NAME
FED FROM
LOAD
(KW)
LOAD
TYPE
B.B/CABLE
section(mm2)
LENGTH
(m)
VOLTAGE
(V)
I
(A)
V.D./A*KM
FIRST
STAGE (V)
FINAL
TOTAL VOLTAGE
STAGE (V)
DROP (V)
VD/V%
<2.5%
MLTP1A
1.1
CHILLER-1
MLTP1A
1001.000
3 PHASE
3000A B.B
55
415.00
1740.80
0.00
2.24
2.24
0.54%
1.2
COOLING TOWER-1
MLTP1A
37.500
3 PHASE
50
115
415.00
65.21
0.87
0.00
6.52
6.52
1.57%
1.3
MLTP1A
94.000
3 PHASE
185
66
415.00
163.47
0.26
0.00
2.81
2.81
0.68%
1.4
MLTP1A
40.000
3 PHASE
50
60
415.00
69.56
0.87
0.00
3.63
3.63
0.87%
1.5
CONDENSING-1
MLTP1A
90.000
3 PHASE
150
68
415.00
156.52
0.3
0.00
3.19
3.19
0.77%
1.6
BOILER-1
MLTP1A
150.000
3 PHASE
240
90
415.00
260.86
0.21
0.00
4.93
4.93
1.19%
MLTP1B
2.1
TVSS
MLTP1B
2.200
3 PHASE
415.00
3.83
6.8
0.00
0.16
0.16
0.04%
2.2
CHILLER-2
MLTP1B
1001.000
3 PHASE
3000A B.B
60
415.00
1740.80
0.00
2.44
2.44
0.59%
2.3
COOLING TOWER-2
MLTP1B
37.500
3 PHASE
50
116
415.00
65.21
0.87
0.00
6.58
6.58
1.59%
2.4
MLTP1B
94.000
3 PHASE
185
68
415.00
163.47
0.26
0.00
2.89
2.89
0.70%
2.5
MLTP1B
40.000
3 PHASE
50
61
415.00
69.56
0.87
0.00
3.69
3.69
0.89%
2.6
CONDENSING-2
MLTP1B
90.000
3 PHASE
150
69
415.00
156.52
0.3
0.00
3.24
3.24
0.78%
2.7
BOILER-2
MLTP1B
150.000
3 PHASE
240
92
415.00
260.86
0.21
0.00
5.04
5.04
1.21%
MLTP 2A
3.1
CHILLER-3
MLTP 2A
1001.000
3 PHASE
3000A B.B
65
415.00
1740.80
0.00
2.65
2.65
0.64%
3.2
COOLING TOWER-3
MLTP 2A
37.500
3 PHASE
50
117
415.00
65.21
0.87
0.00
6.64
6.64
1.60%
3.3
MLTP 2A
94.000
3 PHASE
185
69
415.00
163.47
0.26
0.00
2.93
2.93
0.71%
3.4
MLTP 2A
40.000
3 PHASE
50
57
415.00
69.56
0.87
0.00
3.45
3.45
0.83%
3.5
CONDENSING-3
MLTP 2A
90.000
3 PHASE
150
69
411.55
157.83
0.3
0.00
3.27
3.27
0.79%
3.6
BOILER-3
MLTP 2A
150.000
3 PHASE
240
93
411.55
263.05
0.21
0.00
5.14
5.14
1.24%
MLTP 2B
4.1
MLTP 2B
1001.000
3 PHASE
3000A B.B
70
415.00
1740.80
0.00
2.85
2.85
0.69%
4.2
MLTP 2B
37.500
3 PHASE
50
118
415.00
65.21
0.87
0.00
6.69
6.69
1.61%
4.3
MLTP 2B
94.000
3 PHASE
185
70
415.00
163.47
0.26
0.00
2.98
2.98
0.72%
4.4
MLTP 2B
40.000
3 PHASE
50
58
415.00
69.56
0.87
0.00
3.51
3.51
0.85%
1 OF 6
REM.
