Академический Документы
Профессиональный Документы
Культура Документы
PROJECT SUMMARY
Project Title
Donor
Project Financing
Agreement
Main Objectives
Executing Agency
An Executive Summary of Project Completion Report - F/A No. IND-0053 and IND-0054
Project
Administration
Project Schedule
Initial schedule
An Executive Summary of Project Completion Report - F/A No. IND-0053 and IND-0054
An Executive Summary of Project Completion Report - F/A No. IND-0053 and IND-0054
On the other hand, the vocational equipment procurement was conducted centrally in
the Ministry of Religious Affairs, under consideration that:
1. The vocational equipment should have been related and shall support the
practice of curriculum content, which have been developed by central government
for these years. The curriculum development aims at strengthening the quality of
curriculum teaching and content of all Madrasah Aliyahs.
2. In implementing the assessment of curriculum development, the academic
consultant should discuss with all related government institutions, covering the
material and regulations. Therefore, the placement of academic consultant
centrally is beneficial. The results of academic consultant works were then
addressed into vocational equipment procurement, covering the types,
specification, quantity as well as estimated price.
Upon the consideration as above, the project management of Madrasah Aliyah
Vocational Training Project was arranged into two components, consisting of CPIU
(Central Project Implementation Unit) and PPIU (Provincial Project Implementation
Unit), which are illustrated in following figure 2.1a, 2.1b and 2.1c.
An Executive Summary of Project Completion Report - F/A No. IND-0053 and IND-0054
Consultant
Project Madrasah
Aliyah Vocational
Training
Bid
Committee
Provincial
Tender
Bid
Committee
Implementation
Implementation
Program held in Jakarta, centrally:
Program of 2-IND-0054: vocational
equipment procurement
Program under government budget:
curriculum development, teacher training,
and other curriculum component
development
Management of Supervision
and Monitoring untuk for
the Implementation of IND
0053 (CPIU)
Bidding Process
Progress Summary
Examination Report
Progress
Disbursement Request
Payment Request
Monitoring and
Project Supervision
Construction
Works
Ministry of
Finance
Jakarta
Contract
Maintenance
Utilization
Figure 2.1b: Relation Between CPIU and PPIU for IND 0053 Program
An Executive Summary of Project Completion Report - F/A No. IND-0053 and IND-0054
Islamic
Development
Bank
Madrasah Aliyah
The Implementation of
IND 0054 Program at Site
Regionally (PPIU)
Academic Consultant
Assignment Process
Results of Academic
Consultant Works
Background and
Existing Conditions
Report
Contract
Report
Ministry of
Finance
Jakarta
Equipment
Procurement
Report
Progress Works
Site Monitoring,
Supervision and
Approval
Maintenance and
Warranty Period
Figure 2.1c: Relation Between CPIU, Madrasah Aliyah and PPIU
For IND 0054 Program
An Executive Summary of Project Completion Report - F/A No. IND-0053 and IND-0054
Pemeliharaan / Masa
Warranty
Utilization
An Executive Summary of Project Completion Report - F/A No. IND-0053 and IND-0054
An Executive Summary of Project Completion Report - F/A No. IND-0053 and IND-0054
Specific for IND 0054 program (equipment procurement), there was not any
significant problem because most of the contract was made in US$ basis.
However, an IDR price component might become a problem in case the value of
IDR to US$ might be increased. Fortunately, until end of project, this case was
not happen.
4) The fourth problem, which cause to project schedule, was the ethnical dispute in
several regions especially in Aceh, Kalimantan and Maluku.
5) The fifth problem was the impact of the application of regional autonomy policies.
Considering the problems described in point 2 and 3 above, it was expected that
the sub project in all regions was led by the same sub project managers, who
had already been familiar with the problems and IDB procedures. Factually,
Regional Offices of MORA in several provinces had changed the sub project
managers who did not understand the on-going problems and were not familiar
with IDB procedures. This also contributed the delay of the project.
An Executive Summary of Project Completion Report - F/A No. IND-0053 and IND-0054
3. ASSESSMENT
3.1. CRITERIA OF MADRASAH ALIYAH RECEIVING THIS
PROJECT
The criteria in selecting the Madrasah Aliyah, were:
Availability of land (space). Madrasah Aliyah following this program should have
sufficient land for the additional building to be used for vocational teaching and
practices
The ability to provide teachers and human resources development
implementation, including training and teachers allowance.
The ability to maintain the building and equipment including furniture.
The acceptance to implement collaboration scheme with other schools and
industries.
Response of communities surrounding Madrasah Aliyah.
The criteria applied to select Madrasah Aliyah was sufficient to achieve this project.
