C264 Built-In Automation

Configuration
PACiS Technical Training Level 2
CS&P Support Team

PCL

Content
 xPS/xPC Association
 Pole Discordance
 AVR

Schneider Electric - CS&P C264 Built-in Automations E01

Content
 xPS/xPC Association
 Pole Discordance
 AVR

Schneider Electric - CS&P C264 Built-in Automations E01

xPS/xPC Association
1) SPS / DPS status can activate SPC / DPC
=> Example
PSL is producing SPS which acts on SPC

CAUTION : NO CHECK DONE ON CONTROL, IF C264 OPERATIONAL,


control is accepted and sent
Relation controls on state change :
relation has attributes => per state, choose
associated control

Note : resulting SPC / DPC can be permanent or transient


Schneider Electric - CS&P C264 Built-in Automations E01

Content
 xPS/xPC Association
 Pole Discordance
 AVR

Schneider Electric - CS&P C264 Built-in Automations E01

Add / Configure a Phases Not


Together
1) Phases Not Together SPS is added at Single Phase Circuit Breaker level.

2) Phases Not Together attributes

Timer :
when phases not together is set => timer
elapsed => CB trip

Schneider Electric - CS&P C264 Built-in Automations E01

Content
 xPS/xPC Association
 Pole Discordance
 AVR

Schneider Electric - CS&P C264 Built-in Automations E01

Add / Configure an AVR

Cf. C264 AP chapter

Schneider Electric - CS&P C264 Built-in Automations E01