Progress of

works in
NHAI
projects in
State of
Gujarat

Date of
Total
commenceme
Contract
Lengt Project
S.
nt /
Stretch
h
Cost
No
Cumulative
(State)/NH No. (Km.) (Rs. in
physical
Crores)
progress

Gujarat /
Maharashtra
Border-SuratHazira Port
section (NH-6)

30.03.10
133

1509.00
82.14%

19.01.2011
2

Kandla - Mundra
Port (NH 8A Ext.)

71.4

954.00
74%

Name of
Concessionaire/
Independent
Engineer

M/s. Soma - Isolux


25.09.2012
Surat - Hazira
Tollway Pvt. Ltd./
Sheladia
30.11.2015
Associates Inc

M/s. KM Tollway
Private Ltd./DCDCI (JV)

31.03.2012

JetpurSomnath(NH8D)

123.5

828.00
81.80%

Stipulate
d/
Anticipat
ed
Completio
n

16.07.201
3
30.04.201
6
27.09.201
4

M/s. IDFC and


PLUS Expressway
Ltd./
Intercontinental
Consultants Pvt.
Ltd. In JV with
Stup consultants
Pvt. Ltd.

PCC
achieved
on
04.05.201
5
(Except
Junagadh
Bypass
and
Supasi)

S.
No
.

Contract
Stretch
(State)/NH
No.

Six laning of
SamakhiyaliGandhidham
Section from
Km 306.000 to
Km
362.160(NH
8A)

Length
(Km.)

Total
Project
Cost
(Rs. in
Crores)

Date of
Name of
Stipulate
commenceme Concessionaire
d/
nt /
/
Anticipat
Cumulative
Name of
ed
physical
Independent Completi
progress
Engineer
on
11.09.2010

56.16

805

96%

01.01.2013

AhmedabadVadodara
(NH8) section
& NE-1
(AVEXP)

102.30

2125.2

68.19%

11.03.2013
M/s L&T/ M/s
Louis
Burger
Group Inc
31.10.2015

M/s. IRB AVSE 31.12.2015


Pvt.
Ltd./Aarvee
Associates
Architects,
31.12.2015
Engineers
&
Consultants Pvt
Ltd

S.
No
.

Contract
Stretch
(State)

Construction of
a new four
lane Narmada
bridge (Extra
dosed bridge)
across river
Narmada in the
State of
Gujarat on
EPC(NH8)

Length
(km.)

6.00

Total
Project
Cost
(Rs. in
Crores)

379.00

Date of
Name of
commencem
Concession
ent
aire/
/Cumulative
Authority
Physical
Engineer
Progress

31.88%
03.03.2014

Contractor
M/s. L&T
Ltd
Mumbai/
M/s. Aarvee
Associates
Engineers

Stipulated
Completion

29.08.2016.
Progress is
ahead of
schedule