PROJECT: BLUEWATERS HOSPITALITY

Rebar- (Pile breaking ongoing) Material to be shifted from SA1 to start excavation

ZONE 1
Stair B1-Basement Mezzanine

12

23-Sep-15

Level 03 FRP Walls/Columns & Slab

10

30-Aug-15

8-Sep-15

Level 04 FRP Walls/Columns & Slab (Lower Roof)

15-Sep-15

21-Sep-15

Level 04 FRP Walls/Columns & Slab (Upper Roof)

22-Sep-15

26-Sep-15

ZONE 2

ZONE 3
Ground Floor Mezzanine FRP Column/walls & Slab (Part1 + Part2)

23-Aug-15

31-Aug-15

Level 01 FRP Columns/Walls & Slab(Part 1 + Part 2)

19

24-Aug-15

11-Sep-15

Level 02 FRP Columns/Walls & Slab

29-Sep-15

6-Oct-15

Level 03 FRP Columns/Walls & Slab

9-Oct-15

15-Oct-15

Ground Floor FRP Slab (Pour 1+2)

14

2-Sep-15

15-Sep-15

Ground Floor Mezzanine FRP Slab (Pour 1)

16-Sep-15

24-Sep-15

Ground Floor Mezzanine FRP Slab (Pour 2)

1-Oct-15

7-Oct-15

21-Sep-15

28-Sep-15

TBC

TBC

ZONE 4

LV Transformer Room Access for Rebar (Planned Start - 30/9)-Rebar still not shifted by PLG

FAMILY HOTEL
B1-SUBSTRUCTURE (RAFT)
ZONE 4 (+4.8 LvL)
Rebar for Raft at 4.8 SSL Pour-1
Raft Cast at 4.8 SSL Pour2
ZONE 1
Ground Beams (Part 1) - Waterproofing Ongoing

17-Sep-15

20-Sep-15

Ground Beams (Part 2)

30-Sep-15

3-Oct-15

Level 3 Slab FRP - Pour2

8-Sep-15

14-Sep-15

B1 Grade Slab (Part-1)

13-Sep-15

15-Sep-15

Staircase -B1 - B1 Mezzanine

24-Sep-15

26-Sep-15

SUPERSTRUCTURE
ZONE 1

ZONE 2
Ground Floor Slab FRP Part-2

11

9-Sep-15

19-Sep-15

Ground Floor Slab FRP Part-A

11

14-Sep-15

24-Sep-15

Ground Mezzanine Floor Slab FRP

30-Sep-15

8-Oct-15

ZONE 3
Basement Verticals FRP (Internal & External)

12

10-Sep-15

21-Sep-15

Basement Mezzanine FRP Slab

10

24-Sep-15

3-Oct-15

Ground Floor Double Height FRP Slab

30-Sep-15

8-Oct-15

1 of 2

25-10-2015

24-10-2015

23-10-2015

22-10-2015

21-10-2015

20-10-2015

19-10-2015

18-10-2015

17-10-2015

16-10-2015

15-10-2015

14-10-2015

13-10-2015

12-10-2015

11-10-2015

10-10-2015

09-10-2015

08-10-2015

07-10-2015

06-10-2015

05-10-2015

04-10-2015

03-10-2015

02-10-2015

01-10-2015

4-Oct-15

SUPERSTRUCTURE

30-09-2015

TBC

Rebar- (Rebar not shifted by PLG to start excavation)

29-09-2015

TBC

ZONE 7

28-09-2015

7-Oct-15

ZONE 6 South

27-09-2015

4-Oct-15

B1-SUBSTRUCTURE (RAFT)

26-09-2015

LUXURY HOTEL

25-09-2015

Finish

24-09-2015

Start

23-09-2015

Duration

22-09-2015

Activity Name

21-09-2015

Sr.No

20-09-2015

STRUCTURAL WORKS SCHEDULE STATUS AS OF 20-SEP-2015 (3 Weeks Look Ahead)

SERVICED APARTMENT 01
SUBSTRUCTURE
ZONE 2(+3.500 LVL)
ZONE 2(+1.500LVL)
ZONE 4
Pour-2
SUPERSTRUCTURE
ZONE 1 (FRP WALLS)
Pour 3 Lift (Jumpform) (+18.6 to +22.4 SSL)

14-Sep-15

17-Sep-15

Pour 4b Lift (Jumpform) (+22.4 to +26.0 SSL)

