Troubled Waters
Need to salvage Dabhol power project
hhe Dabhol gas-based
power project contin-
ues to face problems.
The 1,967 MW’ project,
owned by Ratnagiri Gas
and Power Private Limited
{RGPPL) has not generat-
eda single unit of elecric-
lity since January 2014,
| mainly on account of domestic gas short-
age. Power generation from the project
hhas declined consistently over the years
| from 11,877 MUs in 2010-11 10 around
| 1,506 MUs in 2013-14. The project has
been allocated 7.6 milion standard cubic
metres per day (mscmd) of gas from
Reliance Industries Limited's Krishna-
Godavari-D6 block (KG-D6) and 09
| msemd of gas from the marginal gas
fields of the Oil and Natural Gas Corpo-
ration (through GAIL (India) Limited)
However, gas supply from the KG-D5
block has plunged to zero since March
2013 due to lower-than-anticipated pro-
duction. While the promoters are finding
ways (0 revive the project, lenders are
looking at options to recover their dues.
Background
‘The plant was initially owned by the
Dabhol Power Company (DPC) and was
promoted by US-based energy, com
modities and services company, Enron
Corporation, in 1992. It marked the
largest foreign investment in the coun-
try and the power sector,
‘The plant ran into trouble
soon after the 640 MW
Block 1 was commis-
sioned in 1999 due to
Power purchase agree-
‘ment (PPA)-related issues
with the erstwhile Maha-
rashtra State Electricity
Board (MSEB). In 2001, Enron filed for
bankruptey, following which DPC was
shut down,
In July 2005, the project was revived with
the incorporation of RGPPL, promoted
by NTPC Limited and GAIL which took
over the assets of DPC, RGPPL settled the
claims of General Electric Company and
Bechtel Corporation, which were minori
{y partners with Enron in DPC, with sup-
port from the financial institutions.
NTPC and GAIL each have a 32.86 per
cent stake in the company, 17.81 per cent
is held by MSEB Holding Company
Limited and financial institutions such as
IDBI Bank Limited, State Bank of India
(SBN), ICICI Bank Limited, and Canara
Bank own the remaining 16.87 per cent.
{In 2006, the plant resumed power gener-
ation amid a severe power crisis in
Maharashtra, using naphtha to make up
for the power shortage. In 2009, loans for
the project were restructured due to its
inability to pay its dues.
Year-wise power generation from RGPPL
Year Installed capacity (MW) Gross generation (MUs)_
21810 1967 em
wien 1967 wero
iti 1967 wie
mei ‘7 i
| aio 1367
| aoiets wperrgatanra 1367
Source: Wit rply to @ Lok Sabha question n March 2013, ental Etc Authonty
2
POWER LINE » Octobe
Current status
Currently, RGPPL owes around Rs 85 bil-
lion as debt repayment to various
lenders. To add to its woes, Maharashtra
State Electricity Distribution Company
Limited (MSEDCL), the sole buyer of
power from the project. reportedly owes
it nearly Rs 15 billion, In April 2014, the
Ministry of Finance stepped in to resolve
theissue between two companies, stating
it would deduct the dues payable by
MSEDCL from the central funds to be
transferred to the state in case the dispute
‘was not resolved amicably. However, the
ministry considered this option only as a
last resort. The matter escalated further
in May 2014, when MSEDCL served a
notice on RGPPL for the termination of
the PPA owing to frequent closures and
high generation costs due to the use of
expensive liquefied natural gas (LNG)
While the lenders are oscillating between,
the options of hiving off the projects
assets or declaring it a non-performing
asset (NPA), the Power Finance
Corporation has already declared the
project an NPA, on account of the com-
pany’s inability to pay interest install
‘ments for three months. Further, there
are proposals to convert a part of the
lenders’ debt into equity; however, a final
decision in this regard is pending, Other
lenders including SBI and ICICI are also.
planning to convert their dues into equi-
{y: After the conversion, their stake would,
increase to 27 per cent while that of
NTPC and GAIL would reduce to 28.8 per
cent each, and the stake of MSEB Holding,
Company would reduce to 15.2 per cent.
In September 2014, the lenders consid-
ered the option of hiving off the LNG ter-
minal associated with the project to
recover their debt. The 5 mtpa Dabhol
LNG terminal in Ratnagiri was commis-
sioned by GAIL in January 2013 and
entailed an Investment of Rs 40 billion.
The terminal is owned by RGPPL while
GAIL is the commercial operator. This
proposal, however, has been opposed by
the promoters NTPC and GAIL, as well
as the Maharashtra government as it
‘would significantly diminish the pro-
ject’s valuation.