NAME
FED FROM
LOAD
(KW)
LOAD
TYPE
B.B/CABLE
section(mm2)
LENGTH
(m)
VOLTAGE
(V)
I
(A)
V.D./A*KM
FIRST
STAGE (V)
FINAL
TOTAL VOLTAGE
STAGE (V)
DROP (V)
VD/V%
<2.5%
4.5
MLTP 2B
90.000
3 PHASE
150
70
415.00
156.52
0.3
0.00
3.29
3.29
0.79%
4.6
MLTP 2B
150.000
3 PHASE
240
95
415.00
260.86
0.21
0.00
5.20
5.20
1.25%
4.7
FIRE PUMP 1
MLTP 2B
120.000
3 PHASE
240
70
415.00
208.69
0.21
0.00
3.07
3.07
0.74%
4.8
FIRE PUMP 2
MLTP 2B
120.000
3 PHASE
240
72
415.00
208.69
0.21
0.00
3.16
3.16
0.76%
4.9
JOCKEY PUMP
MLTP 2B
7.500
3 PHASE
16
70
415.00
13.04
2.5
0.00
2.28
2.28
0.55%
4.1
SAND FILTER
MLTP 2B
4.500
3 PHASE
16
45
415.00
7.83
2.5
0.00
0.88
0.88
0.21%
4.11
BOOSTER PUMP
MLTP 2B
45.000
3 PHASE
70
65
415.00
78.26
0.6
0.00
3.05
3.05
0.74%
4.12
HEAT EXCHANGER-1
MLTP 2B
122.000
3 PHASE
240
65
415.00
212.17
0.21
0.00
2.90
2.90
0.70%
B.B-1
MLTP 5A
866.000
3 PHASE
2500A B.B
115
415.00
1506.02
0.00
4.47
4.47
1.08%
5.1.1
B.B-1
78.000
3 PHASE
120
410.53
137.12
0.37
4.47
0.36
4.83
1.16%
5.1.2
B.B-1
26.000
3 PHASE
35
75
410.53
45.71
1.15
4.47
3.94
8.41
2.03%
5.1.3
B.B-1
72.000
3 PHASE
120
410.53
126.58
0.37
4.47
0.33
4.80
1.16%
5.1.4
B.B-1
54.000
3 PHASE
120
100
410.53
94.93
0.37
4.47
3.51
7.98
1.92%
5.1.5
MSB-GF-4
B.B-1
234.000
3 PHASE
3 X 150
100
410.53
411.37
0.1
4.47
4.11
8.58
2.07%
5.1.6
B.B-1
60.000
3 PHASE
70
410.53
105.48
0.6
4.47
0.44
4.91
1.18%
5.1.7
B.B-1
45.000
3 PHASE
95
100
410.53
79.11
0.45
4.47
3.56
8.03
1.93%
5.1.8
MSB-1F-4
B.B-1
120.000
3 PHASE
240
100
410.53
210.96
0.21
4.47
4.43
8.90
2.14%
5.1.9
B.B-1
45.000
3 PHASE
50
410.53
79.11
0.87
4.47
0.48
4.95
1.19%
5.1.10
B.B-1
38.000
3 PHASE
50
410.53
66.80
0.87
4.47
0.41
4.88
1.18%
5.1.11
B.B-1
38.000
3 PHASE
50
410.53
66.80
0.87
4.47
0.41
4.88
1.18%
5.1.12
B.B-1
38.000
3 PHASE
25
410.53
66.80
0.87
2.28
0.41
2.69
0.65%
5.1.13
B.B-1
18.000
3 PHASE
16
410.53
31.64
2.5
2.28
0.55
2.84
0.68%
MLTP 3A
5.1
MLTP 3B
6.1
B.B-2
MLTP 5B
455.740
3 PHASE
1350A B.B
110
415.00
792.56
0.00
4.63
4.63
1.12%
6.2
B.B-10
MLTP 5B
535.000
3 PHASE
1600A B.B
55
415.00
930.40
0.00
2.20
2.20
0.53%
B.B-2
27.260
3 PHASE
35
410.37
47.94
1.15
4.63
0.39
5.02
1.21%
6.1.1
2 OF 6
REM.