10

10-Sep-15

19-Sep-15

TBC

TBC

Pour 7 Lift (+1.8 to +5.4 SSL)

15-Sep-15

17-Sep-15

Internal Watertank Walls Pour 5- Lift 1,2 & 3

18-Aug-15

20-Aug-15

Internal Watertank Walls Pour 6- Lift 1, 2 & 3

21-Aug-15

23-Aug-15

Internal Watertank Walls Pour 7 - Lift 1, 2 & 3

26-Aug-15

28-Aug-15

FRP Slab +12.650

22

19-Sep-15

10-Oct-15

Pour 7 Lift (+8.650 to +12.250 SSL)

ZONE 2 (FRP WALLS)


Pour 1 (+1.500 to +4.500) FRP (Await MEP Clearance)

9-Aug-15

15-Aug-15

Pour 2 (+11.7 to +15.2) FRP - Jumpform

20-Sep-15

26-Sep-15

Pour 2 (+8.1 to +11.7) FRP -Jumpform

5-Sep-15

8-Sep-15

FRP slab at +4.5 SSL

16-Sep-15

20-Sep-15

FRP slab at +0.5 SSL

15-Sep-15

20-Sep-15

FRP Slab @ 8.65 (above -0.1 SSL)

12

29-Aug-15

9-Sep-15

Ground Floor Slab FRP (Part-1) Above +1.5 SSL

11

10-Sep-15

20-Sep-15

ZONE 2

SERVICED APARTMENT 02
SUBSTRUCTURE
ZONE 3(-0.500LVL)
Rebar for Raft (Rebar Ongoing) Part2 Minor

26-Aug-15

1-Sep-15

Retaining Wall (4 Parts)

11

23-Aug-15

2-Sep-15

Raft at -0.100 SSL Cast (Waterproofing Ongoing)

20-Sep-15

24-Sep-15

Pour 1+2 (+2.3 to +4.5 SSL)

12-Sep-15

17-Sep-15

Pour 3 (+2.3 to +4.500 SSL) -Jumpform

19-Sep-15

24-Sep-15

Pour 4b (+2.300 to 4.500 SSL) -Jumpform

19-Sep-15

24-Sep-15

Pour 5,6 +7 (+2.300 to 4.500 SSL)

19-Sep-15

24-Sep-15

FRP 3.5 SSL

8-Sep-15

12-Sep-15

FRP 8.65 SSL

19

27-Sep-15

15-Oct-15

Pour 1 (+1.5 to +4.5 SSL) - Water tank

23-Sep-15

26-Sep-15

Pour 2 (+1.5 to 4.5 SSL) (Stair jumpform)

15-Sep-15

17-Sep-15

Pour 3 (Pass Lift Jumpform)

13

18-Sep-15

30-Sep-15

FRP Slab +3.5 SSL

13

29-Aug-15

10-Sep-15

TBC

TBC

26-Sep-15

28-Sep-15

ZONE 2(-0.100LVL)
SUPERSTRUCTURE
ZONE 1 (Verticals + Slabs)

ZONE 2 (FRP WALLS)

ZONE 3
FRP Slab +8.65 SSL

TUNNEL
Deep Tank Pits (Waterproofing to commence)

LEGEND C

2 of 2

CASTED

DELAY

ON TIME

PLANNED

COMMITTED BY PLG

25-10-2015

24-10-2015

23-10-2015

22-10-2015

21-10-2015

20-10-2015

19-10-2015

18-10-2015

17-10-2015

16-10-2015

15-10-2015

14-10-2015

13-10-2015

12-10-2015

11-10-2015

10-10-2015

09-10-2015

08-10-2015

07-10-2015

TBC

06-10-2015

30-Sep-15

TBC

05-10-2015

26-Sep-15

04-10-2015

03-10-2015

Pour-1 (L-shape)-Rebar

02-10-2015

9-Sep-15

01-10-2015

7-Sep-15

30-09-2015

29-09-2015

Rebar for Raft (Waterproofing + Rebar Ongoing)

28-09-2015

26-Aug-15

27-09-2015

23-Aug-15

26-09-2015

25-09-2015

Raft Cast- Pour1 Minor (Waterproofing Ongoing)

24-09-2015

Finish

23-09-2015

Start

22-09-2015

Duration

21-09-2015

Activity Name

20-09-2015

Sr.No