Академический Документы
Профессиональный Документы
Культура Документы
Diaphragm Wall
- Principles and Applications
- Le Havre Port 2000
- The Sail
Le Havre : Design
The site on
10/09/2001
Le Havre : Design
Plan View
AGS-ATS Perth Aug 2010
Le Havre : Design
Capping beam
with bollards and
fenders
A reinforced
concrete
front wall.
Tie rods
between the
walls.
Sheet piled as
rear wall
Le Havre : Design
Quay : 1600 lm Diaphragm Wall
42 m deep, 1,2 m wide, 150 kg/m3
67 000 m2, 80 000 m3 concrete, 12 000 t steel
Dewatering
Anchors
Sheet Piles
Dredging
Earthworks
Civil Works
Bored piles
Le Havre: phase 1
PHASE 1
Preparation of working platform
Construction of Guide Walls
Installation of Well Points
Le Havre: phase 1
Le Havre: phase 2
PHASE 2
Construction of Diaphragm Walls
Le Havre: phase 1
Le Havre:
Le Havre: phase 3
PHASE 3
Le Havre: phase 3
Le Havre: phase 4
PHASE 4
Cast capping beam and dock buffers
Le Havre: phase 4
Le Havre: phase 5
PHASE 5
Earthwork excavation behind wall during
dewatering
Le Havre: phase 5
Le Havre: phase 6
PHASE 6
Installation of sheet pile curtain
Lay lower layer of anchors
Le Havre: phase 6
Le Havre: phase 6
Le Havre: phase 6
PHASE 6
Backfill to level upper anchor layer and
lay upper layer of anchors
Le Havre: phase 6
Le Havre: phase 6
Sea side
DWall 1,20 m
FF -7.50
Sheet piles
Land side
Tie backs
Le Havre: phase 6
PHASE 6
Backfill to formation level, construct all civil
works, install bumpers, stop dewatering,
dredging, crane rail foundations and rails.
Le Havre: phase 6
Le Havre: phase 6
Le Havre: phase 6
Le Havre: Now
Now in Cotonou
Now in Cotonou
9,090.9 sqm
Permissible GFA
118,182 sqm
Tower 1
No of floors: 70
Typical Floor GFA: 1,026 sqm
Height: 242m
Tower 2
No of floors: 63
Typical Floor GFA: 746 sqm
Height: 202m
Podium
No of floors: 7
Typical Floor Plate: 3,726 sqm
Existing
Buried Pier
Expected Fort
Canning
Boulder Bed
Tower 1
Tower 2
CST
8m Canal
Site specificities
Thick marine clay (up to 35m
of Kallang formation = very
soft to soft)
Fort Canning Boulder Bed
UG obstacle = old pier below
the tower
MTR running tunnel & CS
excavation along the site
Project issues
To control movement of
MRT tunnels & CS Tunnel is
a REAL must
Very tight program = 6
months for foundations +
excavation
3 rd
MR
T
Re
ser
ved
Lin
e
T1
Temporary
D-W all
Perimeter
3 symmetrical 32.2m diam
circular Dwalls,
29 m deep, 220 ml long
800 mm thick
with cross walls.
Barettes
79 Nos. of 1,2 x 2,8
up to 67 m deep, incl 20 m in
SPT>100
all toes grouted ;
AGS-ATS Perth Aug 2010
Isle of Grain
Conclusion
Le Havre Port 2000
Site opportunity : shallow water
Issue : optimisation (phasage/dewatering/quantities/..)
The Sail
Project constraint: tight program, neighb. structures
Issue : design, execution
Ronan Le Roy
rleroy@menardbachy.com.au
AGS-ATS Perth Aug 2010