NAME
FED FROM
LOAD
(KW)
LOAD
TYPE
B.B/CABLE
section(mm2)
LENGTH
(m)
VOLTAGE
(V)
I
(A)
V.D./A*KM
FIRST
STAGE (V)
FINAL
TOTAL VOLTAGE
STAGE (V)
DROP (V)
VD/V%
<2.5%
6.1.2
B.B-2
27.260
3 PHASE
50
75
410.37
47.94
0.87
4.63
3.13
7.76
1.87%
6.1.3
B.B-2
18.250
3 PHASE
25
410.37
32.10
1.65
4.63
0.37
5.00
1.20%
6.1.4
B.B-2
18.250
3 PHASE
35
100
410.37
32.10
1.15
4.63
3.69
8.32
2.01%
6.1.5
B.B-2
19.460
3 PHASE
25
410.37
34.22
1.65
4.63
0.40
5.03
1.21%
6.1.6
B.B-2
19.460
3 PHASE
35
100
410.37
34.22
1.15
4.63
3.94
8.57
2.06%
6.1.7
B.B-2
4.300
3 PHASE
16
410.37
7.56
2.5
4.63
0.13
4.76
1.15%
6.1.8
B.B-2
4.300
3 PHASE
16
410.37
7.56
2.5
4.63
0.13
4.76
1.15%
6.1.9
B.B-2
3.700
3 PHASE
16
410.37
6.51
2.5
4.63
0.11
4.74
1.14%
6.1.10
B.B-2
5.000
3 PHASE
16
410.37
8.79
2.5
4.63
0.15
4.78
1.15%
6.1.11
B.B-2
308.500
3 PHASE
3 X 240
410.37
542.55
0.07
4.63
0.27
4.90
1.18%
6.2.1
MSB-KIT-1
B.B-10
179.000
3 PHASE
2 X 150
10
412.80
312.95
0.15
2.20
0.47
2.67
0.64%
6.2.2
MSB-KIT-2
B.B-10
179.000
3 PHASE
2 X 150
11
412.80
312.95
0.15
2.20
0.52
2.72
0.65%
6.2.3
MSB-KIT-3
B.B-10
179.000
3 PHASE
2 X 150
12
412.80
312.95
0.15
2.20
0.56
2.76
0.67%
1042.000
3 PHASE
3000A B.B
110
415.00
1812.10
0.00
4.66
4.66
1.12%
MLTP 4A
7.1
B.B-3
MLTP 4A
7.1.1
MSB-BF-3
B.B-3
27.000
3 PHASE
25
410.34
47.49
1.65
4.66
0.55
5.21
1.26%
7.1.2
MSB-BF-4
B.B-3
18.000
3 PHASE
25
75
410.34
31.66
1.65
4.66
3.92
8.58
2.07%
7.1.3
MSB-GF-3
B.B-3
312.000
3 PHASE
4 X 120
410.34
548.75
0.0925
4.66
0.36
5.02
1.21%
7.1.4
MSB-1F-3
B.B-3
80.000
3 PHASE
120
410.34
140.70
0.37
4.66
0.36
5.02
1.21%
7.1.5
MSB-1F-11(LAB)
B.B-3
80.000
3 PHASE
120
410.34
140.70
0.37
4.66
0.36
5.02
1.21%
7.1.6
MSB-2F-2
B.B-3
125.000
3 PHASE
240
410.34
219.85
0.21
4.66
0.32
4.98
1.20%
7.1.7
MSB-3F-2
B.B-3
125.000
3 PHASE
240
410.34
219.85
0.21
4.66
0.32
4.98
1.20%
7.1.8
MSB-4F-2
B.B-3
125.000
3 PHASE
240
28
410.34
219.85
0.21
4.66
1.29
5.95
1.43%
7.1.9
MSB-5F-2
B.B-3
170.000
3 PHASE
2 X 150
31
410.34
299.00
0.15
4.66
1.39
6.05
1.46%
1054.000
3 PHASE
3200A B.B
65
415.00
1832.97
0.00
2.17
2.17
0.52%
58.500
3 PHASE
95
412.83
102.27
0.45
2.17
0.32
2.49
0.60%
MLTP 4B
8.1
8.1.1
B.B-4
MLTP 4B
B.B-4
3 OF 6
REM.
