Animal Feed Processing Project Proposal for Operational

purpose only
After site visit, the following observations and comments are made with
regard to civil work:
1. The main factory is almost completed and only small finishing and
roofing work is important and estimated to be 950,633.25 Birr to
complete for the operation of the plant. The remaining work can not
obstruct the operation of the plant.
2. The Boiler Room in not constructed and it is important for the
operation of the plant and its civil work cost is estimated at the current
market price about 210,000 Birr for completion of the building.
3. The Site work; the entrance road, the road to the loading and
unloading of the raw material and product inside the plant is important
since the soil is clay soil and its civil work cost is estimated about
650,000 Birr. And the fence work needs to strengthen with gabion
mesh and LTZ steel post.
4. The office, cafeteria, Guard house, Spare part house and power house
shall be constructed at a later stage since it does not affect the
operation of the plant. But temporary office, cafeteria and toilet and
shower can be constructed at a minimum cost (up to 1,200,000.00
Birr) at site if there is no financial constraint.
5. The weighing room is important to be constructed if the weigh bridge
is on site, However there is no weigh bridge and it is not necessary to
construct now.
6. The power house in the design shall be placed on the boiler room
already constructed earlier by modifying and completing the building
and its civil costs 50,000 Birr.