
8,910
1,089
3,267
17,721
-

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

17,721
2,658.15
20,379.15

A. 5.1.1.19 1 piece faucet mounting diameter 1/2 "or 3/4"/Pemasangan 1 buah kran diameter 1/2" atau 3/4"

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
water faucet/Kran air
Sealtape

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.01
82,500
L.02
Manday
0.4
99,000
L.03
Manday
0.04
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

825
39,600
4,840
605
45,870

M
1.00
11,000
Buah
0.025
3,850
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

11,000
96
11,096

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

56,966
8,544.94
65,511.19

A. 5.1.1.20 Installation of 1 m1 diameter galvanized pipe 3/4 "/Pemasangan 1 m1 pipa galvanis diameter 3/4"

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Galvanized pipe /Pipa galvanis 3/4"
Equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.054
82,500
L.02
Manday
0.09
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.027
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
4,455
8,910
1,089
3,267
17,721

M
1.20
%
35.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

17,721
2,658.15
20,379.15

A. 5.1.1.21 Installation of 1 m1, galvanized pipe diameter 1 "/Pemasangan 1 m1 pipa galvanis diameter 1"

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Galvanized pipe/Pipa galvanis 1"
Equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.054
82,500
L.02
Manday
0.09
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.027
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
4,455
8,910
1,089
3,267
17,721

M
1.20
%
35.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

17,721
2,658.15
20,379.15

A. 5.1.1.22 Installation of 1 m1 diameter galvanized pipe 1 1/2 "/Pemasangan 1 m1 pipa galvanis diameter 1 1/2"

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Galvanized pipe /Pipa galvanis 1 1/2"
Equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.108
82,500
L.02
Manday
0.18
99,000
L.03
Manday
0.018
121,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
8,910
17,820
2,178
605
29,513

M
1.20
%
35.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

29,513
4,426.95
33,939.95

A. 5.1.1.23 Installation of 1 m1 diameter galvanized pipe 3 "/Pemasangan 1 m1 pipa galvanis diameter 3"
Code
Nr./No.

Description/Uraian

Unit

Coefficient

Unit Price

Total Price

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Galvanized pipe /Pipa galvanis 3"
Equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Kode

Satuan

Koefisien

Harga Satuan
(Rp.)

Total Harga
(RP.)

L.01
Manday
0.135
82,500
L.02
Manday
0.225
99,000
L.03
Manday
0.023
121,000
L.04
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

11,138
22,275
2,783
847
37,043

M
1.20
%
35.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

37,043
5,556.38
42,598.88

15% x D

A. 5.1.1.24 Installation of 1 m1 diameter galvanized pipe 4 "/Pemasangan 1 m1 pipa galvanis diameter 4"

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Galvanized pipe /Pipa galvanis 4"
Equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.135
82,500
L.02
Manday
0.225
99,000
L.03
Manday
0.023
121,000
L.04
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

11,138
22,275
2,783
847
37,043

M
1.20
%
35.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

37,043
5,556.38
42,598.88

15% x D

A. 5.1.1.25 Installation of 1 m1 of type AW diameter PVC pipe 1/2 "/Pemasangan 1 m1 pipa PVC tipe AW diameter 1/2"

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
PVC pipe /Pipa PVC 1/2"
Equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.036
82,500
L.02
Manday
0.06
99,000
L.03
Manday
0.006
121,000
L.04
Manday
0.002
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

2,970
5,940
726
242
9,878

M
1.20
4,400
%
35.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

5,280
5,280

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

15,158
2,273.70
17,431.70

15% x D

A. 5.1.1.26 Installation of 1 m1 of type AW diameter PVC pipe 3/4 "/Pemasangan 1 m1 pipa PVC tipe AW diameter 3/4"

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
PVC pipe /Pipa PVC 3/4"
Equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.036
82,500
L.02
Manday
0.06
99,000
L.03
Manday
0.006
121,000
L.04
Manday
0.002
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

2,970
5,940
726
242
9,878

M
1.20
6,050
%
35.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

7,260
7,260

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

17,138
2,570.70
19,708.70

15% x D

A. 5.1.1.27 Installation of 1 m1 of type AW diameter PVC pipe 1 "/Pemasangan 1 m1 pipa PVC tipe AW diameter 1"

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
PVC pipe/Pipa PVC 1"

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.036
82,500
L.02
Manday
0.06
99,000
L.03
Manday
0.006
121,000
L.04
Manday
0.002
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M

1.20

8,250

Total Price
Total Harga
(RP.)
2,970
5,940
726
242
9,878
9,900

Equipment/Perlengkapan
C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

%
35.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

9,900

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

19,778
2,966.70
22,744.70

15% x D

A. 5.1.1.28 Installation of 1 m1 of type AW diameter PVC pipe 1 1/2 "/Pemasangan 1 m1 pipa PVC tipe AW diameter 1 1/2"
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
PVC Pipe/Pipa PVC 1 1/2"
Equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.054
82,500
L.02
Manday
0.09
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

4,455
8,910
1,089
363
14,817

M
1.20
14,300
%
35.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

17,160
17,160

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

31,977
4,796.55
36,773.55

15% x D

A. 5.1.1.29 Installation of 1 m1 of type AW diameter PVC pipe 2 "/Pemasangan 1 m1 pipa PVC tipe AW diameter 2"

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
PVC pipe/Pipa PVC 2"
Equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.054
82,500
L.02
Manday
0.09
99,000
L.03
Manday
0.009
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

4,455
8,910
1,089
363
14,817

M
1.20
18,013
%
35.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

21,615
21,615

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

36,432
5,464.80
41,896.80

15% x D

A. 5.1.1.30 Installation of 1 m1 of type AW PVC pipe diameter of 2 1/2 "/Pemasangan 1 m1 pipa PVC tipe AW diameter 2 1/2"
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
PVC pipe/Pipa PVC 2 1/2"
Equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.081
82,500
L.02
Manday
0.135
99,000
L.03
Manday
0.0135
121,000
L.04
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

6,683
13,365
1,634
484
22,165

M
1.20
%
35.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

22,165
3,324.75
25,489.75

15% x D

A. 5.1.1.31 Installation of 1 m1 of type AW diameter PVC pipe 3 "/Pemasangan 1 m1 pipa PVC tipe AW diameter 3"

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
PVC pipe/Pipa PVC 3"
Equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.081
82,500
L.02
Manday
0.135
99,000
L.03
Manday
0.0135
121,000
L.04
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

6,683
13,365
1,634
484
22,165

M
1.20
35,338
%
35.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

42,405
42,405

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

64,570
9,685.50
74,255.50

A. 5.1.1.32 Installation of 1 m1 of type AW diameter PVC pipe 4 "/Pemasangan 1 m1 pipa PVC tipe AW diameter 4"

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
PVC pipe/Pipa PVC 4"
Equipment/Perlengkapan

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.081
82,500
L.02
Manday
0.135
99,000
L.03
Manday
0.0135
121,000
L.04
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

6,683
13,365
1,634
484
22,165

M
1.20
57,200
%
35.00
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

68,640
68,640

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

90,805
13,620.75
104,425.75

15% x D

A. 5.1.1.33 Installation of 1 m1 pipe wastewater soil type pipe 20cm/Pemasangan 1 m1 pipa air limbah jenis pipa tanah
20cm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
soil pipe/Pipa tanah
Portland cement/Semen Portland
Sand plug/Pasir pasang
Sand fill/Pasir urug

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.08
82,500
L.02
Manday
0.04
99,000
L.03
Manday
0.004
121,000
L.04
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

6,600
3,960
484
484
11,528

Bh
1.60
Kg
35.00
1,375
M3
0.014
101,750
M3
0.014
71,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

48,125
1,425
1,001
50,551

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

62,079
9,311.78
71,390.28

15% x D

A. 5.1.1.34 Installation of 1 m1 pipe wastewater soil type pipe 15cm/Pemasangan 1 m1 pipa air limbah jenis pipa tanah
15cm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Soil pipe/Pipa tanah 15cm
Portland cement/Semen Portland
Sand plug/Pasir pasang
Sand fill/Pasir urug

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.06
82,500
L.02
Manday
0.03
99,000
L.03
Manday
0.003
121,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

4,950
2,970
363
363
8,646

Bh
1.60
Kg
0.68
1,375
M3
0.013
101,750
M3
0.011
71,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

935
1,323
787
3,044

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

11,690
1,753.54
13,443.79

15% x D

A. 5.1.1.35 Installation of 1 m1 concrete pipe diameter 15-20 cm/Pemasangan 1 m1 pipa beton diameter 15 - 20 cm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Diameter soil pipe/Pipa tanah diameter 15cm
Red brick/Bata merah
Portland cement/Semen Portland
Sand plug/Pasir pasang
Sand fill/Pasir urug

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.14
82,500
L.02
Manday
0.07
99,000
L.03
Manday
0.007
121,000
L.04
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

11,550
6,930
847
847
20,174

Bh
1.10
M3
0.027
Kg
3.92
1,375
M3
0.056
101,750
M3
0.024
71,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

5,390
5,698
1,716
12,804

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

32,978
4,946.70
37,924.70

15% x D

A. 5.1.1.36 Installation of 1 m1 diameter concrete pipe 30-100 cm/Pemasangan 1 m1 pipa beton diameter 30 - 100 cm
Code
Nr./No.

Description/Uraian

Unit

Coefficient

Unit Price

Total Price

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Mason/Tukang batu
Chief of Skill Labour/Kepala Tukang
Foreman/Mandor
MATERIALS/BAHAN
Diameter soil pipe/Pipa tanah dia 30cm
Red brick/Bata merah
Portland cement/Semen Portland
Sand plug/Pasir pasang
Sand fill/Pasir urug

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Kode

Satuan

Koefisien

Harga Satuan
(Rp.)

Total Harga
(RP.)

L.01
Manday
0.38
82,500
L.02
Manday
0.19
99,000
L.03
Manday
0.019
121,000
L.04
Manday
0.019
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

31,350
18,810
2,299
2,299
54,758

Bh
1.10
M3
0.55
Kg
10.30
1,375
M3
0.061
101,750
M3
0.069
71,500
MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

14,163
6,207
4,934
25,303

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

80,061
12,009.11
92,069.86

A. 8.4.1 PIPE FITTING WORK UNIT PRICE/HARGA SATUAN PEKERJAAN PEMASANGAN PIPA
A. 8.4.1.1 Installation of 1 m PVC pipe 63 mm/Pemasangan 1 m pipa PVC 63 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.081
82,500
L.02
Manday
0.041
99,000
L.04
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC Pipe/Pipa PVC 63 mm

Total Price
Total Harga
(RP.)
6,683
4,059
968
11,710

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.006

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

11,710
1,756.43
13,465.93

Note/Catatan :
Coefficient of equipment used in A.8.4.1 are as listed in the table. If there is additional equipment used, must be tailored to the
specifications and working drawings. / Koefisien peralatan yang digunakan pada A.8.4.1 ini adalah seperti yang tercantum pada tabel.
Apabila ada tambahan peralatan yang digunakan, harus disesuaikan dengan spesifikasi dan gambar kerja.

A. 8.4.1.2 Installation of 1 m PVC pipe 90 mm/Pemasangan 1 m pipa PVC 90 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.094
82,500
L.02
Manday
0.047
99,000
L.04
Manday
0.009
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 90 mm

Total Price
Total Harga
(RP.)
7,755
4,653
1,089
13,497

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.008

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

13,497
2,024.55
15,521.55

A. 8.4.1.3 Installation of 1 m PVC pipe 110 mm/Pemasangan 1 m pipa PVC 110 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.105
82,500
L.02
Manday
0.053
99,000
L.04
Manday
0.011
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 110 mm

Total Price
Total Harga
(RP.)
8,663
5,247
1,331
15,241

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.010

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

15,241
2,286.08
17,526.58

A. 8.4.1.4 Installation of 1 m PVC pipe 150 mm/Pemasangan 1 m pipa PVC 150 mm

Nr./No.

Description/Uraian

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan

Total Price
Total Harga

Nr./No.

Description/Uraian
(Rp.)

MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

L.01
Manday
0.118
82,500
L.02
Manday
0.059
99,000
L.04
Manday
0.012
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 150 mm

(RP.)
9,735
5,841
1,452
17,028

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.012

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

17,028
2,554.20
19,582.20

A. 8.4.1.5 Installation of 1 m PVC pipe 200 mm/Pemasangan 1 m pipa PVC 200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.189
82,500
L.02
Manday
0.095
99,000
L.04
Manday
0.019
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 200 mm

Total Price
Total Harga
(RP.)
15,593
9,405
2,299
27,297

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.024

15% x D

27,297
4,094.48
31,390.98

A. 8.4.1.6 Installation of 1 m PVC pipe 250 mm/Pemasangan 1 m pipa PVC 250 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.256
82,500
L.02
Manday
0.128
99,000
L.04
Manday
0.026
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 250 mm

Total Price
Total Harga
(RP.)
21,120
12,672
3,146
36,938

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.034

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

36,938
5,540.70
42,478.70

A. 8.4.1.7 Installation of 1 m PVC pipe 300 mm/Pemasangan 1 m pipa PVC 300 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.294
82,500
L.02
Manday
0.147
99,000
L.04
Manday
0.029
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 300 mm

Total Price
Total Harga
(RP.)
24,255
14,553
3,509
42,317

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.040

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

42,317
6,347.55
48,664.55

A. 8.4.1.8 Installation of 1 m PVC pipe 400 mm/Pemasangan 1 m pipa PVC 400 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.544
82,500
L.02
Manday
0.272
99,000
L.04
Manday
0.054
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
44,880
26,928
6,534
78,342

PVC pipe/Pipa PVC 400 mm

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.080

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

78,342
11,751.30
90,093.30

A. 8.4.1.9 Installation of 1 m PVC pipe 450 mm/Pemasangan 1 m pipa PVC 450 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.669
82,500
L.02
Manday
0.335
99,000
L.04
Manday
0.067
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 450 mm

Total Price
Total Harga
(RP.)
55,193
33,165
8,107
96,465

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.100

15% x D

96,465
14,469.68
110,934.18

A. 8.4.1.10 Installation of 1 m PVC pipe 500 mm/Pemasangan 1 m pipa PVC 500 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.809
82,500
L.02
Manday
0.405
99,000
L.04
Manday
0.081
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 500 mm

Total Price
Total Harga
(RP.)
66,743
40,095
9,801
116,639

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.122

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

116,639
17,495.78
134,134.28

A. 8.4.1.11 Installation of 1 m PVC pipe 600 mm/Pemasangan 1 m pipa PVC 600 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.957
82,500
L.02
Manday
0.479
99,000
L.04
Manday
0.096
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 600 mm

Total Price
Total Harga
(RP.)
78,953
47,421
11,616
137,990

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.145

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

137,990
20,698.43
158,687.93

A. 8.4.1.12 Installation of 1 m PVC pipe 800 mm/Pemasangan 1 m pipa PVC 800 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
PVC pipe/Pipa PVC 800 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.618
82,500
L.02
Manday
0.809
99,000
L.04
Manday
0.162
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.250

Total Price
Total Harga
(RP.)
133,485
80,091
19,602
233,178
-

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

233,178
34,976.70
268,154.70

A. 8.4.1.13 Installation of 1 m PVC pipe 900 mm/Pemasangan 1 m pipa PVC 900 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.691
82,500
L.02
Manday
0.846
99,000
L.04
Manday
0.169
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 900 mm

Total Price
Total Harga
(RP.)
139,508
83,754
20,449
243,711

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.262

15% x D

243,711
36,556.58
280,267.08

A. 8.4.1.14 Installation of 1 m PVC pipe 1000 mm/Pemasangan 1 m pipa PVC 1000 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.895
82,500
L.02
Manday
0.948
99,000
L.04
Manday
0.190
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 1000 mm

Total Price
Total Harga
(RP.)
156,338
93,852
22,990
273,180

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.294

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

273,180
40,976.93
314,156.43

A. 8.4.1.15 Installation of 1 m PVC pipe 1100 mm/Pemasangan 1 m pipa PVC 1100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.099
82,500
L.02
Manday
1.050
99,000
L.04
Manday
0.210
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 1100 mm

Total Price
Total Harga
(RP.)
173,168
103,950
25,410
302,528

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.327

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

302,528
45,379.13
347,906.63

A. 8.4.1.16 Installation of 1 m PVC pipe 1200 mm/Pemasangan 1 m pipa PVC 1200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
PVC pipe/Pipa PVC 1200 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.303
82,500
L.02
Manday
1.152
99,000
L.04
Manday
0.230
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.359

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

Total Price
Total Harga
(RP.)
189,998
114,048
27,830
331,876
-

331,876
49,781.33
381,656.83

A. 8.4.1.17 Installation of 1 m 63 mm HDPE pipes/Pemasangan 1 m pipa HDPE 63 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.035
82,500
L.02
Manday
0.017
99,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 63 mm

Total Price
Total Harga
(RP.)
2,888
1,683
363
4,934

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.019

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

4,934
740.03
5,673.53

A. 8.4.1.18 Installation of 1 m 100 mm HDPE pipes/Pemasangan 1 m pipa HDPE 100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.040
82,500
L.02
Manday
0.020
99,000
L.04
Manday
0.004
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 100 mm

Total Price
Total Harga
(RP.)
3,300
1,980
484
5,764

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.019

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

5,764
864.60
6,628.60

A. 8.4.1.19 Installation of 1 m 125 mm HDPE pipes/Pemasangan 1 m pipa HDPE 125 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.045
82,500
L.02
Manday
0.023
99,000
L.04
Manday
0.005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 125 mm

Total Price
Total Harga
(RP.)
3,713
2,277
605
6,595

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.019

15% x D

6,595
989.18
7,583.68

A. 8.4.1.20 Installation of 1 m 150 mm HDPE pipes/Pemasangan 1 m pipa HDPE 150 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.062
82,500
L.02
Manday
0.031
99,000
L.04
Manday
0.006
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 150 mm

Total Price
Total Harga
(RP.)
5,115
3,069
726
8,910

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.019

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

8,910
1,336.50
10,246.50

A. 8.4.1.21 Installation of 1 m 200 mm HDPE pipes/Pemasangan 1 m pipa HDPE 200 mm

Nr./No.

