POST TENSIONING
PLACEMENT OF TENDONS
Horizontal: + 100 mm
PROJECT 3
DESIGN OF SHUTTERING
LOADS ON FALSEWORK
Loads on Falsework are any combinations of
the following:
Dead loads,
Imposed loads,
Environmental loads,
Incidental loads during erection and
operation, and
Lateral pressure.
accordance with IS 875 (Part I) the unit weight of wet concrete including
reinforcement shall be taken as 26 kN/m. However, in absence of the
data, load may be assumed as 500 N/M2 for the purpose of initial
calculations .
Loads during constructional operation shall constitute the imposed
loads [see IS 875 (Part 2 ) Where allowance has only to be made for
access and inspection purposes, a loading of 750 N/m should be
adequate
The lateral pressure due to fresh concrete depends on the temperature
of concrete as placed, the rate of placing of concrete and the concrete
mix proportion
Wind loads should be taken for design in accordance with IS 875 (Part
3 ) subject to a minimum horizontal load equal to 3 percent of the
vertical loads at critical level.
Snow loads should be assumed in accordance with IS 875(4) . The
maximum density of ice may be assumed to be 900 kg/m.
End Note