PROJECT SUMMARY

1.

Number of Contract Package

NHDP-III/BOT/TN/04

2.

Name of Contract Package

DESIGN, ENGINEERING, FINANCE, CONSTRUCTION,


OPERATION AND MAINTENANCE OF MADURAITUTICORIN SECTION FROM KM 138.800 TO KM
266.865 OF NH-38 (45B) IN THE STATE OF
TAMILNADU UNDER NHDP PHASE IIIA ON BUILD,
OPERATE AND TRANSFER (BOT) BASIS

3.

Location

Km 138.800 - Km 266.865

4.

Length km.

128.065 Appox (Including Bypasses)

5.

Concession period

20 years from the Appointed Date

6.

Name of the Concessionaire

MADURAI - TUTICORIN EXPRESSWAYS LIMITED

7.

Independent Consultant

CDM SMITH ASSOCIATES(formally WIlber Smith


Associates).

8.

Notification Date

27th September 2005

9.

Issue of RFP document

23rd December 2005

10. Letter of Acceptance Date

23rd February 2006

11.

24th July 2006

Agreement Date

12. Development period

180 days from the Agreement date

13. Appointed Date

20th January 2007

14. Construction period

36 months from the Appointed Date

15.

Schedule date of project


completion

19th January 2010

16. Total Project Cost

Rs. 6290 million

17. Grant amount

Rs. 1440 million

18. Provisional COD issued

02-07-2011