Description/Uraian

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

L.01
Manday
0.102
82,500
L.02
Manday
0.051
99,000
L.04
Manday
0.010
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 200 mm

8,415
5,049
1,210
14,674

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.019

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

14,674
2,201.10
16,875.10

A. 8.4.1.22 Installation of 1 m 250 mm HDPE pipes/Pemasangan 1 m pipa HDPE 250 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.133
82,500
L.02
Manday
0.067
99,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 250 mm

Total Price
Total Harga
(RP.)
10,973
6,633
1,573
19,179

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.042

15% x D

19,179
2,876.78
22,055.28

A. 8.4.1.23 Installation of 1 m 300 mm HDPE pipes/Pemasangan 1 m pipa HDPE 300 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.170
82,500
L.02
Manday
0.085
99,000
L.04
Manday
0.017
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 300 mm

Total Price
Total Harga
(RP.)
14,025
8,415
2,057
24,497

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.065

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

24,497
3,674.55
28,171.55

A. 8.4.1.24 Installation of 1 m 400 mm HDPE pipes/Pemasangan 1 m pipa HDPE 400 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.290
82,500
L.02
Manday
0.145
99,000
L.04
Manday
0.029
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 400 mm

Total Price
Total Harga
(RP.)
23,925
14,355
3,509
41,789

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.152

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

41,789
6,268.35
48,057.35

A. 8.4.1.25 Installation of 1 m 450 mm HDPE pipes/Pemasangan 1 m pipa HDPE 450 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.359
82,500
L.02
Manday
0.180
99,000
L.04
Manday
0.036
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
29,618
17,820
4,356
51,794

HDPE pipe/Pipa HDPE 450 mm

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.200

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

51,794
7,769.03
59,562.53

A. 8.4.1.26 Installation of 1 m 500 mm HDPE pipes/Pemasangan 1 m pipa HDPE 500 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.433
82,500
L.02
Manday
0.216
99,000
L.04
Manday
0.043
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 500 mm

Total Price
Total Harga
(RP.)
35,723
21,384
5,203
62,310

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.251

15% x D

62,310
9,346.43
71,655.93

A. 8.4.1.27 Installation of 1 m 600 mm HDPE pipes/Pemasangan 1 m pipa HDPE 600 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.512
82,500
L.02
Manday
0.256
99,000
L.04
Manday
0.051
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 600 mm

Total Price
Total Harga
(RP.)
42,240
25,344
6,171
73,755

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.307

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

73,755
11,063.25
84,818.25

A. 8.4.1.28 Installation of 1 m 800 mm HDPE pipes/Pemasangan 1 m pipa HDPE 800 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.893
82,500
L.02
Manday
0.446
99,000
L.04
Manday
0.089
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 800 mm

Total Price
Total Harga
(RP.)
73,673
44,154
10,769
128,596

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.573

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

128,596
19,289.33
147,884.83

A. 8.4.1.29 Installation of 1 m 900 mm HDPE pipes/Pemasangan 1 m pipa HDPE 900 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 900 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.353
82,500
L.02
Manday
0.677
99,000
L.04
Manday
0.135
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.883

Total Price
Total Harga
(RP.)
111,623
67,023
16,335
194,981
-

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

194,981
29,247.08
224,227.58

A. 8.4.1.30 Installation of 1 m 1000 mm HDPE pipes/Pemasangan 1 m pipa HDPE 1000 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.659
82,500
L.02
Manday
0.830
99,000
L.04
Manday
0.166
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 1000 mm

Total Price
Total Harga
(RP.)
136,868
82,170
20,086
239,124

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

1.093

15% x D

239,124
35,868.53
274,992.03

A. 8.4.1.31 Installation of 1 m 1100 mm HDPE pipes/Pemasangan 1 m pipa HDPE 1100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.818
82,500
L.02
Manday
0.909
99,000
L.04
Manday
0.182
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 1100 mm

Total Price
Total Harga
(RP.)
149,985
89,991
22,022
261,998

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

1.205

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

261,998
39,299.70
301,297.70

A. 8.4.1.32 Installation of 1 m 1200 mm HDPE pipes/Pemasangan 1 m pipa HDPE 1200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.370
82,500
L.02
Manday
1.185
99,000
L.04
Manday
0.237
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 1200 mm

Total Price
Total Harga
(RP.)
195,525
117,315
28,677
341,517

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

1.584

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

341,517
51,227.55
392,744.55

A. 8.4.1.33 Installation of 1 m 63 mm pipe GIP/Pemasangan 1 m pipa GIP 63 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
GIP pipe/Pipa GIP 63 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.345
82,500
L.02
Manday
0.172
99,000
L.04
Manday
0.034
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

Total Price
Total Harga
(RP.)
28,463
17,028
4,114
49,605
-

49,605
7,440.68
57,045.18

A. 8.4.1.34 Installation of 1 m 100 mm pipe GIP/Pemasangan 1 m pipa GIP 100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.400
82,500
L.02
Manday
0.200
99,000
L.04
Manday
0.040
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 100 mm

Total Price
Total Harga
(RP.)
33,000
19,800
4,840
57,640

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

57,640
8,646.00
66,286.00

A. 8.4.1.35 Installation of 1 m 125 mm pipe GIP/Pemasangan 1 m pipa GIP 125 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.448
82,500
L.02
Manday
0.224
99,000
L.04
Manday
0.045
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 125 mm

Total Price
Total Harga
(RP.)
36,960
22,176
5,445
64,581

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

64,581
9,687.15
74,268.15

A. 8.4.1.36 Installation of 1 m 150 mm pipe GIP/Pemasangan 1 m pipa GIP 150 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.506
82,500
L.02
Manday
0.253
99,000
L.04
Manday
0.051
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 150 mm

Total Price
Total Harga
(RP.)
41,745
25,047
6,171
72,963

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

72,963
10,944.45
83,907.45

A. 8.4.1.37 Installation of 1 m 200 mm pipe GIP/Pemasangan 1 m pipa GIP 200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.796
82,500
L.02
Manday
0.398
99,000
L.04
Manday
0.080
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 200 mm

Total Price
Total Harga
(RP.)
65,670
39,402
9,680
114,752

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

114,752
17,212.80
131,964.80

A. 8.4.1.38 Installation of 1 m 250 mm pipe GIP/Pemasangan 1 m pipa GIP 250 mm

Nr./No.

Description/Uraian

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

L.01
Manday
0.949
82,500
L.02
Manday
0.475
99,000
L.04
Manday
0.095
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 250 mm

78,293
47,025
11,495
136,813

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

136,813
20,521.88
157,334.38

A. 8.4.1.39 Installation of 1 m 300 mm pipe GIP/Pemasangan 1 m pipa GIP 300 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.958
82,500
L.02
Manday
0.479
99,000
L.04
Manday
0.096
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 300 mm

Total Price
Total Harga
(RP.)
79,035
47,421
11,616
138,072

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

138,072
20,710.80
158,782.80

A. 8.4.1.40 Installation of 1 m 400 mm pipe GIP/Pemasangan 1 m pipa GIP 400 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.212
82,500
L.02
Manday
0.606
99,000
L.04
Manday
0.121
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 400 mm

Total Price
Total Harga
(RP.)
99,990
59,994
14,641
174,625

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

174,625
26,193.75
200,818.75

A. 8.4.1.41 Installation of 1 m 450 mm pipe GIP/Pemasangan 1 m pipa GIP 450 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.353
82,500
L.02
Manday
0.676
99,000
L.04
Manday
0.135
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 450 mm

Total Price
Total Harga
(RP.)
111,623
66,924
16,335
194,882

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

194,882
29,232.23
224,113.73

A. 8.4.1.42 Installation of 1 m 500 mm pipe GIP/Pemasangan 1 m pipa GIP 500 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.469
82,500
L.02
Manday
0.735
99,000
L.04
Manday
0.147
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
121,193
72,765
17,787
211,745

GIP pipe/Pipa GIP 500 mm

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

211,745
31,761.68
243,506.18

A. 8.4.1.43 Installation of 1 m 600 mm pipe GIP/Pemasangan 1 m pipa GIP 600 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.327
82,500
L.02
Manday
0.664
99,000
L.04
Manday
0.133
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 600 mm

Total Price
Total Harga
(RP.)
109,478
65,736
16,093
191,307

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

191,307
28,695.98
220,002.48

A. 8.4.1.44 Installation of 1 m 800 mm pipe GIP/Pemasangan 1 m pipa GIP 800 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.327
82,500
L.02
Manday
1.163
99,000
L.04
Manday
0.233
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 800 mm

Total Price
Total Harga
(RP.)
191,978
115,137
28,193
335,308

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

335,308
50,296.13
385,603.63

A. 8.4.1.45 Installation of 1 m 900 mm pipe GIP/Pemasangan 1 m pipa GIP 900 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.623
82,500
L.02
Manday
1.312
99,000
L.04
Manday
0.262
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 900 mm

Total Price
Total Harga
(RP.)
216,398
129,888
31,702
377,988

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

377,988
56,698.13
434,685.63

A. 8.4.1.46 Installation of 1 m 1000 mm pipe GIP/Pemasangan 1 m pipa GIP 1000 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
GIP pipe/Pipa GIP 1000 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.911
82,500
L.02
Manday
1.456
99,000
L.04
Manday
0.291
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

Total Price
Total Harga
(RP.)
240,158
144,144
35,211
419,513
-

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

419,513
62,926.88
482,439.38

A. 8.4.1.47 Installation of 1 m 1100 mm pipe GIP/Pemasangan 1 m pipa GIP 1100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
3.200
82,500
L.02
Manday
1.600
99,000
L.04
Manday
0.320
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 1100 mm

Total Price
Total Harga
(RP.)
264,000
158,400
38,720
461,120

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

461,120
69,168.00
530,288.00

A. 8.4.1.48 Installation of 1 m 1200 mm pipe GIP/Pemasangan 1 m pipa GIP 1200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
3.488
82,500
L.02
Manday
1.744
99,000
L.04
Manday
0.349
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 1200 mm

Total Price
Total Harga
(RP.)
287,760
172,656
42,229
502,645

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

502,645
75,396.75
578,041.75

A. 8.4.1.49 Installation of 1 m DCI pipe 100 mm/Pemasangan 1 m pipa DCI 100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.489
82,500
L.02
Manday
0.098
99,000
L.04
Manday
0.049
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 100 mm

Total Price
Total Harga
(RP.)
40,343
9,702
5,929
55,974

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.380

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

55,974
8,396.03
64,369.53

A. 8.4.1.50 Installation of 1 m DCI pipe 125 mm/Pemasangan 1 m pipa DCI 125 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
DCI pipe/Pipa DCI 125 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.547
82,500
L.02
Manday
0.109
99,000
L.04
Manday
0.055
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.380

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

Total Price
Total Harga
(RP.)
45,128
10,791
6,655
62,574
-

62,574
9,386.03
71,959.53

A. 8.4.1.51 Installation of 1 m DCI pipe 150 mm/Pemasangan 1 m pipa DCI 150 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.613
82,500
L.02
Manday
0.123
99,000
L.04
Manday
0.061
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 150 mm

Total Price
Total Harga
(RP.)
50,573
12,177
7,381
70,131

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.380

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

70,131
10,519.58
80,650.08

A. 8.4.1.52 Installation of 1 m DCI pipe 200 mm/Pemasangan 1 m pipa DCI 200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.855
82,500
L.02
Manday
0.171
99,000
L.04
Manday
0.085
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 200 mm

Total Price
Total Harga
(RP.)
70,538
16,929
10,285
97,752

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.380

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

97,752
14,662.73
112,414.23

A. 8.4.1.53 Installation of 1 m DCI pipe 250 mm/Pemasangan 1 m pipa DCI 250 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.951
82,500
L.02
Manday
0.190
99,000
L.04
Manday
0.095
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 250 mm

Total Price
Total Harga
(RP.)
78,458
18,810
11,495
108,763

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.050

15% x D

108,763
16,314.38
125,076.88

A. 8.4.1.54 Installation of 1 m DCI pipe 300 mm/Pemasangan 1 m pipa DCI 300 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.973
82,500
L.02
Manday
0.195
99,000
L.04
Manday
0.097
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 300 mm

Total Price
Total Harga
(RP.)
80,273
19,305
11,737
111,315

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.071

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

111,315
16,697.18
128,011.68

A. 8.4.1.55 Installation of 1 m DCI pipe 400 mm/Pemasangan 1 m pipa DCI 400 mm

Nr./No.

Description/Uraian

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Heavy equipment operator/Operator alat berat
Foreman/Mandor

L.01
Manday
1.545
82,500
L.02
Manday
0.309
99,000
L.08
Manday
0.093
L.04
Manday
0.154
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 400 mm

127,463
30,591
18,634
176,688

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.023

Day / Hari

0.031

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

176,688
26,503.13
203,190.63

A. 8.4.1.56 Installation of 1 m DCI pipe 450 mm/Pemasangan 1 m pipa DCI 450 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Heavy equipment operator/Operator alat berat
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.813
82,500
L.02
Manday
0.363
99,000
L.08
Manday
0.143
L.04
Manday
0.181
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 450 mm

Total Price
Total Harga
(RP.)
149,573
35,937
21,901
207,411

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.029

Day / Hari

0.039

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

207,411
31,111.58
238,522.08

A. 8.4.1.57 Installation of 1 m DCI pipe 500 mm/Pemasangan 1 m pipa DCI 500 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Heavy equipment operator/Operator alat berat
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.047
82,500
L.02
Manday
0.409
99,000
L.08
Manday
0.193
L.04
Manday
0.205
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 500 mm

Total Price
Total Harga
(RP.)
168,878
40,491
24,805
234,174

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.034

Day / Hari

0.045

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

234,174
35,126.03
269,299.53

A. 8.4.1.58 Installation of 1 m DCI pipe 600 mm/Pemasangan 1 m pipa DCI 600 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Heavy equipment operator/Operator alat berat
Foreman/Mandor
MATERIALS/BAHAN
DCI pipe/Pipa DCI 600 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.011
82,500
L.02
Manday
0.402
99,000
L.08
Manday
0.293
L.04
Manday
0.201
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

165,908
39,798
24,321
230,027
-

Day / Hari

0.058

Day / Hari

0.077

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total Price
Total Harga
(RP.)

