90 MW Simple Cycle Power Plant Magboro, Nigeria

Project name:

Document

name:

Appendix A: Technical Specification


Contract Agreement

No.:

EPC-1312-32-ERT-001

to Onshore

Project No.:

EPC-1312-2011

Rev:

Date:

B
22-05-2015

Individual tests pumps local / remote operation


Individual tests connection measurement equipments TIR, PIR, FIR
Individual tests compressor local / remote operation
Individual tests signals in DCS
Individual tests C02 Fire Protection System
Individual tests High Voltage System,
Test interlocks simulation
Preparation on the first start gas turbine
The first start gas turbine
Training operation personal
Pre - complex

test s :

Checks of control, interlocks, alerting, measuring and regulation


Function tests automatic operation (all algorithms)
Dynamic Testing/Setting
Combustor Mapping
Preparation on the complex tests
Training operation personal
Complex

tests:

Start of 3daysTrial run of Power Plant


Performance tests
Final take - over

This phase contains also practicai instruction of the Cliens

operating

personnel

as a part of

personnel training.
Prior to commissioning,

protocols on individual test runs of relevant equipment as for its function

will be prepared.
Fittings operated electrically will be checked as for stop/start location, proper connection to driving
media and control system, possibility of being controlled either locally or remotely in manual of
automatic mode.
Electric cabling and control cabling will be asked and tested according to relevant international
standards. Based on these checks, relevant protocols and certifications will be issued.

Page 26 of 30