NAME
FED FROM
LOAD
(KW)
LOAD
TYPE
B.B/CABLE
section(mm2)
LENGTH
(m)
VOLTAGE
(V)
I
(A)
V.D./A*KM
FIRST
STAGE (V)
FINAL
TOTAL VOLTAGE
STAGE (V)
DROP (V)
VD/V%
<2.5%
8.1.2
B.B-4
58.500
3 PHASE
95
80
412.83
102.27
0.45
2.17
3.68
5.85
1.41%
8.1.3
B.B-4
36.000
3 PHASE
50
412.83
62.94
0.87
2.17
0.38
2.55
0.62%
8.1.4
B.B-4
36.000
3 PHASE
50
100
412.83
62.94
0.87
2.17
5.48
7.65
1.84%
8.1.5
MSB-GF-8
B.B-4
156.000
3 PHASE
2 X 120
412.83
272.72
0.185
2.17
0.35
2.52
0.61%
8.1.6
B.B-4
30.000
3 PHASE
50
412.83
52.45
0.87
2.17
0.32
2.49
0.60%
8.1.7
B.B-4
30.000
3 PHASE
50
100
412.83
52.45
0.87
2.17
4.56
6.73
1.62%
8.1.8
B.B-4
45.000
3 PHASE
50
412.83
78.67
0.87
2.17
0.48
2.65
0.64%
8.1.9
B.B-4
38.000
3 PHASE
50
412.83
66.43
0.87
2.17
0.40
2.57
0.62%
8.1.10
B.B-4
38.000
3 PHASE
50
412.83
66.43
0.87
2.17
0.40
2.57
0.62%
8.1.11
MSB-4F-6 (ICU)
B.B-4
100.000
3 PHASE
185
412.83
174.82
0.26
2.17
0.32
2.49
0.60%
8.1.12
MSB-4F-7 (ICU)
B.B-4
100.000
3 PHASE
185
412.83
174.82
0.26
2.17
0.32
2.49
0.60%
8.1.13
B.B-4
38.000
3 PHASE
50
412.83
66.43
0.87
2.17
0.40
2.57
0.62%
8.1.14
MSB-5F-6 (ICU)
B.B-4
136.000
3 PHASE
300
412.83
237.76
0.19
2.17
0.32
2.49
0.60%
8.1.15
MSB-5F-7 (ICU)
B.B-4
136.000
3 PHASE
300
412.83
237.76
0.19
2.17
0.32
2.49
0.60%
8.1.16
B.B-4
18.000
3 PHASE
25
412.83
31.47
1.65
2.17
0.36
2.53
0.61%
555.800
3 PHASE
2000A B.B
65
415.00
966.57
0.00
2.26
2.26
0.54%
MLTP 5A
9.1
B.B-5
MLTP 5A
9.1.1
MCC-BF-3(FOR A/C's)
B.B-5
27.260
3 PHASE
35
412.74
47.67
1.15
2.26
0.38
2.64
0.64%
9.1.2
MCC-BF-4(FOR A/C's)
B.B-5
27.260
3 PHASE
35
80
412.74
47.67
1.15
2.26
4.39
6.65
1.60%
9.1.3
MCC-GF-3(FOR A/C's)
B.B-5
18.280
3 PHASE
25
412.74
31.96
1.65
2.26
0.37
2.63
0.63%
9.1.4
MCC-GF-4(FOR A/C's)
B.B-5
18.280
3 PHASE
25
100
412.74
31.96
1.65
2.26
5.27
7.53
1.82%
9.1.5
MCC-1F-3(FOR A/C's)
B.B-5
19.460
3 PHASE
25
412.74
34.03
1.65
2.26
0.39
2.65
0.64%
9.1.6
MCC-1F-4(FOR A/C's)
B.B-5
19.460
3 PHASE
25
100
412.74
34.03
1.65
2.26
5.61
7.87
1.90%
9.1.7
MCC-2F-2(FOR A/C's)
B.B-5
4.300
3 PHASE
16
412.74
7.52
2.5
2.26
0.13
2.39
0.58%
9.1.8
MCC-3F-2(FOR A/C's)
B.B-5
4.300
3 PHASE
16
412.74
7.52
2.5
2.26
0.13
2.39
0.58%
9.1.9
MSB-3F-5 (ICU)
B.B-5
100.000
3 PHASE
185
412.74
174.86
0.26
2.26
0.32
2.58
0.62%
9.1.10
MCC-4F-2(FOR A/C's)
B.B-5
3.700
3 PHASE
16
412.74
6.47
2.5
2.26
0.11
2.37
0.57%
4 OF 6
REM.