15% x D

230,027
34,503.98
264,530.48

A. 8.4.1.59 Installation of 1 m DCI pipe 800 mm/Pemasangan 1 m pipa DCI 800 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Heavy equipment operator/Operator alat berat
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
3.859
82,500
L.02
Manday
0.772
99,000
L.08
Manday
0.493
L.04
Manday
0.386
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 800 mm

Total Price
Total Harga
(RP.)
318,368
76,428
46,706
441,502

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.084

Day / Hari

0.225

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

441,502
66,225.23
507,726.73

A. 8.4.1.60 Installation of 1 m DCI pipe 900 mm/Pemasangan 1 m pipa DCI 900 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Heavy equipment operator/Operator alat berat
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
4.995
82,500
L.02
Manday
0.999
99,000
L.08
Manday
0.593
L.04
Manday
0.499
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 900 mm

Total Price
Total Harga
(RP.)
412,088
98,901
60,379
571,368

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

0.093

Day / Hari

0.248

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Day / Hari

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

571,368
85,705.13
657,072.63

A. 8.4.1.61 Installation of 1 m DCI pipe 1000 mm/Pemasangan 1 m pipa DCI 1000 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Heavy equipment operator/Operator alat berat
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
5.931
82,500
L.02
Manday
1.186
99,000
L.08
Manday
0.793
L.04
Manday
0.693
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 1000 mm

Total Price
Total Harga
(RP.)
489,308
117,414
83,853
690,575

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

0.112

Day / Hari

0.298

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Day / Hari

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

690,575
103,586.18
794,160.68

A. 8.4.1.62 Installation of 1 m DCI pipe 1100 mm/Pemasangan 1 m pipa DCI 1100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Heavy equipment operator/Operator alat berat
Foreman/Mandor
MATERIALS/BAHAN
DCI pipe/Pipa DCI 1100 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
6.949
82,500
L.02
Manday
1.390
99,000
L.08
Manday
0.793
L.04
Manday
0.695
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Total Price
Total Harga
(RP.)
573,293
137,610
84,095
794,998
-

Day / Hari

0.152

Day / Hari

0.304

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

794,998
119,249.63
914,247.13

A. 8.4.1.63 Installation of 1 m DCI pipe 1200 mm/Pemasangan 1 m pipa DCI 1200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Heavy equipment operator/Operator alat berat
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
8.056
82,500
L.02
Manday
1.611
99,000
L.08
Manday
0.893
L.04
Manday
0.806
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 1200 mm

Total Price
Total Harga
(RP.)
664,620
159,489
97,526
921,635

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

0.180

Day / Hari

0.360

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Day / Hari

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

921,635
138,245.25
1,059,880.25

A. 8.4.1.64 Installation of steel pipe 1 m 63 mm/Pemasangan 1 m pipa baja 63 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.499
82,500
L.02
Manday
0.100
99,000
L.04
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 63 mm

Total Price
Total Harga
(RP.)
41,168
9,900
6,050
57,118

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.004

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

57,118
8,567.63
65,685.13

A. 8.4.1.65 Installation of steel pipe 1 m 100 mm/Pemasangan 1 m pipa baja 100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.579
82,500
L.02
Manday
0.116
99,000
L.04
Manday
0.058
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 100 mm

Total Price
Total Harga
(RP.)
47,768
11,484
7,018
66,270

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.004

15% x D

66,270
9,940.43
76,209.93

A. 8.4.1.66 Installation of steel pipe 1 m 125 mm/Pemasangan 1 m pipa baja 125 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
Steel pipe/Pipa baja 125 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.648
82,500
L.02
Manday
0.130
99,000
L.04
Manday
0.065
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.004

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)

15% x D

Total Price
Total Harga
(RP.)
53,460
12,870
7,865
74,195
-

74,195
11,129.25

Unit Price Work/Harga Satuan Pekerjaan (D+E)

85,324.25

A. 8.4.1.67 Installation of steel pipe 1 m 150 mm/Pemasangan 1 m pipa baja 150 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.708
82,500
L.02
Manday
0.142
99,000
L.04
Manday
0.071
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 150 mm

Total Price
Total Harga
(RP.)
58,410
14,058
8,591
81,059

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.004

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

81,059
12,158.85
93,217.85

A. 8.4.1.68 Installation of steel pipe 1 m 200 mm/Pemasangan 1 m pipa baja 200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.113
82,500
L.02
Manday
0.223
99,000
L.04
Manday
0.111
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 200 mm

Total Price
Total Harga
(RP.)
91,823
22,077
13,431
127,331

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.004

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

127,331
19,099.58
146,430.08

A. 8.4.1.70 Installation of steel pipe 1 m 300 mm/Pemasangan 1 m pipa baja 300 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.415
82,500
L.02
Manday
0.283
99,000
L.04
Manday
0.141
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 300 mm

Total Price
Total Harga
(RP.)
116,738
28,017
17,061
161,816

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.004

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

161,816
24,272.33
186,087.83

A. 8.4.1.71 Installation of steel pipe 1 m 400 mm/Pemasangan 1 m pipa baja 400 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
Steel pipe/Pipa baja 400 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.366
82,500
L.02
Manday
0.473
99,000
L.04
Manday
0.237
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

195,195
46,827
28,677
270,699
-

Day / Hari

0.027

Day / Hari

0.039

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total Price
Total Harga
(RP.)

15% x D

A. 8.4.1.72 Installation of steel pipe 1 m 450 mm/Pemasangan 1 m pipa baja 450 mm

270,699
40,604.85
311,303.85

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.231
82,500
L.02
Manday
0.446
99,000
L.04
Manday
0.223
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 450 mm

Total Price
Total Harga
(RP.)
184,058
44,154
26,983
255,195

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.026

Day / Hari

0.037

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

255,195
38,279.18
293,473.68

A. 8.4.1.73 Installation of steel pipe 1 m 500 mm/Pemasangan 1 m pipa baja 500 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.432
82,500
L.02
Manday
0.486
99,000
L.04
Manday
0.243
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 500 mm

Total Price
Total Harga
(RP.)
200,640
48,114
29,403
278,157

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

0.029

Day / Hari

0.045

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Day / Hari

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

278,157
41,723.55
319,880.55

A. 8.4.1.74 Installation of steel pipe 1 m 600 mm/Pemasangan 1 m pipa baja 600 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.208
82,500
L.02
Manday
0.442
99,000
L.04
Manday
0.221
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 600 mm

Total Price
Total Harga
(RP.)
182,160
43,758
26,741
252,659

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.027

Day / Hari

0.039

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

252,659
37,898.85
290,557.85

A. 8.4.1.75 Installation of steel pipe 1 m 800 mm/Pemasangan 1 m pipa baja 800 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
Steel pipe/Pipa baja 800 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
3.897
82,500
L.02
Manday
0.779
99,000
L.04
Manday
0.390
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

321,503
77,121
47,190
445,814
-

Day / Hari

0.046

Day / Hari

0.098

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total Price
Total Harga
(RP.)

15% x D

445,814
66,872.03
512,685.53

A. 8.4.1.76 Installation of steel pipe 1 m 900 mm/Pemasangan 1 m pipa baja 900 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
4.403
82,500
L.02
Manday
0.081
99,000
L.04
Manday
0.440
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 900 mm

Total Price
Total Harga
(RP.)
363,248
8,019
53,240
424,507

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.052

Day / Hari

0.115

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

424,507
63,675.98
488,182.48

A. 8.4.1.77 Installation of steel pipe 1 m 1000 mm/Pemasangan 1 m pipa baja 1000 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
4.895
82,500
L.02
Manday
0.979
99,000
L.04
Manday
0.489
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 1000 mm

Total Price
Total Harga
(RP.)
403,838
96,921
59,169
559,928

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

0.058

Day / Hari

0.133

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Day / Hari

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

559,928
83,989.13
643,916.63

A. 8.4.1.78 Installation of steel pipe 1 m 1100 mm/Pemasangan 1 m pipa baja 1100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
5.387
82,500
L.02
Manday
1.077
99,000
L.04
Manday
0.539
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 1100 mm

Total Price
Total Harga
(RP.)
444,428
106,623
65,219
616,270

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.064

Day / Hari

0.150

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

616,270
92,440.43
708,709.93

A. 8.4.1.79 Installation of steel pipe 1 m 1200 mm/Pemasangan 1 m pipa baja 1200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
Steel pipe/Pipa baja 1200 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
5.897
82,500
L.02
Manday
1.176
99,000
L.04
Manday
0.588
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent excavator type 225. Capacity 0.5 - 1.0 m3/
Sewa excavator type 225 kap. 0.5 - 1.0 m3
Rent Tripot/ Sewa Tripot/Tackel & handle Crane 2
T

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)

486,503
116,424
71,148
674,075
-

Day / Hari

0.070

Day / Hari

0.167

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E

Total Price
Total Harga
(RP.)

15% x D

674,075
101,111.18

Unit Price Work/Harga Satuan Pekerjaan (D+E)

775,185.68

A. 8.4.2 WORK UNIT PRICE CUTTING PIPE/HARGA SATUAN PEKERJAAN PEMOTONGAN PIPA
A. 8.4.2.1 Cutting 1 piece of PVC pipe 63 mm/Pemotongan 1 buah pipa PVC 63 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.005
82,500
L.02
Manday
0.002
99,000
L.04
Manday
0.0005
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 63 mm

bh

413
198
61
671

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Day / Hari

T1 pipe cutting equipment/manual(chainsaw)/saw


/ Peralatan potong pipa T1/manual (gergaji)/saw

0.003

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

671
100.65
771.65

A. 8.4.2.2 Cutting 1 piece of PVC pipe 90 mm/Pemotongan 1 m pipa PVC 90 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.014
82,500
L.02
Manday
0.007
99,000
L.04
Manday
0.001
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 90 mm

bh

Total Price
Total Harga
(RP.)
1,155
693
121
1,969

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Day / Hari

T1 pipe cutting equipment/manual(chainsaw)/saw


/ Peralatan potong pipa T1/manual (gergaji)/saw

0.003

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

1,969
295.35
2,264.35

A. 8.4.2.3 Cutting 1 piece of PVC pipe 110 mm/Pemotongan 1 buah pipa PVC 110 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.022
82,500
L.02
Manday
0.011
99,000
L.04
Manday
0.002
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 110 mm

bh

Total Price
Total Harga
(RP.)
1,815
1,089
242
3,146

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Day / Hari

T1 pipe cutting equipment/manual(chainsaw)/saw


/ Peralatan potong pipa T1/manual (gergaji)/saw

0.003

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

3,146
471.90
3,617.90

A. 8.4.2.4 Cutting 1 piece of PVC pipe 150 mm/Pemotongan 1 buah pipa PVC 150 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
PVC pipe/Pipa PVC 150 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.031
82,500
L.02
Manday
0.015
99,000
L.04
Manday
0.003
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

2,558
1,485
363
4,406
-

EQUIPMENT/PERALATAN
T1 pipe cutting equipment/manual(chainsaw)/saw
/ Peralatan potong pipa T1/manual (gergaji)/saw

Day / Hari

0.003

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total Price
Total Harga
(RP.)

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

4,406
660.83
5,066.33

A. 8.4.2.5 Cutting 1 piece of PVC pipe 200 mm/Pemotongan 1 buah pipa PVC 200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.081
82,500
L.02
Manday
0.040
99,000
L.04
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 200 mm

bh

Total Price
Total Harga
(RP.)
6,683
3,960
968
11,611

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Day / Hari

T1 pipe cutting equipment/manual(chainsaw)/saw


/ Peralatan potong pipa T1/manual (gergaji)/saw

0.017

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

11,611
1,741.58
13,352.08

A. 8.4.2.6 Cutting 1 piece of PVC pipe 250 mm/Pemotongan 1 buah pipa PVC 250 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.128
82,500
L.02
Manday
0.064
99,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 250 mm

bh

Total Price
Total Harga
(RP.)
10,560
6,336
1,573
18,469

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Day / Hari

T1 pipe cutting equipment/manual(chainsaw)/saw


/ Peralatan potong pipa T1/manual (gergaji)/saw

0.030

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

18,469
2,770.35
21,239.35

A. 8.4.2.7 Cutting 1 piece of PVC pipe 300 mm/Pemotongan 1 buah pipa PVC 300 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.155
82,500
L.02
Manday
0.077
99,000
L.04
Manday
0.015
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 300 mm

bh

Total Price
Total Harga
(RP.)
12,788
7,623
1,815
22,226

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Day / Hari

T1 pipe cutting equipment/manual(chainsaw)/saw


/ Peralatan potong pipa T1/manual (gergaji)/saw

0.037

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

22,226
3,333.83
25,559.33

A. 8.4.2.8 Cutting 1 piece of PVC pipe 400 mm/Pemotongan 1 buah pipa PVC 400 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.331
82,500
L.02
Manday
0.166
99,000
L.04
Manday
0.033
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 400 mm

bh

Total Price
Total Harga
(RP.)
27,308
16,434
3,993
47,735

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Day / Hari

T1 pipe cutting equipment/manual(chainsaw)/saw


/ Peralatan potong pipa T1/manual (gergaji)/saw

0.086

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

47,735
7,160.18
54,894.68

A. 8.4.2.9 Cutting 1 piece of PVC pipe 450 mm/Pemotongan 1 buah pipa PVC 450 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
B

L.01
Manday
0.420
82,500
L.02
Manday
0.210
99,000
L.04
Manday
0.042
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 450 mm

bh

34,650
20,790
5,082
60,522

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Day / Hari

T1 pipe cutting equipment/manual(chainsaw)/saw


/ Peralatan potong pipa T1/manual (gergaji)/saw

0.054

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

60,522
9,078.30
69,600.30

A. 8.4.2.10 Cutting 1 piece of PVC pipe 500 mm/Pemotongan 1 buah pipa PVC 500 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.518
82,500
L.02
Manday
0.259
99,000
L.04
Manday
0.052
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 500 mm

bh

Total Price
Total Harga
(RP.)
42,735
25,641
6,292
74,668

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Day / Hari

T1 pipe cutting equipment/manual(chainsaw)/saw


/ Peralatan potong pipa T1/manual (gergaji)/saw

0.069

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

74,668
11,200.20
85,868.20

A. 8.4.2.11 Cutting 1 piece of PVC pipe 600 mm/Pemotongan 1 buah pipa PVC 600 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.623
82,500
L.02
Manday
0.311
99,000
L.04
Manday
0.062
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 600 mm

bh

Total Price
Total Harga
(RP.)
51,398
30,789
7,502
89,689

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Day / Hari

T1 pipe cutting equipment/manual(chainsaw)/saw


/ Peralatan potong pipa T1/manual (gergaji)/saw

0.086

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

89,689
13,453.28
103,141.78

A. 8.4.2.12 Cutting 1 piece of PVC pipe 800 mm/Pemotongan 1 buah pipa PVC 800 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.089
82,500
L.02
Manday
0.545
99,000
L.04
Manday
0.109
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 800 mm

bh

Total Price
Total Harga
(RP.)
89,843
53,955
13,189
156,987

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Day / Hari

T1 pipe cutting equipment/manual(chainsaw)/saw


/ Peralatan potong pipa T1/manual (gergaji)/saw

0.160

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

156,987
23,547.98
180,534.48

A. 8.4.2.13 Cutting 1 piece of PVC pipe 900 mm/Pemotongan 1 buah pipa PVC 900 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
PVC pipe/Pipa PVC 900 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.141
82,500
L.02
Manday
0.571
99,000
L.04
Manday
0.114
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

Total Price
Total Harga
(RP.)
94,133
56,529
13,794
164,456
-

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Day / Hari

T1 pipe cutting equipment/manual(chainsaw)/saw


/ Peralatan potong pipa T1/manual (gergaji)/saw

0.168

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

164,456
24,668.33
189,123.83

A. 8.4.2.14 Cutting 1 piece of PVC pipe 1000 mm/Pemotongan 1 buah pipa PVC 1000 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.285
82,500
L.02
Manday
0.643
99,000
L.04
Manday
0.129
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 1000 mm

bh

Total Price
Total Harga
(RP.)
106,013
63,657
15,609
185,279

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Day / Hari

T1 pipe cutting equipment/manual(chainsaw)/saw


/ Peralatan potong pipa T1/manual (gergaji)/saw

0.191

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

185,279
27,791.78
213,070.28

A. 8.4.2.15 Cutting 1 piece of PVC pipe 1100 mm/Pemotongan 1 buah pipa PVC 1100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.429
82,500
L.02
Manday
0.715
99,000
L.04
Manday
0.143
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 1100 mm

bh

Total Price
Total Harga
(RP.)
117,893
70,785
17,303
205,981

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

Day / Hari

T1 pipe cutting equipment/manual(chainsaw)/saw


/ Peralatan potong pipa T1/manual (gergaji)/saw

0.213

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

EQUIPMENT/PERALATAN

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

205,981
30,897.08
236,877.58

A. 8.4.2.16 Cutting 1 piece of PVC pipe 1200 mm/Pemotongan 1 buah pipa PVC 1200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.573
82,500
L.02
Manday
0.787
99,000
L.04
Manday
0.157
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
PVC pipe/Pipa PVC 1200 mm

bh

Total Price
Total Harga
(RP.)
129,773
77,913
18,997
226,683

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.236

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

226,683
34,002.38
260,684.88

A. 8.4.2.17 Cutting 1 HDPE pipes 63 mm/Pemotongan 1 buah pipa HDPE 63 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
Operator
MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 63 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.002
82,500
L.02
Manday
0.001
99,000
L.04
Manday
0.0002
121,000
L.08
Manday
0.034
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.004

Total Price
Total Harga
(RP.)
165
99
24
288
-

T2 pipe cutting equipment/mechanical/cilinder


saw / Peralatan potong pipa T2/mekanik/cilinder
saw
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT
D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

288
43.23
331.43

A. 8.4.2.18 Cutting 1 HDPE pipes 100 mm/Pemotongan 1 buah pipa HDPE 100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
Operator

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.006
82,500
L.02
Manday
0.003
99,000
L.04
Manday
0.001
121,000
L.08
Manday
0.071
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 100 mm

bh

495
297
121
913

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.005

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

913
136.95
1,049.95

A. 8.4.2.19 Cutting 1 HDPE pipes 125 mm/Pemotongan 1 buah pipa HDPE 125 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
Operator

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.009
82,500
L.02
Manday
0.005
99,000
L.04
Manday
0.001
121,000
L.08
Manday
0.096
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 125 mm

bh

Total Price
Total Harga
(RP.)
743
495
121
1,359

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.006

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

1,359
203.78
1,562.28

A. 8.4.2.20 Cutting 1 HDPE pipes 150 mm/Pemotongan 1 buah pipa HDPE 150 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
Operator

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.016
82,500
L.02
Manday
0.008
99,000
L.04
Manday
0.002
121,000
L.08
Manday
0.121
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 150 mm

bh

Total Price
Total Harga
(RP.)
1,320
792
242
2,354

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.009

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

2,354
353.10
2,707.10

A. 8.4.2.21 Cutting 1 HDPE pipes 200 mm/Pemotongan 1 buah pipa HDPE 200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
Operator
MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 200 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.044
82,500
L.02
Manday
0.022
99,000
L.04
Manday
0.004
121,000
L.08
Manday
0.171
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.017

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total Price
Total Harga
(RP.)
3,630
2,178
484
6,292
-

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

6,292
943.80
7,235.80

15% x D

A. 8.4.2.22 Cutting 1 HDPE pipes 250 mm/Pemotongan 1 buah pipa HDPE 250 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
Operator

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.067
82,500
L.02
Manday
0.033
99,000
L.04
Manday
0.007
121,000
L.08
Manday
0.221
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 250 mm

bh

Total Price
Total Harga
(RP.)
5,528
3,267
847
9,642

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.023

15% x D

9,642
1,446.23
11,087.73

A. 8.4.2.23 Cutting 1 HDPE pipes 300 mm/Pemotongan 1 buah pipa HDPE 300 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
Operator

