OBRA
PERIODO DE EJECUCION
FECHA
PARTIDA
"Construccion de Local Multiuso CC.PP. Villa Virginia del Distrito de Rio Negro-Satipo-Junin"
: 75 DIAS
: ABRIL DEL 2013
DESCRIPCION
PRESUPU
1 SEM
ESTO
2 SEM
3 SEM
4 SEM
90 DIAS
5 SEM
6 SEM
7 SEM
8 SEM
9 SEM
10 SEM
450.00
01.00.00
OBRAS PROVISIONALES
450.00
224.94
02.00.00
TRABAJOS PRELIMINARES
224.94
628.55
03.00.00
MOVIMIENTO DE TIERRAS
314.28
314.28
3,758.44
04.00.00
1,252.81
1,252.81
1,252.81
5,774.27
5,774.27
5,774.27
5,774.27
5,025.52
5,025.52
5,025.52
23,097.09
05.00.00
06.00.00
07.00.00
COBERTURA LIVIANA
3,715.78
3,715.78
3,647.28
08.00.00
1,823.64
1,823.64
4,359.91
09.00.00
4,359.91
2,652.29
10.00.00
2,652.29
CIELORRASOS
5,376.60
11.00.00
5,376.60
PISOS Y PAVIMENTOS
1,274.46
12.00.00
1,274.46
13.00.00
390.86
CONTRAZOCALOS
11,209.00
14.00.00
CARPINTERIA METALICA
5,604.50
5,604.50
2,711.57
2,711.57
5,423.14
15.00.00
PINTURA
3,070.49
16.00.00
INSTALACIONES ELECTRICAS
1,535.25
1,535.25
852.69
17.00.00
VARIOS
COSTO DIRECTO
AVANCE MENSUAL (%)
88,923.85
989.215
170.54
170.54
170.54
170.54
170.54
15330.2405
9653.773
6696.018
12674.143
8486.608
PROGRAMADO
1.11%
1.76%
9.95%
15.60%
12.14%
17.24%
10.86%
7.53%
14.25%
9.54%
EJECUTADO
1.11%
1.76%
9.95%
15.60%
12.14%
17.24%
10.86%
7.53%
14.25%
9.54%
PROGRAMADO
1.11%
1.76%
9.95%
15.60%
12.14%
17.24%
10.86%
7.53%
14.25%
9.54%
EJECUTADO
1.11%
2.87%
12.83%
28.43%
40.58%
57.82%
68.67%
76.20%
90.46%
100.00%