NAME
FED FROM
LOAD
(KW)
LOAD
TYPE
B.B/CABLE
section(mm2)
LENGTH
(m)
VOLTAGE
(V)
I
(A)
V.D./A*KM
FIRST
STAGE (V)
FINAL
TOTAL VOLTAGE
STAGE (V)
DROP (V)
VD/V%
<2.5%
9.1.11
MCC-5F-2(FOR A/C's)
B.B-5
5.000
3 PHASE
16
412.74
8.74
2.5
2.26
0.15
2.41
0.58%
9.1.12
MCC-RF-2(FOR A/C's)
B.B-5
308.500
3 PHASE
3 X 240
412.74
539.44
0.07
2.26
0.26
2.52
0.61%
1088.000
3 PHASE
3200A B.B
60
415.00
1892.09
0.00
2.09
2.09
0.50%
10
MLTP 5B
10.1
B.B-6
MLTP 5B
10.1.1
MSB-BF-7
B.B-6
18.000
3 PHASE
25
412.91
31.46
1.65
2.09
0.36
2.45
0.59%
10.1.2
MSB-BF-8
B.B-6
18.000
3 PHASE
25
412.91
31.46
1.65
2.09
0.36
2.45
0.59%
10.1.3
MSB-GF-7
B.B-6
156.000
3 PHASE
2 X 120
412.91
272.67
0.185
2.09
0.35
2.44
0.59%
10.1.4
MSB-1F-7
B.B-6
80.000
3 PHASE
120
412.91
139.83
0.37
2.09
0.36
2.45
0.59%
10.1.5
MSB-1F-8
B.B-6
80.000
3 PHASE
120
412.91
139.83
0.37
2.09
0.36
2.45
0.59%
10.1.6
MSB-2F-5 (ICU)
B.B-6
100.000
3 PHASE
185
412.91
174.79
0.26
2.09
0.32
2.41
0.58%
10.1.7
MSB-2F-6 (ICU)
B.B-6
100.000
3 PHASE
185
412.91
174.79
0.26
2.09
0.32
2.41
0.58%
10.1.8
MSB-2F-7 (ICU)
B.B-6
100.000
3 PHASE
185
412.91
174.79
0.26
2.09
0.32
2.41
0.58%
10.1.9
MSB-3F-6 (ICU)
B.B-6
100.000
3 PHASE
185
412.91
174.79
0.26
2.09
0.32
2.41
0.58%
10.1.10
MSB-3F-7 (ICU)
B.B-6
100.000
3 PHASE
185
412.91
174.79
0.26
2.09
0.32
2.41
0.58%
10.1.11
MSB-4F-5 (ICU)
B.B-6
100.000
3 PHASE
185
412.91
174.79
0.26
2.09
0.32
2.41
0.58%
10.1.12
MSB-5F-5 (ICU)
B.B-6
136.000
3 PHASE
300
412.91
237.71
0.19
2.09
0.32
2.41
0.58%
11
MLTB 6A
11.1
B.B-7
MLTB 6A
390.800
3 PHASE
1250A B.B
120
415.00
679.62
0.00
4.74
4.74
1.14%
11.2
B.B-8
MLTB 6A
607.500
3 PHASE
2000A B.B
120
415.00
1056.48
0.00
4.56
4.56
1.10%
11.2.1
B.B-8
58.500
3 PHASE
95
410.44
102.87
0.45
4.56
0.32
4.88
1.18%
11.2.2
B.B-8
72.000
3 PHASE
120
410.44
126.60
0.37
4.56
0.33
4.89
1.18%
11.2.3
MSB-LAUNDRY
B.B-8
240.000
3 PHASE
2 X 240
20
410.44
422.01
0.105
4.56
0.89
5.45
1.31%
11.2.4
B.B-8
60.000
3 PHASE
95
410.44
105.50
0.45
4.56
0.33
4.89
1.18%
11.2.5
B.B-8
45.000
3 PHASE
70
410.44
79.13
0.6
4.56
0.33
4.89
1.18%
11.2.6
B.B-8
38.000
3 PHASE
50
410.44
66.82
0.87
4.56
0.41
4.97
1.20%
11.2.7
B.B-8
38.000
3 PHASE
50
410.44
66.82
0.87
4.56
0.41
4.97
1.20%
11.2.8
B.B-8
38.000
3 PHASE
50
410.44
66.82
0.87
4.56
0.41
4.97
1.20%
5 OF 6
REM.