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.090
82,500
L.02
Manday
0.045
99,000
L.04
Manday
0.009
121,000
L.08
Manday
0.271
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 300 mm

bh

Total Price
Total Harga
(RP.)
7,425
4,455
1,089
12,969

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.030

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

12,969
1,945.35
14,914.35

A. 8.4.2.24 Cutting 1 HDPE pipes 400 mm/Pemotongan 1 buah pipa HDPE 400 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
Operator

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.177
82,500
L.02
Manday
0.088
99,000
L.04
Manday
0.018
121,000
L.08
Manday
0.371
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 400 mm

bh

Total Price
Total Harga
(RP.)
14,603
8,712
2,178
25,493

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.055

15% x D

25,493
3,823.88
29,316.38

A. 8.4.2.25 Cutting 1 HDPE pipes 450 mm/Pemotongan 1 buah pipa HDPE 450 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
Operator
MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 450 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.225
82,500
L.02
Manday
0.113
99,000
L.04
Manday
0.023
121,000
L.08
Manday
0.421
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.070

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)

15% x D

Total Price
Total Harga
(RP.)
18,563
11,187
2,783
32,533
-

32,533
4,879.88

Unit Price Work/Harga Satuan Pekerjaan (D+E)

37,412.38

A. 8.4.2.26 Cutting 1 HDPE pipes 500 mm/Pemotongan 1 buah pipa HDPE 500 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
Operator

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.277
82,500
L.02
Manday
0.139
99,000
L.04
Manday
0.028
121,000
L.08
Manday
0.471
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 500 mm

bh

Total Price
Total Harga
(RP.)
22,853
13,761
3,388
40,002

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.085

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

40,002
6,000.23
46,001.73

A. 8.4.2.31 Cutting 1 HDPE pipes 1100 mm/Pemotongan 1 buah pipa HDPE 1100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
Operator

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.238
82,500
L.02
Manday
0.619
99,000
L.04
Manday
0.124
121,000
L.08
Manday
1.071
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 1100 mm

bh

Total Price
Total Harga
(RP.)
102,135
61,281
15,004
178,420

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.365

15% x D

178,420
26,763.00
205,183.00

A. 8.4.2.32 Cutting 1 HDPE pipes 1200 mm/Pemotongan 1 buah pipa HDPE 1200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
Operator

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.619
82,500
L.02
Manday
0.809
99,000
L.04
Manday
0.162
121,000
L.08
Manday
1.171
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
HDPE pipe/Pipa HDPE 1200 mm

bh

Total Price
Total Harga
(RP.)
133,568
80,091
19,602
233,261

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.477

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

233,261
34,989.08
268,249.58

A. 8.4.2.33 Cutting one GIP pipes 63 mm/Pemotongan 1 buah pipa GIP 63 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
GIP pipe/Pipa GIP 63 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.019
82,500
L.02
Manday
0.010
99,000
L.04
Manday
0.002
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

Total Price
Total Harga
(RP.)
1,568
990
242
2,800
-

2,800
419.93
3,219.43

A. 8.4.2.34 Cutting one GIP pipes 100 mm/Pemotongan 1 buah pipa GIP 100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.058
82,500
L.02
Manday
0.029
99,000
L.04
Manday
0.006
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 100 mm

bh

Total Price
Total Harga
(RP.)
4,785
2,871
726
8,382

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

8,382
1,257.30
9,639.30

A. 8.4.2.35 Cutting one GIP pipes 125 mm/Pemotongan 1 buah pipa GIP 125 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.092
82,500
L.02
Manday
0.046
99,000
L.04
Manday
0.009
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 125 mm

bh

Total Price
Total Harga
(RP.)
7,590
4,554
1,089
13,233

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

13,233
1,984.95
15,217.95

A. 8.4.2.36 Cutting one GIP pipes 150 mm/Pemotongan 1 buah pipa GIP 150 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.131
82,500
L.02
Manday
0.066
99,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 150 mm

bh

Total Price
Total Harga
(RP.)
10,808
6,534
1,573
18,915

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

18,915
2,837.18
21,751.68

A. 8.4.2.37 Cutting one GIP pipes 200 mm/Pemotongan 1 buah pipa GIP 200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.340
82,500
L.02
Manday
0.170
99,000
L.04
Manday
0.034
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 200 mm

bh

Total Price
Total Harga
(RP.)
28,050
16,830
4,114
48,994

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

48,994
7,349.10
56,343.10

A. 8.4.2.38 Cutting one GIP pipes 250 mm/Pemotongan 1 buah pipa GIP 250 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
B

L.01
Manday
0.475
82,500
L.02
Manday
0.237
99,000
L.04
Manday
0.047
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 250 mm

bh

39,188
23,463
5,687
68,338

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

68,338
10,250.63
78,588.13

A. 8.4.2.39 Cutting one GIP pipes 300 mm/Pemotongan 1 buah pipa GIP 300 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.504
82,500
L.02
Manday
0.252
99,000
L.04
Manday
0.050
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 300 mm

bh

Total Price
Total Harga
(RP.)
41,580
24,948
6,050
72,578

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

72,578
10,886.70
83,464.70

A. 8.4.2.40 Cutting one GIP pipes 400 mm/Pemotongan 1 buah pipa GIP 400 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.738
82,500
L.02
Manday
0.369
99,000
L.04
Manday
0.074
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 400 mm

bh

Total Price
Total Harga
(RP.)
60,885
36,531
8,954
106,370

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

106,370
15,955.50
122,325.50

A. 8.4.2.41 Cutting one GIP pipes 450 mm/Pemotongan 1 buah pipa GIP 450 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.848
82,500
L.02
Manday
0.424
99,000
L.04
Manday
0.085
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 450 mm

bh

Total Price
Total Harga
(RP.)
69,960
41,976
10,285
122,221

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

122,221
18,333.15
140,554.15

A. 8.4.2.42 Cutting one GIP pipes 500 mm/Pemotongan 1 buah pipa GIP 500 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
GIP pipe/Pipa GIP 500 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.941
82,500
L.02
Manday
0.471
99,000
L.04
Manday
0.094
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

Total Price
Total Harga
(RP.)
77,633
46,629
11,374
135,636
-

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

135,636
20,345.33
155,980.83

A. 8.4.2.43 Cutting one GIP pipes 600 mm/Pemotongan 1 buah pipa GIP 600 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.864
82,500
L.02
Manday
0.432
99,000
L.04
Manday
0.086
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 600 mm

bh

Total Price
Total Harga
(RP.)
71,280
42,768
10,406
124,454

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

124,454
18,668.10
143,122.10

A. 8.4.2.44 Cutting one GIP pipes 800 mm/Pemotongan 1 buah pipa GIP 800 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.567
82,500
L.02
Manday
0.783
99,000
L.04
Manday
0.157
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 800 mm

bh

Total Price
Total Harga
(RP.)
129,278
77,517
18,997
225,792

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

225,792
33,868.73
259,660.23

A. 8.4.2.45 Cutting one GIP pipes 900 mm/Pemotongan 1 buah pipa GIP 900 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.770
82,500
L.02
Manday
0.885
99,000
L.04
Manday
0.177
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 900 mm

bh

Total Price
Total Harga
(RP.)
146,025
87,615
21,417
255,057

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

255,057
38,258.55
293,315.55

A. 8.4.2.46 Cutting one GIP pipes 1000 mm/Pemotongan 1 buah pipa GIP 1000 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
GIP pipe/Pipa GIP 1000 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.974
82,500
L.02
Manday
0.987
99,000
L.04
Manday
0.197
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

Total Price
Total Harga
(RP.)
162,855
97,713
23,837
284,405
-

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

284,405
42,660.75
327,065.75

A. 8.4.2.47 Cutting one GIP pipes 1100 mm/Pemotongan 1 buah pipa GIP 1100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.178
82,500
L.02
Manday
1.089
99,000
L.04
Manday
0.218
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 1100 mm

bh

Total Price
Total Harga
(RP.)
179,685
107,811
26,378
313,874

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

313,874
47,081.10
360,955.10

A. 8.4.2.48 Cutting one GIP pipes 1200 mm/Pemotongan 1 buah pipa GIP 1200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.382
82,500
L.02
Manday
1.191
99,000
L.04
Manday
0.238
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
GIP pipe/Pipa GIP 1200 mm

bh

Total Price
Total Harga
(RP.)
196,515
117,909
28,798
343,222

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

343,222
51,483.30
394,705.30

A. 8.4.2.49 DCI cuts 1 piece pipe 100 mm/Pemotongan 1 buah pipa DCI 100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.071
82,500
L.02
Manday
0.014
99,000
L.04
Manday
0.007
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 100 mm

bh

Total Price
Total Harga
(RP.)
5,858
1,386
847
8,091

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle crane 2
T

Day / Hari

0.003

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

8,091
1,213.58
9,304.08

A. 8.4.2.50 DCI cuts 1 piece pipe 125 mm/Pemotongan 1 buah pipa DCI 125 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
DCI pipe/Pipa DCI 125 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.112
82,500
L.02
Manday
0.022
99,000
L.04
Manday
0.011
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle crane 2
T

Day / Hari

0.010

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

A. 8.4.2.51 DCI cuts 1 piece pipe 150 mm/Pemotongan 1 buah pipa DCI 150 mm

Total Price
Total Harga
(RP.)
9,240
2,178
1,331
12,749
12,749
1,912.35
14,661.35

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.159
82,500
L.02
Manday
0.032
99,000
L.04
Manday
0.016
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 150 mm

bh

Total Price
Total Harga
(RP.)
13,118
3,168
1,936
18,222

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle crane 2
T

Day / Hari

0.018

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

18,222
2,733.23
20,954.73

A. 8.4.2.52 DCI cuts 1 piece pipe 200 mm/Pemotongan 1 buah pipa DCI 200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.366
82,500
L.02
Manday
0.073
99,000
L.04
Manday
0.037
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 200 mm

bh

Total Price
Total Harga
(RP.)
30,195
7,227
4,477
41,899

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.054

15% x D

41,899
6,284.85
48,183.85

A. 8.4.2.53 DCI cuts 1 piece pipe 250 mm/Pemotongan 1 buah pipa DCI 250 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.476
82,500
L.02
Manday
0.095
99,000
L.04
Manday
0.048
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 250 mm

bh

Total Price
Total Harga
(RP.)
39,270
9,405
5,808
54,483

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle crane 2
T

Day / Hari

0.073

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

54,483
8,172.45
62,655.45

A. 8.4.2.54 DCI cuts 1 piece pipe 300 mm/Pemotongan 1 buah pipa DCI 300 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.512
82,500
L.02
Manday
0.102
99,000
L.04
Manday
0.051
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 300 mm

bh

Total Price
Total Harga
(RP.)
42,240
10,098
6,171
58,509

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot/ Sewa Tripot/Tackel & handle crane 2
T

Day / Hari

0.079

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

58,509
8,776.35
67,285.35

A. 8.4.2.55 DCI cuts 1 piece pipe 400 mm/Pemotongan 1 buah pipa DCI 400 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
DCI pipe/Pipa DCI 400 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.941
82,500
L.02
Manday
0.188
99,000
L.04
Manday
0.094
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

Total Price
Total Harga
(RP.)
77,633
18,612
11,374
107,619
-

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.158

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

107,619
16,142.78
123,761.28

A. 8.4.2.56 DCI cuts 1 piece pipe 450 mm/Pemotongan 1 buah pipa DCI 450 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.137
82,500
L.02
Manday
0.227
99,000
L.04
Manday
0.114
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 450 mm

bh

Total Price
Total Harga
(RP.)
93,803
22,473
13,794
130,070

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.176

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

130,070
19,510.43
149,579.93

A. 8.4.2.57 DCI cuts 1 piece pipe 500 mm/Pemotongan 1 buah pipa DCI 500 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.312
82,500
L.02
Manday
0.262
99,000
L.04
Manday
0.131
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 500 mm

bh

Total Price
Total Harga
(RP.)
108,240
25,938
15,851
150,029

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.192

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

150,029
22,504.35
172,533.35

15% x D

A. 8.4.2.58 DCI cuts 1 piece pipe 600 mm/Pemotongan 1 buah pipa DCI 600 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.309
82,500
L.02
Manday
0.262
99,000
L.04
Manday
0.131
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipeDCI pipe/Pipa DCI 600 mm

bh

Total Price
Total Harga
(RP.)
107,993
25,938
15,851
149,782

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.192

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

149,782
22,467.23
172,248.73

A. 8.4.2.59 DCI cuts 1 piece pipe 800 mm/Pemotongan 1 buah pipa DCI 800 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
DCI pipe/Pipa DCI 800 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.598
82,500
L.02
Manday
0.520
99,000
L.04
Manday
0.260
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.310

Total Price
Total Harga
(RP.)
214,335
51,480
31,460
297,275
-

T2 pipe cutting equipment / mechanical / cilinder


saw/ Peralatan potong pipa T2/mekanik/cilinder
saw
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT
D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

297,275
44,591.25
341,866.25

A. 8.4.2.60 DCI cuts 1 piece pipe 900 mm/Pemotongan 1 buah pipa DCI 900 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
3.370
82,500
L.02
Manday
0.674
99,000
L.04
Manday
0.337
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 900 mm

bh

Total Price
Total Harga
(RP.)
278,025
66,726
40,777
385,528

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.381

15% x D

385,528
57,829.20
443,357.20

A. 8.4.2.61 DCI cuts 1 piece pipe 1000 mm/Pemotongan 1 buah pipa DCI 1000 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
4.021
82,500
L.02
Manday
0.804
99,000
L.04
Manday
0.402
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 1000 mm

bh

Total Price
Total Harga
(RP.)
331,733
79,596
48,642
459,971

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.441

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

459,971
68,995.58
528,966.08

A. 8.4.2.62 DCI cuts 1 piece pipe 1100 mm/Pemotongan 1 buah pipa DCI 1100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
4.731
82,500
L.02
Manday
0.946
99,000
L.04
Manday
0.473
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
DCI pipe/Pipa DCI 1100 mm

bh

Total Price
Total Harga
(RP.)
390,308
93,654
57,233
541,195

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.506

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

541,195
81,179.18
622,373.68

A. 8.4.2.63 DCI cuts 1 piece pipe 1200 mm/Pemotongan 1 buah pipa DCI 1200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
DCI pipe/Pipa DCI 1200 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
5.502
82,500
L.02
Manday
1.100
99,000
L.04
Manday
0.550
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.576

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

Total Price
Total Harga
(RP.)
453,915
108,900
66,550
629,365
-

629,365
94,404.75
723,769.75

A. 8.4.2.65 Cutting 1 piece of steel pipe 100 mm/Pemotongan 1 buah pipa baja 100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.085
82,500
L.02
Manday
0.017
99,000
L.04
Manday
0.008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 100 mm

bh

Total Price
Total Harga
(RP.)
7,013
1,683
968
9,664

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.040

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

9,664
1,449.53
11,113.03

A. 8.4.2.66 Cutting 1 piece of steel pipe 125 mm/Pemotongan 1 buah pipa baja 125 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.133
82,500
L.02
Manday
0.027
99,000
L.04
Manday
0.013
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 125 mm

bh

Total Price
Total Harga
(RP.)
10,973
2,673
1,573
15,219

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.042

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

15,219
2,282.78
17,501.28

A. 8.4.2.67 Cutting 1 piece of steel pipe 150 mm/Pemotongan 1 buah pipa baja 150 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.184
82,500
L.02
Manday
0.037
99,000
L.04
Manday
0.018
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 150 mm

bh

Total Price
Total Harga
(RP.)
15,180
3,663
2,178
21,021

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.045

15% x D

21,021
3,153.15
24,174.15

A. 8.4.2.68 Cutting 1 piece of steel pipe 200 mm/Pemotongan 1 buah pipa baja 200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.476
82,500
L.02
Manday
0.095
99,000
L.04
Manday
0.048
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 200 mm

bh

Total Price
Total Harga
(RP.)
39,270
9,405
5,808
54,483

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.060

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

54,483
8,172.45
62,655.45

A. 8.4.2.69 Cutting 1 piece of steel pipe 250 mm/Pemotongan 1 buah pipa baja 250 mm

Nr./No.

