1.
Initial Design
Form base mapping establish extent of catchments crossing the highway. Based on the
preliminary vertical alignment (VA) establish location of low points.
Does VA allow sufficient height for culverts and to allow drainage to discharge to
watercourses including balancing pond where required?
Where the road crosses a flood plain assess impact in accordance with HA71/95. Assess
the need for flood culverts and flood relief areas.
Agree pollution control requirements with the EA. Environmental assessment as Design
Manual for Roads and Bridges (DMRB), Volume II, Part 10 may be required.
2.
Identify minor watercourses and ditches crossing the road. Decide whether to provide a
culvert or divert. Size the culverts.
3.
Highway Drainage
Use drainage model to confirm discharge rates and size balancing ponds to the storm
return periods agreed with the EA.
Obtain Consents.
Pollution Control
Obtain Consents.