NAME
FED FROM
LOAD
(KW)
LOAD
TYPE
B.B/CABLE
section(mm2)
LENGTH
(m)
VOLTAGE
(V)
I
(A)
V.D./A*KM
FIRST
STAGE (V)
FINAL
TOTAL VOLTAGE
STAGE (V)
DROP (V)
VD/V%
<2.5%
11.2.9
B.B-8
18.000
3 PHASE
25
410.44
31.65
1.65
4.56
0.37
4.93
1.19%
11.1.1
MCC-BF-5(FOR A/C's)
B.B-7
27.260
3 PHASE
35
410.26
47.95
1.15
4.74
0.39
5.13
1.24%
11.1.2
MCC-GF-5(FOR A/C's)
B.B-7
18.280
3 PHASE
35
100
410.26
32.16
1.15
4.74
3.70
8.44
2.03%
11.1.3
MCC-1F-5(FOR A/C's)
B.B-7
19.460
3 PHASE
25
410.26
34.23
1.65
4.74
0.40
5.14
1.24%
11.1.4
MCC-2F-3(FOR A/C's)
B.B-7
4.300
3 PHASE
16
410.26
7.56
2.5
4.74
0.13
4.87
1.17%
11.1.5
MCC-3F-3(FOR A/C's)
B.B-7
4.300
3 PHASE
16
410.26
7.56
2.5
4.74
0.13
4.87
1.17%
11.1.6
MCC-4F-3(FOR A/C's)
B.B-7
3.700
3 PHASE
16
410.26
6.51
2.5
4.74
0.11
4.85
1.17%
11.1.7
MCC-5F-3(FOR A/C's)
B.B-7
5.000
3 PHASE
16
410.26
8.80
2.5
4.74
0.15
4.89
1.18%
11.1.8
MCC-RF-2(FOR A/C's)
B.B-7
308.500
3 PHASE
3 X 240
410.26
542.70
0.07
4.74
0.27
5.01
1.21%
1035.000
3 PHASE
3200A B.B
115
415.00
1799.92
0.00
3.81
3.81
0.92%
12
MLTP 6B
12.1
B.B-9
MLTP 6B
12.1.1
MSB-BF-10
B.B-9
18.000
3 PHASE
25
411.19
31.59
1.65
3.81
0.36
4.17
1.01%
12.1.2
MSB-GF-10
B.B-9
312.000
3 PHASE
3 X 185
411.19
547.61
0.0867
3.81
0.33
4.14
1.00%
12.1.3
MSB-1F-10
B.B-9
160.000
3 PHASE
2 X 120
411.19
280.83
0.185
3.81
0.36
4.17
1.01%
12.1.4
B.B-9
125.000
3 PHASE
240
411.19
219.40
0.21
3.81
0.32
4.13
1.00%
12.1.5
MSB-3F-6
B.B-9
125.000
3 PHASE
240
411.19
219.40
0.21
3.81
0.32
4.13
1.00%
12.1.6
MSB-4F-6
B.B-9
125.000
3 PHASE
240
411.19
219.40
0.21
3.81
0.32
4.13
1.00%
12.1.7
MSB-5F-6
B.B-9
170.000
3 PHASE
2 X 120
411.19
298.38
0.185
3.81
0.39
4.20
1.01%
6 OF 6
REM.