Description/Uraian

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

L.01
Manday
0.663
82,500
L.02
Manday
0.133
99,000
L.04
Manday
0.066
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 250 mm

bh

54,698
13,167
7,986
75,851

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.068

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

75,851
11,377.58
87,228.08

A. 8.4.2.70 Cutting 1 piece of steel pipe 300 mm/Pemotongan 1 buah pipa baja 300 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.745
82,500
L.02
Manday
0.149
99,000
L.04
Manday
0.074
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 300 mm

bh

Total Price
Total Harga
(RP.)
61,463
14,751
8,954
85,168

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.072

15% x D

85,168
12,775.13
97,942.63

A. 8.4.2.71 Cutting 1 piece of steel pipe 400 mm/Pemotongan 1 buah pipa baja 400 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.440
82,500
L.02
Manday
0.288
99,000
L.04
Manday
0.144
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 400 mm

bh

Total Price
Total Harga
(RP.)
118,800
28,512
17,424
164,736

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.105

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

164,736
24,710.40
189,446.40

A. 8.4.2.72 Cutting 1 piece of steel pipe 450 mm/Pemotongan 1 buah pipa baja 450 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.399
82,500
L.02
Manday
0.280
99,000
L.04
Manday
0.140
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 450 mm

bh

Total Price
Total Harga
(RP.)
115,418
27,720
16,940
160,078

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.107

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

160,078
24,011.63
184,089.13

A. 8.4.2.73 Cutting 1 piece of steel pipe 500 mm/Pemotongan 1 buah pipa baja 500 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.558
82,500
L.02
Manday
0.312
99,000
L.04
Manday
0.156
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

Total Price
Total Harga
(RP.)
128,535
30,888
18,876
178,299

Steel pipe/Pipa baja 500 mm

bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.107

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

178,299
26,744.85
205,043.85

A. 8.4.2.74 Cutting 1 piece of steel pipe 600 mm/Pemotongan 1 buah pipa baja 600 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.437
82,500
L.02
Manday
0.287
99,000
L.04
Manday
0.144
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 600 mm

bh

Total Price
Total Harga
(RP.)
118,553
28,413
17,424
164,390

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.113

15% x D

164,390
24,658.43
189,047.93

A. 8.4.2.75 Cutting 1 piece of steel pipe 800 mm/Pemotongan 1 buah pipa baja 800 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.624
82,500
L.02
Manday
0.525
99,000
L.04
Manday
0.262
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 800 mm

bh

Total Price
Total Harga
(RP.)
216,480
51,975
31,702
300,157

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.166

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

300,157
45,023.55
345,180.55

A. 8.4.2.76 Cutting 1 piece of steel pipe 900 mm/Pemotongan 1 buah pipa baja 900 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.971
82,500
L.02
Manday
0.594
99,000
L.04
Manday
0.297
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 900 mm

bh

Total Price
Total Harga
(RP.)
245,108
58,806
35,937
339,851

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.183

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

339,851
50,977.58
390,828.08

A. 8.4.2.77 Cutting 1 piece of steel pipe 1000 mm/Pemotongan 1 buah pipa baja 1000 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
Steel pipe/Pipa baja 1000 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
3.319
82,500
L.02
Manday
0.664
99,000
L.04
Manday
0.332
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.201

Total Price
Total Harga
(RP.)
273,818
65,736
40,172
379,726
-

T2 pipe cutting equipment / mechanical / cilinder


saw/ Peralatan potong pipa T2/mekanik/cilinder
saw
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT
D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

379,726
56,958.83
436,684.33

A. 8.4.2.78 Cutting 1 piece of steel pipe 1100 mm/Pemotongan 1 buah pipa baja 1100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
3.667
82,500
L.02
Manday
0.733
99,000
L.04
Manday
0.367
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 1100 mm

bh

Total Price
Total Harga
(RP.)
302,528
72,567
44,407
419,502

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment / mechanical / cilinder
saw/ Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.218

15% x D

419,502
62,925.23
482,426.73

A. 8.4.2.79 Cutting 1 piece of steel pipe 1200 mm/Pemotongan 1 buah pipa baja 1200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
4.015
82,500
L.02
Manday
0.803
99,000
L.04
Manday
0.402
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Steel pipe/Pipa baja 1200 mm

bh

Total Price
Total Harga
(RP.)
331,238
79,497
48,642
459,377

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical/cilinder
saw / Peralatan potong pipa T2/mekanik/cilinder
saw

Day / Hari

0.236

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

459,377
68,906.48
528,282.98

A. 8.4.3 UNIT PRICE WORK PIPE FITTING ACCESSORIES/HARGA SATUAN PEK. PEMASANGAN AKSESORIS PIPA
A. 8.4.3.1 Installation of 1 piece 150 mm Valve/Pemasangan 1 buah Valve 150 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.429
82,500
L.02
Manday
0.715
99,000
L.04
Manday
0.143
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Valve 150 mm

Bh

Total Price
Total Harga
(RP.)
117,893
70,785
17,303
205,981

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.100

15% x D

205,981
30,897.08
236,877.58

A. 8.4.3.2 Installation of 1 piece 200 mm Valve/Pemasangan 1 buah Valve 200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
Valve 200 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.714
82,500
L.02
Manday
0.857
99,000
L.04
Manday
0.171
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.300

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

Total Price
Total Harga
(RP.)
141,405
84,843
20,691
246,939
246,939
37,040.85
283,979.85

A. 8.4.3.3 Installation of 1 piece 250 mm Valve/Pemasangan 1 buah Valve 250 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.714
82,500
L.02
Manday
0.857
99,000
L.04
Manday
0.171
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Valve 250 mm

Bh

Total Price
Total Harga
(RP.)
141,405
84,843
20,691
246,939

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.400

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

246,939
37,040.85
283,979.85

A. 8.4.3.4 Installation of 1 piece 300 mm Valve/Pemasangan 1 buah Valve 300 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.000
82,500
L.02
Manday
1.000
99,000
L.04
Manday
0.200
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Valve 300 mm

Bh

Total Price
Total Harga
(RP.)
165,000
99,000
24,200
288,200

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.500

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

288,200
43,230.00
331,430.00

A. 8.4.3.5 Installation of 1 piece 400 mm Valve/Pemasangan 1 buah Valve 400 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
3.429
82,500
L.02
Manday
1.715
99,000
L.04
Manday
0.343
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Valve 400 mm

Bh

Total Price
Total Harga
(RP.)
282,893
169,785
41,503
494,181

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

1.000

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

494,181
74,127.08
568,307.58

A. 8.4.3.6 Installation of 1 piece 450 mm Valve/Pemasangan 1 buah Valve 450 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
3.429
82,500
L.02
Manday
1.715
99,000
L.04
Manday
0.343
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Valve 450 mm

Bh

Total Price
Total Harga
(RP.)
282,893
169,785
41,503
494,181

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

1.000

15% x D

494,181
74,127.08
568,307.58

A. 8.4.3.7 Installation of 1 piece 500 mm Valve/Pemasangan 1 buah Valve 500 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

L.01
L.02
L.04

Manday
Manday
Manday

Coefficient
Koefisien

4.000
2.000
0.400

Unit Price
Harga Satuan
(Rp.)
82,500
99,000
121,000

Total Price
Total Harga
(RP.)
330,000
198,000
48,400

MANPOWER TOTAL / JUMLAH TENAGA KERJA


B

MATERIALS/BAHAN
Valve 500 mm

Bh

576,400

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

1.000

15% x D

576,400
86,460.00
662,860.00

A. 8.4.3.8 Installation of 1 piece 600 mm Valve/Pemasangan 1 buah Valve 600 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.421
82,500
L.02
Manday
0.711
99,000
L.04
Manday
0.142
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Valve 600 mm

Bh

Total Price
Total Harga
(RP.)
117,233
70,389
17,182
204,804

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

D
E
F

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T
Mobile crane =< 3 ton

Day / Hari

Day / Hari
0.300
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.600

15% x D

204,804
30,720.53
235,524.03

A. 8.4.3.9 Installation of 1 piece 700 mm Valve/Pemasangan 1 buah Valve 700 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.429
82,500
L.02
Manday
0.715
99,000
L.04
Manday
0.143
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Valve 700 mm

Bh

Total Price
Total Harga
(RP.)
117,893
70,785
17,303
205,981

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

D
E
F

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T
Mobile crane =< 3 ton

Day / Hari

0.500

Day / Hari
0.500
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

205,981
30,897.08
236,877.58

A. 8.4.3.10 Installation of 1 piece 800 mm Valve/Pemasangan 1 buah Valve 800 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.786
82,500
L.02
Manday
0.893
99,000
L.04
Manday
0.179
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Valve 800 mm

Bh

Total Price
Total Harga
(RP.)
147,345
88,407
21,659
257,411

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

D
E
F

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T
Mobile crane =< 3 ton

Day / Hari

Day / Hari
0.500
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.500

15% x D

257,411
38,611.65
296,022.65

A. 8.4.3.11 Installation of 1 piece 900 mm Valve/Pemasangan 1 buah Valve 900 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
Valve 900 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.714
82,500
L.02
Manday
0.857
99,000
L.04
Manday
0.171
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.750

Total Price
Total Harga
(RP.)
141,405
84,843
20,691
246,939
-

Rent Tripot / Sewa Tripot/Tackel & handle Crane 2


T
Mobile crane =< 3 ton
D
E
F

Day / Hari
0.750
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

246,939
37,040.85
283,979.85

A. 8.4.3.12 Installation of 1 piece 1000 mm Valve/Pemasangan 1 buah Valve 1000 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.571
82,500
L.02
Manday
1.286
99,000
L.04
Manday
0.257
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Valve 1000 mm

Bh

Total Price
Total Harga
(RP.)
212,108
127,314
31,097
370,519

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

D
E
F

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T
Mobile crane =< 3 ton

Day / Hari

1.000

Day / Hari
1.000
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

370,519
55,577.78
426,096.28

A. 8.4.3.13 Installation of 1 piece 1100 mm Valve/Pemasangan 1 buah Valve 1100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
3.000
82,500
L.02
Manday
1.500
99,000
L.04
Manday
0.300
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Valve 1100 mm

Bh

Total Price
Total Harga
(RP.)
247,500
148,500
36,300
432,300

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

D
E
F

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T
Mobile crane =< 3 ton

Day / Hari

1.000

Day / Hari
1.000
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

432,300
64,845.00
497,145.00

A. 8.4.3.14 Installation of 1 piece 1200 mm Valve/Pemasangan 1 buah Valve 1200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
3.000
82,500
L.02
Manday
1.500
99,000
L.04
Manday
0.300
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Valve 1200 mm

Bh

Total Price
Total Harga
(RP.)
247,500
148,500
36,300
432,300

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

D
E
F

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T
Mobile crane =< 3 ton

Day / Hari

Day / Hari
1.000
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

1.000

15% x D

432,300
64,845.00
497,145.00

A. 8.4.3.15 Installation of 1 piece Tee 150 mm/Pemasangan 1 buah Tee 150 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
Tee 150 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.106
82,500
L.02
Manday
0.053
99,000
L.04
Manday
0.011
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.028

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

Total Price
Total Harga
(RP.)
8,745
5,247
1,331
15,323
15,323
2,298.45
17,621.45

A. 8.4.3.16 Installation of 1 piece Tee 200 mm/Pemasangan 1 buah Tee 200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.216
82,500
L.02
Manday
0.108
99,000
L.04
Manday
0.022
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Tee 200 mm

Bh

Total Price
Total Harga
(RP.)
17,820
10,692
2,662
31,174

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.029

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

31,174
4,676.10
35,850.10

A. 8.4.3.17 Installation of 1 piece Tee 250 mm/Pemasangan 1 buah Tee 250 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.326
82,500
L.02
Manday
0.163
99,000
L.04
Manday
0.033
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Tee 250 mm

Bh

Total Price
Total Harga
(RP.)
26,895
16,137
3,993
47,025

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.039

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

47,025
7,053.75
54,078.75

A. 8.4.3.18 Installation of 1 piece Tee 300 mm/Pemasangan 1 buah Tee 300 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.436
82,500
L.02
Manday
0.218
99,000
L.04
Manday
0.044
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Tee 300 mm

Bh

Total Price
Total Harga
(RP.)
35,970
21,582
5,324
62,876

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.500

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

62,876
9,431.40
72,307.40

A. 8.4.3.19 Installation of 1 piece Tee 400 mm/Pemasangan 1 buah Tee 400 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.656
82,500
L.02
Manday
0.328
99,000
L.04
Manday
0.066
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Tee 400 mm

Bh

Total Price
Total Harga
(RP.)
54,120
32,472
7,986
94,578

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.500

15% x D

94,578
14,186.70
108,764.70

A. 8.4.3.20 Installation of 1 piece Tee 450 mm/Pemasangan 1 buah Tee 450 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

L.01
L.02
L.04

Manday
Manday
Manday

Coefficient
Koefisien

0.766
0.383
0.077

Unit Price
Harga Satuan
(Rp.)
82,500
99,000
121,000

Total Price
Total Harga
(RP.)
63,195
37,917
9,317

MANPOWER TOTAL / JUMLAH TENAGA KERJA


B

MATERIALS/BAHAN
Tee 450 mm

Bh

110,429

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.500

15% x D

110,429
16,564.35
126,993.35

A. 8.4.3.21 Installation of 1 piece Tee 500 mm/Pemasangan 1 buah Tee 500 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.876
82,500
L.02
Manday
0.438
99,000
L.04
Manday
0.088
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Tee 500 mm

Bh

Total Price
Total Harga
(RP.)
72,270
43,362
10,648
126,280

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.600

15% x D

126,280
18,942.00
145,222.00

A. 8.4.3.22 Installation of 1 piece Tee 600 mm/Pemasangan 1 buah Tee 600 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.096
82,500
L.02
Manday
0.548
99,000
L.04
Manday
0.110
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Tee 600 mm

Bh

Total Price
Total Harga
(RP.)
90,420
54,252
13,310
157,982

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

D
E
F

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T
Mobile crane =< 3 ton

Day / Hari

0.193

Day / Hari
0.096
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

157,982
23,697.30
181,679.30

A. 8.4.3.23 Installation of 1 piece Tee 700 mm/Pemasangan 1 buah Tee 700 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.316
82,500
L.02
Manday
0.658
99,000
L.04
Manday
0.132
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Tee 700 mm

Bh

Total Price
Total Harga
(RP.)
108,570
65,142
15,972
189,684

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

D
E
F

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T
Mobile crane =< 3 ton

Day / Hari

0.225

Day / Hari
0.113
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

189,684
28,452.60
218,136.60

A. 8.4.3.24 Installation of 1 piece Tee 800 mm/Pemasangan 1 buah Tee 800 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
Tee 800 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.536
82,500
L.02
Manday
0.768
99,000
L.04
Manday
0.154
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T

Day / Hari

0.257

Total Price
Total Harga
(RP.)
126,720
76,032
18,634
221,386
-

Mobile crane =< 3 ton


D
E
F

Day / Hari
0.129
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

221,386
33,207.90
254,593.90

A. 8.4.3.25 Installation of 1 piece Tee 900 mm/Pemasangan 1 buah Tee 900 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.756
82,500
L.02
Manday
0.878
99,000
L.04
Manday
0.176
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Tee 900 mm

Bh

Total Price
Total Harga
(RP.)
144,870
86,922
21,296
253,088

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

D
E
F

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T
Mobile crane =< 3 ton

Day / Hari

Day / Hari
0.161
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

0.321

15% x D

253,088
37,963.20
291,051.20

A. 8.4.3.26 Installation of 1 piece Tee 1000 mm/Pemasangan 1 buah Tee 1000 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.976
82,500
L.02
Manday
0.988
99,000
L.04
Manday
0.198
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Tee 1000 mm

Bh

Total Price
Total Harga
(RP.)
163,020
97,812
23,958
284,790

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

D
E
F

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T
Mobile crane =< 3 ton

Day / Hari

0.366

Day / Hari
0.183
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

284,790
42,718.50
327,508.50

A. 8.4.3.27 Installation of 1 piece Tee 1100 mm/Pemasangan 1 buah Tee 1100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.196
82,500
L.02
Manday
1.098
99,000
L.04
Manday
0.220
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Tee 1100 mm

Bh

Total Price
Total Harga
(RP.)
181,170
108,702
26,620
316,492

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

D
E
F

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T
Mobile crane =< 3 ton

Day / Hari

0.386

Day / Hari
0.193
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

316,492
47,473.80
363,965.80

A. 8.4.3.28 Installation of 1 piece Tee 1200 mm/Pemasangan 1 buah Tee 1200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
Tee 1200 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.416
82,500
L.02
Manday
1.208
99,000
L.04
Manday
0.242
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
Bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

D
E
F

EQUIPMENT/PERALATAN
Rent Tripot / Sewa Tripot/Tackel & handle Crane 2
T
Mobile crane =< 3 ton
Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

Day / Hari

0.450

Day / Hari
0.225
PRICE TOOLS TOTAL / JUMLAH HARGA ALAT
15% x D

Total Price
Total Harga
(RP.)
199,320
119,592
29,282
348,194
348,194
52,229.10
400,423.10

A. 8.4.4 WORK UNIT PRICE NEW PIPE CONNECTIONS TO PIPE OLD / HARGA SATUAN PEKERJAAN
PENYAMBUNGAN PIPA BARU KE PIPA LAMA
A. 8.4.4.1 Splicing 1 piece of new pipe to the existing pipe 80 mm/Penyambungan 1 buah pipa baru ke pipa yang ada 80
mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.466
82,500
L.02
Manday
0.733
99,000
L.04
Manday
0.147
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Pipe/Pipa 80 mm

bh

Total Price
Total Harga
(RP.)
120,945
72,567
17,787
211,299

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical / Peralatan
potong pipa T2/mekanik/cilinder saw
Rent Generator/Sewa Genset 1500 watt
Submersible Pump Hire / Sewa Pompa
Submersible 3 m3/h
Rent Tripod / Sewa Tripod/Tackel & handle crane
2T

Day / Hari

0.606

Day / Hari

0.075

Day / Hari

0.968

Day / Hari

0.865

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

211,299
31,694.85
242,993.85

A. 8.4.4.2 Splicing 1 piece of new pipe to the existing pipe 100 mm/Penyambungan 1 buah pipa baru ke pipa yang ada 100
mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
1.646
82,500
L.02
Manday
0.823
99,000
L.04
Manday
0.165
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Pipe/Pipa 100 mm

bh

Total Price
Total Harga
(RP.)
135,795
81,477
19,965
237,237

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical / Peralatan
potong pipa T2/mekanik/cilinder saw
Rent Generator/Sewa Genset 1500 watt
Submersible Pump Hire / Sewa Pompa
Submersible 3 m3/h
Rent Tripod / Sewa Tripod/Tackel & handle crane
2T