It is recommended that the following additional criteria may give more advantages to
project benefits:
An Executive Summary of Project Completion Report - F/A No. IND-0053 and IND-0054
10
solved it by request of this allocation to IDB (and was approved) and covered
other necessary parties by appointing experts as an individual consultants, and by
included it into other allotment, such as project management advisory, equipment
system within consultancy service for human resources training and teaching
material development.
2) The domestic budget as government participation (dana pendamping). This
allocation was used for government contribution to this project. It had started
from 1997/1998 fiscal year for recruiting teacher and teacher training and
teaching material development, consisting books and vocational guidelines.
Upon the initial project condition, the project breakdown structure (figure 2.1) was
developed in order to anticipate the weaknesses as describe above.
11
documents were not given detailed and completed information, therefore several
disbursement process were perceived incorrectly, such as the transferred
payment was returned by the Indonesian banks due to unclear information, and
few money transfers were less than the disbursement request (Maluku, West
Nusa Tenggara and South Sumatera cases).
By the help of the Ministry of Finance (MOF), actually this matter could be
minimized. However, more than hundreds of contracts were made in this project,
meaning that more than hundreds disbursement request were made to IDB,
therefore CPIU and KPKN Jakarta VI (Ministry of Finance) faced it difficult to
ensure that all information in Certificate of Payment documents had been
completed to be delivered to IDB.
5) Other issues which in accordance with Keppres 16/1994 and 18/2000, but not in
line with IDB procedures, for example:
Indonesia regulation (Keppres 16/1994): 5% of contract for performance bond
IDB procedures: a minimum of 10% of contract for performance bond
Indonesia regulation (Keppres 16/1994): 30% for advanced payment
IDB procedures: 20% maximum for advanced payment
Project document reports for Bappenas and Ministry of Finance (MOF) which
should be made in different format, and project documents reports to IDB
which also in different format with Bappenas and MOF.
This matter had already been covered in the training material to fulfil the
inexperience sub project managers.
An Executive Summary of Project Completion Report - F/A No. IND-0053 and IND-0054
12
Table 3.1: A Brief Description of Project Output The Comparison Between Expected Project Results in Project Proposal and
Project Actual Results at End of Project
No.
1 Eighty two Madrasah Aliyah spread out all 27 provinces will be equipped to
train a total of 4440 students each year in the proposed trades of :
Automotives
Computer Repair
Motorcycle Repairing
Refrigerator/AC Repair
Tailoring
Secretarial Training
Computer Operator
Catering
In each school, 3 trades will be introduced with the exception of those
schools which are too small and in which only 2 or 1 trade can be
introduced.
2 The 82 schools will be provides with additional accommodation of
workshops, classroom and other requirements as well as equipment,
furniture and a supply of materials
An Executive Summary of Project Completion Report - F/A No. IND-0053 and IND-0054
13
Table 3.1: A Brief Description of Project Output The Comparison Between Expected Project Results in Project Proposal and
Project Actual Results at End of Project (Contd)
No.
3 444 teacher on the basis of 2 teachers per trade per school will be recruited
from existing technical and vocational teacher training institutions (IKIP and
equivalent) and be upgraded for teaching vocational subjects.
More than 600 teachers and vocational instructors have been trained
within 4 (four) fiscal years on different aspects of training program on
advisory and management; vocational training related to engineering
aspects, such as radio & TV repair, furniture production and wood
working; preparing, as well as modifying and developing teaching
material method; vocational aspects related to agriculture fields.
Most of them are recruited teachers specially assigned to teach
vocational subjects.
An Executive Summary of Project Completion Report - F/A No. IND-0053 and IND-0054
14
It was the first foreign financing project applying the direct payment
disbursement method conducted by the Ministry of Religious Affairs.
Currently, the Ministry has already experience in other foreign financing
project using other disbursement system such as Special Account and L/C.
Therefore, the experience of this Ministry for implementing any type of foreign
financing project has been completed.
Although this project had faced significant problems, however the project
officers had completed successfully. It is expected that the project officers
should be one of competitive advantages of the Ministrys human resources.
The experience of this project should be used as a sound study cases in the
management courses of training division of the Ministry of Religious Affairs.
2) Project outputs:
The project has achieved all tasks according to the financing agreement
number IND 0053 and 0054.
Under the perspective of civil works, the project has added sufficient numbers
of infrastructures and facilities, such as poultry pens and fishery ponds,
whereas these infrastructures were not, firstly, accommodated in the IND 0053
program.
An Executive Summary of Project Completion Report - F/A No. IND-0053 and IND-0054
15
4) Project impacts:
At present, the evaluation activity to measure the performance of project impact
may not be accurate due to:
The project benefit and impacts will give accurate picture, after the Madrasah
Aliyahs receiving this project have their alumni who benefiting the IND 0054
program. The fastest period to conduct project benefit and impacts analysis
(after study) will be at the end of 2003.
An Executive Summary of Project Completion Report - F/A No. IND-0053 and IND-0054
16