Академический Документы
Профессиональный Документы
Культура Документы
Rebar- (Pile breaking ongoing) Material to be shifted from SA1 to start excavation
ZONE 1
Stair B1-Basement Mezzanine
12
23-Sep-15
10
30-Aug-15
8-Sep-15
15-Sep-15
21-Sep-15
22-Sep-15
26-Sep-15
ZONE 2
ZONE 3
Ground Floor Mezzanine FRP Column/walls & Slab (Part1 + Part2)
23-Aug-15
31-Aug-15
19
24-Aug-15
11-Sep-15
29-Sep-15
6-Oct-15
9-Oct-15
15-Oct-15
14
2-Sep-15
15-Sep-15
16-Sep-15
24-Sep-15
1-Oct-15
7-Oct-15
21-Sep-15
28-Sep-15
TBC
TBC
ZONE 4
LV Transformer Room Access for Rebar (Planned Start - 30/9)-Rebar still not shifted by PLG
FAMILY HOTEL
B1-SUBSTRUCTURE (RAFT)
ZONE 4 (+4.8 LvL)
Rebar for Raft at 4.8 SSL Pour-1
Raft Cast at 4.8 SSL Pour2
ZONE 1
Ground Beams (Part 1) - Waterproofing Ongoing
17-Sep-15
20-Sep-15
30-Sep-15
3-Oct-15
8-Sep-15
14-Sep-15
13-Sep-15
15-Sep-15
24-Sep-15
26-Sep-15
SUPERSTRUCTURE
ZONE 1
ZONE 2
Ground Floor Slab FRP Part-2
11
9-Sep-15
19-Sep-15
11
14-Sep-15
24-Sep-15
30-Sep-15
8-Oct-15
ZONE 3
Basement Verticals FRP (Internal & External)
12
10-Sep-15
21-Sep-15
10
24-Sep-15
3-Oct-15
30-Sep-15
8-Oct-15
1 of 2
25-10-2015
24-10-2015
23-10-2015
22-10-2015
21-10-2015
20-10-2015
19-10-2015
18-10-2015
17-10-2015
16-10-2015
15-10-2015
14-10-2015
13-10-2015
12-10-2015
11-10-2015
10-10-2015
09-10-2015
08-10-2015
07-10-2015
06-10-2015
05-10-2015
04-10-2015
03-10-2015
02-10-2015
01-10-2015
4-Oct-15
SUPERSTRUCTURE
30-09-2015
TBC
29-09-2015
TBC
ZONE 7
28-09-2015
7-Oct-15
ZONE 6 South
27-09-2015
4-Oct-15
B1-SUBSTRUCTURE (RAFT)
26-09-2015
LUXURY HOTEL
25-09-2015
Finish
24-09-2015
Start
23-09-2015
Duration
22-09-2015
Activity Name
21-09-2015
Sr.No
20-09-2015
SERVICED APARTMENT 01
SUBSTRUCTURE
ZONE 2(+3.500 LVL)
ZONE 2(+1.500LVL)
ZONE 4
Pour-2
SUPERSTRUCTURE
ZONE 1 (FRP WALLS)
Pour 3 Lift (Jumpform) (+18.6 to +22.4 SSL)
14-Sep-15
17-Sep-15
10
10-Sep-15
19-Sep-15
TBC
TBC
15-Sep-15
17-Sep-15
18-Aug-15
20-Aug-15
21-Aug-15
23-Aug-15
26-Aug-15
28-Aug-15
22
19-Sep-15
10-Oct-15
9-Aug-15
15-Aug-15
20-Sep-15
26-Sep-15
5-Sep-15
8-Sep-15
16-Sep-15
20-Sep-15
15-Sep-15
20-Sep-15
12
29-Aug-15
9-Sep-15
11
10-Sep-15
20-Sep-15
ZONE 2
SERVICED APARTMENT 02
SUBSTRUCTURE
ZONE 3(-0.500LVL)
Rebar for Raft (Rebar Ongoing) Part2 Minor
26-Aug-15
1-Sep-15
11
23-Aug-15
2-Sep-15
20-Sep-15
24-Sep-15
12-Sep-15
17-Sep-15
19-Sep-15
24-Sep-15
19-Sep-15
24-Sep-15
19-Sep-15
24-Sep-15
8-Sep-15
12-Sep-15
19
27-Sep-15
15-Oct-15
23-Sep-15
26-Sep-15
15-Sep-15
17-Sep-15
13
18-Sep-15
30-Sep-15
13
29-Aug-15
10-Sep-15
TBC
TBC
26-Sep-15
28-Sep-15
ZONE 2(-0.100LVL)
SUPERSTRUCTURE
ZONE 1 (Verticals + Slabs)
ZONE 3
FRP Slab +8.65 SSL
TUNNEL
Deep Tank Pits (Waterproofing to commence)
LEGEND C
2 of 2
CASTED
DELAY
ON TIME
PLANNED
COMMITTED BY PLG
25-10-2015
24-10-2015
23-10-2015
22-10-2015
21-10-2015
20-10-2015
19-10-2015
18-10-2015
17-10-2015
16-10-2015
15-10-2015
14-10-2015
13-10-2015
12-10-2015
11-10-2015
10-10-2015
09-10-2015
08-10-2015
07-10-2015
TBC
06-10-2015
30-Sep-15
TBC
05-10-2015
26-Sep-15
04-10-2015
03-10-2015
Pour-1 (L-shape)-Rebar
02-10-2015
9-Sep-15
01-10-2015
7-Sep-15
30-09-2015
29-09-2015
28-09-2015
26-Aug-15
27-09-2015
23-Aug-15
26-09-2015
25-09-2015
24-09-2015
Finish
23-09-2015
Start
22-09-2015
Duration
21-09-2015
Activity Name
20-09-2015
Sr.No