Day / Hari

0.650

Day / Hari

0.159

Day / Hari

1.078

Day / Hari

0.911

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

237,237
35,585.55
272,822.55

A. 8.4.4.3 Splicing 1 piece of new pipe to the existing pipe 150 mm/Penyambungan 1 buah pipa baru ke pipa yang ada 150
mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.096
82,500
L.02
Manday
1.048
99,000
L.04
Manday
0.210
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Pipe/Pipa 150 mm

bh

Total Price
Total Harga
(RP.)
172,920
103,752
25,410
302,082

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical / Peralatan
potong pipa T2/mekanik/cilinder saw
Rent Generator/Sewa Genset 1500 watt
Submersible Pump Hire / Sewa Pompa
Submersible 3 m3/h
Rent Tripod / Sewa Tripod/Tackel & handle crane
2T

Day / Hari

0.760

Day / Hari

0.369

Day / Hari

1.353

Day / Hari

1.026

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

302,082
45,312.30
347,394.30

A. 8.4.4.4 Splicing 1 piece of new pipe to the existing pipe 200 mm/Penyambungan 1 buah pipa baru ke pipa yang ada 200
mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
Pipe/Pipa 200 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.546
82,500
L.02
Manday
1.273
99,000
L.04
Manday
0.255
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

Total Price
Total Harga
(RP.)
210,045
126,027
30,855
366,927
-

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical / Peralatan
potong pipa T2/mekanik/cilinder saw
Rent Generator/Sewa Genset 1500 watt
Submersible Pump Hire / Sewa Pompa
Submersible 3 m3/h
Rent Tripod / Sewa Tripod/Tackel & handle crane
2T

Day / Hari

0.870

Day / Hari

0.579

Day / Hari

1.628

Day / Hari

1.141

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

366,927
55,039.05
421,966.05

A. 8.4.4.5 Splicing 1 piece of new pipe to the existing pipe 250 mm/Penyambungan 1 buah pipa baru ke pipa yang ada 250
mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
2.996
82,500
L.02
Manday
1.498
99,000
L.04
Manday
0.300
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Pipe/Pipa 250 mm

bh

Total Price
Total Harga
(RP.)
247,170
148,302
36,300
431,772

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical / Peralatan
potong pipa T2/mekanik/cilinder saw
Rent Generator/Sewa Genset 1500 watt
Submersible Pump Hire / Sewa Pompa
Submersible 3 m3/h
Rent Tripod / Sewa Tripod/Tackel & handle crane
2T

Day / Hari

0.980

Day / Hari

0.789

Day / Hari

1.903

Day / Hari

1.256

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

431,772
64,765.80
496,537.80

A. 8.4.4.6 Splicing 1 piece of new pipe to the existing pipe 300 mm/Penyambungan 1 buah pipa baru ke pipa yang ada 300
mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
3.446
82,500
L.02
Manday
1.723
99,000
L.04
Manday
0.345
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Pipe/Pipa 300 mm

bh

Total Price
Total Harga
(RP.)
284,295
170,577
41,745
496,617

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical / Peralatan
potong pipa T2/mekanik/cilinder saw
Rent Generator/Sewa Genset 1500 watt
Submersible Pump Hire / Sewa Pompa
Submersible 3 m3/h
Rent Tripod / Sewa Tripod/Tackel & handle crane
2T

Day / Hari

1.090

Day / Hari

0.999

Day / Hari

2.178

Day / Hari

1.371

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

496,617
74,492.55
571,109.55

A. 8.4.4.7 Splicing 1 piece of new pipe to the existing pipe 400 mm/Penyambungan 1 buah pipa baru ke pipa yang ada 400
mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
Pipe/Pipa 400 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
4.346
82,500
L.02
Manday
2.173
99,000
L.04
Manday
0.435
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical / Peralatan
potong pipa T2/mekanik/cilinder saw
Rent Generator/Sewa Genset 1500 watt
Submersible Pump Hire / Sewa Pompa
Submersible 3 m3/h
Rent Tripod / Sewa Tripod/Tackel & handle crane
2T
Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

358,545
215,127
52,635
626,307
-

Day / Hari

1.310

Day / Hari

1.419

Day / Hari

2.728

Day / Hari

1.601

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total Price
Total Harga
(RP.)

15% x D

626,307
93,946.05
720,253.05

A. 8.4.4.8 Splicing 1 piece of new pipe to the existing pipe 450 mm/Penyambungan 1 buah pipa baru ke pipa yang ada 450
mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
4.796
82,500
L.02
Manday
2.398
99,000
L.04
Manday
0.480
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Pipe/Pipa 450 mm

bh

Total Price
Total Harga
(RP.)
395,670
237,402
58,080
691,152

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical / Peralatan
potong pipa T2/mekanik/cilinder saw
Rent Generator/Sewa Genset 1500 watt
Submersible Pump Hire / Sewa Pompa
Submersible 3 m3/h
Rent Tripod / Sewa Tripod/Tackel & handle crane
2T

Day / Hari

1.420

Day / Hari

1.629

Day / Hari

3.003

Day / Hari

1.716

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

691,152
103,672.80
794,824.80

A. 8.4.4.9 Splicing 1 piece of new pipe to the existing pipe 500 mm/Penyambungan 1 buah pipa baru ke pipa yang ada 500
mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
5.246
82,500
L.02
Manday
2.623
99,000
L.04
Manday
0.525
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Pipe/Pipa 500 mm

bh

Total Price
Total Harga
(RP.)
432,795
259,677
63,525
755,997

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical / Peralatan
potong pipa T2/mekanik/cilinder saw
Rent Generator/Sewa Genset 1500 watt
Submersible Pump Hire / Sewa Pompa
Submersible 3 m3/h
Rent Tripod / Sewa Tripod/Tackel & handle crane
2T

Day / Hari

1.530

Day / Hari

1.839

Day / Hari

3.278

Day / Hari

1.831

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

755,997
113,399.55
869,396.55

A. 8.4.4.10 Splicing 1 piece of new pipe to the existing pipe 600 mm/Penyambungan 1 buah pipa baru ke pipa yang ada
600 mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
6.146
82,500
L.02
Manday
3.073
99,000
L.04
Manday
0.615
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Pipe/Pipa 600 mm

bh

Total Price
Total Harga
(RP.)
507,045
304,227
74,415
885,687

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical / Peralatan
potong pipa T2/mekanik/cilinder saw
Rent Generator/Sewa Genset 1500 watt
Submersible Pump Hire / Sewa Pompa
Submersible 3 m3/h
Rent Tripod / Sewa Tripod/Tackel & handle crane
2T

Day / Hari

1.750

Day / Hari

2.259

Day / Hari

3.828

Day / Hari

2.061

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

885,687
132,853.05
1,018,540.05

A. 8.4.4.11 Splicing 1 piece of new pipe to the existing pipe 700 mm/Penyambungan 1 buah pipa baru ke pipa yang ada
700 mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor
MATERIALS/BAHAN
Pipe/Pipa 700 mm

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
7.046
82,500
L.02
Manday
3.523
99,000
L.04
Manday
0.705
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
bh

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN

Total Price
Total Harga
(RP.)
581,295
348,777
85,305
1,015,377
-

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical / Peralatan
potong pipa T2/mekanik/cilinder saw
Rent Generator/Sewa Genset 1500 watt
Submersible Pump Hire / Sewa Pompa
Submersible 3 m3/h
Rent Tripod / Sewa Tripod/Tackel & handle crane
2T

Day / Hari

1.970

Day / Hari

2.679

Day / Hari

4.378

Day / Hari

2.291

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

1,015,377
152,306.55
1,167,683.55

A. 8.4.4.12 Splicing 1 piece of new pipe to the existing pipe 800 mm/Penyambungan 1 buah pipa baru ke pipa yang ada
800 mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Plumber/Tukang pipa
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
7.946
82,500
L.02
Manday
3.973
99,000
L.04
Manday
0.795
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Pipe/Pipa 800 mm

bh

Total Price
Total Harga
(RP.)
655,545
393,327
96,195
1,145,067

1.00

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN
T2 pipe cutting equipment/mechanical / Peralatan
potong pipa T2/mekanik/cilinder saw
Rent Generator/Sewa Genset 1500 watt
Submersible Pump Hire / Sewa Pompa
Submersible 3 m3/h
Rent Tripod / Sewa Tripod/Tackel & handle crane
2T

Day / Hari

2.190

Day / Hari

3.099

Day / Hari

4.928

Day / Hari

2.521

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

15% x D

1,145,067
171,760.05
1,316,827.05

A. 8.4.5 PIPE WORK UNIT PRICE TESTING/HARGA SATUAN PEKERJAAN PENGETESAN PIPA
A. 8.4.5.1 Testing 1 m pipe 50 mm/Pengetesan 1 m pipa 50 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.008
82,500
L.04
Manday
0.0008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Test water (clean water) / Air test (air bersih)
fuel/Bahan bakar
Oil / Oli

M3
Liter
Liter

660
97
757

0.002
0.060
0.002

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

757
113.52
870.32

A. 8.4.5.2 Testing 1 m pipe 75 mm/Pengetesan 1 m pipa 75 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.008
82,500
L.04
Manday
0.0008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Test water (clean water) / Air test (air bersih)
fuel/Bahan bakar
Oil / Oli

M3
Liter
Liter

660
97
757

0.004
0.060
0.002

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

757
113.52
870.32

A. 8.4.5.3 Testing 1 m pipe 100 mm/Pengetesan 1 m pipa 100 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

Code
Kode

Unit
Satuan

L.01
L.04

Manday
Manday

Coefficient
Koefisien

0.008
0.0008

Unit Price
Harga Satuan
(Rp.)
82,500
121,000

Total Price
Total Harga
(RP.)
660
97

MANPOWER TOTAL / JUMLAH TENAGA KERJA


B

MATERIALS/BAHAN
Test water (clean water) / Air test (air bersih)
fuel/Bahan bakar
Oil / Oli

M3
Liter
Liter

757

0.008
0.060
0.002

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

757
113.52
870.32

A. 8.4.5.4 Testing 1 m pipe 150 mm/Pengetesan 1 m pipa 150 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.008
82,500
L.04
Manday
0.0008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Test water (clean water) / Air test (air bersih)
fuel/Bahan bakar
Oil / Oli

M3
Liter
Liter

660
97
757

0.018
0.060
0.002

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

757
113.52
870.32

A. 8.4.5.5 Testing 1 m pipe 200 mm/Pengetesan 1 m pipa 200 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.008
82,500
L.04
Manday
0.0008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Test water (clean water) / Air test (air bersih)
fuel/Bahan bakar
Oil / Oli

M3
Liter
Liter

660
97
757

0.031
0.060
0.002

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

757
113.52
870.32

A. 8.4.5.6 Testing 1 m pipe 250 mm/Pengetesan 1 m pipa 250 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.008
82,500
L.04
Manday
0.0008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Test water (clean water) / Air test (air bersih)
fuel/Bahan bakar
Oil / Oli

M3
Liter
Liter

660
97
757

0.049
0.060
0.002

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

757
113.52
870.32

A. 8.4.5.7 Testing 1 m pipe 300 mm/Pengetesan 1 m pipa 300 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor
MATERIALS/BAHAN
Test water (clean water) / Air test (air bersih)
fuel/Bahan bakar
Oil / Oli

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.008
82,500
L.04
Manday
0.0008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA
M3
Liter
Liter

0.071
0.060
0.002

Total Price
Total Harga
(RP.)
660
97
757
-

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

757
113.52
870.32

A. 8.4.5.8 Testing 1 m pipe 400 mm/Pengetesan 1 m pipa 400 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.008
82,500
L.04
Manday
0.0008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Test water (clean water) / Air test (air bersih)
fuel/Bahan bakar
Oil / Oli

M3
Liter
Liter

660
97
757

0.126
0.060
0.002

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

757
113.52
870.32

A. 8.4.5.9 Testing 1 m pipe 500 mm/Pengetesan 1 m pipa 500 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

L.01
Manday
0.008
82,500
L.04
Manday
0.0008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Test water (clean water) / Air test (air bersih)
fuel/Bahan bakar
Oil / Oli

M3
Liter
Liter

660
97
757

0.158
0.060
0.002

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

757
113.52
870.32

A. 8.4.5.10 Testing 1 m pipe 600 mm/Pengetesan 1 m pipa 600 mm

Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
Labour/Pekerja
Foreman/Mandor

Code
Kode

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

L.01
Manday
0.008
82,500
L.04
Manday
0.0008
121,000
MANPOWER TOTAL / JUMLAH TENAGA KERJA

MATERIALS/BAHAN
Test water (clean water) / Air test (air bersih)
fuel/Bahan bakar
Oil / Oli

M3
Liter
Liter

0.283
0.060
0.002

MATERIAL PRICE TOTAL / JUMLAH HARGA BAHAN


C

EQUIPMENT/PERALATAN

D
E
F

Total/Jumlah (A+B+C)
Overhead & Profit (Contoh 15%)
Unit Price Work/Harga Satuan Pekerjaan (D+E)

PRICE TOOLS TOTAL / JUMLAH HARGA ALAT


15% x D

699

Total Price
Total Harga
(RP.)
660
97
757
-

757
113.52
870.32

DAFTAR HARGA SATUAN UPAH, BAHAN BANGUNAN DAN PERALATAN


TAHUN 2014 SEMESTER I

NO

URAIAN

A
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

UPAH
Kepala Tukang
Tukang
Mandor
Pekerja Tidak Terlatih
Pekerja Terlatih
Masinis
Operator
Sopir
Pembantu Masinis / Operator
Supervisor
Pemasak Aspal
Penjaga
Pembantu Sopir
Mekanik
Surveyor

A
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27

BAHAN / MATERIAL
Agregat Halus
Agregat Kasar
Aluminium Foil
Acubond
Amplas Biasa
Amplas Niken
Atap Aluminium Zink Coated (seng) tebal 0,25 mm
Atap Aluminium Zink Coated (seng) tebal 0,3 mm
Atap Aluminium Zink Coated (seng) tebal 0,4 mm
Atap Aluminium Zincalume, tebal 0,25 mm
Atap Aluminium Zincalume, tebal 0,3 mm
Atap Aluminium Zincalume, tebal 0,4 mm
Atap Aluminium Gelombang tebal 0,5 mm
Atap Fiber warna "Polycarbonat" tbl. 4-5 mm
Atap Genteng Beton Lokal
Atap Genteng Beton
Atap Genteng Beton Cisangkan
Atap Genteng Buleleng
Atap Genteng Keramik biasa berglazur
Atap Genteng Keramik Berglazur Natural
Atap Genteng Keramik sejenis Berglazur warna
Atap Genteng Metal Biasa (88 cm x 77 cm)
Atap Genteng Metal Warna (120 cm x 76 cm)
Atap Genteng Metal Zincalume 2x4 (38,5 cm x 80 cm)
Atap Genteng Metal Zincalume berpasir (77 cm x 100 cm)
Atap Genteng Metal Zincalume berpasir biasa
Atap Genteng Kodok

SATUAN

HARGA SATUAN
(RUPIAH)

Oh
Oh
Oh
Oh
Oh
Oh
Oh
Oh
Oh
Oh
Oh
Oh
Oh
Oh
Oh

121,000.00
99,000.00
121,000.00
71,500.00
82,500.00
82,500.00
165,000.00
110,000.00
82,500.00
82,500.00
49,500.00
44,000.00
82,500.00
148,500.00
82,500.00

m3
m3
m2
m2
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
m2
buah
buah
buah
buah
buah
buah
buah
m2
m2
m2
m2
m2
buah

518,850.62
518,850.62
20,350.00
715,000.00
3,850.00
7,150.00
47,300.00
66,000.00
91,300.00
68,200.00
68,750.00
83,600.00
110,000.00
88,000.00
4,620.00
6,270.00
8,250.00
2,530.00
8,800.00
13,200.00
18,700.00
40,700.00
44,000.00
176,000.00
93,500.00
66,000.00
1,100.00

28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78

Atap Onduline
Asbes polos 100 x 100 tbl = 4 mm
Asbes Gelombang Kecil, lebar 80 cm
Asbes Gelombang Kecil, lebar 105 cm
Asbes Gelombang Besar, lebar 105 cm
Asbes Gelombang motif genteng
Aspal Curah
Aspal Drum
Aquaproof
Bak Cuci Stainless Steel
Bak Cuci Teraso
Bak Fibreglass
Bak Teraso
Bambu dia. 6-8 cm/6m
Batako
Batu Andesit hitam kecoklatan
Batu alam kecoklatan (Sangarong)
Batu Bata lobang
Batu Bata Kecil
Batu Bata lobang
Batu Candi hitam
Batu Kali
Batu Kali tempel
Batu Karang Pilang
Batu Kerikil
Batu Koral beton pecah split 0-5 mm
Batu Koral beton pecah split 5-10 dan 10-20 mm
Batu Belah/Kerakal
Batu Palimanan kuning/hijau
Batu Palimanan kuning/hijau + bevel
Batu Marmer
Batu Roster / Terawang biasa
Besi dia. 5 mm
Besi dia. 6 mm KS
Besi dia. 8 mm KS TI
Besi dia. 10 mm KS TI
Besi dia. 12 mm KS TI
Besi dia. 14 mm KS TI
Besi dia. 16 mm KS TI
Besi dia. 19 mm KS TI
Besi Beton Polos
Besi Baja Profil WF, I dan H
Besi Baja Konstruksi (CNP, INP, dan besi L)
Besi Beam Clamp dan Plat Siku
Besi Hollow baja 20 x 40, tb. 2 mm
Besi Hollow baja 40 x 40, tb. 2 mm
Besi Hollow baja 30 x 60, tb. 2 mm
Besi Hollow Plafond 2 x 4
Besi Strip
Besi Strip 2 x 3
Beton Ready Mix K - 125

m2
Lbr
m2
m2
m2
m2
kg
kg
kg
buah
buah
buah
buah
Btg
buah
m2
m2
m2
buah
buah
m2
m2
m2
m2
m2
m2
m3
m3
m2
m2
m2
buah
Batang
Batang
Batang
Batang
Batang
Batang
Batang
Batang
kg
kg
kg
m2
Batang
Batang
Batang
Batang
kg
M
m3

