1)
Dear User, thank you for using my template. Please remove sample entries from the "Estimation Sheet".
2)
Please make your data entries on the sheet "Estimation Sheet" only. Cells containing formulas or functions are
protected, the password is blank should you wish to modify anything.
3)
You downloaded this sheet free of charge from
http: project-management.magt.biz
You may use this sheet for your personal use and projects. However, selling the sheet is strictly prohibited.

Estimation Sheet".

ormulas or functions are

ohibited.

This template is downloaded from http://project-management.magt.biz

Project:
Sub-Project or Phase:
Client:
Client's Representative:
Contractor:

[Project Name]
[Sub-Project or Phase]
[Client]
[Client's Representative]
[Contractor]

Activity Duration Control Sheet

Printed on:
Recorded by:

Planned

Actual

Start

Finish

Duration

Start

Finish

Duration

0001

Excavate footings no. 1 - 15

1/1/2015

0002

Pour blinding concrete footings no. 1 - 15

1/6/2015

1/5/2015
1/9/2015

0003

Install reinforcement footings no. 1- 15

1/13/2015 1/17/2015

5 1/2/2015
4 1/6/2015
5 1/12/2015

1/6/2015
1/7/2015

Difference

Remarks

5
2

0
-2

283

278

Total:

276 days lost

0004

Prepared by: Marc Arnecke,PMP

10/21/2015
[Author]

[Work Package Description]

Work Package:

Sub-Contractor:
Activity

[Proj. Mngr.]

Project Mngr.:

This template is downloaded from http://project-management.magt.biz

Prepared by: Marc Arnecke,PMP