74,800.00
26,400.00
27,500.00
35,200.00
38,500.00
36,850.00
13,200.00
13,200.00
286,000.00
212,300.00
357,500.00
198,000.00
198,000.00
55,000.00
2,860.00
209,000.00
203,500.00
563,200.00
1,375.00
797.50
247,500.00
385,000.00
102,300.00
653,400.00
440,000.00
518,850.62
518,850.62
385,000.00
184,800.00
184,800.00
330,000.00
4,675.00
24,200.00
27,500.00
56,100.00
88,000.00
121,000.00
203,500.00
214,500.00
302,500.00
20,900.00
18,700.00
16,500.00
24,750.00
154,000.00
176,000.00
209,000.00
27,500.00
11,000.00
5,500.00
880,000.00

79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130

Beton Ready Mix K - 175


Beton Ready Mix K - 225
Beton Ready Mix K - 250
Beton Ready Mix K - 275
Beton Ready Mix K - 300
Beton Ready Mix K - 350
Beton Ready Mix K - 400
Bubungan Asbes Gelombang Besar
Bubungan Asbes Gelombang Kecil
Bubungan / Nok Genteng Beton
Bubungan Genteng Buleleng
Bubungan / Nok Genteng Keramik biasa berglazur
Bubungan / Nok Genteng Keramik sejenis berglazur
Bubungan gtg Keramik sejenis warna berglazur
Bubungan / Nok Genteng Metal / aluminium
Bubungan Genteng Kodok
Cat Dasar
Cat Antara
Cat Kayu dan Besi Anti Rayap
Cat Khusus Glossy dan Quick Drying
Cat Minyak warna (biasa) mutu C
Cat Minyak mutu B
Cat Minyak Semprot
Cat Meni Besi
Cat Meni Besi / kayu / Flincote
Cat Penutup
Cat Tembok mutu C (Vinotex, Q-Luc, dan sejenis)
Cat Tembok mutu B (Catylax, vinilex, dan sejenis)
Cat Tembok mutu B, And Lumut dan Jamur
Cat Tembok mutu A (Mowilex, Kemtone, Dulux, dll)
Closed Duduk Setara (sejenis standar KIA)
Closed Duduk Standar (sejenis Ex. TOTOC721FV1)
Closed Duduk Halmar
Closed Duduk mutu C
Closed Duduk mutu A
Closed Duduk mutu B
Closed Duduk standar
Closed Duduk / Monoblok
Closed Jongkok Porselen / biasa
Closed Jongkok Teraso
Closed Jongkok Standart / sejenis (mutu B)
Closed Jongkok sejenis (mutu A)
Shower Spray TX 403 SV 3
Coneblock biasa tebal 6 cm
Coneblock warna tebal 6 cm
Coneblock biasa tebal 8 cm
Coneblock warna tebal 8 cm
Cornice (bubuk Semen putih utk gypsum)
Dempul Jadi
Dempul Ross Polac
Dempul Isamu
Dolken Kayu dia. 8 - 10/400 cm

m3
m3
m3
m3
m3
m3
m2
m2
m2
Buah
Buah
Buah
Buah
Buah
M
Buah
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
kg
unit
unit
unit
unit
unit
unit
unit
bh
buah
buah
unit
unit
buah
buah
buah
buah
buah
kg
kg
kg
kg
m3

935,000.00
990,000.00
1,045,000.00
1,100,000.00
1,155,000.00
1,100,000.00
1,265,000.00
26,400.00
25,850.00
6,600.00
5,720.00
11,000.00
22,000.00
27,500.00
33,000.00
4,400.00
35,200.00
27,500.00
49,500.00
33,000.00
44,000.00
52,800.00
46,200.00
40,700.00
46,200.00
90,200.00
13,750.00
28,600.00
30,250.00
104,500.00
605,000.00
2,475,000.00
3,520,000.00
2,062,500.00
4,840,000.00
2,992,000.00
2,530,000.00
594,000.00
176,000.00
35,200.00
198,000.00
297,000.00
357,500.00
1,980.00
2,640.00
2,695.00
3,300.00
7,700.00
22,000.00
30,800.00
52,800.00
319,000.00

131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181

Door Closer
Door Holder
Door Stoper
Door Stop
Ember Hitam
Engsel Biasa
Engsel Kuningan 4"
Engsel Pintu
Epoxi
Eternit 100 x 100 tebal 2,7 mm
Eternit 100 x 100 tebal 3,5 mm
Filler
Fitting plafond listrik
Glass Block
Grendel/Slot Tanam 4"
Grendel biasa
Gypsum Board (120x240x9) mm
Hordeng Horizontal Blind (aluminium)
Hordeng Vertikal Blind
Ijuk
Jendela Aluminium + Kaca Reyband 5 mm
Jendela Besi
Jendela Bingkai Nako 100 cm x 70 cm
Jendela Bingkai Nako
Kabel NYA 1,5 mm
Kabel NYA 2,5 mm
Kabel NYA 4,0 mm
Kabel NYM 2 X 1,5 mm
Kabel NYM 2 X 2,5 mm
Kabel NYM 2 X 4,0 mm
Kaca Cermin 3 mm
Kaca Cermin 5 mm
Kaca Patri
Kaca Bening 3 mm
Kaca Bening 4 mm
Kaca Bening 5 mm
Kaca Bening 8 mm
Kaca Bening 10 mm
Kaca Buram 12 mm
Kaca Rayband 5 mm
Kaca Buram/Es 5 mm
Bingkai Kaca Naco
Kaca Naco 6 daun
Kaca Naco 8 daun
Kaca Naco Rayben 5 mm, 6 daun
Kaca Naco Rayben 5 mm, 8 daun
Kait Angin Jendela
Kalsiboard 3,5 mm (120 cm X 240 cm)
Kalsiboard 4,5 mm (120 cm X 240 cm)
Kapur
Karpet Tebal 6 mm

buah
buah
buah
buah
buah
buah
buah
buah
Kg
Lbr
Lbr
m3
buah
Buah
Buah
Buah
Lbr
m2
m3
Kg
m2
m2
Unit
m2
m'
m'
m'
m'
m'
m1
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
set
set
set
set
set
buah
kpg
kpg
kg
m2

264,000.00
33,000.00
33,000.00
24,200.00
7,150.00
19,800.00
13,000.00
19,800.00
55,000.00
25,300.00
29,700.00
1,375.00
9,900.00
26,400.00
82,500.00
17,600.00
74,800.00
101,200.00
104,500.00
9,900.00
902,000.00
330,000.00
99,000.00
148,500.00
4,290.00
5,720.00
6,600.00
11,000.00
14,300.00
19,800.00
136,400.00
212,300.00
1,760,000.00
71,500.00
82,500.00
121,000.00
220,000.00
260,700.00
429,000.00
110,000.00
118,800.00
15,400.00
59,400.00
68,200.00
59,400.00
67,100.00
16,500.00
60,500.00
63,800.00
6,600.00
82,500.00

182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224

Kawat beton
Kawat burung
Kawat duri
Kawat Harmonika
Kawat Jaring pagar
Kawat Kassa
Kawat Las
Kawat Nyamuk
Kawat Seng polos
Kayu Gelam dia. 6-8
Kayu Gelam dia. 10-12
Kayu Hek
Kayu Lis 1/3
Kayu Lis 1/4
Kayu Lis profil kecil
Kayu Lis profil sedang
Kayu Lis profil besar
Kayu Mosaik 30 X 30 cm
Kayu Kaso 5/7 Kelas III (Meranti dan sejenis)
Kayu Kelas I (Unglen, Jati)
Kayu Kelas II (Petanang dan sejenis)
Kayu Kelas III (Meranti dan sejenis)
Kayu Papan 3/20 Kelas III
Kayu Kelas IV (Racuk dan sejenis)
Kayu Papan Kelas IV
Kayu Racuk
Kayu Reng
Keramik Lantai/Dinding 20 X 2/25 cm putih polos
Keramik Lantai/Dinding 20 X 2/25 cm putih polos
Keramik Lantai 20 X 20 cm warna, mutu C
Keramik Lantai 20 X 20 cm warna, mutu C
Keramik Lantai 20 X 20 cm warna, mutu B
Keramik Lantai 20 X 20 cm warna, mutu B
Keramik Lantai 20 X 25 cm warna
Keramik Lantai 20 X 25 cm warna
Keramik Lantai 20 X 25 cm warna, mutu B
Keramik Lantai 20 X 25 cm warna, mutu B
Keramik Lantai 30 X 30 cm warna
Keramik Lantai 30 X 30 cm warna
Keramik Lantai 30 X 30 cm putih polos
Keramik Lantai 30 X 30 cm putih polos
Keramik Lantai 40 X 40 cm warna, mutu C
Keramik Lantai 40 X 40 cm warna, mutu C
Keramik Lantai 40 X 40 cm warna, mutu B
Keramik Lantai 40 X 40 cm warna, mutu B
Keramik Lantai Motif Kayu (Kasar) Mutu A
Klem Talang Peralon
Klem Kabel Listrik Biasa
Klem Kabel Listrik
Korosin
Kran Air
Kuas 3"-4"

kg
m2
m'
m2
lbr
m2
Dos
m2
kg
btg
btg
btg
m'
m'
m'
m'
m'
buah
btg
m3
m3
m3
m3
m3
keping
m3
btg
kotak
buah
kotak
buah
kotak
buah
kotak
buah
kotak
buah
kotak
buah
kotak
buah
kotak
buah
kotak
buah
kotak
buah
buah
buah
Ltr
buah
buah

19,800.00
22,000.00
16,500.00
42,900.00
30,800.00
16,500.00
11,000.00
19,800.00
20,900.00
8,800.00
9,900.00
9,900.00
11,550.00
12,650.00
2,750.00
3,850.00
8,250.00
6,875.00
60,500.00
9,075,000.00
6,600,000.00
3,630,000.00
3,630,000.00
1,650,000.00
18,150.00
1,815,000.00
33,000.00
63,800.00
2,552.00
57,200.00
2,288.00
68,200.00
2,728.00
74,800.00
3,740.00
51,260.00
2,563.00
52,800.00
4,752.00
52,800.00
4,752.00
57,200.00
9,152.00
71,500.00
11,440.00
55,000.00
3,025.00
154.00
3,300.00
2,200.00
11,000.00
13,750.00

225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277

Kunci Gembok
Kunci Lemari
Kunci Pintu Kamar Tidur (Hotel)
Kunci Pintu KM/WX (Lux)
Kunci Selot
Kunci Tanam biasa mutu C
Kunci Tanam 2 Slaag biasa
Kunci Tanam 2 Slaag biasa mutu B
Kunci Tanam Kamar Mandi
L. Bow Listrik
Lampu Down Light
Lampu Hologen 50 Watt
Lampu Hologen 150 Watt
Lampu Hologen Box
Lampu TL 10 watt
Lampu TL 20 watt
Lampu TL 40 watt (bambu)
Lampu Pijar 25 watt putih
Lampu Pijar 40 watt putih
Lantai Granit 30/30
Lantai Granit 40/40
Lantai Granit 60/60
Lantai Kayu Panil Greacewood
Las dop listrik
Lem Kayu
Lem vinyl
List Gypsum besar
List Gypsum Kecil
Mangkok Saklar Listrik
MCB
MCB Box isi 4 group
MCB Box isi 8 group
Melamic Clear
Melamic gloss/dop (finishing)]
Mill
Minyak Bekisting
Minyak Cat
Minyak solar untuk industri/minyak aspal
Mozaik Kayu Lantai Uk. 30/30 cm
Pagar BRC, uk. 240 cm X 129 cm dia. 5,5 mm
Pagar BRC, uk. 240 cm X 90 cm dia. 6 mm
Paku biasa bermacam ukuran 2" - 5"
Paku biasa 1/2 - 1"
Paku Sumbat
Paku Beton
Paku Gypsum
Paku Seng Asbes
Paku Asbes
Paku Sekrup 3,5"
Paku Sekrup 3,5"
Parquet Jati
Pasir Beton/Pasang
Pasir Urug

buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
m2
buah
ltr
kg
m'
m'
buah
buah
buah
buah
kg
kg
kg
liter
liter
liter
buah
unit
unit
kg
kg
buah
buah
kg
kg
buah
kg
buah
m3
m3
m3

9,350.00
8,800.00
440,000.00
385,000.00
14,300.00
27,500.00
71,500.00
99,000.00
29,700.00
2,750.00
46,750.00
13,750.00
27,500.00
110,000.00
7,700.00
11,000.00
115,500.00
5,000.00
6,050.00
22,550.00
48,400.00
128,700.00
387,750.00
550.00
22,000.00
9,350.00
24,200.00
13,200.00
1,980.00
48,400.00
27,500.00
60,500.00
66,000.00
66,000.00
36,300.00
13,200.00
6,600.00
6,050.00
8,250.00
379,500.00
412,500.00
16,500.00
19,800.00
660.00
770.00
27,500.00
24,200.00
660.00
49,500.00
495.00
423,500.00
101,750.00
71,500.00

278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330

Pewarna Nat
Pintu Almunium
Pintu Besi Baja
Pintu Lipat
Pintu PVC Lengkap + Pemasangan
Pipa Besi Medium 2 mm & 1/2", pjg 6 mm
Pipa Besi Medium 2 mm & 3/4", pjg 6 mm
Pipa Besi Medium 2 mm & 1", pjg 6 mm
Pipa Besi Medium 2 mm & 1,5", pjg 6 mm
Pipa Besi Medium 2 mm & 2", pjg 6 mm
Pipa Besi Medium 2 mm & 2,5", pjg 6 mm
Pipa Besi Medium 2 mm & 3", pjg 6 mm
Pipa Besi Medium 2 mm & 4", pjg 6 mm
Pipa Paralon Listrik 5/8"
Pipa PVC & 1,2 mutu A (Mavin dan Sejenis)
Pipa PVC Biasa & 1/2" mutu B
Pipa PVC & 3/4" mutu A (Mavin dan Sejenis)
Pipa PVC & 3/4" mutu B
Pipa PVC & 1" mutu A (Mavin dan Sejenis)
Pipa PVC & 1" mutu B
Pipa PVC & 1,5" mutu A (Mavin dan Sejenis)
Pipa PVC & 1,5" mutu B
Pipa PVC & 2" mutu A (Mavin dan Sejenis)
Pipa PVC & 2" mutu B
Pipa PVC & 3" mutu A (Mavin dan Sejenis)
Pipa PVC & 3" mutu B
Pipa PVC & 4" mutu A (Mavin dan Sejenis)
Pipa PVC & 4" mutu B
Pipa PVC & 6" (15cm) mutu A (Mavin dan sejenis)
Pipa Stainless 2", tebal 1 mm
Pipa Stainless 2", tebal 0,8 mm
Pipa Stainless 2,5", tebal 1 mm
Pipa Stainless 2,5", tebal 1,2 mm
Plamir Tembok
Plamir Kyau
Plat Stainless, tebal 1 mm, uk. 244 cm X 122 cm
Plint Keramik 10 X 30 cm Warna
Plint Keramik 10 X 40 cm warna
Plint Ubin PC Abu-abu 15 x 20 cm
Plint Ubin PC Abu-abu 10 x 30 cm
Plint Ubin PC Abu-abu 10 x 40 cm
Plywoood warna / Jabar Wood
Plywood Jati 3 mm
Plywood Sunkay 3 mm/megatic
Plywood 3 mm
Plywood 4 mm
Plywood 6 mm
Plywood 9 mm
Plywood 12 mm
Plyawood 20 mm
Politur Dasar
Politur Jadi
Porselin Putih Uk. 10 x 10 cm

Bks
m2
m2
m2
unit
m'
m'
m'
m'
m'
m'
m'
m'
Btg
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
m'
kg
kg
Lbr
buah
buah
buah
buah
buah
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
ltr
ltr
buah

11,000.00
704,000.00
2,145,000.00
418,000.00
231,000.00
20,350.00
25,740.00
32,092.00
45,870.00
57,750.00
75,350.00
119,350.00
155,540.00
6,600.00
4,400.00
4,125.00
6,050.00
5,060.00
8,250.00
5,225.00
14,300.00
8,800.00
18,012.00
11,550.00
5,337.00
19,250.00
57,200.00
33,000.00
136,125.00
82,500.00
73,920.00
104,720.00
92,400.00
8,800.00
18,700.00
1,870,000.00
4,400.00
14,520.00
880.00
935.00
962.00
121,000.00
121,000.00
121,000.00
46,200.00
74,800.00
96,800.00
137,500.00
176,000.00
231,000.00
53,900.00
58,300.00
770.00

331 Porselin Warna 10 x 10 cm


332 Rangka Atap baja ringan untuk atap genteng, genteng keramik
beton, dll + pemasangan
333 Rangka atap baja ringan untuk atap seng metal, atap asbes,
almunium, sirap dll
334 Rangka atap baja ringan bentuk joglo/ bertumpuk/ khusus
+pemasangan
335 Rangka atap baja ringan "Pyrda" untuk atap pelana, metal
dan keramik + pemasangan
336 Rangka atap baja ringan "Pyrda" untuk atap perisai, metal
dan keramik + pemasangan
337 Rangka atap baja ringan "Pyrda" untuk atap joglo, metal
dan keramik + pemasangan
338 Rel pintu dorong
339 Rolling door standar, t=4 mm, (minimal pas. 7 M2)
340 Rolling door standar, t=5 mm, (minimal pas. 7 M2)
341 Sanding Sealer Impra (Cat Dasar)
342 Seal Tape
343 Semen (50 kg)
344 Semen Portland (PC)
345 Semen Putih (40 kg)
346 Semen Putih
347 Semen Merah
348 Semen Nat
349 Seng Gelombang, lebar 70 cm
350 Seng Plat 120cm X 240cm
351 Seng plat 33 cm
352 Seng plat 38 cm
353 Seng plat 45 cm
354 Seng plat 55 cm
355 Seng plat 88 cm
356 Seng plat 92 cm
357 Sabun
358 Soda Api
359 Soft board (120 x240 ) mm
360 Saklar Tunggal biasa
361 Saklar Ganda biasa
362 Saklar Tunggal National
363 Saklar Ganda National
364 Scafolding tg 1,77 m x 1,77 m
366 Smartruss Alumunium Magnesium
- Lysaght Samartruss C 75.000
- Lysaght Samartruss C 75.75
- Reng U T S 40
- Screw / Dynabolt
- Valery Gutter Talang Jurai
- Strap Bracing
367 Stop Kontak Biasa
368 Stop Konta AC
369 Sunscreen Alumunium
370 T. Duss Listrik
371 Talang Paralon, pjg 4 m

buah
m2
m2
m2
m2
m2
m2
unit
m2
m2
kg
buah
Zak
kg
Zak
kg
m3
kg
m2
lbr
m'
m'
m'
m'
m'
m'
kg
kg
lbr
buah
buah
buah
buah
unit
m'
m'
m'
buah
M'
M'
buah
buah
m2
buah
btg

1,100.00
313,500.00
237,820.00
309,870.00
281,050.00
309,870.00
360,360.00
264,000.00
643,500.00
693,000.00
41,800.00
3,850.00
68,750.00
1,375.00
93,500.00
2,200.00
41,800.00
13,200.00
8,167.00
116,600.00
14,520.00
20,350.00
22,000.00
28,600.00
36,300.00
38,500.00
12,320.00
33,000.00
74,250.00
6,600.00
14,850.00
19,140.00
33,000.00
880,000.00
24,750.00
20,680.00
17,930.00
2,090.00
137,940.00
13,750.00
18,700.00
82,500.00
412,500.00
1,320.00
52,800.00

372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391
392

Tali Ijuk
Ijuk
Tanah Liat/ Urug
Tanah Puru
Tanah Sirtu
Taekwood 3 mm
Taekwood 4 mm biasa
Ter / Residu
Texil Tape
Thinner Biasa
Thinner Cat Glossy (Cobra dan Sejenis)
Urinoir
Urinoir mutu A
Vernis
Vernis Batu
Wellpaper
Wastafel biasa
Wastafel Halmar
Wastafel Mutu A
Wood Filler Impra (dempul)
Woos Stain Impra (cat warna)

C.
1
2
3
4
5
6
7
8
9
10

PERALATAN
Concrete Pump
Dump Truck 10 Ton
Dump Truck 35 Ton
Genset
Flatbed truck 3,5 ton/ mesin gilas roda
Alat bantu
Sprayer, selfprof
Scaffolding 117 cm X 177 cm, Tg. 177 cm
Pengaduk beton/Mollen
Water Pump

D.

INSTALASI
Instalasi Listrik
Catatan : Harga satuan diatas belum termasuk PPn 10 %

kg
m3
m3
m3
m3
m2
m2
liter
roll
liter
liter
buah
unit
ltr
kg
m2
buah
unit
unit
klg
klg

12,540.00
26,400.00
55,000.00
60,500.00
88,000.00
39,600.00
44,000.00
49,500.00
7,535.00
13,200.00
38,500.00
154,000.00
181,500.00
17,500.00
71,500.00
308,000.00
291,500.00
308,000.00
495,000.00
35,200.00
66,000.00

jam
jam
jam
jam
jam
jam
jam
Set/bulan
jam
jam

409,884.92
343,200.00
385,000.00

LS

93,500.00

154,000.00
52,250.00
110,000.00
275,000.00

DAN PERALATAN

HARGA
SWAKELOLA (Rp)

HARGA
DASAR (Rp)

110,000.00
90,000.00
110,000.00
65,000.00
75,000.00
75,000.00
150,000.00
100,000.00
75,000.00
75,000.00
45,000.00
40,000.00
75,000.00
135,000.00
75,000.00

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

471,682.38
471,682.38
18,500.00
650,000.00
3,500.00
6,500.00
43,000.00
60,000.00
83,000.00
62,000.00
62,500.00
76,000.00
100,000.00
80,000.00
4,200.00
5,700.00
7,500.00
2,300.00
8,000.00
12,000.00
17,000.00
37,000.00
40,000.00
160,000.00
85,000.00
60,000.00
1,000.00

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

68,000.00
24,000.00
25,000.00
32,000.00
35,000.00
33,500.00
12,000.00
12,000.00
260,000.00
193,000.00
325,000.00
180,000.00
180,000.00
50,000.00
2,600.00
190,000.00
185,000.00
512,000.00
1,250.00
725.00
225,000.00
350,000.00
93,000.00
594,000.00
400,000.00
471,682.38
47,168,238.00
350,000.00
168,000.00
168,000.00
300,000.00
4,250.00
22,000.00
25,000.00
51,000.00
80,000.00
110,000.00
185,000.00
195,000.00
275,000.00
19,000.00
17,000.00
15,000.00
22,500.00
140,000.00
160,000.00
190,000.00
25,000.00
10,000.00
5,000.00
800,000.00

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

850,000.00
900,000.00
950,000.00
1,000,000.00
1,050,000.00
1,000,000.00
1,150,000.00
24,000.00
23,500.00
6,000.00
5,200.00
10,000.00
20,000.00
25,000.00
30,000.00
4,000.00
32,000.00
25,000.00
45,000.00
30,000.00
40,000.00
48,000.00
42,000.00
37,000.00
42,000.00
82,000.00
12,500.00
26,000.00
27,500.00
95,000.00
550,000.00
2,250,000.00
3,200,000.00
1,875,000.00
4,400,000.00
2,720,000.00
2,300,000.00
540,000.00
160,000.00
32,000.00
180,000.00
270,000.00
325,000.00
1,800.00
2,400.00
2,450.00
3,000.00
7,000.00
20,000.00
28,000.00
48,000.00
290,000.00

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

240,000.00
30,000.00
30,000.00
22,000.00
6,500.00
18,000.00
3,000.00
18,000.00
50,000.00
23,000.00
27,000.00
1,250.00
9,000.00
24,000.00
75,000.00
16,000.00
68,000.00
92,000.00
95,000.00
9,000.00
820,000.00
300,000.00
90,000.00
135,000.00
3,900.00
5,200.00
6,000.00
10,000.00
13,000.00
18,000.00
124,000.00
193,000.00
1,600,000.00
65,000.00
75,000.00
110,000.00
200,000.00
237,000.00
390,000.00
100,000.00
108,000.00
14,000.00
54,000.00
62,000.00
54,000.00
61,000.00
15,000.00
55,000.00
58,000.00
6,000.00
75,000.00

###
###
###
###
###
###
30,000.00
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
6,500.00
###

18,000.00
20,000.00
15,000.00
39,000.00
28,000.00
15,000.00
100,000.00
18,000.00
19,000.00
8,000.00
9,000.00
9,000.00
10,500.00
11,500.00
2,500.00
3,500.00
7,500.00
6,250.00
55,000.00
8,250,000.00
6,000,000.00
3,300,000.00
3,300,000.00
1,500,000.00
16,500.00
1,650,000.00
30,000.00
58,000.00
2,320.00
52,000.00
2,080.00
62,000.00
2,480.00
68,000.00
3,400.00
46,600.00
2,330.00
48,000.00
4,320.43
48,000.00
4,320.43
52,000.00
8,320.00
65,000.00
10,400.00
50,000.00
2,750.00
140.00
3,000.00
2,000.00
10,000.00
12,500.00

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
8,320.00
###
###
###
###
###
###
###
###
###

8,500.00
8,000.00
400,000.00
350,000.00
13,000.00
25,000.00
65,000.00
90,000.00
27,000.00
2,500.00
42,500.00
2,500.00
25,000.00
100,000.00
7,000.00
10,000.00
105,000.00
5,000.00
5,500.00
20,500.00
44,000.00
117,000.00
352,500.00
500.00
20,000.00
8,500.00
22,000.00
12,000.00
1,800.00
44,000.00
25,000.00
55,000.00
60,000.00
60,000.00
33,000.00
12,000.00
6,000.00
5,500.00
7,500.00
345,000.00
375,000.00
15,000.00
18,000.00
600.00
700.00
25,000.00
22,000.00
600.00
45,000.00
450.00
385,000.00
92,500.00
55,000.00

###
###
###
###
###
###
###
###
###
###
###
12,500.00
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
65,000.00

10,000.00
640,000.00
1,950,000.00
380,000.00
210,000.00
18,500.00
23,400.00
29,175.00
41,700.00
52,500.00
68,500.00
108,500.00
141,400.00
6,000.00
4,000.00
9,750.00
5,500.00
4,600.00
7,500.00
4,750.00
13,000.00
8,000.00
16,375.00
10,500.00
32,125.00
17,500.00
52,000.00
30,000.00
123,750.00
75,000.00
67,200.00
95,200.00
84,000.00
8,000.00
17,000.00
1,700,000.00
4,000.00
13,200.00
800.00
850.00
875.00
110,000.00
110,000.00
110,000.00
42,000.00
68,000.00
88,000.00
125,000.00
160,000.00
210,000.00
49,000.00
53,000.00
700.00

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
3,750.00
55,000.00
###
###
###
###
###
###
###
###
###
###
###
###
###
###
95,000.00
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

1,000.00
285,000.00
216,200.00
281,700.00
255,500.00
281,700.00
327,600.00
240,000.00
585,000.00
630,000.00
38,000.00
3,500.00
62,500.00
1,250.00
85,000.00
2,000.00
38,000.00
12,000.00
7,425.00
106,000.00
13,200.00
18,500.00
20,000.00
26,000.00
33,000.00
35,000.00
11,200.00
30,000.00
67,500.00
6,000.00
13,500.00
17,400.00
30,000.00
800,000.00
22,500.00
18,800.00
16,300.00
1,900.00
125,400.00
12,500.00
17,000.00
75,000.00
375,000.00
1,200.00
48,000.00

###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

11,400.00
24,000.00
50,000.00
55,000.00
80,000.00
36,000.00
40,000.00
45,000.00
6,850.00
12,000.00
35,000.00
140,000.00
165,000.00
25,000.00
65,000.00
280,000.00
265,000.00
280,000.00
450,000.00
32,000.00
60,000.00

###
###
###
###
###
###
###
450,000.00
###
###
###
###
###
###
###
###
###
###
###
###
###

372,622.65
312,000.00
350,000.00
250,000.00
225,000.00
75,000.00
140,000.00
47,500.00
100,000.00
250,000.00

###
###
###
250,000.00
###
###
###
###
###
###

85,000.00

###

WALIKOTA PALEMBANG

H. RONI HERTON

UNIT PRICES ANALYS/ANALISA HARGA SATUAN PEKERJAAN


CK-B.1 Digging 1m3 ordinary soil. depth of 1 meter / Menggali 1m3 tanah biasa sedalam 1 meter
Nr./No.
A

B
C

Unit
Satuan

Description/Uraian
MANPOWER/TENAGA
- Labour/Pekerja
- Foreman/Mandor
MATERIALS/BAHAN
EQUIPMENT/PERALATAN

Manday
Manday

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

0.750
0.025
0
0

0
0

Total price per unit of work/Jumlah harga per satuan pekerjaan

CK-B.2 Installing 1m3 foundation stone sides, mix 1PC : 3 PP / Memasang 1m 3 pondasi batu belah, campuran 1PC : 3 PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
- Labour/Pekerja
- Mason/Tukang Batu
- Chief of Skill Labour/kepala tukang
- Foreman/Mandor
MATERIALS/BAHAN
- Rock Split/Batu Belah
- Portland Cement
- Sang Plug/Pasir Pasang

Unit
Satuan

Coefficient
Koefisien

Manday
Manday
Manday
Manday

1.500
0.750
0.075
0.075

1.200
202.000
0.485

m3
kg
m3

EQUIPMENT/PERALATAN

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

Total price per unit of work/Jumlah harga per satuan pekerjaan

CK-B.3 Installing 1m2 acian / Memasang 1m2 acian


Nr./No.
A

B
C

Description/Uraian
MANPOWER/TENAGA
- Labour/Pekerja
- Mason/Tukang Batu
- Chief of Skill Labour/kepala tukang
- Foreman/Mandor
MATERIALS/BAHAN
- Sand Plug/Pasir pasang
EQUIPMENT/PERALATAN

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

Manday
Manday
Manday
Manday

3.250
0.200
0.100
0.010

kg
0

3.250

Total price per unit of work/Jumlah harga per satuan pekerjaan

CK-B.4 Installing 1m2 asbestos cement ceiling, 4mm thick / Memasang 1m 2 langit-langit asbes semen, tebal 4mm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
- Labour/Pekerja
- Labour/Tukang Batu
- Chief of Skill Labour/kepala tukang
- Foreman/Mandor
MATERIALS/BAHAN
- Asbestos Cement/Asbes Semen
- Nail 3cm/Paku 3cm
EQUIPMENT/PERALATAN

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Manday
Manday
Manday
Manday

0.070
0.070
0.007
0.004

m2
kg

1.100
0.010
0

Total price per unit of work/Jumlah harga per satuan pekerjaan

271597928.xls

Total Price
Total Harga
(RP.)

Page 175

Nr./No.

Description/Uraian

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

CK-B.5 Installing 1m2 red brick wall (5x11x22)cm 1 brick thick, spaced 1 PC : 2 PP / Memasang 1m 2 dinding bata merah (5x11x22)
cm tebal 1 bata, spesi 1PC : 2PP
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
- Labour/Pekerja
- Mason/Tukang Batu
- Chief of Skill Labour/kepala tukang
- Foreman/Mandor
MATERIALS/BAHAN
- Red Brick/Bata merah
- Portland Cement
- Sand Plug/Pasir pasang
EQUIPMENT/PERALATAN

Unit
Satuan

Coefficient
Koefisien

Manday
Manday
Manday
Manday

0.600
0.200
0.020
0.030

140.000
43.500
0.080
0

buah
kg
m3

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

Total price per unit of work/Jumlah harga per satuan pekerjaan

CK-B.6 Installing 1m3 concrete f'c = 7.4 MPa (K100) Slump (12 2) cm w / c = 0.87 / Memasang 1m 3 beton f'c = 7,4 Mpa (K100)
slump (12 2)cm w/c = 0,87
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
- Labour/Pekerja
- Mason/Tukang Batu
- Chief of Skill Labour/kepala tukang
- Foreman/Mandor
MATERIALS/BAHAN
- Portland Cement
- Concrete Sand / Pasir Beton
- Gravel / Kerikil
- Water / Air
EQUIPMENT/PERALATAN

Unit
Satuan

Coefficient
Koefisien

Manday
Manday
Manday
Manday

0.600
0.200
0.020
0.030

247.000
869.000
999.000
215.000
0

kg
m3
m3
Liter

Unit Price
Harga Satuan
(Rp.)

Total Price
Total Harga
(RP.)

Total price per unit of work/Jumlah harga per satuan pekerjaan

CK-B.7 Installing tile floor 1m2 gray PC. size (40 x 40) cm / Memasang 1m 2 lantai ubin PC abu-abu ukuran (40 x 40 ) cm
Nr./No.
A

Description/Uraian
MANPOWER/TENAGA
- Labour/Pekerja
- Mason/Tukang Batu
- Chief of Skill Labour/kepala tukang
- Foreman/Mandor
MATERIALS/BAHAN
- Gray Tiles / Ubin abu-abu
- Portland Cement
- Sand Plug / Pasir pasang
EQUIPMENT/PERALATAN

Unit
Satuan

Coefficient
Koefisien

Unit Price
Harga Satuan
(Rp.)

Manday
Manday
Manday
Manday

0.250
0.125
0.013
0.013

buah
kg
m3

6.630
9.800
0.045
0

Total price per unit of work/Jumlah harga per satuan pekerjaan

271597928.xls

Total Price
Total Harga
(RP.)

Page 176

Вам также может понравиться